Exhibit E - Cost Summary.xlsx
XLSX spreadsheet 22 KB Posted
- Attached to
- Hope Coliseum AC-4 Replacement
- Solicitation number
- RFP202790000749
- Issued by
- West Virginia
About this file
This is a Cost Summary exhibit for the Hope Coliseum AC-4 Replacement project in West Virginia. The project involves the removal of an existing indoor packaged HVAC Unit AC-4 located within the mechanical mezzanine ring of Hope Coliseum and its replacement with a contractor-furnished HVAC unit. The selected proposer must complete all work and billing by May 14, 2027, and is responsible for demolition of the existing unit, supply and installation of the new AC-4 unit, all connections to power, gas, vents, drains, and controls, as well as startup and balancing in coordination with the owner. The proposer must also provide protection for all existing conditions during equipment removal and installation.
The cost summary requires proposers to submit a total base cost as a lump-sum, all-inclusive amount. The form provides detailed breakout sections for labor rates categorized by position (supervisor and laborer classifications) and work type (standard hours, non-standard hours, and holidays/Sundays), with rates calculated on an hourly basis inclusive of all burden. Additional cost sections address subcontractor markups, consumable materials, individual items exceeding $999.99, and equipment costs where required. Proposers must supply the company name, address, authorized personnel signature, email, and phone number on the form.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1 Exhibit E - Cost Summary
| Supplier (Company Name and Address) | |
| ( ) | |
| Phone |
| Print: Authorized Personnel | Signature |
| Base Cost | |
| The successful Proposer will be required to have all work completed and billed in full by May 14, 2027. The selected Proposer will be responsible for the demolition of the existing AC-4 unit located within the mechanical mezzanine ring located in the Hope Coliseum. The selected Proposer will supply and install the required new AC-4 unit within the existing space. The selected Proposer will be responsible for all connections of the new unit to power, gas, vents, drains, and controls. The selected Proposer will include startup and balancing of the new unit in coordination with Owner. Selected Proposer is required to provide protection for all existing conditions while removing and installing HVAC equipment. |
Total Base Cost (Total ALL Inclusive, Lump Sum): $_______________________
Breakout (For informational purposes)
| Item | Labor Rates (based on normal standard hours) | UOM | Rate per Hour | |
| 1 | Supervisor (Inclusive of all burden) Standard Hours - per man | Hour | ||
| 2 | Supervisor (Inclusive of all burden) Non-Standard Hours - per man | Hour | ||
| 3 | Supervisor (Inclusive of all burden) Holidays & Sundays - per man | Hour | ||
| 4 | Laborer: (Inclusive of all burden) Standard Hours - per man | Hour | ||
| 5 | Laborer: (Inclusive of all burden) Non-Standard Hours - per man | Hour | ||
| 6 | Laborer: (Inclusive of all burden) Holidays & Sundays - per man | Hour | ||
| 7 | Laborer 2 Standard Hours - per man IF REQUIRED | Hour | ||
| 8 | Laborer 2 Non-Standard Hours - per man IF REQUIRED | Hour | ||
| 9 | Laborer 2 (Inclusive of all burden) Holidays & Sundays - per man IF REQUIRED | Hour | ||
| 10 | Laborer 3 Standard Hours - per man IF REQUIRED | Hour | ||
| 11 | Laborer 3 Non-Standard Hours - per man IF REQUIRED | Hour | ||
| 12 | Laborer 3 (Inclusive of all burden) Holidays & Sundays - per man IF REQUIRED | Hour | ||
| TOTAL Aggregate Labor | Qty | UOM | TOTAL per UOM | |
| TOTAL Aggregate Labor Cost for Entire Project | 1 | LOT |
| No. | Subcontractor if required (add as needed) | % Markup | Cost per UOM | |
| 1 | Subcontractor name | |||
| 2 | Subcontractor name | |||
| No. | Materials (add lines as needed) | Qty | UOM | TOTAL per UOM |
| 1 | Total Lump Sum for all Consumable Materials | 1 | LOT | |
| 2 | Any item that is over $999.99 (not included in Unit Pricing) | 1 | EACH | |
| 3 | Any item that is over $999.99 (not included in Unit Pricing) | 1 | EACH | |
| No. | Equipment (list only if required) | Qty | UOM | TOTAL per UOM |
| 1 | List Equip #1 | 1 | LOT | |
| 2 | List Equip #2 | 1 | LOT |