This file is an as-built plans and drawings exhibit for the West Virginia Army National Guard Camp Dawson located in Kingwood, West Virginia, specifically for the Pringle Training Site West Pond Sediment Remediation project. The document provides detailed construction specifications and requirements for demolition, grading, drainage, and erosion control operations at the site. Key project requirements include stripping and redistributing topsoil to a minimum depth of six inches across cut and fill areas, mulching and seeding all graded areas within 15 days of completion, constructing temporary erosion control measures prior to grading operations, and removing sediment from all drainage structures and detention ponds before final acceptance. The contractor must obtain all required permits, locate and mark existing utilities prior to commencing work, and coordinate with local utility companies for disconnections. All storm drainage pipe shall be 12-gauge Type II aluminized corrugated metal pipe, cut and fill slopes shall not exceed 3:1 gradient, and earthwork fill must be placed in maximum eight-inch compacted lifts at 98 percent density per ASTM D698 standards. An as-built set of plans must be submitted to the West Virginia Department of Environmental Protection upon completion of sedimentation basin construction.

The project is subject to West Virginia Department of Environmental Protection's General NPDES Permit requirements for storm water discharge associated with construction activity, as the work disturbs more than five acres. The contractor bears responsibility for all contractor-caused damage repairs at no additional cost to the owner, proper disposal of demolished materials in a legal manner, and removal of temporary erosion control devices when no longer required. Finish grade tolerances are established at 0.10 foot above or below design elevations, and the contractor must verify existing elevations and inverts prior to beginning work. Excess material must be disposed of on the owner's property at no additional cost in a legal manner. The document was prepared by a West Virginia registered engineer and dated June 8, 2010.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT D- AS-BUILT PLANS & DRAWINGS

(For informational purposes only)

**This is NOT a new design**

WEST VIRGINIA ARMY NATIONAL GUARD

CAMP DAWSON, KINGWOOD WV

Pringle Training Site

West Pond Sediment Remediation

D

C

B

A

DEMOLITION NOTES

1.

2.

3.

4.

5.

6.

DEMOLITION ANO REMOVAL OPERATIONS SHALL COMMENCE ONLY AFTER ALL EROSION ANO

SEDIMENTATION CONTROL MEASURES ARE IN PLACE ANO FUNCTIONAL.

ALL DEMOLISHED MATERIALS BECOME THE PROPERTY OF THE CONTRACTOR UNLESS OTHERWISE

DESIGNATED. DISPOSE OF OFF THE OWNER'S PROPERTY IN A LEGAL MANNER.

CONTRACTOR SHALL OBTAIN ALL PERMITS REQUIRED FOR EXECUTION OF THE WORK.

ALL ITEMS OF CONSTRUCTION REMAINING AND NOT SPECIFICALLY MENTIONED THAT

INTERFERE WITH THE NEW CONSTRUCTION SHALL BE IMMEDIATELY BROUGHT TO THE

ATTENTION OF THE ARCHITECT/ENGINEER.

CONTRACTOR SHALL PROVIDE PROTECTION TO ALL STREETS, FENCES, TREES, UTILITIES

ANO STRUCTURES THAT ARE TO REMAIN. CONTRACTOR-CAUSED DAMAGE SHALL BE REPAIRED

TO MATCH EXISTING AT NO ADDITIONAL COST TO THE OWNER.

CONTRACTOR SHALL LOCATE ANO MARK ALL EXISTING UTILITIES PRIOR TO COMMENCING

WORK. COORDINATE WITH LOCAL UTILITY COMPANIES PRIOR TO UTILITY DISCONNECT.

2 3

GRADING, DRAIN &: EROSION CONTROL NOTES

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

11.

NO TREES SHALL BE REMOVED NOR VEGETATION DISTURBED EXCEPT AS NECESSARY FOR

GRADING PURPOSES ANO ONLY AS APPROVED BY THE ARCHITECT/ENGINEER.

TOPSOIL SHALL BE STRIPPED FROM ALL CUT ANO FILL AREAS. STOCKPILED ANO REDISTRIB-

UTED OVER GRADED AREAS TO A MINIMUM DEPTH OF 6 INCHES. MAKE STOCKPILES FREE

DRAINING ANO PROVIDE EROSION ANO SEDIMENTATION CONTROLS AROUND STOCKPILES.

ALL GRADED (OTHER THAN TRAINING AREAS) AREAS SHALL BE MULCHED ANO SEEDED

WITHIN 15 DAYS AFTER GRADING IS COMPLETED. SEE SEED MIX ON THIS SHEET.

CONSTRUCT TEMPORARY EROSION CONTROL AS SHOWN ON THE DRAWINGS PRIOR TO BEGINNING

GRADING OPERATIONS.

ALL DRAINAGE STRUCTURES, PIPES WITHIN THE LIMITS OF CONSTRUCTION, ANO DETENTION

PONDS SHALL HAVE SEDIMENT REMOVED PRIOR TO FINAL ACCEPTANCE.

SILT BARRIERS SHALL BE CLEANED OF ACCUMULATED SEDIMENT WHEN APPROXIMATELY 50%

FILLED.

ALL LOCATIONS OF TEMPORARY EROSION CONTROL DEVICES SHALL BE SUBJECT TO

ADJUSTMENT AS DIRECTED BY THE ARCHITECT/ENGINEER.

WHEN THE TEMPORARY EROSION CONTROL DEVICES ARE NO LONGER REQUIRED FOR THE

INTENDED PURPOSE (IN THE ARCHITECT/ENGINEER'S OPINION'S), THEY SHALL BE REMOVED.

REPLACE DAMAGED ANO WORN OUT SILT BARRIERS AS DIRECTED BY THE ARCHITECT/ENGINEER.

THE CONTRACTOR SHALL PROTECT ALL TREES DESIGNATED TO REMAIN. 00 NOT OPERATE OR

STORE HEAVY EQUIPMENT, NOR HANDLE/STORE MATERIALS WITHIN THE ORIPLINES OF TREES.

THE CONTRACTOR SHALL VERIFY THE EXACT LOCATION OF ALL EXISTING UTILITIES,

PROTECT UTILITIES TO REMAIN, ANO REPAIR CONTRACTOR-CAUSED DAMAGE ACCORDING TO

LOCAL STANDARDS AT CONTRACTOR'S EXPENSE.

11. NOTIFY LOCAL UTILITY LOCATOR SERVICE (MISS UTILITY OF WEST VIRGINIA, INC.) OF INTENDED

DEMOLITION OPERATIONS. PHONE NUMBER: 1-800-245-4848

13. IN THE EVENT OF ANY DISCREPANCIES FOUND IN THE DRAWINGS OR IF PROBLEMS ARE

ENCOUNTERED DURING CONSTRUCTION, THE CONTRACTOR SHALL NOTIFY THE ARCHITECT/

ENGINEER BEFORE PROCEEDING WITH THE WORK.

14. THE CONTRACTOR SHALL GIVE ALL NECESSARY NOTICES ANO OBTAIN ALL PERMITS.

15. SPOT ELEVATIONS ANO CONTOURS REPRESENT PROPOSED FINISHED GRADE ANO TOP OF

FINISHED PAVEMENT.

16. CONTRACTOR SHALL VERIFY EXISTING ELEVATIONS ANO INVERTS PRIOR TO BEGINNING WORK.

17. EXCESS MATERIAL SHALL BE DISPOSED OF BY THE CONTRACTOR ON THE OWNER'S PROPERTY

AT NO ADDITIONAL COST IN A LEGAL MANNER.

18.

19.

20.

21.

22.

ALL STORM DRAINAGE PIPE SHALL BE 12 GAUGE TYPE II ALUMINIZEO

CMP UNLESS OTHERWISE NOTED.

ALL CUT ANO FILL SLOPES TO BE 3: 1 MAXIMUM.

SATISFACTORY TOPSOIL IS DEFINED AS SOIL BEING FREE OF SUBSOIL, CLAY LUMPS,

STONES, ANO OTHER OBJECTS OVER 1 INCH IN DIAMETER.

FINISH GRADES TOLERANCES ARE 0.10 FOOT ASOVE OR BELOW DESIGN ELEVATIONS.

PROVIDE TEMPORARY SEEDING ON STOCKPILES ANO ALL OTHER AREAS OF THE SITE THAT

WILL REMAIN UNDISTURBED FOR 30 DAYS OR MORE.

23. EARTHWORK FILL SHALL INCLUDE STRIPPING TOPSOIL ANO PLACING ENGINEERED FILL IN

MAXIMUM 8" COMPACTED LIFTS WITH DENSITY OF 98% OF MAXIMUM PER ASTM 0698.

24. AN 'AS-BUILT' SET OF PLANS SHALL BE SUBMITTED TO THE WV OEP UPON COMPLETION OF

SEDIMENTATION BASIN CONSTRUCTION.

25. I CERTIFY THAT THESE PLANS HAVE BEEN PREPARED BY ME ANO/OR UNDER MY DIRECT

SUPERVISION. THIS PROJECT IS PLANNED TO DISTURB MORE THAN FIVE ACRES.

IT THEREFORE FALLS UNDER THE WEST VIRGINIA DEPARTMENT OF ENVIRONMENTAL PROTECTION'S

GENERAL NPOES PERMIT TO DISCHARGE STORM WATER ASSOCIATED WITH CONSTRUCTION

ACTMTY.

&..J..f.c� 6-8-10

WV REGISTERED ENGINEER DATE

EROSION CONTROL IMPLEMENTATION SCHEDULE:

1, INSTAlL CONSTRUCTION ENTRANCES

2. ESTABLISH "cLEAN WATER' DIVERSION SWALE AlONG EASTERN PERIMITER OF SITE

3. INSTAlL SILT FENCE AT BASE OF SEOIMENT BASINS

4. INSTAlL SEOMENTATION BASINS

5. INSTAlL DIVERSION SWAlES TO OIRECT FLOW TO SEOIMENTATION BASINS o(,,/oi/10 Ir SHtEI IS LESS ,_ :J.4••2i?'" USC GRAPHIC SCAl.t

V> "1Z w:3 V> z« rll.

o- vi v,Z v,O 0 ;:c:, "'"' �g:

z

D5 <rz Wo ll.r V>u i;i ::;v, <')� NZ 3 0 w

Sheet reference number:

C-2 Sheet 2 of 7

Exhibit D-Cover
SOW WEST POND Pringle-SubmittedDraft - Copy
12E Sediment_Erosion Drawings

File details come from the government source that posted it. Updated .