This solicitation requests proposals for construction services at Beale Air Force Base in California. The selected contractor will construct a new 10,000 barrel jet fuel tank, transfer pump house with 600 gallon per minute pumps and filtration equipment, two truck offloading stations providing combined 1200 gallon per minute throughput, and modifications to an existing truck fill stand. Additionally, the project includes site preparation such as clearing, grading, demolition and improvements like fencing, paving, drainage and utilities. Optional items include construction of canopies over the offloading stations and unit pricing for removal of contaminated soil. Proposals are due by July 20, 2021 with award planned for September 2021. The estimated value is between $10-25 million. The soliciting agency is the Department of the Army Corps of Engineers, Sacramento District.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DRAFT PRICING SCHEDULE
BID ITEM DESCRIPTIONS QTY
UNIT OF
MEASURE
TOTAL
PRICE
0001 Jet Fuel Storage Tank and Containment Description: The base bid job price and payment constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for construction of one 10,000 Barrel Jet Fuel AST and containment with utilities within 5’-0” of the tanks/containment as well as all associated appurtenances excluding Item 0005 below.
1 JOB $________________
0002 Transfer Pump Shelter and Control Building for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for construction of a new Transfer Pump Shelter and Control Building with two
600 gpm pumps and four filter separators, fuel piping within the facility, 2,000 gal PRT, utilities within 5’-0” of the facility, and all associated appurtenances.
0003 Fuel Truck Off-Load Stations (Unloading) for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for construction of two Truck Off-Loading Stations in series that will provide a nominal off-loading rate of 600 gpm per truck, for a total of 1,200 gpm simultaneously, with truck containment, and utilities within 5’-0” of the and all associated appurtenances.
0004 Fuel Truck Fill Stand
Description: The base bid job price and payment constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for repair by removing and replacing non-standard components to include truck containment, integrating the controls into the new pump shelter, and all associated appurtenances.
0005 Automatic Tank Gauging System (ATG) for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for the
ATG infrastructure, equipment, connection to the system, and all associated appurtenances not included in Item 0001.
0006 Supporting Facilities for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for Site
Preparation, Site Improvements, Utilities, Communications, and Cybersecurity measures not identified above or listed in the options listed below. Site Preparation includes clearing and grading activities as well as demolition of the existing transfer pump shelter, off load stations, pavements, and utilities. Site Improvements entails fencing, gates, seeding, signage, all work necessary for concrete pavement, curbs, sidewalks, access drives, storm drainage piping, trench drains, and spill containment basin. Utilities, Communications, and Cybersecurity to include cathodic protection, canopy and site lighting, transformers, lightning protection, grounding, and diesel standby emergency generation.
0007 Option 1 – Fuel Truck Off-load Canopies Description: The Optional bid job price and payment constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for construction of the two Truck Off-Load canopies above/below ground structure, lighting, and all associated appurtenances.
0008 Option 2 – Unit Price – Contaminated Soil Description: All work complete for offsite removal, stockpile, quantify, and testing of fuel contaminated soil. See specifications Sections 01 00 00, 01 22
00, and 01 57 19 for requirements.
50 Cubic Yard