About this file
This document is a Build America, Buy America (BABA) information and certification exhibit provided by the County of Volusia Community Assistance for the Deland Regional Library Play Yard Walkway project (ITB No. 26-B-55JS). The BABA requirements apply to all federally funded infrastructure projects, including those funded through Community Development Block Grant (CDBG) sources. The document defines infrastructure projects as rehabilitation, maintenance, and reconstruction of buildings and real property, as well as construction and repair of public facilities such as water, sewer, utilities, parks, roads, and sidewalks. The file includes a pre-construction BABA Pre-Certification form that must be completed by the primary contractor following the pre-construction meeting before work begins, and a post-completion BABA Certification form that must be submitted before final payment is dispersed. Both forms may be required from all subcontractors as well.
The phased implementation of BABA requirements is based on the fiscal year in which funds were obligated. For FY 2023/24, contractors must verify that iron and steel are U.S.-manufactured. For FY 2024/25, non-ferrous metals, lumber, and plastic- and polymer-based composite building materials, pipes, and tubes must also be U.S.-produced. For FY 2025/26, additional materials including all other plastic- and polymer-based products, glass, fiber optic cable, optical fiber, engineered wood, and drywall must meet U.S. manufacturing requirements. Supporting documentation such as invoices and receipts must be provided with each certification to verify that all required materials were produced in the United States. The certification forms require contractors to identify all materials to be purchased for the project, whether those materials will be obtained, whether they will be U.S.-manufactured, and to list all planned or actual manufacturers used.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
County of Volusia Community Assistance
121 W. Rich Avenue DeLand, FL 32720
Build America, Buy America (BABA) Information
What is Build America, Buy America (BABA)?
The Build America, Buy America Act (BABA) requires that all iron, steel, manufactured products, and construction materials used for federally funded infrastructure projects are produced in the United States, unless otherwise exempt or subject to an approved waiver. This requirement is known as the “Buy America Preference (BAP)”.
When does BABA apply to projects?
The Build America, Buy America Act (BABA) applies to all federally funded infrastructure projects. The Community Development Block Grant (CDBG) is a federal funding source and BABA would apply for all infrastructure project funded with CDBG. If additional funding sources are being used, the entire project must meet BABA requirements if any federal funding source is being utilized.
What is considered an infrastructure project?
The following are considered infrastructure projects according to BABA:
• Rehabilitation, maintenance, and reconstruction of buildings and real property, including housing
• Construction and repair of public facilities and improvements, such as water, sewer, or other utilities, parks, roads, bridges, sidewalks, homeless shelters, or broadband infrastructure
Do all materials have to be manufactured in the United States?
The U.S. Department of Housing and Urban Development (HUD) is requiring that BABA be met in phases to assist with the current transition. The phases are based on the year the funds were obligated. If you are unsure which fiscal year the funds were obligated for your project, reach out to the city you were awarded by or CDBG@volusia.org.
Obligated Fiscal Year Materials that must follow BABA
FY 2023/24 • Iron
• Steel
FY 2024/25
• Non-ferrous metals
• Lumber
• Plastic- and polymer-based composite building materials, pipes, and tubes
FY 2025/26
• All other plastic- and polymer-based products
• Glass
• Fiber optic cable
• Optical fiber
• Engineered wood
• Drywall
What information is required for BABA reporting?
For Community Development funded infrastructure projects, the following is required:
• BABA Certification form
• Supporting documentation to show that all required materials were produced in the United States o Invoices, receipts, etc.
The form to be completed by the contractor is subject to change as additional information is provided by HUD.
C2074 26-B-55JS
121 W. Rich Avenue DeLand, FL 32720
Build America, Buy America (BABA) Pre-Certification This document must be completed and returned from the primary contactor following the pre-construction meeting before work begins. An additional certification must be submitted once work has been completed before final payment will be dispersed. This document may be required from all sub-contractors as well.
Project Name:
Agency Name:
Material Will this material be purchased for the project?
Will the purchased material be produced in the United States?
Manufacturers (List all planned to utilize)
Iron Yes No Yes No
Steel Yes No Yes No
Non-ferrous metals Yes No Yes No
Lumber Yes No Yes No
Plastic- and polymer-based composite building materials, pipes, and tubes
Yes No Yes No
All other plastic- and polymer-based products Yes No Yes No
Glass Yes No Yes No
Fiber optic cable Yes No Yes No
Optical fiber Yes No Yes No
Engineered wood Yes No Yes No
Drywall Yes No Yes No
I certify to the best of my knowledge that the information contained here within is true and correct.
Print name:
Signature: Date:
Title:
DELAND REGIONAL LIBRARY PLAY YARD WALKWAY
121 W. Rich Avenue DeLand, FL 32720
Build America, Buy America (BABA) Certification This document must be completed and returned from the primary contactor following completion of all on-site work, prior to the final invoice submission. This document may be required from all sub-contractors as well.
Project Name:
Agency Name:
Material Was this material purchase for the specified project?
Was the purchased material produced in the United States?
Manufacturers (List all used)
Iron Yes No Yes No
Steel Yes No Yes No
Non-ferrous metals Yes No Yes No
Lumber Yes No Yes No
Plastic- and polymer-based composite building materials, pipes, and tubes
Yes No Yes No
All other plastic- and polymer-based products Yes No Yes No
Glass Yes No Yes No
Fiber optic cable Yes No Yes No
Optical fiber Yes No Yes No
Engineered wood Yes No Yes No
Drywall Yes No Yes No
Attach supporting documentation (invoices, receipts, etc.) to verify the above information when this form is submitted.
I certify to the best of my knowledge that the information contained here within is true and correct.
Print name:
Signature: Date:
Title:
DELAND REGIONAL LIBRARY PLAY YARD WALKWAY
| undefined: Off |
| undefined_2: Off |
| Manufacturers List all planned to utilizeYes No: |
| undefined_3: Off |
| undefined_4: Off |
| Manufacturers List all planned to utilizeYes No_2: |
| undefined_5: Off |
| undefined_6: Off |
| Manufacturers List all planned to utilizeYes No_3: |
| undefined_7: Off |
| undefined_8: Off |
| Manufacturers List all planned to utilizeYes No_4: |
| undefined_9: Off |
| undefined_10: Off |
| Manufacturers List all planned to utilizeYes No_5: |
| undefined_11: Off |
| undefined_12: Off |
| Manufacturers List all planned to utilizeYes No_6: |
| undefined_13: Off |
| undefined_14: Off |
| Manufacturers List all planned to utilizeYes No_7: |
| undefined_15: Off |
| undefined_16: Off |
| Manufacturers List all planned to utilizeYes No_8: |
| undefined_17: Off |
| undefined_18: Off |
| Manufacturers List all planned to utilizeYes No_9: |
| undefined_19: Off |
| undefined_20: Off |
| Manufacturers List all planned to utilizeYes No_10: |
| undefined_21: Off |
| undefined_22: Off |
| Manufacturers List all planned to utilizeYes No_11: |
| Print name: |
| Date: |
| Title: |
| work prior to the final invoice submission This document may be required from all subcontractors as well 1: |
| work prior to the final invoice submission This document may be required from all subcontractors as well 2: |
| undefined_23: Off |
| undefined_24: Off |
| Manufacturers List all usedYes No: |
| undefined_25: Off |
| undefined_26: Off |
| Manufacturers List all usedYes No_2: |
| undefined_27: Off |
| undefined_28: Off |
| Manufacturers List all usedYes No_3: |
| undefined_29: Off |
| undefined_30: Off |
| Manufacturers List all usedYes No_4: |
| undefined_31: Off |
| undefined_32: Off |
| Manufacturers List all usedYes No_5: |
| undefined_33: Off |
| undefined_34: Off |
| Manufacturers List all usedYes No_6: |
| undefined_35: Off |
| undefined_36: Off |
| Manufacturers List all usedYes No_7: |
| undefined_37: Off |
| undefined_38: Off |
| Manufacturers List all usedYes No_8: |
| undefined_39: Off |
| undefined_40: Off |
| Manufacturers List all usedYes No_9: |
| undefined_41: Off |
| undefined_42: Off |
| Manufacturers List all usedYes No_10: |
| undefined_43: Off |
| undefined_44: Off |
| Manufacturers List all usedYes No_11: |
| Print name_2: |
| Date_2: |
| Title_2: |
| Project Name: |
| Agency Name: |