Exhibit F_Preliminary Project Schedule_01042023.pdf
PDF 166 KB Posted
- Attached to
- OLCC Warehouse and Headquarters Relocation
- Solicitation number
- S-10700-00005334
- Issued by
- Clackamas County, Canyonville City, Oregon
About this file
This document is a preliminary project schedule for the OLCC (Oregon Liquor and Cannabis Commission) Headquarters Warehouse Project. The project timeline covers the design, permitting, CM/GC (Construction Manager/General Contractor) selection, preconstruction services, and the 16-month construction phase from 2023 to 2025. Key milestones include design reviews, public hearings, land use approval, permitting, CM/GC selection and contracting, preconstruction cost validation, and the construction phase. The project is located in Marion County and the City of Salem, Oregon.
The project schedule outlines the timeline for design development, construction documentation, building permit planning, furniture design and contracting, and commissioning and testing. The CM/GC preconstruction services and GMP (Guaranteed Maximum Price) are scheduled to take place over 14-16 weeks for schematic design, 18 weeks for design development, and 18 weeks for construction documentation.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OLCC HQ Warehouse Project Milestone Schedule
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP
Upcoming Key
Decision Points
Design
Material Handling Design
Employee Engagement
Public Hearings
Public Involvement
Land Use Approval
Permitting
CM/GC Selection and Contracting
Preconstruction
Cost Validation by Architech
Third Party Procurement
Construction
2023 2024 Updated: 01/06/2023
RFP & Contracting
Construction (16) Months
CMGC Preconstruction Services
GMP
SD (14-16) wks DD (18) wks CD (18) wks
Building Permit
Planning Commission
Furniture Design & Contract
Move
Commissio ning & Conveyor/ ERP testing
Neighborhood Meeting
Land Use Process (16) wks
Utility Design (6-8) weeks
100% SD 50% DD 50% CD
Neighborhood Meeting segger Image
File details come from the government source that posted it. Updated .