Exhibit F_Preliminary Project Schedule_01042023.pdf

PDF 166 KB Posted

Attached to
OLCC Warehouse and Headquarters Relocation
Solicitation number
S-10700-00005334
Issued by
Clackamas County, Canyonville City, Oregon

About this file

This document is a preliminary project schedule for the OLCC (Oregon Liquor and Cannabis Commission) Headquarters Warehouse Project. The project timeline covers the design, permitting, CM/GC (Construction Manager/General Contractor) selection, preconstruction services, and the 16-month construction phase from 2023 to 2025. Key milestones include design reviews, public hearings, land use approval, permitting, CM/GC selection and contracting, preconstruction cost validation, and the construction phase. The project is located in Marion County and the City of Salem, Oregon.

The project schedule outlines the timeline for design development, construction documentation, building permit planning, furniture design and contracting, and commissioning and testing. The CM/GC preconstruction services and GMP (Guaranteed Maximum Price) are scheduled to take place over 14-16 weeks for schematic design, 18 weeks for design development, and 18 weeks for construction documentation.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OLCC HQ Warehouse Project Milestone Schedule

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP

Upcoming Key

Decision Points

Design

Material Handling Design

Employee Engagement

Public Hearings

Public Involvement

Land Use Approval

Permitting

CM/GC Selection and Contracting

Preconstruction

Cost Validation by Architech

Third Party Procurement

Construction

2023 2024 Updated: 01/06/2023

RFP & Contracting

Construction (16) Months

CMGC Preconstruction Services

GMP

SD (14-16) wks DD (18) wks CD (18) wks

Building Permit

Planning Commission

Furniture Design & Contract

Move

Commissio ning & Conveyor/ ERP testing

Neighborhood Meeting

Land Use Process (16) wks

Utility Design (6-8) weeks

100% SD 50% DD 50% CD

Neighborhood Meeting segger Image