Daytona Beach Ocean Center Kitchen Renovation
Solicitation number
26-P-126JD, C2096
Issued by
Volusia County, Florida

About this file

This Special Conditions document pertains to the Daytona Beach Ocean Center Kitchen Renovation project in Florida and establishes operational requirements for the general contractor executing the commercial kitchen renovation. The contractor must coordinate work around the Ocean Center's scheduled events, with a blackout calendar provided identifying dates when construction is prohibited. The Ocean Center will designate staging areas in proximity to the project site, though these areas may be relocated as needed for ongoing events. Contractors must restrict parking to designated areas only and secure their work sites and staging areas with 6-foot chain link fencing with black liner and appropriate signage. All equipment, tools, and supplies must be secured in agreed staging areas at the end of each workday. The contractor is required to provide four weeks' advanced notice for any closures of building entrances, exits, or work affecting direct building access, and one week's notice for any extensions beyond the approved timeline.

The contractor must supply and maintain a temporary kitchen facility, including a 20-foot freezer trailer, a 20-foot refrigerated trailer, and a 40-foot high-volume dishwashing trailer equipped with drainage storage tank and grease separator for the full project duration. A quote for the temporary kitchen is provided in the attachments but may require updating due to time changes and must be re-quoted accordingly. Xano 521 is designated as the company responsible for installing the epoxy floor system in the kitchen and commissary, with the color to be determined by the Ocean Center.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIAL CONDITIONS

Contractors will work around the Ocean Center scheduled events.

The events Calender will be provided for the project timeframe identifying blackout dates with no construction permitted. The Calander is subject to change.

The Ocean Center will set up the location of staging areas and will make the best efforts to be close to the project area. Staging area may be relocated for the ongoing events and client’s needs.

Contractors must park in designated areas only. Parking on sidewalks or outside dedicated workspace is prohibited.

Contractors are responsible for securing their work site and staging areas with 6-foot chain link fence with black liner and proper signage. All equipment, tools and supplies must be secured at the end of day is agreed staging areas.

The Ocean Center will need 4-week advanced notice for any closures of building entrances/ exits or work affecting direct building access. Extensions beyond approved time will need 1 week’s notice.

The Contractor will supply the temporary kitchen, 20 FT Freezer trailer, 20 Ft refrigerated trailer and a 40ft high volume dishwashing trailer with drainage storage tank and grease separator for the duration of the project. The quote is provided in the attachments for the temporary kitchen to meet the requirements of schedules events. The quote estimate may have changed due to time and will need to be requoted.

SPECIAL CONDITIONS

Xano 521 will be the company to install the epoxy floor system in the kitchen and commissary color to be determined by the Ocean Center.