5.BRIDGE_PRE-CONSTRUCTION_CHECKLIST_-_JAX.pdf
PDF 300 KB Posted
- Solicitation number
- 26-B-92SR
- Issued by
- Volusia County, Florida
About this file
This is a Bridge Pre-Construction Notice and Request form issued by the U.S. Coast Guard Southeast District Bridge Administration in coordination with Sector Jacksonville Waterways for the Main Street Bridge (Bridge No. 794004) Deck Repair Project over Halifax River in Volusia County, Florida. The project involves replacing full-depth concrete on the eastbound deck, sidewalk, and railing on Span 47. The contractor must submit a 60-day advance notice prior to project start and a 30-day advance notice prior to any channel obstructions, closures, or opening restrictions. All notifications must be directed to Sector Jacksonville Waterways (D07-DG-SECJAX-WATERWAYS@uscg.mil) and Southeast District Bridge Administration (Jennifer.N.Zercher@uscg.mil). The form requires the contractor to identify all in-water equipment, describe any petroleum products or hazardous materials to be stored or transferred, propose any channel restrictions or vertical clearance limitations with specific dates and times, and provide details regarding movable span operations, including whether advance notice will be required for full openings and equipment repositioning.
The form mandates that the contractor address whether in-water equipment will remain in place or be moved at end of workday and designate a point of contact responsible for full opening requests and equipment movement. The project falls within the June through November hurricane season; therefore, a hurricane plan must be submitted if applicable. The Coast Guard requires that all in-water equipment be properly lighted in accordance with applicable regulations. The contractor is responsible for all labor, materials, equipment, transportation, traffic control, functional checks, operations and maintenance manuals, and as-built surveys and drawings necessary to complete the work as specified in the project documents.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BRIDGE PRE-CONSTRUCTION NOTICE/REQUEST
Roadway/Bridge:
Waterway:
Bridge Owner:
Contractor Primary/24-Hour POC:
Project: Start Date/Time: Finish Date/Time:
Brief Project Description:
The Coast Guard requires all in-water equipment to be properly lighted. List any in-water equipment to be used:
Describe type/quantity of petroleum products or hazardous materials stored/transferred on site (if any):
Describe any proposed channel restrictions or closures and/or vertical clearance restrictions. Include dates/times of restriction(s):
On a movable span, are you requesting: Complete Closure, Single Leaf Opening, Limited Openings, Advance Notice.
Please Explain:
If Applicable:
Hurricane plan submitted for projects between June & November: Y/N How many hours advance notice needed for a full opening:
How many hours advance notice needed to move equipment to provide access to full channel:
Will in-water equipment remain in place or moved at end of workday:
POC for full opening/moving equipment:
60 days advance notice required prior to starting a project. 30 days advance notice required prior to any channel obstructions, closures, or opening restrictions. Make all notifications to Sector Jacksonville Waterways (D07-DG- SECJAX-WATERWAYS@uscg.mil) and to Southeast District Bridge Administration (Jennifer.N.Zercher@uscg.mil)
US Coast Guard Southeast District ꞏ Bridge Administration Branch (dpb) ꞏ 909 SE 1st Ave. ꞏ Miami, FL 33131