Exhibit C - GRU Construction Inspection & Submittal Form

This document is a construction inspection and submittal form issued by Gainesville Regional Utilities (GRU) in Florida for surface restoration projects involving asphalt and concrete work. The form serves as a standardized template for contractors to document work completion and submit payment requests for various surface restoration activities, including asphalt overlays at different thicknesses (1.0" and 1.5"), concrete sidewalks and driveways, curb installation, brick paver placement, pavement markings, and temporary traffic control services. Contractors must submit the form with each invoice and corresponding work order, providing general project information, contractor representative contact details, work completion date, and total area measurements. The form includes a comprehensive submittal checklist requiring pre- and post-work photographs, batch tickets, mix design documentation, material certifications, calibration certificates, MOT/TTC plans, density test results, and warranty acknowledgments.

The form establishes specific quality standards and inspection requirements aligned with FDOT (Florida Department of Transportation) specifications, including asphalt density verification, concrete finish compliance, proper grading and slope matching, curb alignment, ADA compliance verification, and site cleanup documentation. Both contractors and GRU field inspectors must certify work acceptance, with inspectors verifying quantities, photo documentation, and Cityworks database entries before payment authorization. Contractors must warrant that all materials and workmanship conform to GRU and FDOT specifications and maintain coverage under the applicable warranty provisions, ensuring accountability throughout the project lifecycle and establishing a clear verification pathway for invoice processing and work acceptance.

View the file

Other files

File Type Posted
City_Sidewalk_Project_(Addendum_#1_Revision).pdf PDF
City_Sidewalk_Project.pdf PDF
6TH_AVE_SIDEWALK_CONST_PLANS_REVISED_07AUG26.pdf PDF
ZEPHYR_HEIGHTS_SIDEWALK_CONST_PLANS_S&S_05AUG26.pdf PDF
6TH_AVE_SIDEWALK_CONST_PLANS_REVISED_07AUG26.pdf PDF
ZEPHYR_HEIGHTS_SIDEWALK_CONST_PLANS_S&S_05AUG26.pdf PDF
ZEPH_SAMPLE_CHANGE_ORDER.pdf PDF
ZEPH_SAMPLE_CHANGE_ORDER.pdf PDF
Asphalt_and_Concrete_Services_(Addendum_#2_Revision).pdf PDF
Asphalt_and_Concrete_Services_(Addendum_#1_Revision).pdf PDF
Asphalt_and_Concrete_Services.pdf PDF
Technical_Specifications.docx DOCX document
Technical_Specifications.docx DOCX document
Technical_Specifications.docx DOCX document
Contract_Sample_Document.pdf PDF
2026-005_Pricing_Form.xlsx XLSX spreadsheet
2026-005_Pricing_Form.xlsx XLSX spreadsheet
2026-005_Pricing_Form.xlsx XLSX spreadsheet
Contract_Sample_Document.pdf PDF
Contract_Sample_Document.pdf PDF
Exhibit_C_-_GRU_Construction_Inspection_Form.docx DOCX document
Exhibit_C_-_GRU_Construction_Inspection_Form.docx DOCX document
Attachment_4_GRU_Construction_Inspection_Form_10.6.25.docx DOCX document
Pricing_Form_FInal_10.6.25.xlsx XLSX spreadsheet
Attachment_3_-Tech_Specs_10.6.25.docx DOCX document
Attachment_4_GRU_Construction_Inspection_Form_10.6.25.docx DOCX document
Attachment_4_GRU_Construction_Inspection_Form_10.6.25.docx DOCX document
Pricing_Form_FInal_10.6.25.xlsx XLSX spreadsheet
Attachment_3_-Tech_Specs_10.6.25.docx DOCX document
Attachment_3_-Tech_Specs_10.6.25.docx DOCX document
Pricing_Form_FInal_10.6.25.xlsx XLSX spreadsheet
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT C

GRU Surface Restoration Construction Inspection & Submittal Form To be submitted with each invoice and corresponding Work Order(s).

1. General Information

Contractor Name:
Date of Submittal:
Invoice Number:
GRU PO Number:
GRU Work Order Number(s):
Address / Location of Work:
Description of Work:
Type of Work:
Date Work Completed:
Total Area (SF or LF):

Cityworks Entry Completed: ☐ Yes ☐ No

Contractor Representative:
Phone / Email:

2. Submittal Checklist (Required with Pay Request)

Submittal Item
Attached (Y/N)
Notes

Pre-work timestamped photos (4 required)

Post-work timestamped photos (4 required)

Batch tickets (signed, dated, time-stamped)

Mix Design (gradation, binder, temperature, PG grade)

Material Certifications (binder, aggregates, tack coat, etc.)

Calibration Certificates (paver, roller, scales)

MOT/TTC Plan (signed & sealed by PE)

MOT/TTC Certification of field personnel

Density or QC test results (if required)

Warranty acknowledgment

3. Quantity & Pricing Verification (Per Pricing Form)

Bid Item No.
Description
Unit
Quantity
Unit Price ($)
Total ($)
A.1
SP-12.5 Asphalt (1.0")
SF
A.2
SP-12.5 Asphalt (1.5")
SF
B
Prime / Tack Coat
SF
C
Concrete Sidewalk / Driveway
SF
D
Concrete Sidewalk Ramp
EA
E
Concrete Curb
LF
F
Brick Pavers
SF
G.1
Painted Pavement Markings
SF
G.2
Thermoplastic Pavement Markings
SF
G.3
RPMs
EA
H.1-H.4
Demolition / Milling
SF
I
Temporary Traffic Control
EA

Total Invoice Amount ($)

4. Quality Inspection (To be completed by Contractor)

Inspection Item
Pass/Fail
Notes

Surface restoration matches grades/slopes

Asphalt density & surface finish per FDOT

Concrete finish meets FDOT requirements

Curb alignment & elevation consistent

Brick pattern & elevation match existing

Pavement striping/markers correctly applied

Site cleaned and free of debris

ADA compliance verified

MOT removed after completion

5. Warranty Certification The Contractor certifies that all materials and workmanship conform to GRU and FDOT specifications and are covered under warranty per Section 01780.

Contractor Representative: ___________________________ Date: ________________ Signature: ____________________________________________

6. GRU Field Verification (To Be Completed by GRU Inspector) Work Order verified in Cityworks

Quantities verified

Photos and submittals complete

Work accepted ☐ Yes ☐ No

Inspector Name:

Date:

Signature: