Exhibit F - Specifications Sections 01560 and 01710.pdf
PDF 454 KB Posted
- Attached to
- Rapid Infiltration Basins (RIBS) Rehabilitation: Three-Year Phasing State and local contract opportunity
- Solicitation number
- 145460
- Issued by
- Osceola County, Florida
About this file
This file consists of two specification sections for Solicitation No. ITB-C007144 issued by the Central Florida Tourism Oversight District (CFTOD) for the Rapid Infiltration Basins (RIBS) Rehabilitation project covering fiscal years 2027, 2028, and 2029. Section 01560 addresses erosion control and dewatering requirements, while Section 01710 covers cleaning and site maintenance standards. The contractor must prepare a Storm Water Pollution Prevention Plan (SWPPP) using CFTOD templates and submit it for CFTOD Planning and Engineering review, which requires 30 days for initial review and revision requests. When work occurs within active waterbodies or within 15 feet of the top slope of waterbodies, the contractor must develop a Turbidity Control Plan with detailed best management practices and provide full-depth turbidity curtains. Dewatering permits must be obtained through CFTOD Planning and Engineering with approval from the South Florida Water Management District (SFWMD), and no dewatering may commence until written approval is received.
The contractor bears responsibility for all erosion control devices, maintenance, and environmental compliance throughout the project. If dewatering extends longer than two weeks near wetlands, a professional geotechnical engineer licensed in Florida must provide a wetland rehydration analysis considering normal and seasonal water elevations. Similarly, if dewatering occurs within 1,000 feet of known contamination areas, an engineered analysis must document that plume migration will not occur, with all SFWMD-required monitoring conducted at the contractor's expense. Regarding cleaning obligations, the contractor must maintain the job site and surrounding public properties free of waste and debris throughout construction, conduct final cleaning including removal of all materials and restoration of surfaces to specified condition, and arrange legal disposal of all waste materials off-site. The contractor must wet down materials to control dust, schedule operations to prevent contamination of newly painted surfaces, and leave the site clean and ready for occupancy. If the contractor fails to comply with cleaning requirements, the owner reserves the right to perform cleanup work and deduct costs from monies due to the contractor.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| CENTRAL FLORIDA TOURISM OVERSIGHT PSSP REQUIREMENTS .pdf | ||
| Affidavit of Eligibility Form - Opportunity Zone Program v.12.25.pdf | ||
| Affidavit of Eligibility Form - Buy Local or Veteran Small Business Program 12.25.pdf | ||
| Exhibit C- As-Builts.pdf | ||
| Bidder Requirements Checklist v.3.pdf | ||
| CFTOD Insurance Requirements v. 12.25.pdf | ||
| Exhibit B - Aerial Maps.pdf | ||
| SAMPLE - Services Agreement.pdf | ||
| Foreign Countries of Concern and Human Trafficking Affidavit.pdf | ||
| ITB Exhibit A - Scope of Services.pdf | ||
| Conflict of Interest and Public Entity Crime Affidavit 1.26.pdf | ||
| General Terms and Conditions 07.21.25.pdf | ||
| Florida Trench Safety Act Form v.12.25.pdf | ||
| Exhibit D- Project - Client Reference Form v.12.25.pdf | ||
| Exhibit E- Subcontractor List v.12.25 (1).pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT F
SPECIFICATIONS SECTIONS
SOLICITATION NO.: ITB-C007144
SOLICITATION TITLE: Rapid Infiltration Basins (RIBS) Rehabilitation for Fiscal Years 2027, 2028, and 2029
DOCUMENT TITLE:
SECTION 01560- EROSION CONTROL AND DEWATERING
SECTION 01710- CLEANING
IMPORTANT NOTICE
This Exhibit is incorporated into and made part of the solicitation documents. Bidders/Proposers shall review all information and shall consider the requirements of this Exhibit when preparing and submitting their response.
Section 01560
Erosion Control and Dewatering
CENTRAL FLORIDA TOURISM OVERSIGHT DISTRICT
August 25, 2026
01560-1
SECTION 01560
EROSION CONTROL AND DEWATERING
PART 1 – GENERAL
1.01 Erosion Control
A. Refer to Contract Drawings and Bid Manual.
B. Refer to following list of documents attached with this section.
1. SWPPP: The Contractor shall prepare the Storm Water Pollution Prevention Plan utilizing the template forms published by Central Florida Tourism Oversight District Planning &
Engineering Department. The Contractor shall submit a completed SWPPP to CFTOD Planning and Engineering for review and the Contractor shall make all modifications and refinements to the plan requested by CFTOD Planning and Engineering. Contractor shall be advised CFTOD
Planning and Engineering has 30 days to review SWPPP submittals, including both initial submittal and any request for additional information submittal. Contractors shall plan accordingly. The Contractor shall provide the erosion control devices required by the plan and shall maintain them in accordance with Section 01010 until the punch list is certified to be complete. Rev. October 3, 2019
2. Turbidity Control Plan: When a contractor is working within an active waterbody or within 15 feet of the top of slope (a.k.a the low maintenance zone) of an active waterbody (including lakes, canals, etc.) the Contractor shall be required to create a Turbidity Control Plan providing detailed information regarding means and methods and best management practices to prevent, contain and treat turbidity as may be encountered and generated during the course of work.
This can also include items such as sheet pile information, bypass pumping, etc. that may be required to manage flow during course of work. Contractor shall be advised CFTOD Planning and Engineering has 30 days to review Turbidity Control Plan submittals, including both initial submittal and any request for additional information submittal. Contractors shall plan accordingly.
3. Turbidity Curtains: The Contractor shall provide full depth turbidity curtains wherever required by its approved SWPPP.
4. De-watering: The Contractor shall apply for a de-watering permit(s) through CFTOD Planning and Engineering. Contractor shall be advised CFTOD Planning and Engineering has 30 days to review dewatering submittals, including both initial submittal and any request for additional information submittal. Contractors shall plan accordingly. In addition, Contractors shall be aware that SFWMD has additional review time for dewatering approvals. CFTOD Planning and Engineering shall perform all SFWMD coordination, contractors will be notified of any request for additional information or approval via final dewatering approval. The Contractor shall not begin dewatering activities until CFTOD Planning and Engineering has approved the proposed activities. The list of Submittal Information required by CFTOD P&E for SFWMD follows this Section of the specifications.
a. If any de-watering activity occurs adjacent to a wetland and extends longer than two weeks, then the Contractor shall provide an analysis engineered by a professional geotechnical engineer licensed to do business in the State of Florida that provides for wetland rehydration processes and monitoring. Further, the analysis shall consider the normal pool and seasonal high water elevations of any wetlands and surface waters adjacent to the proposed dewatering activities.
b. If any de-watering activity occurs near a known area of contamination (within 1000 feet), then the Contractor shall provide an analysis engineered by a professional geotechnical engineer licensed to do business in the State of Florida that provides sufficient documentation that any plume will not be adversely impacted or caused to
Section 01560
Erosion Control and Dewatering
CENTRAL FLORIDA TOURISM OVERSIGHT DISTRICT
August 25, 2026
01560-2 migrate as a result of the proposed dewatering activities. In addition, any monitoring required by SFWMD during dewatering activities shall also be at the Contractor’s sole expense.
C. The Contractor shall prepare and submit the NOI (when required) to Owner and CFTOD Planning and Engineering for review. Only after CFTOD Planning and Engineering has reviewed and approved the draft NOI, shall the Contractor submit the NOI to FDEP and pay the filing fee.
END OF SECTION 01560
Section 01710
Cleaning
CENTRAL FLORIDA TOURISM OVERSIGHT DISTRICT
August 25, 2026
01710-1
SECTION 01710
CLEANING
PART 1 - GENERAL
1.01 DESCRIPTION
A. Maintain job site, surrounding areas, and public properties free from improperly stored materials, accumulations of waste, debris, and rubbish caused by operations.
B. At completion of Work, remove waste materials, rubbish, tools, equipment, machinery, surplus materials, and clean all sight-exposed surfaces. Leave job site clean and ready for occupancy.
PART 2 - PRODUCTS
2.01 MATERIALS
A. Use only cleaning materials recommended by manufacturer of materials of surface to be cleaned.
B. Use cleaning materials only on surfaces recommended by cleaning material manufacturer.
PART 3 - EXECUTION
3.01 CLEANING - GENERAL
A. Cleaning and disposal:
1. Conduct cleaning and disposal operations in accord with legal requirements.
2. Do not burn or bury rubbish and waste materials on job site. Do not dispose of volatile wastes such as mineral spirits, oil, or paint thinner in storm or sanitary drains.
B. Burning:
1. Burning of the trees, shrubs, bushes, etc., cleared on the project site will not be allowed within the project site.
C. Hazards control:
1. Store volatile wastes in covered metal containers, and remove from premises daily.
2. Prevent accumulation of wastes which create hazardous conditions.
3. Provide adequate ventilation during use of volatile or noxious substances.
3.02 CLEAN-UP DURING CONSTRUCTION
A. Execute cleaning to ensure job site, premises, adjacent and public properties are maintained free from accumulations of waste materials and rubbish.
B. Wet down dry materials and rubbish to lay dust.
C. At reasonable intervals during progress of Work, clean job site and public properties, and dispose of waste materials, debris and rubbish.
D. Provide dump containers on job site for collection of waste materials, debris and rubbish.
Section 01710
Cleaning
CENTRAL FLORIDA TOURISM OVERSIGHT DISTRICT
August 25, 2026
01710-2
1. Permit Owner's other contractors to place waste materials, debris and rubbish in containers provided by this Contractor.
E. Remove waste materials, debris and rubbish from job site, premises, adjacent and public properties and legally dispose of at public or private dumping areas off Walt Disney World property.
F. Handle materials in a controlled manner with as few handlings as possible. Do not drop or throw materials from height.
G. Schedule cleaning operations so that dust and other contaminants resulting from cleaning process will not fall on wet, newly painted surfaces.
3.03 FINAL CLEANING
A. In preparation for substantial completion or occupancy, conduct final inspection of sight-exposed interior and exterior surfaces, and of concealed spaces.
B. Remove grease, dust, dirt, stains, labels, furniture, fingerprints, and other foreign materials, from sight-exposed interior and exterior finished surfaces.
1. Clean and polish all factory finished surfaces such as plastic laminate, plated metals, stainless steel, and factory baked-on enamel surfaces.
C. Repair, patch and touch-up marred surfaces to specified finish, and to match adjacent surfaces as appropriate.
D. Broom clean paved surfaces; rake clean other surfaces of grounds.
E. Owner will assume responsibility for cleaning as of time designated on Certificate of Substantial
Completion for Owner's acceptance of project or portion thereof.
3.04 GENERAL REQUIREMENTS
A. If the Contractor fails to comply with the requirements of this Article, in the opinion of the Owner, the Owner shall perform the necessary clean-up and deduct the cost of work from the monies due or to become due to said Contractor.
END OF SECTION 01710
File details come from the government source that posted it. Updated .