Exhibit B - Construction Schedule.pdf
PDF 476 KB Posted
- Attached to
- Audio Visual Hardware & Installation
- Solicitation number
- S-X24129-00011345
- Issued by
- Clackamas County, Oregon
About this file
This document is a construction schedule for the CIS project. The project duration is 361 days, starting on March 29, 2024, and finishing on August 28, 2025. The key milestones include the design phase, bidding and contracting, permitting, procurement, and the various construction phases such as sitework, structure, envelope, interior build-out, and building systems. The schedule includes details on the duration and dependencies of each task, as well as specific dates for deliverables such as the 50% construction documents, bid documents, and permit document approvals. The notice to proceed is scheduled for July 5, 2024, with substantial completion targeted for July 30, 2025, and final completion on August 28, 2025.
The construction schedule does not provide information on pricing terms, set-asides, incumbents, funding requirements, or sources. The document focuses solely on the timeline and sequencing of the construction activities for the CIS project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Tab~3.docx | DOCX document | |
| Exhibit C - CIS Bid & Permit Specifications.pdf | ||
| CIS AV Consultant RFP 2024.pdf | ||
| Exhibit A- CIS AV Layout.pdf | ||
| Exhibit C- CIS Bid & Permit Set Drawings.pdf | ||
| AV RFP Addendum Q&A.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task Name Duration Start Finish Predecessors
0 CIS 361 days Fri 3/29/24 Thu 8/28/25 1 Pre-Construction 97 days Fri 3/29/24 Wed 8/14/24 2 Design 37 days Fri 3/29/24 Tue 5/21/24 3 50% CD 0 days Fri 3/29/24 Fri 3/29/24 4 Bid Documents (Approved 90% CDs) 0 days Tue 5/14/24 Tue 5/14/24 5 Permit Documents 0 days Tue 5/21/24 Tue 5/21/24
17 Buyout & Contracting 37 days Tue 5/14/24 Fri 7/5/24 18 Subcontractor Bidding 15 days Tue 5/14/24 Tue 6/4/24 4 19 Bid Analysis / Assemble GMP 5 days Wed 6/5/24 Tue 6/11/24 18 20 Owner Review 10 days Wed 6/12/24 Tue 6/25/24 19 21 Board Review & Approval 5 days Wed 6/26/24 Tue 7/2/24 20 22 GMP Amendment 2 days Wed 7/3/24 Fri 7/5/24 21 6 Permitting 60 days Tue 5/21/24 Wed 8/14/24 7 Early Grading Permit 30 days Tue 5/21/24 Tue 7/2/24 8 Permit Review 20 days Tue 5/21/24 Tue 6/18/24 5 9 Plan Check Comment Response 5 days Wed 6/19/24 Tue 6/25/24 8
10 Pre-Issuance 5 days Wed 6/26/24 Tue 7/2/24 9 11 Early Grading Permit Release 0 days Tue 7/2/24 Tue 7/2/24 10 12 Building Permit 60 days Tue 5/21/24 Wed 8/14/24 13 Permit Review 40 days Tue 5/21/24 Wed 7/17/24 5 14 Plan Check Comments 10 days Thu 7/18/24 Wed 7/31/24 13 15 Pre-Issuance 10 days Thu 8/1/24 Wed 8/14/24 14 16 Building Permit Release 0 days Wed 8/14/24 Wed 8/14/24 15 23 Notice to Proceed 0 days Fri 7/5/24 Fri 7/5/24 22 24 Procurement 186 days Mon 7/8/24 Mon 3/31/25
177 Construction 258 days Mon 7/8/24 Fri 7/11/25 178 Mobilization 2 days Mon 7/8/24 Tue 7/9/24 179 Temporary Fence, Offices 1 day Mon 7/8/24 Mon 7/8/24 23 182 Utility Locates 1 day Mon 7/8/24 Mon 7/8/24 23 180 Temporary Power 1 day Tue 7/9/24 Tue 7/9/24 182 181 Temporary Water 1 day Tue 7/9/24 Tue 7/9/24 182 183 1200C / Erosion Control 3 days Mon 7/8/24 Wed 7/10/24 184 Erosion Control 2 days Mon 7/8/24 Tue 7/9/24 23 186 Existing Tree Protection 1 day Tue 7/9/24 Tue 7/9/24 179 185 Erosion Control Inspection 1 day Wed 7/10/24 Wed 7/10/24 184 187 Initial Sitework 40 days Thu 7/11/24 Thu 9/5/24 188 Demo Existing Hardscapes 2 days Thu 7/11/24 Fri 7/12/24 185,11 189 Clear & Grub 5 days Thu 7/11/24 Wed 7/17/24 179,180,181,185,186 190 Excavate Existing Fill & Import Strucutral Fill at SOG 5 days Tue 8/13/24 Mon 8/19/24 189,166
3/29 8/28
3/29 50% CD
5/14 Bid Documents (Approved 90% CDs)
5/21 Permit Documents
5/14 Subcontractor Bidding 6/5 Bid Analysis / Assemble GMP 6/12 Owner Review
6/26 Board Review & Approval 7/3 GMP Amendment
5/21 Permit Review 6/19 Plan Check Comment Response
6/26 Pre-Issuance 7/2 Early Grading Permit Release
5/21 Permit Review 7/18 Plan Check Comments
8/1 Pre-Issuance 8/14 Building Permit Release
7/5 Notice to Proceed
7/8 Temporary Fence, Offices 7/8 Utility Locates 7/9 Temporary Power 7/9 Temporary Water
7/8 Erosion Control 7/9 Existing Tree Protection
7/10 Erosion Control Inspection
7/11 Demo Existing Hardscapes 7/11 Clear & Grub
8/13 Excavate Existing Fill & Import Strucutral Fill at SOG
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025
Task Milestone Summary Project Summary Progress Critical
CIS Wed 4/10/24
Project: CIS Date: Wed 4/10/24
ID Task Name Duration Start Finish Predecessors
191 Site Surveying 2 days Tue 8/20/24 Wed 8/21/24 190 192 Excavate/Fine Grade Footings 10 days Thu 8/22/24 Thu 9/5/24 190,191,188 193 Site Utilities 47 days Fri 9/6/24 Mon 11/11/24 240 Structure 89 days Fri 9/6/24 Tue 1/14/25 272 Envelope 91 days Tue 1/7/25 Tue 5/13/25 203 Sitework 93 days Wed 1/15/25 Fri 5/23/25 299 Interior Build Out 121 days Wed 1/22/25 Fri 7/11/25 382 Building Systems 65 days Mon 3/17/25 Mon 6/16/25 412 Close Out 65 days Thu 5/29/25 Thu 8/28/25 415 Mechanical Final Inspection 1 day Thu 5/29/25 Thu 5/29/25 347,392,333 416 Electrical Final Inspection 1 day Thu 5/29/25 Thu 5/29/25 348,216,233,286,395,355,334 414 Plumbing Final Inspection 1 day Thu 6/12/25 Thu 6/12/25 388,332,389 413 Fire Sprinkler Final Inspection 1 day Tue 6/17/25 Tue 6/17/25 346,353,331,385,386 417 LV Final Inspection 1 day Fri 6/20/25 Fri 6/20/25 349,408,356,357,335,336 418 Fire Alarm Final Inspection 1 day Fri 6/20/25 Fri 6/20/25 350,410,358,337,411 419 Building Final Inspections 1 day Mon 6/23/25 Mon 6/23/25 414,413,418,417,416,415,292 420 Bulk Clean 3 days Wed 7/9/25 Fri 7/11/25 368 421 Pre Punch 10 days Mon 7/14/25 Fri 7/25/25 368,420 422 Final Clean 3 days Mon 7/28/25 Wed 7/30/25 421 424 Substantial Completion 0 days Wed 7/30/25 Wed 7/30/25 419,422 423 Punch Walk 1 day Thu 7/31/25 Thu 7/31/25 238,366,368,369,370,372,376,377,378,379,380,381,285,298,296,210,232,234,236,235,279,339,422,239,393,297,373,374,375,367 425 Punchlist Corrections 20 days Fri 8/1/25 Thu 8/28/25 423,424 426 Final Completion 0 days Thu 8/28/25 Thu 8/28/25 425
8/20 Site Surveying 8/22 Excavate/Fine Grade Footings
5/29 Mechanical Final Inspection 5/29 Electrical Final Inspection
6/12 Plumbing Final Inspection 6/17 Fire Sprinkler Final Inspection 6/20 LV Final Inspection 6/20 Fire Alarm Final Inspection 6/23 Building Final Inspections
7/9 Bulk Clean 7/14 Pre Punch
7/28 Final Clean 7/30 Substantial Completion 7/31 Punch Walk
8/1 Punchlist Corrections 8/28 Final Completion
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025
Task Milestone Summary Project Summary Progress Critical
CIS Wed 4/10/24
Project: CIS Date: Wed 4/10/24