CITY OF MANITOU SPRINGS Dillion Mobility Hub Phase 1 Lot Construction
Solicitation number
RFB2025-001
Issued by
El Paso County, Manzanola Town, Colorado

About this file

The document is a Bid Tabulation Sheet (RFB 2025-001) for the City of Manitou Springs' Dillon Mobility Hub Phase 1 Lot Construction project in Colorado. The bid covers comprehensive site development including demolition, excavation, pavement and sidewalk installation, curb and gutter work, signage and striping, erosion control, and site amenities. The project involves clearing and grading approximately 1,722 square yards, installing concrete sidewalks and ADA parking, adding curbing, implementing pedestrian crossings, and incorporating infrastructure elements like bollards, lighting, and fencing. Key timeline requirements include project completion by May 30th, 2025, with insurance and bond proof due by March 12th, 2025, and contract signatures required by noon on March 12th, 2025.

The bid tabulation sheet presents a detailed breakdown of construction activities with zero-dollar placeholder unit costs, suggesting that actual pricing will be completed by bidders. The document includes provisions for additional costs such as a 5% and 10% construction contingency, materials testing, quality control, traffic control, and project management. The project appears to be a public infrastructure improvement initiative focused on creating a mobility hub with enhanced accessibility, parking, and community infrastructure. No specific funding sources or budget allocations are explicitly stated in the provided document, though the comprehensive scope suggests municipal or potentially state-level transportation infrastructure funding.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Interim Lot

BID TABULATION SHEET
RFB 2025-001: Dillon Mobility Hub Phase 1 Lot Construction
City of Manitou Springs
Instructions:Complete the fields highlighted in Yellow
Contractor Name:ENTER BIDDER NAME
Date Estimated:ENTER DATE
ITEM NO.DESCRIPTIONUNITSQUANTITYUNIT COSTCOSTSUBTOTAL
BASE BID
Demolition & Excavation
2025001-01Site Clearing & GrubbingLS1$0.00
2025001-02EmankmentCY202$0.00
2025001-03Unclassified ExcavationCY96$0.00
2025001-04Removal of Existing Asphalt & DisposalSY1,722$0.00
2025001-05Demolition of 4' Brick Wall Along Manitou AveLF60$0.00
$0.00
Pavements & Sidewalk
2025001-06Millings PlacementCY530$0.00
2025001-074" Concrete SidewalkCY10$0.00
2025001-088" Concrete ADA ParkingCY39$0.00
2025001-094" Subbase CourseCY29$0.00
$0.00
Curb & Gutter
2025001-106" Concrete Vertical CurbLF50$0.00
2025001-11Traversable Sloped Concrete CurbLF70$0.00
$0.00
Signage & Striping
2025001-12White Pavement StripesLF124$0.00
2025001-13Embedded Detectable Warning UnitsSY12$0.00
2025001-14Pedestrian Crossing Area White StripingSY530$0.00
2025001-15ADA Parking Stall Sign (MUTCD R7-8)EA4$0.00
2025001-16ADA Van Accessible Sign (MUTCD R7-8P)EA1$0.00
2025001-17ADA Handicap Parking SymbolEA4$0.00
2025001-18Sign PostEA1$0.00
$0.00
Erosion & Sediment Control
2025001-19Vehicle Tracking ControlLS1$0.00
2025001-20Silt FenceLF1,600$0.00
2025001-21Concrete WashoutEA1$0.00
2025001-22Sediment Control LogsLF45$0.00
2025001-23Check DamsEA1$0.00
2025001-24Seeding & MulchingSY450$0.00
$0.00
Site Programs
2025001-25Split Wood Rail FenceLF1,595$0.00
2025001-26Concrete Wheel StopsEA115$0.00
2025001-27BollardsEA7$0.00
2025001-28Ornamental Light Standards and LuminariesEA$0.00
2025001-29Rigid 3" ConduitLF$0.00
2025001-30Lighting Control AllowanceLS1$0.00
$0.00
General
2025001-31MobilizationLS1$0.00
2025001-32Construction SurveyingLS1$0.00
2025001-33Traffic Control MeasuresLS1$0.00
$0.00

TOTAL BASE BID COST $ - 0

ADDITIONAL COSTSLUMP SUMPercent of Base BidTOTAL
Construction Contingency (5% assumed if not provided)5.0%$0.00
Construction Contingency (10% assumed if not provided)10.0%$0.00
Construction Materials Testing (enter % or Lump Sum)$0.00
Quality Control and Testing$0.00
Traffic Control Measures$0.00
Project Management$0.00
[OTHER]$0.00
[OTHER]$0.00
[OTHER]$0.00
TOTAL Additional Costs$0.00
TOTAL BASE BID + Additional$0.00
TIMELINE REQUIREMENTSSelect ResponseComments
Are you able to complete the project by May 30th, 2025?
Are you able to provide proof of required Certificate of Insurance and Bond requirements by March 12th, 2025 (noon)?
Are you able obtain contract signatures and notarization by noon March 12th, 2025 (noon)?