6.PRIME-SUB_FORM_for_Contractors_rev._01.15.2025_(lock_before_publishing)_Main_St_Bridge_Deck_Repairs.xls
XLS spreadsheet 38 KB Posted
- Solicitation number
- 26-B-92SR
- Issued by
- Volusia County, Florida
About this file
This is a Prime/Subcontractor Form for the County of Volusia, Department of Public Works, Road & Bridge Division, related to the Main Street Bridge Deck Repairs project (Bridge #794004 over Halifax River) in Florida. The form requires bidders to disclose all proposed subcontractors and their respective work assignments for the project, which involves replacing full-depth concrete on the eastbound deck, sidewalk, and railing on Span 47 of the bridge. Bidders must list the prime contractor and all subcontractors by discipline, including anticipated categories such as electrical, HVAC, plumbing, landscaping, and maintenance of traffic. The form specifies that failure to complete and return this document may result in a non-responsive bid, and any changes to proposed subcontractors during project completion require prior written approval from the County Project Manager.
Bidders must assign dollar values and percentage allocations to each contractor (prime and subcontractors) such that all green-shaded cells total 100 percent and match the total bid price submitted on the bid form. The County reserves the right to seek clarification regarding subcontractors but will not permit changes to the total base bid pricing. The form will also be used to determine local preference in accordance with the solicitation's local bid preference provisions. The prime contractor remains responsible for ensuring all subcontractors hold appropriate licenses, and the contractor must provide all labor, materials, equipment, removal and disposal services, traffic control, functional checks, operation and maintenance manuals, and as-built surveys or drawings necessary to complete the work.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| ITB No. 25-B-##XX | |||||
| PRIME/SUBCONTRACTOR FORM | |||||
| FAILURE TO COMPLETE AND RETURN THIS FORM MAY RESULT IN A NON-RESPONSIVE BID | |||||
| Bidders are to list ALL Subcontractors that he/she proposed to perform scope of work for this project. The bidder hereby states that he/she proposes, if awarded the contract to hire the following Subcontractor(s) for this project. Prime Contractor is responsible for ensuring that all Subcontractors hold the appropriate license(s). Any change to the Subcontractors during the completion of this project shall receive prior approval from the County Project Manager. The County reserves the right to seek clarification regarding subcontractors but will not allow change to the total submitted base bid pricing. | |||||
| TOTAL BID | $ - 0 | This number should match the Total Bid Price |
(inclusive of performance/payment bond, if applicable) as listed on Bid Form/Exhibit ?/Attachment ? - Bid Price Sheet
| PRIME CONTRACTOR | Company name and complete address | Dollar Value performed by Prime Contractor | % of Work performed by Contractor | |||
| $ - 0 | 0.00% | |||||
| List appropriate sub contractors to be used for each displine listed below, if prime is self performing note self performing in the box under company name and address and submit $0.00 to equal 0 % as this should be included in the green box above. If additional subcontractors are required and their discipline is not listed below they may be added in the blank rows. This form will also be used to determine local preference in accordance with Section 2.8, D. Local Bid Preference in the solicitation. | ||||||
| Anticipated Subcontractor Disciplines required for this project. | Company name and complete address | Dollar Value performed by Subcontractor(s) | % of Work performed by Subcontractor | |||
| (Examples: Electrical, HVAC, Plumbing, | ||||||
| Landscaping, etc. for your project) | $ - 0 | 0.00% | ||||
| Maintenance of Traffic | $ - 0 | 0.00% | ||||
| $ - 0 | 0.00% | |||||
| $ - 0 | 0.00% | |||||
| $ - 0 | 0.00% | |||||
| $ - 0 | 0.00% | |||||
| $ - 0 | 0.00% | |||||
| $ - 0 | 0.00% | |||||
| $ - 0 | 0.00% | |||||
| $ - 0 | 0.00% | |||||
| $ - 0 | 0.00% | |||||
| $ - 0 | 0.00% | |||||
| $ - 0 | 0.00% | |||||
| $ - 0 | 0.00% | |||||
| Bidders shall complete the areas shaded in GREEN, which shall be the dollar values assigned to each Contractor (Prime and Subs). All other cells shall be automatically calculated. The total listed in the GREY cell must equal 100% | $ - 0 | 0% |
Sheet2
Sheet3
File details come from the government source that posted it. Updated .