This is a Scope of Services document from West Virginia University (WVU) for the removal and replacement of an existing indoor packaged HVAC Unit (AC-4) located in Hope Coliseum on the WVU campus in Morgantown, West Virginia. WVU is requesting proposals from qualified mechanical contractors to provide a direct replacement unit with all necessary materials, labor, tools, and equipment for connection to existing power, control wiring, piping, and ducts. The project involves removal of one HVAC unit and installation of one replacement unit. The HVAC unit must be ordered and released for production no later than December 31, 2026, with receipt and readiness for installation prior to work commencing on April 5, 2027. Substantial Completion is required by April 16, 2027, and Final Completion with final invoicing must occur no later than May 14, 2027. No specific response deadline, bidder's conference, or site visit information is provided in this document.
The scope of work requires the contractor to provide comprehensive services including crane and rigging, surface protection, isolation and disconnection of existing utilities, installation review with the owner, relocation of existing piping and ductwork, provision of necessary fittings and shutoff valves, disassembly and reassembly as needed, new drain pans, connection of new unit to existing services, reinstallation of smoke detection equipment, manufacturer-coordinated start-up, operational verification and functional testing, leak inspection, and final cleaning. The contractor is responsible for all material quality, quantities, labor, equipment, deliveries, and shipping. Work must be coordinated with WVU Athletics and the WVU Project Manager to minimize impact on facility operations, with after-hours and weekend work required at no additional cost if necessary to maintain the schedule. The contractor must comply with all WVU policies, provide photo identification for personnel, maintain site security and cleanliness, and is prohibited from recording, photographing, or sharing any project information through social media or other electronic means. No specific pricing information, set-asides, incumbent information, or funding sources are detailed in this Scope of Services document.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Exhibit A – Scope of Services
INTRODUCTION
West Virginia University (“WVU”, or within this document “Owner”) is requesting Proposals from qualified mechanical contractors to remove the existing indoor packaged HVAC Unit AC-4 and replace with Contractor furnished replacement HVAC Unit within Hope Coliseum, located on the campus of West Virginia University in Morgantown, WV.
The basis for this RFP document is for the Proposer (referred to herein also as “Supplier”) to provide all material, labor, tools, and equipment necessary to replace a quantity of one
(1) HVAC Unit (AC-4). The new unit is a direct replacement for the existing unit and will require connection to existing power, control wiring, piping, and ducts.
Supplier shall provide all materials, labor, tools, and equipment to complete the project as described herein, in accordance with industry standards and with the standard of care required.
SCHEDULE
All work schedules shall be coordinated prior to mobilization with WVU Athletics’ use of the facility and the WVU Project Manager. Work shall commence on or about April 5, 2027, and reach Substantial Completion as summarized below. Time is of the essence; it is imperative that Substantial Completion be achieved on or before the dates shown:
• HVAC Unit ordered and released for production no later than December 31, 2026.
Unit must be received and ready for installation prior to work beginning on April 5, 2027.
• AC-4 Substantial Completion April 16, 2027
• Final Completion and final invoice for payment sent to WVU Payment Services no later than May 14, 2027
EXISTING CONDITIONS
Hope Coliseum houses a 12,000 + seat arena with concourse, various team/training spaces on the event level, and multiple sport offices on the second level. The mechanical ring is located above the office level and is accessed through various mechanical spaces around the office level. Parking and access to the facility shall be coordinated through the WVU Parking Office and the WVU Project Manager.
COORDINATION WITH OWNER’S USE
Coordination of the construction schedule, safety, and security of the students, staff, and public is of the highest priority. This project will be completed while the campus is occupied, with other scheduled events, camps, and activities ongoing at the facility.
The Supplier shall coordinate with WVU Athletics and WVU Project Manager to schedule equipment and material deliveries, access for unloading and loading, laydown, and staging areas.
The Supplier shall not block or impede access to roadways, walkways, building entrances, paths or otherwise unless coordinated in advance. The roadway and apron in front of the facility may be used for staging, deliveries and loading/offloading equipment with prior coordination and authorization with WVU Athletic Department and the WVU Project Manager. Supplier shall provide a flagman prior to and during all offloading, deliveries, etc., where vehicular traffic is impeded during normal business hours or other activities at the facility. The event schedule for Hope Coliseum will be shared with the awarded Supplier. The Supplier shall coordinate and schedule deliveries during off-hours and specifically not during scheduled events unless coordinated in advance.
Work periods and times may be affected based on scheduled events and/or modified schedules. The Supplier shall plan the work including, deliveries, manpower, equipment, etc., accordingly, to not impact events. This includes off-hour work when necessary to complete the intended Scope of Services without impact to the Owner’s use of the facility.
Supplier shall comply with all state, local, City of Morgantown, and WVU policies, procedures, and processes, and shall comply with all guidelines and standards for WVU Facilities and Services.
OWNER’S RESPONSIBILITIES
The Owner will provide card access and/or keys to Supplier’s Superintendent or Project Manager for access to all areas necessary for the duration of this project. Parking for Supplier’s staff shall be the responsibility of the Supplier to coordinate parking locations and any fees associated for the duration of this project with the WVU Parking Office.
GENERAL REQUIREMENTS
1. The selected Supplier shall work with WVU’s representatives and appointed outside parties, which may include but not limited to WVU Design and Construction Project Manager and other suppliers as necessary.
2. Supplier is responsible for material quality, material quantities, manpower/labor, equipment, deliveries, shipping, etc. included in the Supplier’s Scope as necessary to provide a fully operational unit as described herein.
3. Where necessary Supplier shall make provisions to maintain a clean ingress and egress path through these areas not to impede or conflict with the Owner or other supplier’s use of the adjacent facilities.
4. It is the Owner’s intent that all work described herein shall be completed in accordance with the schedule provided. The Supplier shall schedule, manage and maintain a consistent workforce onsite during the execution of this project to efficiently and effectively complete the work as necessary. Where it becomes necessary for the Supplier to work outside normal work hours to complete the Scope of Services, i.e., weekends, after-hours, etc., the Supplier shall do so at no additional cost to WVU to maintain the project schedule and meet the Substantial Completion Date.
5. The Supplier shall be responsible for any surface damage to all existing surfaces of and adjacent to the work of this project and shall provide repair/replacement at Owner’s discretion where damage is caused by this Supplier. Supplier shall provide protection of all laydown and staging areas specifically on concrete and asphalt pavement surfaces. Damage due to these surfaces shall result in replacement by the Supplier in its entirety at WVU’s discretion. This includes all roadways, walkways, elevators, interior/exterior spaces, electrical and mechanical spaces.
6. Daily cleaning of all work areas is required inclusive of all surfaces, adjacent support areas, pathways, and parking areas, leading to the work areas or access routes to the work areas.
The Supplier shall provide removal and disposal of all construction debris, including but not limited to packaging and construction debris, etc. When necessary, or when instructed by the Owner, Supplier shall provide cleanup and removal of all construction debris, tools, equipment, and job boxes to suit the use of the facility.
7. Supplier shall maintain secure work site, laydown and staging areas as necessary to prevent theft, vandalism, etc. When necessary or when requested by Owner, the Supplier shall provide fully connected chain link construction fencing. All fencing panels shall be securely connected using metal strapping or other, include post feet with sandbag weights at all panel ends. Perforated screening material shall be installed on all fencing to limit visibility of construction/laydown areas. Screening material may include Supplier’s logo/branding and must be approved by Owner prior to installation. Supplier shall be responsible for maintaining fencing/screening throughout the project.
8. Supplier shall comply with all campus and county wide policies, Tobacco Free policies, Sexual Harassment policies, etc. Supplier agrees to adhere to the WVU Supplier Code of Conduct as defined at: https://procurement.wvu.edu/files/d/79435143-86af-40da-a41f- 6b96e0d8b592/supplier-code-of-conduct.pdf
9. Because of the high profile of the facility and the work area, the security needs of the facilities, and the security and safety of the students, residents, staff, and other personnel, the following shall serve as security and safety requirements for the awarded Supplier’s use during the execution of this project:
https://procurement.wvu.edu/files/d/79435143-86af-40da-a41f-6b96e0d8b592/supplier-code-of-conduct.pdf https://procurement.wvu.edu/files/d/79435143-86af-40da-a41f-6b96e0d8b592/supplier-code-of-conduct.pdf
a. Supplier’s work force shall carry photo identification indicating the person’s name, company, and title from the Supplier. Photo ID shall be worn on the exterior and shall always be visible during the execution of this project.
b. The Supplier shall assign primary key holders, maximum of two (2), to be assigned key cards or keys for access into the facility. This may take as much as one (1) week to complete therefore the Supplier should submit the key holders contact information upon issuance of a contract.
c. Supplier shall be responsible for direct supervision of all direct and indirect personnel onsite during the project. This includes portions completed by sub-suppliers and/or sub-contractors regardless of Supplier’s own forces. The Supplier shall always have supervision on site while work is being conducted under this contract. The supervision shall be approved by the Owner.
d. Suppliers are discouraged from engaging with students, residents, staff, student-athletes, coaches, athletic staff, or other personnel during the project. Discussion of Contract parameters outside the Owner’s primary contact is prohibited.
e. All requests for news media, interviews, quotes, or other requests for information regarding the project, Contract, or any portion thereof shall be referred to WVU’s General Counsel, and University Relations departments media relations department through the WVU Project Manager.
f. The use of electronic devices for the purpose of recording data; photo, video, audio is prohibited during the execution of this project. At no time will it be acceptable to post, upload or share any form of data through social media platforms, video sharing software, websites, or other, of any portion of the execution of this project.
There is zero tolerance for noncompliance with this requirement, upon notification of the offense a WVU representative and/or Senior Associate Athletic Director of Athletic Facility Operations will request immediate removal of the offending party from the project site and will not permit return during the remainder of the project period.
SPECIFIC PROJECT REQUIREMENTS
1. The selected Supplier shall provide the following:
a. Crane and rigging as necessary to set the new unit as necessary.
b. Plywood or other protection for roofing, flooring or other surfaces as necessary.
c. Isolate unit as necessary and disconnect piping, duct, electrical, etc.
d. Review installation with Owner prior to execution of the work.
e. Relocate or adjust existing piping, insulation, duct, or other connections as necessary to facilitate removal/replacement.
f. Provide necessary pipe and/or duct fittings to suit/adapt to existing connections.
g. Where necessary replace or provide/install shutoff valves to isolate utilities for replacement.
h. Disassemble/reassemble units as necessary to move into place.
i. Provide new drain pans/drains under each new unit.
j. Provide material, labor, equipment, and tools to connect new unit to existing services, provide isolation valves where necessary. Include piping, ductwork, electrical, etc.
k. Reinstall/reconnect existing smoke detection equipment and verify operation.
Reconnect/adapt existing controls where necessary and applicable.
l. Perform start-up coordinated with manufacturer.
m. Check/verify correct operation and run through functional tests with Owner’s representative.
n. Check for leaks.
o. Perform final cleaning, remove construction debris and any protective materials.
p. Where necessary to remove louvers for installation, provide removal and reinstallation per manufacturer’s instructions.
| Exhibit A – Scope of Services |
| 1. The selected Supplier shall work with WVU’s representatives and appointed outside parties, which may include but not limited to WVU Design and Construction Project Manager and other suppliers as necessary. |
| 2. Supplier is responsible for material quality, material quantities, manpower/labor, equipment, deliveries, shipping, etc. included in the Supplier’s Scope as necessary to provide a fully operational unit as described herein. |
| 3. Where necessary Supplier shall make provisions to maintain a clean ingress and egress path through these areas not to impede or conflict with the Owner or other supplier’s use of the adjacent facilities. |
| 4. It is the Owner’s intent that all work described herein shall be completed in accordance with the schedule provided. The Supplier shall schedule, manage and maintain a consistent workforce onsite during the execution of this project to efficiently ... |
| 9. Because of the high profile of the facility and the work area, the security needs of the facilities, and the security and safety of the students, residents, staff, and other personnel, the following shall serve as security and safety requirements f... |
| 1. The selected Supplier shall provide the following: |
| a. Crane and rigging as necessary to set the new unit as necessary. |
| b. Plywood or other protection for roofing, flooring or other surfaces as necessary. |
| c. Isolate unit as necessary and disconnect piping, duct, electrical, etc. |
| d. Review installation with Owner prior to execution of the work. |
| e. Relocate or adjust existing piping, insulation, duct, or other connections as necessary to facilitate removal/replacement. |
| f. Provide necessary pipe and/or duct fittings to suit/adapt to existing connections. |
| g. Where necessary replace or provide/install shutoff valves to isolate utilities for replacement. |
| h. Disassemble/reassemble units as necessary to move into place. |
| i. Provide new drain pans/drains under each new unit. |
| j. Provide material, labor, equipment, and tools to connect new unit to existing services, provide isolation valves where necessary. Include piping, ductwork, electrical, etc. |
| k. Reinstall/reconnect existing smoke detection equipment and verify operation. Reconnect/adapt existing controls where necessary and applicable. |
| l. Perform start-up coordinated with manufacturer. |
| m. Check/verify correct operation and run through functional tests with Owner’s representative. |
| n. Check for leaks. |
| o. Perform final cleaning, remove construction debris and any protective materials. |
| p. Where necessary to remove louvers for installation, provide removal and reinstallation per manufacturer’s instructions. |