This is a Prime/Subcontractor Form (Exhibit B) for Volusia County, Florida's Invitation for Bid (ITB) No. 26-B-55JS for the Deland Regional Library Play Yard Walkway construction project. The form requires bidders to list all proposed subcontractors performing work on the project and identify the dollar value and percentage of work assigned to each contractor discipline, including earthwork, concrete, fencing, doors and hardware, and security access control. The non-mandatory pre-bid meeting is scheduled for March 12, 2026 at 9:00 a.m., with questions due by March 19, 2026 at 11:59 p.m. and bid responses due April 2, 2026. The project requires substantial completion within 150 days and final completion within 180 days of the Notice to Proceed, with liquidated damages of $250 per day assessed for delays beyond substantial completion.
The estimated construction cost is $250,000, and bidders must submit a bid bond equal to 5 percent of the bid amount. Upon contract award, the prime contractor must secure payment and performance bonds equal to 100 percent of the contract price. The form emphasizes that failure to complete and return it may result in a non-responsive bid and that the prime contractor is responsible for ensuring all subcontractors hold appropriate licenses. The project is federally funded through Community Development Block Grant and Volusia ECHO Grant funding, subjecting it to Davis-Bacon Act prevailing wage requirements, Section 3 labor hour provisions (25 percent minimum by Section 3 workers and 5 percent by Targeted Section 3 workers), M/WBE requirements, Copeland Act anti-kickback provisions, and Build America, Buy America certification requirements. Required insurance includes Workers Compensation with waiver of subrogation, Commercial General Liability with minimum limits of $1,000,000 per occurrence and $2,000,000 general aggregate, Auto Liability with combined single limits of $1,000,000, and Installation Floater coverage on an all-risk basis.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Contract No. C-2074 | ITB No. 26-B-55JS | ||||
| PRIME/SUBCONTRACTOR FORM | |||||
| FAILURE TO COMPLETE AND RETURN THIS FORM MAY RESULT IN A NON-RESPONSIVE BID | |||||
| Bidders are to list ALL Subcontractors that are proposed to perform scope of work for this project. The bidder hereby states that if awarded,the contract must hire the following Subcontractor(s) for this project. Prime Contractor is responsible for ensuring that all Subcontractors hold the appropriate license(s). Any change to the Subcontractors during the completion of this project shall receive prior approval from the County Project Manager. The County reserves the right to seek clarification regarding subcontractors but will not allow change to the total submitted base bid pricing. | |||||
| TOTAL BID | $ - 0 | This number should match the Total Bid Price |
(inclusive of performance/payment bond, if applicable) as listed on Bid Form/Exhibit G- Bid Price Sheet
| PRIME CONTRACTOR | Company name and complete address | Dollar Value performed by Prime Contractor | % of Work performed by Contractor |
| 0.00% | |||
| List appropriate sub contractors to be used for each displine listed below, if prime is self performing note self performing in the box under company name and address and submit $0.00 to equal 0 % as this should be included in the green box above. If additional subcontractors are required and their discipline is not listed below they may be added in the blank rows. This form will also be used to determine local preference in accordance with Section 2.8, D. Local Bid Preference in the solicitation. | |||
| Anticipated Subcontractor Disciplines required for this project. | Company name and complete address | Dollar Value performed by Subcontractor(s) | % of Work performed by Subcontractor |
| EARTHWORK | $ - 0 | 0.00% | |
| CONCRETE | $ - 0 | 0.00% | |
| FENCING | $ - 0 | 0.00% | |
| DOORS AND HARDWARE | $ - 0 | 0.00% | |
| SECURITY ACCESS CONTROL | $ - 0 | 0.00% | |
| $ - 0 | 0.00% | ||
| $ - 0 | 0.00% | ||
| $ - 0 | 0.00% | ||
| $ - 0 | 0.00% | ||
| $ - 0 | 0.00% | ||
| $ - 0 | 0.00% | ||
| $ - 0 | 0.00% | ||
| $ - 0 | 0.00% | ||
| $ - 0 | 0.00% | ||
| Bidders shall complete the areas shaded in GREEN, which shall be the dollar values assigned to each Contractor (Prime and Subs). All other cells shall be automatically calculated. The total listed in the GREY cell must equal 100% | $ - 0 | 0% |