Exhibit C - BECRT Deliverables and Milestones - BECRT.xlsx

XLSX spreadsheet 37 KB Posted

Attached to
RFP 2526053
Solicitation number
0000039947
Issued by
California

About this file

This document is Exhibit C from RFP 2526053, issued by the California Department of Technology, detailing the deliverables and milestones for the Building Embodied Carbon Reporting Tool (BECRT) solution. The exhibit outlines five primary tasks spanning project management, a minimum viable product (MVP), and three subsequent post-MVP releases. Task 1 establishes ongoing project management deliverables including monthly and weekly status reports, project management plans, task accomplishment plans, project scheduling, meeting participation, and documentation management. Task 2 encompasses the BECRT MVP development across planning, analysis, design, execution, testing, and deployment phases, requiring deliverables such as vendor onboarding, implementation planning, Azure DevOps setup, user story development, architecture documentation, security assessments, database design, testing protocols, and knowledge transfer materials. Tasks 3, 4, and 5 define three sequential post-MVP releases, each following the same phase structure with progressively expanded module execution including registration, ledger management, fee calculation, reporting functionality, and correspondence features.

The exhibit specifies completion timeframes ranging from ongoing activities to phase-specific deliverables, with planning phase activities required during planning, analysis deliverables due at phase end, design outputs distributed throughout design phases, and execution and testing activities completed throughout their respective phases. Deployment phase deliverables include user manuals, training materials, standard operating procedures, knowledge transfer sessions, and lessons learned documentation, with Task 5 requiring additional maintenance and operations planning and transition planning upon deployment completion. The document does not contain pricing information, set-asides, incumbent details, or specific funding amounts, as this exhibit focuses solely on deliverable specifications and milestone tracking for the BECRT project implementation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Task 1

A: Deliverable 1: Ongoing
Phase #PhaseReleaseProposed Deliverable #Proposed DeliverablesDeliverable FrequencyBidder Agrees to Produce and Meet? (Yes/No)
1.1OngoingOngoing1.1.1Monthly Status Reports (MSRs)End of the Month
1.1.2Weekly Status Reports (WSRs)End of the Week
1.1.3Project Management Plan (PMP)Submit at pre-planning stage and update until formal CARB Project Manager (PM) acceptance is received
1.1.4Task Accomplishment Plan (TAP)End of the Month
1.1.5Project Schedule Development and UpdatesFirst Draft at Planning Stage and Updates are completed every Week
1.1.6Meeting Participation, Setup and DocumentationOngoing
1.1.7Meeting Notes DevelopmentOngoing
1.1.8Deliverable Tracker Steps ExecutionOngoing
1.1.9Deliverable Tracker Updates/CommunicationOngoing
1.1.10Deliverables' documentation Update and ResubmissionOngoing
1.1.11Deliverables Routing Process for SignaturesOngoing
1.1.12Action Items Log, Issues and Risks Register, Decision Log DocumentationOngoing

State of California California Department of Technology Exhibit C: BERCT Deliverables and Milestones RFP 2526053 Bidder Response July 31, 2026

&P

Task 2

B: Deliverable 2: BECRT Minimum Viable Product (MVP)
Phase #PhaseReleaseProposed Deliverable #Proposed DeliverablesCompletion TimeframeBidder Agrees to Produce and Meet? (Yes/No)
2.1PlanningBECRT Minimum Viable Product (MVP)2.1.1Vendor Onboarding Sessions Participation (PMO Review)Beginning of Planning
2.1.2Vendor Onboarding Sessions and Assignments completion (PMO Review)Beginning of Planning
2.1.3Implementation PlanDuring Planning
2.1.4SharePoint Site Setup and Usage (PMO Review)During Planning
2.1.5Project documentation Setup and Sharing (PMO Review)During Planning
2.1.6Product RoadmapDuring Planning
2.1.7Training PlanDuring Planning
2.1.8Business Continuity PlanDuring Planning
2.1.9Testing PlanDuring Planning
2.1.10Azure DevOps Product Backlog Hierarchy Setup and UpdatesEnd of Planning
2.1.11Azure DevOps Product Backlog, Sprint Backlog, Testing Artifacts and Reporting Metrics Setup and UpdatesEnd of Planning
2.1.12Go-Live PlanEnd of Planning
2.1.13Release PlanEnd of Planning
2.2AnalysisBECRT Minimum Viable Product (MVP)2.2.1User Story Development, Updates and FinalizationDuring Analysis
2.2.2Azure DevOps Sprint Allocation exportsEnd of Analysis
2.3DesignBECRT Minimum Viable Product (MVP)2.3.1Architecture Board Presentation MaterialsInitiation of Design
2.3.2Architecture Board ApprovalInitiation of Design
2.3.3California Cloud Services Assessment (CCSA) ParticipationDuring Design
2.3.4California Cloud Services Assessment (CCSA) DocumentationDuring Design
2.3.5Entity Relationship Diagram (ERD)During Design
2.3.6Data DictionaryDuring Design
2.3.7Enterprise Data QuestionnaireDuring Design
2.3.8Business GlossaryDuring Design
2.3.9Enterprise Data ReviewDuring Design
2.3.10Database ReviewDuring Design
2.3.11Privacy Impact Assessment (PIA)During Design
2.3.12eDiscovery and Litigation Hold PolicyDuring Design
2.3.13Privacy NoticeDuring Design
2.3.14FIPS Data Classification DocumentDuring Design
2.3.15STRIDE ModelDuring Design
2.3.16Information Technology Risk Assessment SessionsDuring Design
2.3.17Information Technology Risk Assessment DocumentDuring Design
2.3.18Firewall Design DiagramDuring Design
2.3.19System Security PlanDuring Design
2.3.20Business Impact Analysis (BIA)End of Design
2.3.21Technology Recovery Plan (TRP)End of Design
2.3.22Information Security Incident Response Plan (ISIRP)End of Design
2.3.23Visual Design ApprovalEnd of Design
2.4ExecutionBECRT Minimum Viable Product (MVP)2.4.1Database Request Form DocumentInitiation of Execution
2.4.2Registration, Fee Module Banner, Data Submission, Reference Tables, Data Query, Filter and Export Results Modules ExecutionEnd of Execution
2.4.3Requirements Traceability Matrix (RTM)End of Execution
2.4.4Database UpdatesDuring Execution
2.4.5Test CasesEnd of Execution
2.5TestingBECRT Minimum Viable Product (MVP)2.5.1Test ExecutionDuring Testing
2.5.2Vulnerability Scan ReportsDuring Testing
2.5.3Security ReviewDuring Testing
2.5.4User Interface ReviewDuring Testing
2.5.5Code ReviewDuring Testing
2.5.6DevOps ReviewDuring Testing
2.5.7GIS ReviewDuring Testing
2.5.8Infrastructure ReviewDuring Testing
2.5.9Defect Management Process ExecutionDuring Testing
2.5.10Test ReportsDuring Testing
2.6DeploymentBECRT Minimum Viable Product (MVP)2.6.1Release Activities DevelopmentInitiation of Deployment
2.6.2User Manuals (Documentation Review)During Deployment
2.6.3Training MaterialsDuring Deployment
2.6.4Standard Operating Procedures (SOP)During Deployment
2.6.5Information Technology Risk Assessment UpdatesDuring Deployment
2.6.6System Security Plan UpdatesDuring Deployment
2.6.7Knowledge Transfer MaterialsDuring Deployment
2.6.8Knowledge Transfer SessionsDuring Deployment
2.6.9Lessons Learned DocumentationEnd of Deployment
2.6.10Lessons Learned SessionsEnd of Deployment
2.6.11Release Activities CompletionEnd of Deployment
2.6.12Release LogEnd of Deployment

State of California California Department of Technology Exhibit C: BERCT Deliverables and Milestones RFP 2526053 Bidder Response

&P

Task 3

C. Deliverable 3: BECRT Post Minimum Viable Product – Release 1
Phase #PhaseReleaseProposed Deliverable #Proposed DeliverablesCompletion DateBidder Agrees to Produce and Meet? (Yes/No)
3.1PlanningBECRT Post Minimum Viable Product – Release 13.1.1Project documentation Setup and Sharing (PMO Review)During Planning
3.1.2Azure DevOps Product Backlog Hierarchy Setup and UpdatesEnd of Planning
3.1.3Azure DevOps Product Backlog, Sprint Backlog, Testing Artifacts and Reporting Metrics Setup and UpdatesEnd of Planning
3.1.4Release PlanEnd of Planning
3.2AnalysisBECRT Post Minimum Viable Product – Release 13.2.1User Story Development, Updates and FinalizationDuring Analysis
3.2.2Azure DevOps Sprint Allocation exportsEnd of Analysis
3.3DesignBECRT Post Minimum Viable Product – Release 13.3.1Entity Relationship Diagram (ERD)During Design
3.3.2Data DictionaryDuring Design
3.3.3Enterprise Data QuestionnaireDuring Design
3.3.4Business GlossaryDuring Design
3.3.5Enterprise Data ReviewDuring Design
3.3.6Database ReviewDuring Design
3.3.7Visual Design ApprovalEnd of Design
3.4ExecutionBECRT Post Minimum Viable Product – Release 13.4.1Registration, Ledger, Data Query, Filter and Export Results Modules ExecutionInitiation of Execution
3.4.2Requirements Traceability Matrix (RTM)End of Execution
3.4.3Database UpdatesDuring Execution
3.4.4Test CasesEnd of Execution
3.5TestingBECRT Post Minimum Viable Product – Release 13.5.1Test ExecutionDuring Testing
3.5.2Vulnerability Scan ReportsDuring Testing
3.5.3Security ReviewDuring Testing
3.5.4User Interface ReviewDuring Testing
3.5.5Code ReviewDuring Testing
3.5.6DevOps ReviewDuring Testing
3.5.7GIS ReviewDuring Testing
3.5.8Infrastructure ReviewDuring Testing
3.5.9Defect Management Process ExecutionDuring Testing
3.5.10Test ReportsDuring Testing
3.6DeploymentBECRT Post Minimum Viable Product – Release 13.6.1Release Activities DevelopmentInitiation of Deployment
3.6.2User Manuals (Documentation Review)During Deployment
3.6.3Training MaterialsDuring Deployment
3.6.4Standard Operating Procedures (SOP)During Deployment
3.6.5Information Technology Risk Assessment UpdatesDuring Deployment
3.6.6System Security Plan UpdatesDuring Deployment
3.6.7Knowledge Transfer MaterialsDuring Deployment
3.6.8Knowledge Transfer SessionsDuring Deployment
3.6.9Lessons Learned DocumentationEnd of Deployment
3.6.10Lessons Learned SessionsEnd of Deployment
3.6.11Release Activities CompletionEnd of Deployment
3.6.12Release LogEnd of Deployment

State of California California Department of Technology Exhibit C: BERCT Deliverables and Milestones RFP 2526053 Bidder Response

&P

Task 4

D. Deliverable 4: BECRT Post Minimum Viable Product – Release 2
Phase #PhaseReleaseProposed Deliverable #Proposed DeliverablesCompletion DateBidder Agrees to Produce and Meet? (Yes/No)
4.1PlanningBECRT Post Minimum Viable Product – Release 24.1.1Project documentation Setup and Sharing (PMO Review)During Planning
4.1.2Azure DevOps Product Backlog Hierarchy Setup and UpdatesEnd of Planning
4.1.3Azure DevOps Product Backlog, Sprint Backlog, Testing Artifacts and Reporting Metrics Setup and UpdatesEnd of Planning
4.1.4Release PlanEnd of Planning
4.2AnalysisBECRT Post Minimum Viable Product – Release 24.2.1User Story Development, Updates and FinalizationDuring Analysis
4.2.2Azure DevOps Sprint Allocation exportsEnd of Analysis
4.3DesignBECRT Post Minimum Viable Product – Release 24.3.1Entity Relationship Diagram (ERD)During Design
4.3.2Data DictionaryDuring Design
4.3.3Enterprise Data QuestionnaireDuring Design
4.3.4Business GlossaryDuring Design
4.3.5Enterprise Data ReviewDuring Design
4.3.6Database ReviewDuring Design
4.3.7Visual Design ApprovalEnd of Design
4.4ExecutionBECRT Post Minimum Viable Product – Release 24.4.1Data Submission, Fee Calculation and Collection, Data Query, Filter and Export Results Modules ExecutionEnd of Execution
4.4.2Requirements Traceability Matrix (RTM)End of Execution
4.4.3Database UpdatesDuring Execution
4.4.4Test CasesEnd of Execution
4.5TestingBECRT Post Minimum Viable Product – Release 24.5.1Test ExecutionDuring Testing
4.5.2Vulnerability Scan ReportsDuring Testing
4.5.3Security ReviewDuring Testing
4.5.4User Interface ReviewDuring Testing
4.5.5Code ReviewDuring Testing
4.5.6DevOps ReviewDuring Testing
4.5.7GIS ReviewDuring Testing
4.5.8Infrastructure ReviewDuring Testing
4.5.9Defect Management Process ExecutionDuring Testing
4.5.10Test ReportsDuring Testing
4.6DeploymentBECRT Post Minimum Viable Product – Release 24.6.1Release Activities DevelopmentInitiation of Deployment
4.6.2User Manuals (Documentation Review)During Deployment
4.6.3Training MaterialsDuring Deployment
4.6.4Standard Operating Procedures (SOP)During Deployment
4.6.5Information Technology Risk Assessment UpdatesDuring Deployment
4.6.6System Security Plan UpdatesDuring Deployment
4.6.7Knowledge Transfer MaterialsDuring Deployment
4.6.8Knowledge Transfer SessionsDuring Deployment
4.6.9Lessons Learned DocumentationEnd of Deployment
4.6.10Lessons Learned SessionsEnd of Deployment
4.6.11Release Activities CompletionEnd of Deployment
4.6.12Release LogEnd of Deployment

State of California California Department of Technology Exhibit C: BERCT Deliverables and Milestones RFP 2526053 Bidder Response

&P

Task 5

E. Deliverable 5: BECRT Post Minimum Viable Product – Release 3
Phase #PhaseReleaseProposed Deliverable #Proposed DeliverablesCompletion DateBidder Agrees to Produce and Meet? (Yes/No)
5.1PlanningBECRT Post Minimum Viable Product – Release 35.1.1Project documentation Setup and Sharing (PMO Review)During Planning
5.1.2Azure DevOps Product Backlog Hierarchy Setup and UpdatesEnd of Planning
5.1.3Azure DevOps Product Backlog, Sprint Backlog, Testing Artifacts and Reporting Metrics Setup and UpdatesEnd of Planning
5.1.4Release PlanEnd of Planning
5.2AnalysisBECRT Post Minimum Viable Product – Release 35.2.1User Story Development, Updates and FinalizationDuring Analysis
5.2.2Azure DevOps Sprint Allocation exportsEnd of Analysis
5.3DesignBECRT Post Minimum Viable Product – Release 35.3.1Entity Relationship Diagram (ERD)During Design
5.3.2Data DictionaryDuring Design
5.3.3Enterprise Data QuestionnaireDuring Design
5.3.4Business GlossaryDuring Design
5.3.5Enterprise Data ReviewDuring Design
5.3.6Database ReviewDuring Design
5.3.7Visual Design ApprovalEnd of Design
5.4ExecutionBECRT Post Minimum Viable Product – Release 35.4.1Reports, Correspondence Functionality, Filter and Export Results Modules ExecutionEnd of Execution
5.4.2Requirements Traceability Matrix (RTM)End of Execution
5.4.3Database UpdatesDuring Execution
5.4.4Test CasesEnd of Execution
5.5TestingBECRT Post Minimum Viable Product – Release 35.5.1Test ExecutionDuring Testing
5.5.2Vulnerability Scan ReportsDuring Testing
5.5.3Security ReviewDuring Testing
5.5.4User Interface ReviewDuring Testing
5.5.5Compliance AnalysisDuring Testing
5.5.6Code ReviewDuring Testing
5.5.7DevOps ReviewDuring Testing
5.5.8Reporting ReviewDuring Testing
5.5.9GIS ReviewDuring Testing
5.5.10Infrastructure ReviewDuring Testing
5.5.11Defect Management Process ExecutionDuring Testing
5.5.12Test ReportsDuring Testing
5.6DeploymentBECRT Post Minimum Viable Product – Release 35.6.1Release Activities DevelopmentInitiation of Deployment
5.6.2User Manuals (Documentation Review)During Deployment
5.6.3Training MaterialsDuring Deployment
5.6.4Standard Operating Procedures (SOP)During Deployment
5.6.5Information Technology Risk Assessment UpdatesDuring Deployment
5.6.6System Security Plan UpdatesDuring Deployment
5.6.7Knowledge Transfer MaterialsDuring Deployment
5.6.8Knowledge Transfer SessionsDuring Deployment
5.6.9Lessons Learned DocumentationEnd of Deployment
5.6.10Lessons Learned SessionsEnd of Deployment
5.6.11Release Activities CompletionEnd of Deployment
5.6.12Release LogEnd of Deployment
5.6.13Maintenance & Operations (M&O) PlanEnd of Deployment
5.6.14Transition PlanEnd of Deployment

State of Calirornia California Department of Technology Exhibit C: BERCT Deliverables and Milestones RFP 2526053 Bidder Response