This document is an Addendum (Addendum Number 2) for Request for Bids (RFB) 2025-001 issued by the City of Manitou Springs for the Dillon Mobility Hub Interim Lot construction project. The addendum, dated February 14, 2025, includes revised documents such as the RFB, Grading & Erosion Control Plans, a Clarifications Log, and a Revised Bid Tabulation. The project involves constructing an interim parking lot located at 132-142 Manitou Avenue, with a bid submittal deadline of Tuesday, February 20, 2025, at 1:00 PM. The City requires the project to be completed by June 1, 2025, with liquidated damages applying if the deadline is not met. The selected contractor will need to obtain a performance bond covering 100% of the project contract amount and a 50% payment bond.
The project scope includes site clearing, excavation, embankment, removal of existing asphalt and a brick wall, pavement and sidewalk installation, curb and gutter work, signage and striping, erosion and sediment control, and various site programs such as wheel stops, fencing, bollards, and lighting infrastructure. The City will provide quality control testing for the project and has specified detailed requirements for tree protection, construction methods, and site restoration. The contract will be awarded to the lowest responsible and responsive bidder, with the City considering factors beyond price, such as product quality, previous experience, qualifications, services offered, warranties, and long-range costs. The project is not subject to Davis-Bacon Wages, and the City of Manitou Springs will be responsible for site maintenance once the project is completed.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1.01 GENERAL
The following changes, addi ons, and/or dele ons are, by issuance of the Addendum for the RFB
2025-001 Dillon Mobility Hub Interim Lot, as if originally contained therein. Execu on of the acknowledgement of receipt shall be the bidder’s acceptance of the condi ons herein set forth.
This Addendum shall be submi ed with and a ached to the submi ed Bid Form. Failure to do so may result in the rejec on of the Bid.
1.02 The addendum includes the following documents: Revised RFB, Revised Grading & Erosion Control
Plans, Clarifica ons Log (i.e. Answers to RFP Ques ons), and a Revised Bid Tabula on.
1.03 ACKNOWLEDGEMENT OF RECEIPT
Receipt is acknowledged this ___________ day of 20_____.
Name of Bidder
Authorized Officer
Title
END OF ADDENDUM
CITY OF MANITOU SPRINGS
ADDENDUM FORM
RFB 2025-001
ADDENDUM NUMBER 2
DATE: February 14, 2025
2025001 413-04-01
CITY OF MANITOU SPRINGS
Request for Bids
Dillon Mobility Hub Interim Lot
RFB NUMBER: 2025-001
Bid Submittal Deadline – Tuesday, February 20th, 2025, 1:00 PM Contact Person – Sarah Lara (sarah.lara@artaicgroup.com
The City of Manitou Springs is accepting bids for construction of the Dillion Mobility Hub interim parking lot located at 132-142 Manitou Avenue. See General Scope of Services Section and attachments for further details.
• Publication date: Thursday, January 9th, 2025
• Pre-bid meeting to be held on Tuesday, January 21st, 2025, at 3:00 PM at 134 Manitou Avenue, Manitou Springs, CO 80829
• Deadline to present questions deadline is Wednesday, January 29th, 2025, at 3:00
PM.
o Questions are to be addressed to the contact person
• Final Addendum (responses to questions) to be published on Friday, February 14th, 2025
• Bid shall be submitted to the contact person electronically no later than the Submittal Deadline o There will not be a public bid opening
• Notice of Award will be Tuesday, March 4th, 2025
• The Selected Contractor will be required to obtain a performance bond to cover 100% of the project contract amount and 50% payment bond
• This project is not subject to Davis Bacon Wages
• The City of Manitou Springs requires the project to be completed by June 1st, 2025, failure to do so will trigger liquidated damages
The bid shall have an Anticipated Scope of Services that includes the following:
1. The Contractor will provide project costs for crews and equipment, anticipated mobilization time, and anticipated project completion time
2. Quantities are for informational use only – This contract is to be awarded as a lump sum contract
3. The Contractor shall follow all standard notes and details stated on the Dillon Motel
– Park N Ride Preliminary & Interim Grading & Erosion Control Plans
4. The Contractor is responsible for providing all materials and equipment necessary for fabrication, construction, and/or installation of this project
5. All construction waste shall be disposed of by the Contractor
6. The Contractor is responsible for damages, inside or outside the project area
7. The Contractor is responsible for their own confined space, roadway, and trenching safety procedures
8. No work shall be done between the hours of 5:30 PM and 7:00 AM, nor at any time on Saturday, Sunday, or holidays, except with the written permission of the city or in case of an emergency
9. If the project requires street closure – partial or otherwise, the Contractor shall provide all necessary traffic control. All traffic control personnel must at a minimum carry the current CDOT Flagger Certification. A Traffic Control Plan must be submitted to and approved by City staff at the pre-construction meeting. The pre-construction is to be scheduled for accepting the contract.
10. It is anticipated that no existing utilities will need to be relocated and there are no proposed utilities
11. The Contractor shall stay within the limits of disturbance depicted in the Dillon Motel – Park N Ride Preliminary & Interim Grading & Erosion Control Plans
12. Below is the Anticipated General Scope of Services for this project:
GENERAL SCOPE OF SERVICES
Overview: The construction of the Dillon Mobility Hub Interim Lot will provide essential parking and accessibility improvements to serve the community's immediate needs. The project involves site preparation, grading, installation of infrastructure, and implementation of temporary and permanent features. The work of the Project is defined by the Dillon Motel – Park N Ride Preliminary & Interim Grading & Erosion Control Plans provided in Exhibit A and containing the following components:
1. Demolition & Excavation:
a. Site Clearing & Grubbing
b. Embankment - Material shall consist of approved material acquired from excavations and placed in embankments. Embankment material will be measured in its final compacted position.
c. Unclassified Excavation – Shall consist of the excavation of all material of whatever character required for the work, obtained within the site including surface boulders and excavations for placement of improvements.
d. Removal of Existing Asphalt & Disposal
e. Demolition of 4’ Brick Wall Along Manitou Ave – this includes disposal of demolished material and backfilling to match existing grade
2. Pavement & Sidewalk
a. Millings Placement – Placement of 4” thickness milling material. Max size of millings to be no greater than 3” (Chunks) compacted to be used as a drivable surface. A compaction report is required
b. 4” Concrete Sidewalk – Minimum compressive strength: 4000 PSI. See detail for reference
c. 8” Concrete Parking – Minimum compressive strength: 4000 PSI, 4” subbase with a compacted subgrade. See detail for reference
3. Curb & Gutter:
a. 6” Concrete Vertical Curb. See detail for reference
b. Traversable Sloped Concrete Curb. See detail for reference
4. Signage & Striping:
a. White Pavement Stripes – 4” wide white epoxy striping
b. Embedded Detectable Warning Unit – 2’x5’ surface mounted ADA warning pad with raised truncated domes (Must be ADA compliant)
c. Pedestrian Crossing Area – 4” wide white epoxy striping
d. ADA Parking Stall Sign – Per MUTCD R7-8 sign
e. ADA Van Accessible Sign – Per MUTCD R7-8P sign
f. ADA Handicap Parking Symbol – White epoxy striping
g. Sign Post – U-Channel heavy duty galvanized steel (or equal) that meets
MUTCD standards
5. Erosion & Sediment Control:
a. Vehicle Tracking Control – See detail for reference
b. Silt Fence – See detail for reference
c. Concrete Washout - See detail for reference
d. Sediment Control Logs - See detail for reference
e. Check Dams - See detail for reference
f. Seeding & Mulching – See detail for reference
6. Site Programs:
a. Installation of wheel stops - See detail for reference
b. Installation of split wood fencing - See detail for reference
c. Bollards - See detail for reference
d. Ornamental Light Standards and Luminaries - See electrical detail for reference
e. Rigid 3” Conduit - See electrical detail for reference
f. Lighting Control Allowance
7. General
a. Mobilization
b. Construction Surveying
c. Traffic Control Measures – Includes implementing traffic controls, flagging, signage, inspections, setup/ tear down, MHT and any permits required
Additional scope components not included in the GEC plans:
8. Electrical components:
a. Installation of adequate conduit for electrical components starting at the
Restroom Building (located on lot 132 Manitou Avenue) to dirt portion of the lot 134 Manitou Avenue to allow for the installation of site electrical at a future date. This work will need to be done prior to the concrete and curb work for the ADA parking spaces.
b. Installation of galvanized pipe pole(s) for security and/or lighting components (5 Each).
9. Compliance and Coordination: All work will adhere to the City of Manitou Springs’ grading, erosion control, and stormwater quality control standards. The contractor will coordinate utility relocations and field adjustments as needed. Regular site inspections and quality control measures will ensure compliance with approved plans and specifications.
10. Construction Quality Control/Testing:
The City of Manitou Springs will provide and schedule QC for this project. it is on the contractor to decide if they want to have testing on their side as a side-by-side comparison. Tests to be performed but are not limited to:
a. Compaction Testing
b. Soil testing
c. Concrete testing
11. Site Clean-up and Final Inspection
a. Post-construction cleaning and removal of all excess materials, debris and equipment.
12. Project Schedule: The Contractor will provide a written schedule for the work to be included in bid package including a timeline that adheres to the completion before June 1st, 2025.
13. Project Bid: Provide estimated costs for the project using the itemized “Bid Tabulation Sheet” in Exhibit B.
INSTRUCTIONS TO BIDDERS
1. A "Bid" is a responsive, conforming, unconditional, complete, legible, and properly executed offer by a Bidder to provide the work specified in the Request for Bids for the compensation specified.
2. Bids shall be clearly marked with the work name, contact person, mailing address, and telephone number of the Bidder.
3. It shall be the responsibility of the Bidder to ensure that the Bid is in proper form and in the City of Manitou Springs possession by or before the time and date designated in the Request for Bids. Bids will not be accepted after the designated time and date.
4. If a mistake is made or discovered during or after the Bid review, the City of Manitou Springs reserves the right to determine which party made the mistake and whether the mistake is material and, after these determinations, the City of Manitou Springs, in its sole reasonable discretion, shall decide whether to accept or reject the Bid. No advantage shall be taken by any party of manifest clerical errors or omissions in any Bid, and the contract and attached documents (the “Contract Documents”). Bidders shall notify the City immediately of any errors or omissions that are encountered.
5. Any interlineation, alteration, or erasure shall be initialed by the Bidder. On the Bid, the price of each item shall be stated in numerals and words; in case of conflict, the words shall dictate. In the case of conflict between the indicated sum of any addition of figures and the correct sum, the correct sum shall dictate.
6. The City of Manitou Springs shall not reimburse any Bidder for any cost incurred in preparing a Bid or attending equipment demonstrations, inspections, pre-bid conferences, or interviews.
7. Any amplification, clarification, explanation, interpretation, or correction of a Bid shall be made only by written addendum, and a copy of the addendum shall be mailed or delivered to each person receiving a Request for Bids. The City of Manitou Springs is not responsible for any amplification, clarification, explanation, or interpretation or correction of a Bid not contained in written addenda.
8. Bids by corporations shall be executed in the corporate name by the president or a vice-president (or a corporate officer accompanied by evidence of authority to sign), and the corporate seal shall be affixed and attested by the secretary or an assistant secretary. The corporate address and state of incorporation shall be shown. Bids submitted by partnerships shall be executed in the partnership name and signed by a partner, and the legal address of the partnership shall be shown.
Bids submitted by limited liability companies shall be executed in the company's name and signed by a member, and the legal address of the company shall be shown. Names and titles shall be typed or printed below each signature.
9. The following information shall be submitted with the Bid:
a. The names and resumes of staff personnel who will be assigned to the work.
b. A complete proposed scope of work, cost and schedule, including any alternatives that can be identified. The Bidder is expected to review the work site prior to submitting the Bid.
c. The names and addresses of any subcontractors who will be retained for the work.
d. A list of the Bidder's previous experience on similar projects.
10. The submission of a Bid shall be conclusive evidence and a legal admission that the Bidder: (1) has no questions, complaints, or objections in connection with the Contract Documents, subject to any requests made by the Bidder for amplification, clarification, explanation, interpretation, or correction; (2) has no questions, complaints, or objections as to the completeness, sufficiency, scope, or detail of the Bid; and (3) has full knowledge of the scope, nature, quality, and quantity of the equipment to be provided, the performance criteria, the requirements of the contract, the site and conditions of delivery, the Superior Municipal Code, and other applicable law.
11. The contract will be awarded to the lowest responsible and responsive Bidder complying with the terms and conditions, guidelines, and specifications presented in the Bid Request and these Instructions to Bidders. The City of Manitou Springs reserves the right to determine, in its sole reasonable discretion, whether any Bid meets the needs or purposes intended and is within the approved budget. The City of Manitou Springs does not base its award on prices alone. Also to be considered are quality of product; previous experience with Bidder or any subcontractors, consultants, products or suppliers; qualifications of Bidder and/or subcontractors or suppliers; services offered; warranties; maintenance considerations; long-range costs; delivery; and similar conditions.
12. The City of Manitou Springs reserves the right to conduct such investigations as it deems necessary to assist in the evaluation of any Bid to establish the experience, responsibility, reliability, references, reputation, qualifications, or financial ability of any Bidder, manufacturer or supplier. The purpose of such investigation is to satisfy the City of Manitou Springs that the Bidder has the experience, resources, and commercial reputation necessary to supply the specified equipment and to perform the necessary warranty and product support in accordance with the Contract Documents in the prescribed manner and time.
13. The City of Manitou Springs reserves the right, if it deems such action to be in its best interests, to reject all Bids or to waive any irregularities or informalities therein.
Any incomplete, false, or misleading information provided by any Bidder shall be grounds for rejection of the Bid. If Bids are rejected, the City of Manitou Springs further reserves the right to investigate and accept the next best Bid in order of ranking, or to reject all Bids and re-solicit for additional Bids.
14. No Bid shall include federal excise taxes or state or local sales or use taxes.
15. In the event of any claim, suit, or demand which may result from any Bid, or the award of any contract in result of submission of a Bid, Colorado State law shall govern any such claim, suit, or demand and the rights and duties of the parties.
16. All parts not specifically mentioned which are necessary to provide a complete unit shall be included in the Bid. Any item listed as "Standard" in the manufacturer's published specification, furnished by the Bidder, is assumed to be included in the Bid. Any variations shall be outlined in writing, noting cost factors where applicable.
17. Bids shall be in accordance with the specifications contained in the Contract Documents. Should any requirement in the specifications not be included in manufacturer's specification sheets, the Bidder shall include with its Bid a statement of compliance. Failure to do so shall be grounds for disqualification of the Bid.
18. Each Bid shall include a statement of standard warranty of the manufacturer.
19. Any Bid received as the result of this request is prepared at the Bidder’s expense and becomes City property and is therefore a public record upon opening by the City. No Bid may be withdrawn for a period of sixty (60) days after the deadline for Bids.
20. Failure to complete work on time will result in a daily charge made against the Contractor for each calendar day, including free time, that any work remains uncompleted after the elapse of contract time. This daily charge will be deducted from any money due to the Contractor. This deduction will not be considered a penalty, but as liquidated damaged.
As it will be extremely difficult to estimate the damages, including, but not limited to, indirect and consequential damages, the schedule of liquidated damages set forth below is an amount, agreed to by the Contractor and the City of Manitou
Springs, as reasonable compensation to the City of Manitou Springs if the
Contractor fails to complete performance within fourteen (14) calendar days of the contract time of the stated completion date of June 1, 2025.
Original Contract Amount Liquidated Damages per Calendar Day ($)
0 - $1,000,000 $500
$1,000,000 – $2,000,000 $750
$2,000,000 – $4,000,000 $1,000
$4,000,000 – $7,000,000 $1,500
$7,000,000 – $10,000,000 $2,000
Above $10,000,000 $2,500
Permitting the Contractor to continue and finish the work or any part thereof after elapse of contract time will not operate as a waiver on the part of the City of Manitou Springs rights under the Contract.
Deduction assessed as liquidated damages under this subsection shall not relieve the Contractor from Liability for any damages or costs resulting from delays to other contractors on the project or other projects caused by a failure of the assessed Contractor to complete the work according to contract times.
The City of Manitou Springs is an Equal Opportunity Employer, and no otherwise qualified individual shall be subject to discrimination on the basis of race, color, religion or religious affiliation, sex, familial status, age, genetics, disability, or national origin in any phase of employment for this position.
HORIZ.
VERT.
DESIGNED BY:
DRAWN BY:
CHECKED BY:
SCALE DATE ISSUED: DRAWING No.
SEAL
FOR AND ON BEHALF OF
MATRIX DESIGN GROUP, INC.
PROJECT No.
PREPARED BY:
REFERENCE
DRAWINGS
FILE NAME:
CTB FILE:
PLOT DATE:
THIS DRAWING IS CURRENT AS OF PLOT DATE AND MAY BE SUBJECT TO CHANGE.
COMPUTER FILE MANAGEMENT
No. DATE DESCRIPTION BY
REVISIONS
SHEET No.
SHEET OF
X-Title-GEC
X-1289-EX-MAP
X-1289-EX-BASE
Know what's below.
before you dig.Call
R
BASIS OF BEARING
BENCHMARK
BEARINGS AARE BASED ON THE NORTHEAST LINE OF THAT PARCEL OF LAND DESCRIBED IN
THE SPECIAL WARRANTY DEED RECORDED AT RECEPTION NO. 220201139 IN THE RECORDS OF
THE EL PASO COUNTY CLERK AND RECORDER'S OFFICE, MONUMENTED AT THE NORTHWEST
END BY A 1 INCH YELLOW PLASTIC CAP STAMPED "UP&E, LS 11624", AND AT THE SOUTHEAST END BY A 1 1/2 INCH ALUMINUM CAP STAMPED "DB&CO, PLS 37913", AND IS ASSUMED TO BEAR
SOUTH 71°01'02" EAST, A DISTANCE OF 117.20 FEET.
FIMS MONUMENT MU07 IS A 2-INCH DIAMETER ALUMINUM CAP STAMPED "CSU FIMS CONTROL
MU07" ON SOUTHEAST CORNER OF STORM SEWER INLET ON NORTH SIDE OF MANITOU AVENUE
AT 461 MANITOU AVENUE. ELEVATION WAS ESTABLISHED BY GPS OBSERVATIONS (GEOID 18B)
AND IS REFERENCED TO NGVD29 ELEVATION = 6,289.77 FEET. COORDINATE SYSTEM: NAD83
COLORADO STATE PLACE, CENTRAL ZONE, US SURVEY FOOT.
SHEET KEY
N
MANITOU AVE.
HWY 24
EL PASO BLVD.
FOUNTAIN CREEK
DILLON MOTEL - PARK-N-RIDE
132 - 142 MANITOU AVENUE
MANITOU SPRINGS, COLORADO, 80829
PRELIMINARY & INTERIM GRADING & EROSION CONTROL PLANS
FEBRUARY 2025
OWNER
CIVIL ENGINEER
ENGINEERING DIVISION
CONTRACTOR
SURVEYOR
CITY OF MANITOU SPRINGS
606 MANITOU AVE, MANITOU
SPRINGS, COLORADO 80829
JUAN ALVAREZ, (719) 685-2600
MATRIX DESIGN GROUP
2435 RESEARCH PARKWAY, SUITE 300
COLORADO SPRINGS, COLORADO 80920
JEFFREY ODOR, (719) 575-0100
CITY OF MANITOU SPRINGS
606 MANITOU AVE, MANITOU
SPRINGS, COLORADO 80829
ANDREW MORREN, (719) 685-2569
D2 DEMO & DIRT
3030 N EL PASO STREET
COLORADO SPRINGS, CO 80907
(719) 400-4722
MATRIX DESIGN GROUP
2435 RESEARCH PARKWAY, SUITE 300
COLORADO SPRINGS, COLORADO 80920
WYATT WEISS, (719) 575-0100
1" = 100'
SITE MAP
FOUNTAIN CREEK
EL PASO BLVD.
MANITOU AVE.
DESIGN ENGINEER'S STATEMENT:
THIS GRADING AND EROSION CONTROL PLAN WAS PREPARED UNDER MY DIRECTION
AND SUPERVISION AND IS CORRECT TO THE BEST OF MY KNOWLEDGE AND BELIEF.
SAID PLAN HAS BEEN PREPARED ACCORDING TO THE CRITERIA ESTABLISHED BY THE
COUNTY FOR GRADING AND EROSION CONTROL PLANS. I ACCEPT RESPONSIBILITY
FOR ANY LIABILITY CAUSED BY ANY NEGLIGENT ACTS, ERRORS OR OMISSIONS ON MY
PART IN PREPARING THIS PLAN.
ENGINEER OF RECORD DATE
OWNER/DEVELOPER'S STATEMENT:
I, THE OWNER/DEVELOPER HAVE READ AND WILL COMPLY WITH THE REQUIREMENTS
OF THE GRADING AND EROSION CONTROL PLAN.
OWNER SIGNATURE DATE
CITY OF MANITOU SPRINGS:
THE CITY OF MANITOU SPRINGS PLAN REVIEW IS PROVIDED ONLY FOR GENERAL
CONFORMANCE WITH CITY OF MANITOU SPRINGS DESIGN CRITERIA. THE SITY IS NOT
RESPONSIBLE FOR THE ACCURACY AND ADEQUACY OF THE DESIGN, DIMENSIONS,
AND/ OR ELEVATIONS WHICH SHALL BE CONFIRMED AT THE JOB SITE. THE CITY
THROUGH THE APPROVAL OF THIS DOCUMENT ASSUMES NO RESPONSIBILITY FOR
COMPLETENESS AND/ OR ACCURACY OF THIS DOCUMENT.
FILED IN ACCORDANCE WITH THE REQUIREMENTS OF THE CITY OF MANITOU SPRINGS
LAND DEVELOPMENT CODE, DRAINAGE CRITERIA MANUAL, VOLUMES 1 AND 2, AND
ENGINEERING CRITERIA MANUAL AS AMENDED.
IN ACCORDANCE WITH ECM SECTION 1.12, THESE CONSTRUCTION DOCUMENTS WILL
BE VALID FOR CONSTRUCTION FOR A PERIOD OF 2 YEARS FROM THE DATE SIGNED BY
THE CITY ENGINEER. IF CONSTRUCTION HAS NOT STARTED WITHIN THOSE 2 YEARS,
THE PLANS WILL NEED TO BE RESUBMITTED FOR APPROVAL, INCLUDING PAYMENT OF
REVIEW FEES AT THE PLANNING AND COMMUNITY DEVELOPMENT DIRECTORS
DISCRETION.
CITY PROJECT ENGINEER SIGNATURE DATE
PROJECT SITE
SHEET LIST TABLE
SHEET TITLE SHEET DESCRIPTION SHEET NUMBER
TS01 TITLE SHEET 1
GN01 EROSION CONTROL NOTES 2
GN02 EROSION CONTROL NOTES 3
GEC01 PRELIMINARY GRADING & EROSION CONTROL PLAN 4
ECN01 EROSION CONTROL DETAILS 6
AGENCIES CONTACT INFORMATION:
VICINITY MAP
N.T.S.
MANITOU AVE.
HWY 24
FOUNTAIN CREEK
PROJECT SITE
EL PASO BLVD
2/11/2025 12:36 PM
Matrix.ctb S:\24.1289.003 Dillon Motel Park N Ride\500 CADD\504 Plan Sets\Construction Plans\GEC Plan\TS01.dwg
DILLON MOTEL - PARK-N-RIDE
MANITOU SPRINGS, COLORADO
GRADING AND EROSION CONTROL PLANS
TITLE SHEET
24.1289.003
KGI
KGI
MDF N/A
FEBRUARY 2025
7 TS01
N/A
GEC02 INTERIM GRADING & EROSIONS CONTROL PLAN 5
DESIGNED BY:
DRAWN BY:
CHECKED BY:
SCALE DATE ISSUED: DRAWING No.
SEAL
FOR AND ON BEHALF OF
MATRIX DESIGN GROUP, INC.
PROJECT No.
PREPARED BY:
REFERENCE
DRAWINGS
FILE NAME:
CTB FILE:
PLOT DATE:
THIS DRAWING IS CURRENT AS OF PLOT DATE AND MAY BE SUBJECT TO CHANGE.
COMPUTER FILE MANAGEMENT
No. DATE DESCRIPTION BY
REVISIONS
SHEET No.
SHEET OF
X-Title-GEC
X-1289-EX-MAP
X-1289-EX-BASE
Know what's below.
before you dig.Call
R
BASIS OF BEARING
BENCHMARK
BEARINGS AARE BASED ON THE NORTHEAST LINE OF THAT PARCEL OF LAND DESCRIBED IN
THE SPECIAL WARRANTY DEED RECORDED AT RECEPTION NO. 220201139 IN THE RECORDS OF
THE EL PASO COUNTY CLERK AND RECORDER'S OFFICE, MONUMENTED AT THE NORTHWEST
END BY A 1 INCH YELLOW PLASTIC CAP STAMPED "UP&E, LS 11624", AND AT THE SOUTHEAST END BY A 1 1/2 INCH ALUMINUM CAP STAMPED "DB&CO, PLS 37913", AND IS ASSUMED TO BEAR
SOUTH 71°01'02" EAST, A DISTANCE OF 117.20 FEET.
FIMS MONUMENT MU07 IS A 2-INCH DIAMETER ALUMINUM CAP STAMPED "CSU FIMS CONTROL
MU07" ON SOUTHEAST CORNER OF STORM SEWER INLET ON NORTH SIDE OF MANITOU AVENUE
AT 461 MANITOU AVENUE. ELEVATION WAS ESTABLISHED BY GPS OBSERVATIONS (GEOID 18B)
AND IS REFERENCED TO NGVD29 ELEVATION = 6,289.77 FEET. COORDINATE SYSTEM: NAD83
COLORADO STATE PLACE, CENTRAL ZONE, US SURVEY FOOT.
SHEET KEY
N
MANITOU AVE.
HWY 24
EL PASO BLVD.
FOUNTAIN CREEK
GENERAL CONSTRUCTION NOTES:
1. ALL MATERIALS AND WORKMANSHIP SHALL BE IN CONFORMANCE WITH THE CITY OF MANITOU SPRINGS
SPECIFICATIONS, UNLESS NOTED OTHERWISE.
2. IT IS SUGGESTED THAT THE CONTRACTOR INITIATE A REQUEST TO THE COLORADO SPRINGS UTILITIES FOR ANY
CONSTRUCTION RELATED TEMPORARY ELECTRICAL POWER SOURCES AS SOON AS POSSIBLE. IN SOME
INSTANCES UP TO 30 DAYS MAY BE REQUIRED TO PROVIDE THE SOURCE.
3. THE CONTRACTOR IS RESPONSIBLE FOR THE RE-ESTABLISHMENT OF ALL SURVEY MONUMENTS DISTURBED
WITHIN THE PROJECT LIMITS.
4. THE CONTRACTOR IS RESPONSIBLE FOR PROVIDING THEIR OWN ESTIMATE OF EARTHWORK QUANTITIES.
5. IF ANY EXISTING STRUCTURES TO REMAIN ARE DAMAGED DURING CONSTRUCTION, IT SHALL BE THE CONTRACTOR'S RESPONSIBILITY TO INSPECT, REPAIR, AND/OR REPLACE THE EXISTING STRUCTURES AS
NECESSARY TO RETURN THEM TO EXISTING CONDITIONS OR BETTER.
6. CONTRACTOR SHALL ADJUST AND/OR REMOVE AND REPLACE EXISTING PAVEMENT AS NECESSARY TO ASSURE
A SMOOTH FIT AND CONTINUOUS GRADE.
7. CONSTRUCTION SHALL COMPLY WITH ALL APPLICABLE GOVERNING CODES AND BE CONSTRUCTED TO SAME.
8. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO VERIFY THE EXISTENCE AND LOCATION OF ALL UNDERGROUND AND ABOVE GROUND UTILITIES WITHIN AND ADJACENT TO THE SITE. PRIOR TO ANY EXCAVATION, CONTACT THE UTILITY NOTIFICATION CENTER OF COLORADO AT 811 AT LEAST TWO WORKING DAYS PRIOR TO DIGGING. THE OMISSION FROM OR THE INCLUSION OF UTILITY LOCATIONS ON THE PLANS IS NOT TO BE CONSIDERED AS THE NONEXISTENCE OF OR A DEFINITE LOCATION OF EXISTING UNDERGROUND UTILITIES. THE CONTRACTOR ASSUMES RESPONSIBILITY FOR THE PROTECTION OF ALL UTILITIES DURING THE WORK. ANY DAMAGE TO THE EXISTING UTILITIES WILL BE REPAIRED AT THE CONTRACTOR'S EXPENSE AND ANY
SERVICE DISRUPTION WILL BE SETTLED BY THE CONTRACTOR.
9. ALL UTILITIES (MANHOLES, VALVE COVERS, CLEANOUTS, VAULTS, BOXES, ETC.) SHALL BE ADJUSTED TO FINAL
GRADE.
GENERAL GRADING NOTES:
1. THE SITE SHALL BE STRIPPED A MINIMUM OF 0.5' BELOW EXISTING GRADE. STRIPPED TOPSOIL SHALL REMAIN
ONSITE IN THE DESIGNATED STOCKPILE LOCATIONS PER NPDES.
2. MAXIMUM CUT/FILL SLOPES SHALL NOT EXCEED 3:1, UNLESS OTHERWISE NOTED. ALL SLOPES MUST BE
PROTECTED FROM EROSION.
3. IF DURING THE OVERLOT GRADING PROCESS, CONDITIONS ARE ENCOUNTERED WHICH COULD INDICATE AN UNIDENTIFIED SITUATION IS PRESENT, THE SOILS ENGINEER SHALL BE CONTACTED FOR RECOMMENDATIONS.
4. THE CONTRACTOR SHALL PROTECT ALL WORK AREAS AND FACILITIES FROM FLOODING AT ALL TIMES. AREAS AND FACILITIES SUBJECTED TO FLOODING, REGARDLESS OF THE SOURCE OF WATER, SHALL BE PROMPTLY
DEWATERED AND RESTORED.
5. THE CONTRACTOR IS RESPONSIBLE FOR PREVENTING AND CONTROLLING EROSION DURING CONSTRUCTION
ACTIVITIES AT ALL TIMES DURING GRADING AND CONSTRUCTION.
6. SPOT ELEVATIONS SHALL TAKE PRECEDENCE OVER CONTOURS AND SLOPES SHOWN. THE CONTRACTOR SHALL NOTIFY THE ENGINEER OF THE SPOT ELEVATIONS THAT DO NOT APPEAR TO BE CONSISTENT WITH THE
CONTOURS AND SLOPES.
7. BENCHMARK VERIFICATION: CONTRACTOR SHALL USE BENCHMARKS AND DATUMS SHOWN HEREON TO SET PROJECT BENCHMARK(S), AND SHALL PROVIDE SURVEY NOTES OF SUCH TO PROJECT ENGINEER PRIOR TO
COMMENCING CONSTRUCTION.
8. SPOT ELEVATIONS REPRESENT FLOW LINE OR FINISH GRADE UNLESS OTHERWISE NOTED.
9. EXISTING GRADE CONTOUR INTERVALS SHOWN AT 1 FOOT INTERVALS.
10. PROPOSED GRADE CONTOUR INTERVALS SHOWN AT 1 FOOT INTERVALS.
TIMING
ANTICIPATED STARTING AND COMPLETION TIME PERIOD OF SITE GRADING:
AUGUST 2024 - JUNE 2025
EXPECTED DATE ON WHICH THE FINAL STABILIZATION WILL BE COMPLETED:
DECEMBER 2025
AREAS
1. TOTAL AREA OF THE SITE TO BE CLEARED, EXCAVATED OR GRADED FOR THE PRELIMINARY GRADING:
0.67 ACRES
2. TOTAL AREA OF THE SITE TO BE CLEARED, EXCAVATED OR GRADED FOR THE INTERIM GRADING:
0.99 ACRES
RECEIVING WATERS: FOUNTAIN CREEK
OPINION OF PROBABLE EROSION CONTROL COSTS
1. SILT FENCE 1,190 L.F. AT $3.00 = $ 3,570.00
2. SEDIMENT CONTROL LOG 78 L.F. AT $8.00 = $ 624.00
3. VEHICLE TRACKING CONTROL (1) EACH AT $3,085.00 = $ 3,085.00
$ 7,279.00
MAINTENANCE CONTINGENCY (40%) = $ 2,911.60
TOTAL = $ 10,190.60
MATRIX DESIGN GROUP, INC. CANNOT AND DOES NOT GUARANTEE THAT THE CONSTRUCTION COSTS WILL NOT VARY FROM THESE OPINIONS OF PROBABLE COSTS. THESE OPINIONS REPRESENT OUR BEST JUDGEMENT AS A DESIGN
PROFESSIONAL, FAMILIAR WITH THE CONSTRUCTION INDUSTRY AND THIS DEVELOPMENT.
GENERAL NOTES:
1. ANY LAND DISTURBANCE BY ANY OWNER, DEVELOPER, BUILDER, CONTRACTOR, OR OTHER PERSON SHALL COMPLY WITH THE BASIC GRADING, EROSION AND STORMWATER QUALITY CONTROL REQUIREMENTS BASED ON
THE CITY OF MANITOU SPRINGS STANDARDS AND CRITERIA.
2. NO CLEARING, GRADING, EXCAVATION, FILLING OR OTHER LAND DISTURBING ACTIVITIES SHALL BE PERMITTED UNTIL SIGNOFF AND ACCEPTANCE OF THE GRADING PLAN AND EROSION AND STORMWATER QUALITY CONTROL
PLAN IS RECEIVED FROM ENGINEERING DEVELOPMENT REVIEW.
3. SEDIMENT TRANSPORTED ONTO A PUBLIC ROAD, REGARDLESS OF THE SIZE OF THE SITE,
SHALL BE CLEANED IMMEDIATELY.
4. THE GRADING AND EROSION CONTROL PLANS WILL BE SUBJECT TO RE-REVIEW AND RE-ACCEPTANCE BY ENGINEER OF RECORD SHOULD ANY OF THE FOLLOWING OCCUR: GRADING DOES NOT COMMENCE WITHIN TWELVE (12) MONTHS OF THE CITY ENGINEER'S ACCEPTANCE OF THE PLAN, A CHANGE IN PROPERTY
OWNERSHIP, PROPOSED DEVELOPMENT CHANGES, OR PROPOSED GRADING REVISIONS.
5. THE PLAN SHALL NOT SUBSTANTIALLY CHANGE THE DEPTH OF COVER, OR ACCESS TO EXISTING UTILITY FACILITIES. ACCEPTANCE OF THIS PLAN DOES NOT CONSTITUTE APPROVAL TO GRADE IN ANY UTILITY EASEMENT OR RIGHT OF WAY. APPROVALS TO GRADE WITHIN UTILITY EASEMENTS MUST BE OBTAINED FROM THE APPROPRIATE UTILITY COMPANY. IT IS NOT PERMISSIBLE FOR ANY PERSON TO MODIFY THE GRADE OF THE EARTH ON ANY COLORADO SPRINGS UTILITIES EASEMENT OR UTILITY RIGHT-OF-WAY WITHOUT THEIR WRITTEN APPROVAL. THE PLAN SHALL NOT INCREASE OR DIVERT WATER TOWARDS UTILITY FACILITIES. ANY CHANGES TO EXISTING UTILITY FACILITIES TO ACCOMMODATE THE PLAN MUST BE APPROVED BY THE AFFECTED UTILITY OWNER PRIOR TO IMPLEMENTING THE PLAN. THE RESULTING COST TO RELOCATE OR PROTECT EXISTING
UTILITIES OR TO PROVIDE INTERIM ACCESS IS AT THE EXPENSE OF THE PLAN APPLICANT.
6. NON-STRUCTURAL EROSION CONTROL MEASURES THAT ARE NOT DESIGNATED WITHIN THE PLAN SET ARE
STREET SWEEPING, LANDSCAPING AND VEGETATIVE BUFFER STRIPS.
NRCS SOIL SURVEY FOR EL PASO COUNTY
HYDROLOGIC
SOIL ID NO. SOIL TYPE CLASSIFICATION
20 CONNERTON-ROCK OUTCROP D
COMPLEX (8% TO 90% SLOPES)
101 USTIC TORRIFLUVENTS, LOAMY B
2/11/2025 12:36 PM
Matrix.ctb S:\24.1289.003 Dillon Motel Park N Ride\500 CADD\504 Plan Sets\Construction Plans\GEC Plan\TS01.dwg
DILLON MOTEL - PARK-N-RIDE
MANITOU SPRINGS, COLORADO
GRADING AND EROSION CONTROL PLANS
EROSION CONTROL NOTES
24.1289.003
KGI
KGI
MDF N/A
FEBRUARY 2025
7 GN01
N/A
DESIGNED BY:
DRAWN BY:
CHECKED BY:
SCALE DATE ISSUED: DRAWING No.
SEAL
FOR AND ON BEHALF OF
MATRIX DESIGN GROUP, INC.
PROJECT No.
PREPARED BY:
REFERENCE
DRAWINGS
FILE NAME:
CTB FILE:
PLOT DATE:
THIS DRAWING IS CURRENT AS OF PLOT DATE AND MAY BE SUBJECT TO CHANGE.
COMPUTER FILE MANAGEMENT
No. DATE DESCRIPTION BY
REVISIONS
SHEET No.
SHEET OF
X-Title-GEC
X-1289-EX-MAP
X-1289-EX-BASE
Know what's below.
before you dig.Call
R
BASIS OF BEARING
BENCHMARK
BEARINGS AARE BASED ON THE NORTHEAST LINE OF THAT PARCEL OF LAND DESCRIBED IN
THE SPECIAL WARRANTY DEED RECORDED AT RECEPTION NO. 220201139 IN THE RECORDS OF
THE EL PASO COUNTY CLERK AND RECORDER'S OFFICE, MONUMENTED AT THE NORTHWEST
END BY A 1 INCH YELLOW PLASTIC CAP STAMPED "UP&E, LS 11624", AND AT THE SOUTHEAST END BY A 1 1/2 INCH ALUMINUM CAP STAMPED "DB&CO, PLS 37913", AND IS ASSUMED TO BEAR
SOUTH 71°01'02" EAST, A DISTANCE OF 117.20 FEET.
FIMS MONUMENT MU07 IS A 2-INCH DIAMETER ALUMINUM CAP STAMPED "CSU FIMS CONTROL
MU07" ON SOUTHEAST CORNER OF STORM SEWER INLET ON NORTH SIDE OF MANITOU AVENUE
AT 461 MANITOU AVENUE. ELEVATION WAS ESTABLISHED BY GPS OBSERVATIONS (GEOID 18B)
AND IS REFERENCED TO NGVD29 ELEVATION = 6,289.77 FEET. COORDINATE SYSTEM: NAD83
COLORADO STATE PLACE, CENTRAL ZONE, US SURVEY FOOT.
SHEET KEY
N
MANITOU AVE.
HWY 24
EL PASO BLVD.
FOUNTAIN CREEK
CFS CUBIC FEET PER SECOND
BOULEVARDBLVD
BTM BOTTOM
AVERAGEAVG
OFFSETO/S
LP LOW POINT
VERTICAL CURVEVC
SIDEWALKSW or S/W
TANGENTTAN
RIGHT-OF-WAYROW
PRC POINT OF REVERSE CURVE
POINT OF CURB RETURNPCR
PC POINT OF CURVATURE
LEFTLT
LANELN
HYDRAULIC GRADE LINEHGL
FLARED END SECTIONFES
EASEMENTESMT
EGL ENERGY GRADE LINE
CDOT COLORADO DEPARTMENT OF TRANSPORTATION
POINT OF VERTICAL TANGENTPVT
POINT OF TANGENCYPT
UTILITYUTIL
POINT OF VERTICAL INTERSECTIONPVI
POINT OF COMPOUND CURVEPCC
VERTICAL CURVE FACTORK
ASSY
ASTM
APPROX
CEN
C or CLL
CONC
CONST
CONT
DIA
DWG
ELEV or EL
EX or EXIST
F or FL
FLG
FT
HORIZ
INV
LF
MH
MIN
MJ
NTS
P or P/LL
PVC
R or RAD
PR
PVMT
RED
REF
REQ
REV
STA
STD
TB
TYP
UG
VERT
W w/
ASSEMBLY
AMERICAN SOCIETY OF TESTING AND MATERIALS
APPROXIMATE or APPROXIMATELY
CENTER
CENTERLINE
CONCRETE
CONSTRUCTION
CONTINUOUS
DIAMETER
DRAWING
ELEVATION
EXISTING
FLOWLINE
FLANGE
FOOT/FEET
HORIZONTAL
INVERT
LINEAR FEET
MANHOLE
MINIMUM
MECHANICAL JOINT
NOT TO SCALE
PROPERTY LINE
PROPOSED
POINT OF VERTICAL CURVE or POLYVINYL CHLORIDE
PAVEMENT
RADIUS
REDUCER
REFERENCE
REQUIRED
REVISION
STATION
STANDARD
THRUST BLOCK
TYPICAL
UNDERGROUND
VERTICAL
WIDTH
WITH
ABBREVIATIONS
AVENUEAVE
EACHEA
HP HIGH POINT
HORIZONTAL CONTROL LINEHCL
MAX MAXIMUM
RCP REINFORCED CONCRETE PIPE
RT RIGHT
SS SANITARY SEWER
ST STREET
SD STORM SEWER
SANITARY SEWERSAN-SEW
TOP BACK OF CURBTBC
PROPOSED CURB & GUTTER
EXISTING CURB & GUTTER
EXISTING SIGN
EXISTING STORM INLET
PROPOSED CENTERLINE
EXISTING WATER VALVE
EXISTING STORM MANHOLE
SYMBOLS
EXISTING POWER POLE
EXISTING PAVED ROAD
FIRE HYDRANT
EXISTING SANTARY MANHOLE
STANDARD GEC PLAN NOTES:
1. NO CLEARING, GRADING, EXCAVATION, OR OTHER LAND DISTURBING ACTIVITIES SHALL BE ALLOWED (EXCEPT FOR WORK DIRECTLY RELATED TO THE INSTALLATION OF INITIAL CONTROL MEASURES) UNTIL A CITY GEC PERMIT HAS BEEN ISSUED.
2. ALL LAND DISTURBING ACTIVITIES MUST BE PERFORMED IN ACCORDANCE WITH AND THE APPROVED GEC PLAN AND CSWMP.
3. INITIAL CONTROL MEASURES SHALL BE INSTALLED AND INSPECTED PRIOR TO ANY LAND DISTURBANCE ACTIVITIES TAKING PLACE. AN INITIAL SITE INSPECTION WILL NOT BE SCHEDULED UNTIL A CITY GEC PERMIT HAS BEEN "CONDITIONALLY APPROVED." CALL CITY STORMWATER INSPECTIONS, 385-5980, AT LEAST 48 HOURS PRIOR TO CONSTRUCTION TO SCHEDULE AN INITIAL INSPECTION AND OBTAIN FULL PERMIT APPROVAL.
4. INDIVIDUALS SHALL COMPLY WITH THE "COLORADO WATER QUALITY CONTROL ACT" (TITLE 25, ARTICLE 8, CRS) AND THE "CLEAN WATER ACT" (33 USC 1344), INCLUDING REGULATIONS PROMULGATED AND CERTIFICATIONS OR PERMITS ISSUED, IN ADDITION TO THE REQUIREMENTS INCLUDED IN THE CITY'S MS4 PERMIT, STORMWATER CONSTRUCTION MANUAL. IN THE EVENT OF CONFLICTS BETWEEN THESE REQUIREMENTS AND WATER QUALITY CONTROL LAWS, RULES, OR REGULATIONS OF OTHER FEDERAL OR STATE AGENCIES, THE MORE RESTRICTIVE LAWS, RULES, OR REGULATIONS SHALL
APPLY.
5. STORMWATER DISCHARGES FROM CONSTRUCTION SITES SHALL NOT CAUSE OR THREATEN TO CAUSE POLLUTION, CONTAMINATION, OR DEGRADATION OF STATE WATERS. ALL WORK AND EARTH DISTURBANCE SHALL BE DONE IN A MANNER THAT MINIMIZES PPOLLUTION OF ANY ON-SITE
OR OFF-SITE WATERS, INCLUDING WETLANDS.
6. ALL CONSTRUCTION CONTROL MEASURES SHALL BE MAINTAINED UNTIL PERMANENT STABILIZATION MEASURES ARE IMPLEMENTED. TEMPORARY
CONSTRUCTION CONTROL MEASURES MUST BE REMOVED PRIOR TO PERMIT CLOSEOUT.
7. CONCRETE WASH WATER SHALL NOT BE DISCHARGED TO OR ALLOWED TO RUNOFF TO STATE WATERS OR ANY SURFACE OR SUBSURFACE STORM
DRAINAGE SYSTEM OR FACILITIES.
8. BUILDING, CONSTRUCTION, EXCAVATION, OR OTHER WASTE MATERIALS SHALL NOT BE TEMPORARILY PLACED OR STORED IN THE STREET, ALLEY, OR OTHER PUBLIC WAY, UNLESS IN ACCORDANCE WITH AN APPROVED TRAFFIC CONTROL PLAN. CONSTRUCTION CONTROL MEASURES MAY BE REQUIRED BY THE GEC INSPECTOR IF DEEMED NECESSARY BASED ON SPECIFIC CONDITIONS AND CIRCUMSTANCES (E.G., ESTIMATED TIME OF EXPOSURE, SEASON OF THE YEAR, ETC.).
9. ALL WASTES COMPOSED OF BUILDING MATERIALS MUST BE REMOVED FROM THE CONSTRUCTION SITE FOR DISPOSAL IN ACCORDANCE WITH LOCAL AND STATE REGULATORY REQUIREMENTS. NO BUILDING MATERIAL WASTES OR UNUSED BUILDING MATERIALS SHALL BE BURIED, DUMPED, OR
DISCHARGED AT THE SITE.
10. THE PERMITTEE SHALL BE RESPONSIBLE FOR THE REMOVAL OF ALL CONSTRUCTION DEBRIS, DIRT, TRASH, ROCK, SEDIMENT, AND SAND THAT MAY ACCUMULATE IN THE STORM SEWER OR OTHER DRAINAGE CONVEYANCE SYSTEM AS A RESULT OF CONSTRUCTION ACTIVITIES.
11. THE QUANTITY OF MATERIALS STORED ON THE PROJECT SITE SHALL BE LIMITED, AS MUCH AS PRACTICAL, TO THAT QUANTITY REQUIRED TO PERFORM THE WORK IN AN ORDERLY SEQUENCE. ALL MATERIALS STORED ON-SITE SHALL BE STORED IN A NEAT, ORDERLY MANNER, IN THEIR ORIGINAL CONTAINERS, WITH ORIGINAL MANUFACTURER'S LABELS. MATERIALS SHALL NOT BE STORED IN A LOCATION WHERE THEY MAY BE CARRIED
BY STORMWATER RUNOFF INTO THE STORM SEWER SYSTEM AT ANY TIME.
12. SPILL PREVENTION AND CONTAINMENT MEASURES SHALL BE USED AT ALL STORAGE, EQUIPMENT FUELING, AND EQUIPMENT SERVICING AREAS SO AS TO CONTAIN ALL SPILLS AND PREVENT ANY SPILLED MATERIAL FROM ENTERING THE MS4, INCLUDING ANY SURFACE OR SUBSURFACE STORM DRAINAGE SYSTEM OR FACILITY. BULK STORAGE STRUCTURES FOR PETROLEUM PRODUCTS AND OTHER CHEMICALS SHALL HAVE SECONDARY CONTAINMENT OR EQUIVALENT ADEQUATE PROTECTION. ALL SPILLS SHALL BE CLEANED UP IMMEDIATELY AFTER DISCOVERY, OR CONTAINED UNTIL APPROPRIATE CLEANUP METHODS CAN BE EMPLOYED. MANUFACTURER'S RECOMMENDED METHODS FOR SPILL CLEANUP SHALL BE FOLLOWED, ALONG WITH PROPER DISPOSAL METHODS.
13. SEDIMENT (MUD AND DIRT) TRANSPORTED ONTO A PUBLIC ROAD, REGARDLESS OF THE SIZE OF THE SITE, SHALL BE CLEANED AS SOON AS POSSIBLE
AFTER DISCOVERY.
14. NO CHEMICALS ARE TO BE ADDED TO THE DISCHARGE UNLESS PERMISSION FOR THE USE OF A SPECIFIC CHEMICAL IS GRANTED BY THE STATE. IN GRANTING THE USE OF SUCH CHEMICALS, SPECIAL CONDITIONS AND MONITORING MAY BE REQUIRED.
15. CONTROL MEASURES FOR ALL SLOPES, CHANNELS, DITCHES, OR ANY DISTURBED LAND AREA SHALL BE COMPLETED WITHIN FOURTEEN (14) CALENDAR DAYS AFTER FINAL GRADING OR FINAL LAND DISTURBANCE HAS BEEN COMPLETED. DISTURBED AREAS WHICH ARE NOT AT FINAL GRADE BUT WILL REMAIN DORMANT FOR LONGER THAN FOURTEEN (14) DAYS SHALL BE ROUGHENED, MULCHED, TACKIFIED, OR STABILIZED WITH TARPS WITHIN FOURTEEN (14) DAYS AFTER INTERIM GRADING. AN AREA THAT IS GOING TO REMAIN IN AN INTERIM STATE FOR MORE THAN SIXTY (60) DAYS SHALL ALSO BE SEEDED, UNLESS AN ALTERNATIVE STABILIZATION MEASURE IS ACCEPTED AT THE INSPECTOR'S DISCRETION. ALL TEMPORARY CONSTRUCTION CONTROL MEASURES SHALL BE MAINTAINED UNTIL FINAL STABILIZATION IS ACHIEVED.
16. THE GEC PLAN WILL BE SUBJECT TO RE-REVIEW AND RE-ACCEPTANCE BY THE STORMWATER ENTERPRISE SHOULD ANY OF THE FOLLOWING OCCUR:
GRADING DOES NOT COMMENCE WITHIN TWELVE (12) MONTHS OF THE CITY'S ACCEPTANCE OF THE PLAN, THE CONSTRUCTION SITE IS IDLE FOR TWELVE (12) CONSECUTIVE MONTHS, A CHANGE IN PROPERTY OWNERSHIP OCCURS, THE PLANNED DEVELOPMENT CHANGES, OR ANY OTHER MAJOR
MODIFICATIONS ARE PROPOSED AS DEFINED IN THE STORMWATER CONSTRUCTION MANUAL.
17. IT IS NOT PERMISSIBLE FOR ANY PERSON TO MODIFY THE GRADE OF THE EARTH ON ANY UTILITY EASEMENT OR UTILITY RIGHT-OF-WAY WITHOUT WRITTEN APPROVAL FROM THE UTILITY OWNER. CITY ACCEPTANCE OF THE GEC PLAN AND CSWMP DOES NOT SATISFY THIS REQUIREMENT. THE PLAN SHALL NOT INCREASE OR DIVERT WATER TOWARDS UTILITY FACILITIES. ANY CHANGES TO EXISTING UTILITY FACILITIES TO ACCOMMODATE THE PLAN MUST BE APPROVED BY THE AFFECTED UTILITY OWNER PRIOR TO IMPLEMENTING THE PLAN. THE COST TO RELOCATE OR PROTECT EXISTING
UTILITIES OR TO PROVIDE INTERIM ACCESS SHALL BE AT THE APPLICANT'S EXPENSE.
18. APPLICANT REPRESENTS AND WARRANTS THAT THEY HAVE THE LEGAL AUTHORITY TO GRADE AND/OR CONSTRUCT IMPROVEMENTS ON ADJACENT PROPERTY. THE CITY HAS NOT REVIEWED THE DEVELOPER'S AUTHORITY TO MODIFY ADJACENT PROPERTY. AN APPROVED GEC PERMIT DOES NOT
PROVIDE APPROVAL FOR THE APPLICANT TO PERFORM WORK ON ADJACENT PROPERTY.
19. ALL UTILITY INSTALLATIONS WITHIN THE LIMITS OF DISTURBANCE SHOWN ON THIS PLAN ARE COVERED UNDER THIS PLAN. LOCATIONS OF UTILITIES WITHIN THE LIMITS OF DISTURBANCE MAY BE MODIFIED AFTER PLAN APPROVAL AS A FIELD CHANGE. UTILITY INSTALLATIONS RELATED TO THE PRIVATE DEVELOPMENT THAT EXTEND BEYOND THE LIMITS OF DISTURBANCE SHOWN ON THIS PLAN ARE CONSIDERED TO BE PART OF THE LARGER DEVELOPMENT, AND THEREFORE REQUIRE A PLAN MODIFICATION OR SEPARATE PLAN FOR THE ADDITIONAL DISTURBANCE AREA.
PROPOSED CONTOURS
EXISTING CONTOURS
LIMITS OF DISTURBANCE/
CONSTRUCTION SITE BOUNDARY
PROJECT BOUNDARY LINE
EX UNDERGROUND ELECTRIC
EX UNDERGROUND CABLE TV
EX UNDERGROUND GAS
EX SANITARY SEWER
EX UNDERGROUND TELECOM
EX WATER
EX WATER 8" CIP
EX WATER 30" DIP
2/11/2025 12:36 PM
Matrix.ctb S:\24.1289.003 Dillon Motel Park N Ride\500 CADD\504 Plan Sets\Construction Plans\GEC Plan\TS01.dwg
DILLON MOTEL - PARK-N-RIDE
MANITOU SPRINGS, COLORADO
GRADING AND EROSION CONTROL PLANS
EROSION CONTROL NOTES
24.1289.003
KGI
KGI
MDF N/A
FEBRUARY 2025
7 GN02
UVE
C
UVF
ETWV
EM
SS
EM
GM
GM
C
UVC
EM
W
WV
UVC
G
CO
CO
CO
CO
401359 6217.18
MISC NOTE - MISC /UTILITY-GREEN-2X4
401363 6217.85
MISC NOTE - MISC /TOP-CONC-LID
CO
MANITOU AVE.
(ROW. VARIES)
FOUNTAIN CREEK
EX. TYPE 2
CURB& GUTTER
EX. BUILDING TO REMAIN
EX. TYPE 2
CURB& GUTTER
SCHEDULE NO: 7404410024
OWNER: CITY OF MANITOU SPRINGS
ADDRESS: 142 MANITOU AVENUE
SCHEDULE NO: 7404410035
OWNER: CITY OF MANITOU SPRINGS
ADDRESS: 134 MANITOU AVENUE
SCHEDULE NO: 7404410036
OWNER: CITY OF MANITOU SPRINGS
ADDRESS: 132 MANITOU AVENUE
SCHEDULE NO: 7404410042
OWNER: MY HOUSING LLC.
ADDRESS: 120 MANITOU AVENUE
EX. SILT
FENCE TO
REMAIN
PROP CONSTRUCTION
FENCE
PROP CONSTRUCTION
FENCE
PROP CONSTRUCTION
FENCE
EX. FENCE
EX. SILT
FENCE TO
REMAIN
23 62
6221 6221 6220
15 62
62236224
EX. UNPAVED
ACCESS ROAD
EX. 45.00'
DRIVEWAY
EX. 35.00'
DRIVEWAY
.25
.7
5%
.6
0%
54.81%
.0
8%
4.7%
5.1%
FEMA FLOODPLAIN
ZONE A
FEMA FLOODPLAIN
ZONE A
FEMA FLOODPLAIN
ZONE X
FEMA FLOODPLAIN
ZONE AE
PROPERTY BOUNDARY
PROPERTY
BOUNDARY
PROPERTY
BOUNDARY
PROPERTY
BOUNDARY
PROP SILT
FENCE
EXISTING TREES (10)
TO REMAIN
EDGE OF EXISTING
PAVEMENT
LIMITS OF
DISTURBANCE
EDGE OF EXISTING
PAVEMENT
EX. ±10' WIDE
RIPRAP RUNDOWN
CONSTRUCTION SITE
ENTRANCE GATE
EX. DRIVEWAY
EX. GRAVEL PARKING
& DRIVE AREA
PROP CONSTRUCTION
FENCE
DENVER & RIO GRAND
WESTERN RAILROAD
(ROW VARIES)
EXISTING TREE
TO BE REMOVED
BY OTHERS
EXISTING WOOD
FENCE TO BE
REMOVED
HORIZ.
VERT.
DESIGNED BY:
DRAWN BY:
CHECKED BY:
SCALE DATE ISSUED: DRAWING No.
SEAL
FOR AND ON BEHALF OF
MATRIX DESIGN GROUP, INC.
PROJECT No.
PREPARED BY:
REFERENCE
DRAWINGS
FILE NAME:
CTB FILE:
PLOT DATE:
THIS DRAWING IS CURRENT AS OF PLOT DATE AND MAY BE SUBJECT TO CHANGE.
COMPUTER FILE MANAGEMENT
No. DATE DESCRIPTION BY
REVISIONS
SHEET No.
SHEET OF
X-1289-EX-BASE
X-1289-EX-MAP
X-Title-GEC
X-1289-EX-UTLS
X-FEMA
Know what's below.
before you dig.Call
R
BASIS OF BEARING
BENCHMARK
BEARINGS AARE BASED ON THE NORTHEAST LINE OF THAT PARCEL OF LAND DESCRIBED IN
THE SPECIAL WARRANTY DEED RECORDED AT RECEPTION NO. 220201139 IN THE RECORDS OF
THE EL PASO COUNTY CLERK AND RECORDER'S OFFICE, MONUMENTED AT THE NORTHWEST
END BY A 1 INCH YELLOW PLASTIC CAP STAMPED "UP&E, LS 11624", AND AT THE SOUTHEAST END BY A 1 1/2 INCH ALUMINUM CAP STAMPED "DB&CO, PLS 37913", AND IS ASSUMED TO BEAR
SOUTH 71°01'02" EAST, A DISTANCE OF 117.20 FEET.
FIMS MONUMENT MU07 IS A 2-INCH DIAMETER ALUMINUM CAP STAMPED "CSU FIMS CONTROL
MU07" ON SOUTHEAST CORNER OF STORM SEWER INLET ON NORTH SIDE OF MANITOU AVENUE
AT 461 MANITOU AVENUE. ELEVATION WAS ESTABLISHED BY GPS OBSERVATIONS (GEOID 18B)
AND IS REFERENCED TO NGVD29 ELEVATION = 6,289.77 FEET. COORDINATE SYSTEM: NAD83
COLORADO STATE PLACE, CENTRAL ZONE, US SURVEY FOOT.
SHEET KEY
N
MANITOU AVE.
HWY 24
EL PASO BLVD.
FOUNTAIN CREEK
2/11/2025 12:36 PM
S:\24.1289.003 Dillon Motel Park N Ride\500 CADD\504 Plan Sets\Construction Plans\GEC Plan\GEC01.dwg
DILLON MOTEL - PARK-N-RIDE
MANITOU SPRINGS, COLORADO
GRADING AND EROSION CONTROL PLANS
PRELIMINARY GRADING & EROSION CONTROL PLAN
22.1289.001
WAN
WAN
MDF N/A
FEBRUARY 2025
7 GEC01
1"=20'
VEHICLE TRACKING
CONTROL
SILT FENCE
EROSION CONTROL LEGEND
PROPOSED CONTOURS
SEDIMENT CONTROL LOG
EXISTING CONTOURS
SLOPE LABEL1.0%
HIGH POINT / LOW POINT
STOCKPILE MANAGEMENT /
STABILIZED STAGING AREA
LIMITS OF DISTURBANCE/
PROPOSED OVERLAND FLOW
CONSTRUCTION SITE BOUNDARY
PROJECT BOUNDARY LINE
EX UNDERGROUND ELECTRIC
EX UNDERGROUND CABLE TV
EX UNDERGROUND GAS
EX SANITARY SEWER
EX UNDERGROUND TELECOM
EX WATER
EX WATER 8" CIP
EXISTING OVERLAND FLOW
PROPOSED CONSTRUCTION FENCE (CHAIN LINK)
FEMA FLOODPLAIN LIMITS
GENERAL NOTES:
1. CONTRACTOR TO FIELD VERIFY LOCATION AND ELEVATION OF ALL EXISTING DRY AND WET UTILITIES PRIOR TO CONSTRUCTION AND NOTIFY ENGINEER OF ANY ISSUES. UTILITY RELOCATION MAY BE
REQUIRED.
2. STRIP AND STOCKPILE TOPSOIL FROM GRADING AREAS. USE STOCKPILED TOPSOIL AND IMPORTED
TOPSOIL AS NECESSARY FOR SURFACE RESTORATION.
3. STOCKPILE LOCATION WILL BE DETERMINED BY THE CONTRACTOR IN ACCORDANCE WITH THE COLORADO SPRINGS STORM WATER CRITERIA MANUAL. STOCKPILE LOCATIONS TO BE DETERMINED
BY THE CONTRACTOR MUST NOT RESULT IN ADDITIONAL LAND DISTURBANCE.
4. GRADE AREAS AT SITE PERIMETER TO MATCH GRADES OF ADJACENT PROPERTIES.
5. REMOVE EXCESS SOIL FROM SITE AND DISPOSE OF PROPERLY IN ACCORDANCE WITH APPLICABLE
REGULATIONS.
6. PROVIDE TEMPORARY GRADING FEATURES SUCH AS BERMS, SWALES, SUMPS AND BASINS TO
MANAGE INTERIM STORM WATER RUNOFF DURING THE CONSTRUCTION PROCESS. STORM WATER
RUNOFF LEAVING THE SITE SHALL MEET ALL FEDERAL, STATE AND LOCAL QUALITY REGULATIONS.
7. CONTOURS ARE AT A 1.0' MINOR 5.0' MAJOR INTERVAL.
8. FREQUENT OBSERVATIONS AND MAINTENANCE OF NONSTRUCTURAL CONTROL MEASURES WILL BE
PERFORMED TO ENSURE NO SEDIMENT LEAVES THE SITE. STREET SWEEPING WILL OCCUR AS
REQUIRED TO KEEP SURROUNDING STREETS CLEAN.
9. THERE ARE NO PRESERVATION EASEMENTS ON THIS SITE.
10. THERE IS NO ASPHALT, CONCRETE ASPHALT PLANTS, OR MASONRY MIX STATIONS NEEDED FOR THE
PROJECT.
11. THIS SITE IS A TRIBUTARY AREA TO FOUNTAIN CREEK.
12. THERE ARE NO GEO HAZARDS FOR THIS PROJECT PER GEOTECHNICAL INVESTIGATION FOR ATLAS
MIDDLE SCHOOL ADDITION PREPARED BY CTL THOMPSON, DATED OCTOBER 13, 2023.
13. THE SITE IS NOT LOCATED WITHIN A STREAM SIDE ZONE NOR IS IT LOCATED WITHIN ANY REGULATORY FLOODWAY OR FLOODPLAIN. SEE FIRM PANEL #08041C0707G EFFECTIVE DECEMBER 7, 2018.
14. TOTAL AREA OF THE SITE WHERE ANY CONSTRUCTIVE ACTIVITY IS EXPECTED TO RESULT IN LAND
DISTURBANCE OF THE GROUND SURFACE: 0.67 ACRES.
CHECK DAM
PORTABLE TOILET
AutoCAD SHX Text
SM
AutoCAD SHX Text
SF
AutoCAD SHX Text
SCL
AutoCAD SHX Text
SF
AutoCAD SHX Text
SCL
AutoCAD SHX Text
CD
AutoCAD SHX Text
PT
AutoCAD SHX Text
SSA
AutoCAD SHX Text
VTC
AutoCAD SHX Text
SF
AutoCAD SHX Text
VTC
AutoCAD SHX Text
SCL
AutoCAD SHX Text
LP
AutoCAD SHX Text
HP
AutoCAD SHX Text
SSA
AutoCAD SHX Text
SM
AutoCAD SHX Text N
AutoCAD SHX Text N
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
60 FT
AutoCAD SHX Text
1" = 20' SCALE BAR
AutoCAD SHX Text
CD
AutoCAD SHX Text
PT
19.55
FFE 19.55
EX. BUILDING
FFE= 6219.55
7.6%
EX. BUILDING
FFE= 6220.60
FL 19.47
8.00'
13.50' 10.00'
6.00'
10.00'
TBC 19.96
FL 19.47
20.03
19.60
19.61
19.47 19.67
0.1%0.6% 0.4%
6.00'
5.00'
FL 19.47
FFE 19.55
19.56 19.60
1.
3%
0.
1%
19.15 19.11
19.15
PROP 2' WIDE CONCRETE
PAN
PROP ADA RAMP
PROP WOODEN
SPLIT RAIL FENCE
19.36
1.
1%
20.00' 22.00'22.00'20.00'
.0
0'
206219
(R7-8) (R7-8, R7-8P)
19.66
MANITOU AVE.
(ROW. VARIES)
FOUNTAIN CREEK
1578 SF
EX BUILDING
FFE 6219.55
634 SF
EX BUILDING
FFE 6220.60
SCHEDULE NO: 7404410024
OWNER: CITY OF MANITOU SPRINGS
ADDRESS: 142 MANITOU AVENUE
SCHEDULE NO: 7404410035
OWNER: CITY OF MANITOU SPRINGS
ADDRESS: 134 MANITOU AVENUE
SCHEDULE NO: 7404410036
OWNER: CITY OF MANITOU SPRINGS
ADDRESS: 132 MANITOU AVENUE
SCHEDULE NO: 7404410042
OWNER: MY HOUSING LLC.
ADDRESS: 120 MANITOU AVENUE
4.5%
9.00'
.0
0'
9.00'
18.00' 9.00'
.0
0'
9.00'
.0
0'
9.00'
.0
0'
9.00'
.0
0'
9.00'
.0
0'
.0
0'
24.00'
.0
0'
.0
0'
24.00' 20 .0
0'
.0
0'
6217 6216
216223
24.00'
.0
0'
.0
0'
EX. TYPE 2
CURB& GUTTER
EX. CHAINLINK
FENCE TO BE REMOVED
PROP WOOD SPLIT
RAIL FENCE
PROP WOOD SPLIT
RAIL FENCE
PROP WOOD SPLIT
RAIL FENCE
EX. UNPAVED
ACCESS ROAD
EX. 35.00'
DRIVEWAY
TO REMAIN
FEMA FLOODPLAIN
ZONE X
FEMA FLOODPLAIN
ZONE AE
PROPERTY BOUNDARY
PROPERTY
BOUNDARY
PROPERTY
BOUNDARY
PROPERTY
BOUNDARY
PROP WOOD SPLIT
RAIL FENCE
EXISTING SIBERIAN ELM
TREES (10)TO REMAIN
LIMITS OF
DISTURBANCE
EX. EDGE OF EXISTING
PAVEMENT
EX. ±10' WIDE
RIPRAP RUNDOWN
EX. 45' DRIVEWAY FOR
CONSTRUCTION USE ONLY
EX. GRAVEL PARKING
& DRIVE AREA
PROP CONCRETE HANDICAP
PARKING STALLS - SEE INSERT
THIS SHEET FOR DETAIL
ADA ROUTE TO BUS
STOP AT 142 MANITOU
AVE, MANITOU SPRINGS,
CO 80829
EXISTING 7'
CONCRETE SIDEWALK
PROP 6.0' CONCRETE
SIDEWALK TO TIE INTO
EXISTING SIDEWALK
PROP WOOD SPLIT
RAIL FENCE
EXISTING TREE
TO BE REMOVED
(BY OTHERS)
MAINTAIN MIN. 24.0'
DRIVE AISLE
EX. CHAINLINK FENCE
TO BE REMOVED
EX. CHAINLINK FENCE
TO BE REMOVED
EX. CHAINLINK FENCE
TO BE REMOVED
PROP WOOD SPLIT
RAIL FENCE
2.60%
4.77% 0.
4.
6217 6216
6:1
EX. SILT FENCE
TO REMAIN
PROPOSED CHAIN LINK
FENCE FOR STAGING
AREA PROTECTION
10' BUILDING
SETBACK
15' LANDSCAPE
SETBACK
10' BUILDING
SETBACK
10' BUILDING
SETBACK
10' BUILDING
SETBACK
15' LANDSCAPE
SETBACK
PROP BOLLARD (7) SEE
SHEET 7 FOR DETAIL
PROP 6" VERTICAL SPILL CURB
SEE SHEET 7 FOR DETAIL
EX. CHAINLINK FENCE TO
BE REMOVED
DEMOLISH 47 LF
EXISTING WOOD
FENCE
PROP 80 LF SILT
FENCE
PROP 55 LF SILT
FENCE
PROP 135 LF
SILT FENCE
PROP 125 LF
SILT FENCE
PROP 105 LF
SILT FENCE
FEMA FLOODPLAIN
ZONE AE
HORIZ.
VERT.
DESIGNED BY:
DRAWN BY:
CHECKED BY:
SCALE DATE ISSUED: DRAWING No.
SEAL
FOR AND ON BEHALF OF
MATRIX DESIGN GROUP, INC.
PROJECT No.
PREPARED BY:
REFERENCE
DRAWINGS
FILE NAME:
CTB FILE:
PLOT DATE:
THIS DRAWING IS CURRENT AS OF PLOT DATE AND MAY BE SUBJECT TO CHANGE.
COMPUTER FILE MANAGEMENT
No. DATE DESCRIPTION BY
REVISIONS
SHEET No.
SHEET OF
X-Title-GEC
X-1289-EX-BASE
X-1289-EX-MAP
X-1289-PR-TEMP_SITE
X-FEMA
Know what's below.
before you dig.Call
R
BASIS OF BEARING
BENCHMARK
BEARINGS AARE BASED ON THE NORTHEAST LINE OF THAT PARCEL OF LAND DESCRIBED IN
THE SPECIAL WARRANTY DEED RECORDED AT RECEPTION NO. 220201139 IN THE RECORDS OF
THE EL PASO COUNTY CLERK AND RECORDER'S OFFICE, MONUMENTED AT THE NORTHWEST
END BY A 1 INCH YELLOW PLASTIC CAP STAMPED "UP&E, LS 11624", AND AT THE SOUTHEAST END BY A 1 1/2 INCH ALUMINUM CAP STAMPED "DB&CO, PLS 37913", AND IS ASSUMED TO BEAR
SOUTH 71°01'02" EAST, A DISTANCE OF 117.20 FEET.
FIMS MONUMENT MU07 IS A 2-INCH DIAMETER ALUMINUM CAP STAMPED "CSU FIMS CONTROL
MU07" ON SOUTHEAST CORNER OF STORM SEWER INLET ON NORTH SIDE OF MANITOU AVENUE
AT 461 MANITOU AVENUE. ELEVATION WAS ESTABLISHED BY GPS OBSERVATIONS (GEOID 18B)
AND IS REFERENCED TO NGVD29 ELEVATION = 6,289.77 FEET. COORDINATE SYSTEM: NAD83
COLORADO STATE PLACE, CENTRAL ZONE, US SURVEY FOOT.
SHEET KEY
N
MANITOU AVE.
HWY 24
EL PASO BLVD.
FOUNTAIN CREEK
2/11/2025 12:36 PM
S:\24.1289.003 Dillon Motel Park N Ride\500 CADD\504 Plan Sets\Construction Plans\GEC Plan\GEC02.dwg
DILLON MOTEL - PARK-N-RIDE
MANITOU SPRINGS, COLORADO
GRADING AND EROSION CONTROL PLANS
INTERIM GRADING & EROSIONS CONTROL PLAN
24.1289.003
KGI
KGI
MDF N/A
FEBRUARY 2025
7 GEC02
N/A
VEHICLE TRACKING
CONTROL
SILT FENCE
EROSION CONTROL LEGEND
PROPOSED CONTOURS
SEDIMENT CONTROL LOG
EXISTING CONTOURS
SLOPE LABEL1.0%
HIGH POINT / LOW POINT
STOCKPILE MANAGEMENT /
STABILIZED STAGING AREA
LIMITS OF DISTURBANCE/
PROPOSED OVERLAND FLOW
CONSTRUCTION SITE BOUNDARY
PROJECT BOUNDARY LINE
EX UNDERGROUND ELECTRIC
EX UNDERGROUND CABLE TV
EX UNDERGROUND GAS
EX…