This is a bid price sheet for Invitation for Bid 26-B-77IF, Contract C2077, issued by the County of Volusia, Florida for taxiway improvements at Daytona Beach International Airport. The project encompasses 58 line items of construction work including pavement demolition and reconstruction, excavation and grading, asphalt courses totaling 4,840 tons, pavement markings across 25,200 to 28,500 square feet, drainage infrastructure with corrugated metal pipes and inlets, sodding of 27,600 square yards, and comprehensive electrical work. The electrical scope includes 27,500 linear feet of cable installation, 8,350 linear feet of PVC duct installation, grounding systems with 280 copper clad steel ground rods, and FAA-rated lighting fixtures including runway edge lights, taxiway edge lights, and LED signage. The mandatory pre-bid conference was scheduled for April 2, 2026 at 1:30 PM at the airport location with virtual Microsoft Teams attendance available. Electronic bid submission through the County's eProcurement Portal was required by 3:00 PM on April 24, 2026. The contractor must achieve substantial completion within 216 days after Notice to Proceed and final completion within 246 days, with liquidated damages of $2,000 per calendar day assessed for delays beyond the substantial completion date.
This bid price sheet presents all 58 line items with quantities specified but unit prices and extensions left blank for bidder completion. The estimated construction cost is $4,851,000.00, with mobilization capped at 10 percent of the construction subtotal. The project is funded through the FAA Airport Improvement Program and FEMA-funded construction, requiring compliance with Buy American preferences and Davis-Bacon prevailing wage requirements ranging from approximately $15.54 to $33.61 per hour depending on labor classification. Contractors must obtain a Bid Bond equal to five percent of the total bid amount and, upon award, provide a Payment and Performance Bond equal to 100 percent of the contract price. Comprehensive insurance requirements include Workers Compensation with waiver of subrogation, Commercial General Liability of $1,000,000 per occurrence with $5,000,000 aggregate, Auto Liability of $1,000,000 combined single limits, Contractors Pollution Liability of $1,000,000, and an Installation Floater covering wind, hail, and named storm damage. The County processes payment on undisputed invoices within 20 business days from receipt, with five percent retainage withheld pursuant to Florida Statute 255.078 and released upon final project acceptance. DBE participation requirements apply under 49 CFR Part 26, and no incumbent contractor is identified for this project.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| EXHIBIT G - BID PRICE SHEET |
| 26-B-77IF, C2077, DAYTONA BEACH INTERNATIONAL AIRPORT |
| TAXIWAY P3 AND P4 IMPROVEMENTS |
BIDDER:
| INDEX | PAY ITEM | DESCRIPTION | UNIT | QUANTITY | UNIT PRICE | EXTENSION |
| 1 | C-105-1 | MOBILIZATION (LIMITED TO 10% OF CONSTRUCTION SUBTOTAL) | LS | 1 | $ - 0 | $ - 0 |
| 2 | C-100-1 | CONTRACTOR QUALITY CONTROL PROGRAM (CQCP) | LS | 1 | $ - 0 | $ - 0 |
| 3 | C-102-1 | TEMPORARY AIR AND WATER POLLUTION, SOIL EROSION, AND SILTATION CONTROL | LS | 1 | $ - 0 | $ - 0 |
| 4 | C-102-2 | DEWATERING | LS | 1 | $ - 0 | $ - 0 |
| 5 | C-104-1 | CONSTRUCTION SURVEY | LS | 1 | $ - 0 | $ - 0 |
| 6 | C-106-1 | SAFETY, SECURITY, AND MAINTENANCE OF AIRPORT OPERATIONS | LS | 1 | $ - 0 | $ - 0 |
| 7 | P-101-1 | FULL DEPTH PAVEMENT DEMOLITION | SY | 1,375 | $ - 0 | $ - 0 |
| 8 | P-101-2 | FULL DEPTH PAVEMENT DEMOLITION, OPEN CUT | SY | 195 | $ - 0 | $ - 0 |
| 9 | P-101-3 | PAVEMENT DEMOLITION (0.5" - 2.5" VARIABLE MILLING) | SY | 6,215 | $ - 0 | $ - 0 |
| 10 | P-101-4 | PAVEMENT DEMOLITION (0.5" MILLING) | SY | 16,720 | $ - 0 | $ - 0 |
| 11 | P-101-5 | JOINT AND CRACK REPAIR | LF | 8,000 | $ - 0 | $ - 0 |
| 12 | P-101-6 | REMOVE EXISTING INLET STRUCTURE | EA | 2 | $ - 0 | $ - 0 |
| 13 | P-101-7 | REMOVE EXISTING 19"X30" ERCP | LF | 64 | $ - 0 | $ - 0 |
| 14 | P-152-1 | UNCLASSIFIED EXCAVATION | CY | 840 | $ - 0 | $ - 0 |
| 15 | P-152-2 | OFFSITE BORROW EXCAVATION | CY | 4,300 | $ - 0 | $ - 0 |
| 16 | P-152-3 | STRIPPING AND STOCKPILING (6" DEPTH) | SY | 28,600 | $ - 0 | $ - 0 |
| 17 | P-154-1 | 6" STABILIZED SHOULDER | SY | 10,200 | $ - 0 | $ - 0 |
| 18 | P-211-1 | LIMEROCK BASECOURSE, 12" DEPTH | SY | 3,050 | $ - 0 | $ - 0 |
| 19 | P-341-1 | GLASPAVE 25 GEOSYNTHETIC HYBRID PAVING MAT | SF | 7,650 | $ - 0 | $ - 0 |
| 20 | P-401-1 | ASPHALT SURFACE COURSE | TON | 3,560 | $ - 0 | $ - 0 |
| 21 | P-401-2 | ASPHALT LEVELING COURSE | TON | 1,280 | $ - 0 | $ - 0 |
| 22 | P-620-1 | PAVEMENT MARKING, PERMANENT, TYPE III BEADS | SF | 9,000 | $ - 0 | $ - 0 |
| 23 | P-620-2 | PAVEMENT MARKING, PERMANENT, NO BEADS | SF | 8,200 | $ - 0 | $ - 0 |
| 24 | P-620-3 | PAVEMENT MARKING, TEMPORARY, NO BEADS | SF | 9,000 | $ - 0 | $ - 0 |
| 25 | P-620-4 | SURFACE PREPARATION | SF | 28,500 | $ - 0 | $ - 0 |
| 26 | P-620-5 | SURFACE PAINTED HOLD POSITION SIGN | EA | 4 | $ - 0 | $ - 0 |
| 27 | P-620-6 | PAVEMENT MARKING REMOVAL | SF | 4,000 | $ - 0 | $ - 0 |
| 28 | FP-100-1 | SURVEY, BORROW MATERIAL, RE-GRADING AND SOD AT 5,000 FT RUNWAY DISTANCE REMAINING SIGN | LS | 1 | $ - 0 | $ - 0 |
| 29 | D-701-1 | CONSTRUCT 19"X30" ERCP, CLASS V | LF | 428 | $ - 0 | $ - 0 |
| 30 | D-701-2 | CONSTRUCT 19"X30" MITERED END SECTION | EA | 1 | $ - 0 | $ - 0 |
| 31 | D-751-1 | FDOT TYPE D INLET | EA | 2 | $ - 0 | $ - 0 |
| 32 | T-904-1 | SODDING | SY | 27,600 | $ - 0 | $ - 0 |
TAXIWAY P3 AND P4 IMPROVEMENTS
BID FORM
(CONTINUED)
BIDDER:
| INDEX | PAY ITEM | DESCRIPTION | UNIT | QUANTITY | UNIT PRICE | EXTENSION |
| 33 | SP-104-1 | TEMPORARY POWER & TEMPORARY AIRFIELD LIGHTING/SIGNAGE/ NAVIGATIONAL FACILITIES | LS | 1 | $ - 0 | $ - 0 |
| 34 | SP-105-1 | ELECTRICAL DEMOLITION | LS | 1 | $ - 0 | $ - 0 |
| 35 | L-108-1 | 1/C L-824-TYPE C - UNSHIELDED #8 AWG 5KV STRANDED COPPER CABLE, INSTALLED IN DUCT OR CONDUIT - BLACK INSULATED | LF | 18,000 | $ - 0 | $ - 0 |
| 36 | L-108-2 | 1/C L-824-TYPE C - UNSHIELDED #8 AWG 5KV STRANDED COPPER CABLE, INSTALLED IN DUCT OR CONDUIT - RED INSULATED | LF | 1,500 | $ - 0 | $ - 0 |
| 37 | L-108-3 | 1/C #2 AWG SOLID COPPER COUNTERPOISE CABLE, INSTALLED OVER DUCT OR CONDUIT | LF | 8,500 | $ - 0 | $ - 0 |
| 38 | L-108-4 | 0.75" DIAMETER BY 10.00' LONG COPPER CLAD STEEL SECTIONAL GROUND ROD | EA | 280 | $ - 0 | $ - 0 |
| 39 | L-108-5 | FIELD LIGHTNING ARRESTOR | EA | 8 | $ - 0 | $ - 0 |
| 40 | L-110-1 | 1 WAY 2" SCHEDULE 40 PVC DIRECT EARTH BURIED DUCT | LF | 5,000 | $ - 0 | $ - 0 |
| 41 | L-110-2 | 2 WAY 2" SCHEDULE 40 PVC DIRECT EARTH BURIED DUCT | LF | 1,100 | $ - 0 | $ - 0 |
| 42 | L-110-3 | 2 WAY 4" SCHEDULE 40 PVC DIRECT EARTH BURIED DUCT | LF | 350 | $ - 0 | $ - 0 |
| 43 | L-110-4 | 1 WAY 2" SCHEDULE 40 PVC CONCRETE ENCASED DUCT | LF | 500 | $ - 0 | $ - 0 |
| 44 | L-110-5 | 4 WAY 2" SCHEDULE 40 PVC CONCRETE ENCASED DUCT | LF | 400 | $ - 0 | $ - 0 |
| 45 | L-110-6 | 1 WAY 4" SPLIT DUCT | LF | 1,000 | $ - 0 | $ - 0 |
| 46 | L-115-1 | FAA AIRCRAFT RATED DOGHOUSE ELECTRICAL MANHOLE TYPE A-1 | EA | 4 | $ - 0 | $ - 0 |
| 47 | L-115-2 | JUNCTION CAN PLAZA - TWO L-867D CANS | EA | 2 | $ - 0 | $ - 0 |
| 48 | L-115-3 | JUNCTION CAN PLAZA - FOUR L-867D CANS | EA | 4 | $ - 0 | $ - 0 |
| 49 | L-125-1 | L-804(L) ELEVATED RUNWAY GUARD LIGHT YELLOW (T) | EA | 4 | $ - 0 | $ - 0 |
| 50 | L-125-2 | L-850C(L) RUNWAY EDGE LIGHT - CLEAR/CLEAR (RE) | EA | 1 | $ - 0 | $ - 0 |
| 51 | L-125-3 | L-850C(L) RUNWAY EDGE LIGHT - CLEAR/CLEAR (A) | EA | 2 | $ - 0 | $ - 0 |
| 52 | L-125-4 | L-858(L) SIGN - SINGLE/DOUBLE FACE, LED, SIZE 3 - 2 MODULE | EA | 6 | $ - 0 | $ - 0 |
| 53 | L-125-5 | L-858(L) SIGN - SINGLE/DOUBLE FACE, LED, SIZE 3 - 3 MODULE | EA | 7 | $ - 0 | $ - 0 |
| 54 | L-125-6 | L-858(L) SIGN - SINGLE/DOUBLE FACE, LED, SIZE 3 - 4 MODULE | EA | 2 | $ - 0 | $ - 0 |
| 55 | L-125-7 | L-858B(L) RELOCATE RUNWAY DISTANCE REMAINING SIGN | EA | 1 | $ - 0 | $ - 0 |
| 56 | L-125-8 | L-861T(L) OMNIDIRECTIONAL, BLUE, LED, TAXIWAY EDGE LIGHT (A) | EA | 4 | $ - 0 | $ - 0 |
| 57 | L-125-9 | L-861T(L) OMNIDIRECTIONAL, BLUE, LED, TAXIWAY EDGE LIGHT (T) | EA | 75 | $ - 0 | $ - 0 |
| 58 | L-125-10 | L-861T(L) OMNIDIRECTIONAL, BLUE, LED, TAXIWAY EDGE LIGHT (NE) | EA | 18 | $ - 0 | $ - 0 |
| TOTAL BID PRICE | $ - 0 |