This statement of work describes a design-build project for replacement of domestic hot water piping at the Edith Green-Wendell Wyatt Federal Building in Portland, Oregon. The project scope includes removing polypropylene piping serving Zones 2 and 3 and replacing it with copper piping, along with associated plumbing, architectural, commissioning, and project management work. The General Services Administration Public Buildings Service Region 10 is the contracting agency, with an anticipated award date of October 2020 and requirements for construction management oversight, operations and maintenance support, security services, and commissioning.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Edith Green Wendell Wyatt (EGWW) Federal Building Domestic Hot Water Piping Replacement
EGWW Aquatherm DHWS Pipe Replacement (Project 2) Design-Build Statement of Work
1 PROJECT DESCRIPTION
Project Name: EGWW DHWS Piping Replacement - Project 2
Project Number:
Region: 10
Building Name: Edith Green – Wendell Wyatt Federal Building Building Number: OR0043ZZ
Building Address: 1220 SW 3rd Avenue, Portland, OR 97232
The Edith Green-Wendell Wyatt (EGWW) Federal Building (OR0043ZZ), located at 1220 SW 3rd Ave, Portland, OR 9720, is an 18-story office building located in Portland’s government district. The building has been extensively renovated and modernized in a project that was funded under the American Recovery and Reinvestment Act (ARRA) of 2009 and completed on May 1, 2013. This renovation included the replacement of plumbing and mechanical systems. As part of this renovation, random copolymer polypropylene (PP-R) piping was installed for domestic hot and cold water distribution, rainwater collection and recycle, and zone distribution for chilled water and heating hot water systems. Since March of 2018, a total of ten (10) failures have occurred. Seven (7) failures in the two inch (2”) PP-R domestic hot water primary loop supply main that extends from water heaters in the penthouse to the basement floor. Two (2) subsequent failures have occurred in the one inch (1”) DHW primary loop return and one (1) weld failure in the LTHW hydronic loop. This primary loop serves all of the domestic hot water circulating sub-mains in the building. The most recent failure occurred in January 2020.
Domestic cold water enters the building from the street and splits to feed three (3) pressure zones. Cold water is supplied to fixtures in the basement through Floor Two (2) by street pressure, while Floors 3 through 18, including 18A are fed by a booster pump. Pressure reducing stations for cold water are located on Floors 9 and 17. Water heaters for domestic hot water, located on the mezzanine above Floor 18, serve a primary domestic hot water pipe loop that extends the total rise of the building from the basement to the mezzanine (a total of twenty (20) floors). This loop is circulated by an inline pump that runs continuously. The domestic hot water (DHW) primary supply loop feeds into three (3) pressure reducing stations for the three (3) pressure zones or secondary loops. The reducing stations are located on Floors B1, 9 and 17. Water within each pressure zone is circulated in a loop by an inline pump through an electric water heater for temperature maintenance. Circulation through the secondary zones is continuous.
PROJECT 2:
The scope of this project is removal of the PP-R primary domestic hot water Zone 2 and Zone 3 domestic hot water loops and replacement with copper piping. The project scope of work is summarized as follows:
Plumbing work:
1. Replace all DHW piping in zone 2 (Levels 3 through 10) and zone 3 (Levels 11 through 18) including new zone supply and return risers
2. Replace zone supply and return loops
3. Replace restroom supply and return loops
4. Replace drops and connections to existing fixtures (190 no. total connections
5. Replace concealed DCW piping in restrooms from above-ceiling isolation valve to sink connections
6. Replace Zone 2 and 3 water heaters and circulation pumps
7. Remove and recycle/dispose of all abandoned piping and equipment
8. Insulate to code and label all new piping and equipment to building standards
9. Pressure test
10. Disinfect new piping
Architectural work:
1. Open and repair gypsum board walls to access existing zone riser piping in freight elevator vestibule for replacement
2. Open and repair restroom ceilings and tiled walls for replacement of DHW and in-wall DCW piping
3. Open and repair break room wall for new sink connection
4. Remove and replace light fixtures in restrooms as required to access concealed piping
5. Open and replace plank and lay-in tile ceilings as required for replacement of existing distribution loops (including work in tenant areas)
6. Restore all finishes affected by construction.
Additional Services:
1. Provide construction management oversight
2. Commissioning services
3. O&M project support (this cost of additional support shall be captured by the General Contractor):
a. Drain and fill plumbing systems
b. Mechanical system
c. Remove and replace ceiling systems, et al
4. Security services to monitor after-hours work in tenant spaces.
1.1 PROJECT GOALS AND OBJECTIVES
The overall goal is to utilize a highly collaborative design build delivery approach for this project, with the outcome that the DB contractor will work closely with all the stakeholders to deliver a project that meets the expectations and needs of all stakeholders and avoids any and all disruptions to the tenant’s operations and well-being.
The Construction contractor shall provide a fully functional design and construction for replacement of the domestic hot water system.
GSA shall approve the final design of the system prior to the start of the installation.
The DB team shall also provide all operations and maintenance effort for all newly installed equipment during the measurement and verification period of one year following substantial completion. This effort will consist of all daily operations related to newly installed systems, required maintenance of all newly installed equipment and integration with remaining systems.
The Contractor shall provide management, supervision, labor, materials, equipment, and supplies and will be responsible for the efficient, effective, economical, and satisfactory operation, scheduled and unscheduled maintenance, and repair of equipment and systems installed during the project
1.2 PROJECT DELIVERY APPROACH
GSA envisions a highly collaborative design-build delivery approach for this project. The expectation is that the DB Contractor and their team shall work in close consultation with GSA, GSA’s Construction Management Agent (CMA), all project tenants and stakeholders (internal and external) to deliver a project that meets the expectations and needs of all stakeholders and GSA’s requirements for a high performing green building.
During the Design Phase, the DB team shall work in close consultation with GSA, the stakeholders and the CMA to ensure that all of the goals are addressed. This close consultation and integrated approach will then extend into the Construction, Commissioning and Close-out project phases.
1.3 REFERENCE MATERIALS
All efforts, materials and work performed under this contract shall comply with and/or shall be with knowledge and forethought of applicable Federal, State, and local building codes based on the requirements of the current edition of recognized and accepted building standards, codes and regulations, in compliance with GSA PBS P-100. Any conflicts and/or ambiguities within or among the referenced Standards and Criteria Documents, or any deviations from requirements contained therein, shall be reported to the GSA Contracting Officer, in writing, for determination as to applicability.
Drawings are provided for informational purposes only. All information contained therein shall be verified by the DB Contractor during the due diligence phase of the design process.
All contractual references – documents, codes, standards, etc. – shall be used to measure compliance of the design and construction of the building systems with respect to contractual expectations.
The following documents shall be considered instrumental in providing guidance in the successful completion of the project:
· EGWW PDS Report (Rev 2) 20 Mar 20
· GSA PBS P-100 – Facilities Standards for Public Buildings Service (2018)
· GSA PBS P-120 – Public Buildings Service Cost and Schedule Management Policy Requirements (2016)
· GSA PBS – Building Commissioning Guide (BCG; 2005)
· Performance Specifications (See EGWW PDS Report)
· Prescriptive Specifications (See EGWW PDS Report)
In addition to the above referenced documents, GSA shall make available other historical/relevant building reports and documentation, including, but not limited to: Asbestos Reinspection Survey Reports; Report of Hazardous Materials Survey; as-built drawings; etc., at the contractor’s request.
2 GENERAL REQUIREMENTS
The requirements set forth in this section apply to all stages and phases of the contract as described in the Scope of Services section below.
2.1 OWNER’S PROJECT REQUIREMENTS (OPR)
N/A
2.2 PROJECT MILESTONES SCHEDULE
The anticipated award for the DB, Project 2 contract October 2020.
2.3 PERFORMANCE OBJECTIVES
2.3.1 Standards and Criteria Documents
2.3.1.1 Applicability
All efforts, materials and work performed under this contract shall comply with and/or shall be with knowledge and forethought of applicable Federal, State, and local building codes based on the requirements of the current edition of recognized and accepted building standards, codes and regulations, in compliance with GSA PBS P-100. The applicable version of each document shall be the version current at the time of contract award. In the event of a conflict between the requirements stated in these documents and requirements provided elsewhere in this SOW and the Contract, the requirements of the SOW and Contract shall prevail.
Any conflicts or ambiguities within or among the referenced standards and criteria documents, or any deviations from requirements contained in the standards and criteria documents, shall be reported to GSA’s Contracting Officer in writing, for determination as to applicability.
2.3.1.2 Document List
a. GSA PBS P-100 – Facilities Standards for Public Buildings Service (2018) (https://www.gsa.gov/real-estate/design-construction/engineering-and-architecture/facilities-standards-p100-overview)
b. GSA PBS P-120 – Public Buildings Service Cost and Schedule Management Policy Requirements (2016)
c. (https://www.gsa.gov/directives-library/p120-public-buildings-service-cost-and-schedule-management-policy-10006-pbs)
d. National Environmental Standards for Hazardous Air Pollutants (EPA)
e. Applicable State and Local Safety and Environmental laws and regulations for 911 Federal Building’s Portland OR location
f. GSA PBS – Building Commissioning Guide (BCG; 2005)
g. GSA Accessible Facility Design (https://www.gsa.gov/cdnstatic/National_Accessibility_Program_Standards_Policies_and_Procedures_2.pdf)
h. GSA Region 10 Fire Alarm Design, Installation and Testing Policy
i. GSA Technology Policy for PBS-Owned Building Monitoring and Control Systems (31Mar2011)
j. GSA Policy and Procedure “Document Security for Sensitive But Unclassified Building Information” (PBS P 3490.3)
k. GSA OCIO IT Security 01-05 “Configuration Management Guide” (Rev3 14Jul2015)
l. GSA IT Security Policy 2100.1K “GSA IT Security Policy” (Jun 2017)
m. GSA IT Telecommunications Distribution and Design Guide (TDDG): Telecommunications and Infrastructure Standards (Ver 8 6 Aug 2016)
n. GSA Smart Buildings Implementation Guide (Ver 1 16 Mar 2015)
o. GSA Building Technologies Technical Reference Guide (Ver 1.2 29 Sep 2016)
2.3.1.3 As-Built Documents
As-built drawings of the facility are provided for informational purposes only. All information contained therein shall be verified by the Contractor for accuracy.
2.4 PROJECT MANAGEMENT RESPONSIBILITIES
2.4.1 Communications Plan
The Contractor, in consultation with the stakeholders of the project, shall assist GSA in developing and complying with a project communications plan. The Contractor shall review and comply with GSA’s communication plan. This plan shall be used and maintained throughout the project and modified as necessary to suit each project phase.
The Contractor shall direct all questions and requests from tenant agencies and local community interests to GSA’s Project Manager. Prior to contacting any parties other than GSA Regional personnel, the Contractor shall confirm all meetings and/or communications with GSA’s Project Manager.
The Contractor shall not release any oral, written, or graphic information regarding this project to outside sources without obtaining prior consent from GSA. All such requests for information concerning the project shall be referred to GSA’s Contracting Officer for response.
All presentations to non-GSA entities require prior written approval from GSA.
2.4.2 Detailed Project Schedule
GSA’s overall project schedule will be provided after the award.
The Contractor shall assist GSA in the development and maintenance of the Integrated Master Project (IMP) Schedule. The IMP Schedule shall conform to the milestones and durations provided in GSA’s overall project schedule.
Before starting any other work, the Contractor shall develop and provide a detailed schedule for completion of all Design Phase activities, tasks, and submissions required herein, leading up to and including the final design development submission(s). After the Contractor receives Notice to Proceed with the Construction Phase work, the Contractor shall provide and maintain a detailed schedule for completion of all Construction Phase activities, tasks, and submissions required herein. The Contractor schedules shall itemize all required submission dates and review durations, and shall conform to the milestones and durations provided in GSA’s overall project schedule, and in the Submission and Review Table provided below in the Administration section. The Contractor shall also provide and maintain the construction schedules as further described elsewhere. After approval by GSA, the Contractor schedules shall be incorporated into the IMP Schedule.
The Contractor shall provide weekly schedule updates to GSA, showing progress on and completion of all required Design Phase services and Construction Phase work. This weekly schedule update shall be in the form of a 5 week look ahead, detailing one (1) week prior, current week and three (3) weeks in the future. Contractor shall immediately notify GSA of any anticipated delay in performance of the work.
While the Contractor is free to use whatever scheduling software they desire, the Contractor shall provide GSA with electronic copies of all scheduled submittals in Microsoft Project (mpp) native file format for GSA’s internal use.
2.4.3 Project Progress Meetings/Presentations
During the Design Phase, the Contractor shall host regularly scheduled project progress meetings and/or presentations with GSA and primary stakeholders. The meetings and presentations shall keep all parties apprised of the design progress/status and impending activities. These meetings may coincide with other meetings/presentations required below under the Scope of Services. The Contractor shall also host special project technical meetings as necessary involving Project Delivery Team technical disciplines.
After Construction begins, the GSA Construction Manager (CMA) will host regularly scheduled stakeholders meetings, and will observe the Contractor’s weekly subcontractor meeting(s). The Contractor shall also attend construction oversight meetings with representatives from GSA on a weekly basis.
Refer to the Scope of Services section below for detailed requirements for progress reporting.
2.4.4 Meeting Agendas, Attendance, Minutes, and Correspondence The Contractor shall prepare and distribute an agenda for each contractor-hosted project meeting, in advance of the meeting date. Contractor shall coordinate agenda topics with GSA’s CMA for all other scheduled and unscheduled stakeholder meetings.
Contractor representation at all meetings shall include those individuals having knowledge of the agenda topics and authority to make decisions and commit resources.
The Contractor shall provide minutes of all Contractor-hosted project meetings and presentations to all attendees. Minutes shall identify new and unresolved old action items, along with assigned responsible parties and estimated completion date(s). Contractor shall distribute minutes within (5) calendar days after each meeting.
2.4.5 Design Quality Assurance
GSA requires that all of the Contractor’s Design and Construction Documents submissions undergo the following three general types of Design Review:
2.4.5.1 Owner’s Review
The Owner’s Review ensures that established functional, aesthetic and spatial requirements of the project are satisfied, including but not limited to:
· The design is responsive to GSA program goals, objectives and priorities.
· The completed facility can be efficiently operated and maintained.
· The design adequately and efficiently accommodates the space program.
· Interests of tenant agencies and all other stakeholders, both internal and external, are considered and accommodated to the extent possible.
· Commissioning Design Reviews are provided as indicated in GSA’s PBS Building Commissioning Guide.
2.4.5.2 Codes and Standards Review
The Codes and Standards Review ensures that the proposed design complies with applicable regulations, codes, and standards referenced in the applicable standards and criteria documents. Such reviews shall not be construed as relieving the Contractor of any code compliance responsibilities.
2.4.5.3 Constructability Review
Constructability of the project as designed shall be the sole responsibility of the Contractor. To ensure that the design can be constructed within schedule and budget and that the sequencing of construction is planned for optimum efficiency, the Contractor shall ensure that:
· The level of design complexity is consistent with the project schedule and budget constraints.
· Building systems are compatible and viable.
· Site and building access, logistics, available storage and tenant occupancy requirements are accommodated.
· Existing conditions are shown correctly and adequately.
· Construction duration and phasing plans are reasonable and logical to ensure facility operations during construction period. .
2.4.6 Design Review Procedures
The Contractor shall respond in writing to all design review comments within fourteen (14) calendar days after receipt of the GSA Design Review report.
2.4.7 Electronic Project Management Information System (PMIS) Proliance® software from Meridian Systems, a secure, web-based, electronic project management (ePM) system will be provided by GSA to accommodate the information needs of all project participants. The ePM system shall be implemented at the beginning of the Design Stage and shall be maintained continuously through completion of the Design and Construction Stages. All communications among the major parties involved in the project execution shall be captured and recorded in the ePM system. User licenses and training will be provided for all Government and contracted members of the Project Delivery Team who will require access to the ePM system.
The Contractor shall use ePM for all necessary communications with other major parties involved in the project. Electronic storage and transmission of information via the ePM system shall be compliant with the provisions of the Document Security section of these General Requirements.
2.5 ELECTRONIC/PRINT MEDIA
2.5.1 (CAD) Standards Starting with the Design Development (DD) submission, all drawing materials provided by the Contractor, including final as-built drawings, shall conform to GSA PBS Computer Aided Design (CAD) Standards. Refer to http://www.gsa.gov/cifm for requirements.
2.5.2 BIM Media
Spatial program building information models required with the Contractor’s preliminary and final design development submissions shall be submitted in both the native file format of the BIM authoring tool and in industry foundation classes (IFC) format. BIM deliverables shall supplement, and not replace, GSA PBS CAD Standards and deliverables. Refer to GSA PBS BIM Guide Series 02 Spatial Program Validation (available at http://www.gsa.gov/bim) for specific requirements.
2.5.3 Other Electronic Documents
In addition to any hardcopy submission requirements, all design submissions shall be submitted in electronic format. All electronic media shall be in a form readable by standard office automation applications.
2.5.4 Plans and Specifications
Provide four (4) hardcopy sets of plans (2 full-size, 2-half size) of all plans and specifications, in addition to electronic format, at each required Design Phase submission. In addition, the updated construction cost estimate shall be provided with the plans and specifications submittals, in electronic format.
2.6 CONTRACTOR PERSONNEL SECURITY REQUIREMENTS
Refer to the Construction Contract Agreement Section III, Terms and Conditions, for HSPD-12 suitability investigation requirements for Contract employees requiring access to the facility. Also see http://www.GSA.gov/HSPD12 for security suitability requirements. Contractor shall incorporate provisions in all applicable subcontracts as necessary to ensure compliance with all requirements provided in this Contractor Personnel Security Requirements section.
2.7 DOCUMENT SECURITY
Sensitive But unclassified (SBU) building information may be generated and/or be disseminated to and stored by various parties in the course of executing this project. SBU building information is information that, if misused, poses a potential security risk to a building, its occupants and visitors, and/or its contents. The Contractor shall comply with the requirements regarding handling, disseminating, and storing SBU building information as described in the most recent GSA Order (currently GSA Order PBS 3490.3 dated 16Oct2019).
2.8 RECORD KEEPING
The Contractor shall prepare correspondence and other documentation and maintain accurate and detailed records of the project’s progress during all phases. The Contractor shall maintain records so as to facilitate document storage and retrieval.
2.9 CONSTRUCTION SUBMITTAL AND RFI PROCESSING
On behalf of GSA, the Contractor shall manage and document the processing of the Contractor submittals and requests for information (RFI’s). Refer to Division 01 Specifications for construction submittal and RFI requirements and limitations.
3 SCOPE OF SERVICES
The Contractor shall perform all services described in this Scope of Services (including services required under exercised options, if any), in accordance with applicable requirements and provisions set forth in the General Requirements section above.
3.1 DESIGN STAGE
3.1.1 Overview
As a general matter, the GSA PBS P-100, Division 01 Specifications and the Performance Specifications represent four overarching documents that govern the Contractor’s performance of work. In addition, other policies and procedures (e.g., the P-120, GSA BCG, etc.) provide detailed procedures and requirements that the Contractor shall follow.
The Contractor’s design services shall comply with the P-100 which provides the performance criteria and requirements for the project including, but not limited to: size, function, finishes, equipment, security, resilience, adaptability, servicing, P-100 tier and other performance characteristics.
The purpose of this section is to primarily set forth requirements that the Contractor shall follow in performing work during the Design Stage phase of the project that are in addition to, or supplement, the services identified elsewhere in the Contract Documents, including the Division 01 Specifications. For example, other Division 01 Specifications address subjects such as project management, closeout, schedules, and payment. Accordingly, the Contractor should review this section in conjunction with the P-100, Division 01 Specifications, and other listed design requirements.
The GSA-prepared Division 01 Specifications are being issued as part of the Request for Proposals in order to assist the potential Offerors with pricing the requirement. Part of the successful offeror’s services includes finalizing the Division 01 specifications (as part of the Construction Documents phase).
As supplemented or qualified by this section, the Contractor shall follow the guidelines, procedures, and requirements for design deliverables that are set forth in the P-100. This section provides additional guidance to the Contractor regarding the design services at different phases during the overall project.
3.1.2 General Provisions
3.1.2.1 Design Submission Expectations
The Contractor shall prepare and submit all Design Stage submissions in accordance with PBS P-100 design document submission requirements as they pertain to the scope of the construction work.
Furthermore, the Contractor shall, for each Design Stage submittal, provide a detailed written report that separately lists all design elements that deviate from, are inconsistent with, or in any way conflict or otherwise seek to modify the Contract Documents, including but not limited to the Performance Criteria, and/or P-100. The report shall identify: (1) the design element; (2) how that design element is inconsistent with the Contract Documents; (3) the cost or price to the Government; (3) schedule impact; (4) the benefit of the change; and (5) how the benefit outweighs the cost. The report shall also include a thorough Life Cycle Cost Analysis that complies with the P-120. Any such elements shall not be incorporated or included in the design unless written approval is provided by the GSA Contracting Officer.
The Contractor shall, in any applicable Design Stage submittal, make full written disclosure to, and obtain approval of, the Contracting Officer prior to incorporating any proprietary features, products, or elements into the Contract Documents.
3.1.2.2 Design Submission Reviews
The Contractor shall allow for twenty-one (21) calendar days for the Government’s review for each Design Stage submittal. The Contractor shall, for each Design Stage submittal, reconcile all Government review comments, and provide GSA with written responses to all comments.
3.1.2.3 Performance Criteria Expectations
If a requirement contained in the Performance Criteria exceeds that required by the P-100, the Contractor shall comply with the most stringent requirement unless otherwise directed by the Contracting Officer. The Contractor’s work may exceed requirements contained in the Performance Criteria to accomplish programmatic and functional goals for the project, including but not limited to energy performance, sustainability, or industry best practices. However, that being stated, the Contractor is still responsible for complying with other portions of the contract, including FAR 52.236-22 (Design within Funding Limitations).
3.1.2.4 General Design Meeting Expectations
The Contractor shall anticipate, plan for, and price various meetings, reviews, partnering sessions, and similar discussions throughout the duration of the project. While it is not possible to describe the entire universe of any such meetings, the Contractor should anticipate that the meetings will be commensurate with a PBS-owned capital design and construction project of similar size, scope, and complexity as the one described in the Contract Documents. The following represents a non-exhaustive list of some of the various reviews and partnering sessions that may be necessary during the Design Stage phase:
· Integrated Design Review(s) (IDR): IDR reviews are conducted with GSA Central Office Subject Matter Experts (SME) and other technical experts, prior to submission of any Design Stage phase submission.
· Construction Excellence Peer Review(s): Peer reviews, involving the Contractor, GSA Regional and Central Office staff, and external professional private peers may be conducted during the construction phase of the project. These reviews typically last approximately two days and include a series of interviews. The peers may suggest process improvements that are consistent with the project objectives and program.
· Risk Management Review(s): The Contractor shall participate (in person) at workshops with GSA, CMA, CxA, and other stakeholders to create, update, or modify a Risk Registry using the Construction Industry Institute’s Project Definition Rating Index (PDRI) (or a different industry standard as agreed to by the Contracting Officer) to assess risks and opportunities for the project. The PDRI session will typically occur at the completion of design.
· Partnering Sessions: Refer to Specification Section 013100 – Project Management and Coordination.
· Regular Design Phase Progress Meetings: In addition to any other meetings required elsewhere by the Contract Documents or in this specification, the Contractor shall participate in at least two design progress meetings per month with GSA.
3.1.3 Design Stage Commissioning
To support Design Stage Commissioning, the Contractor shall, at each Design Stage phase, review and comment on Commissioning Plan updates defining roles and responsibilities for the Project Delivery Team in managing the commissioning process. Contractor shall participate in Design Stage commissioning coordination meetings with the Project Delivery Team.
Contractor’s review and comments apply to, but are not necessarily limited to, the Commissioning Record, Commissioning Specifications, Testing and Inspection Plans and Updates.
3.1.4 Design Development (DD) Phase
Contractor shall commence work on the DD Phase upon receipt of a Notice to Proceed (NTP) from the Contracting Officer.
3.1.4.1 Program Review Workshop
Contractor shall conduct a program review workshop prior to the start of DD.
3.1.4.2 Integrated Design Review (IDR) Meeting
Contractor shall conduct an IDR meeting prior to DD submission.
3.1.4.3 Construction Work Sequence Planning
In coordination with GSA and the tenant agencies, Contractor shall develop, maintain and update a construction work sequence plan addressing:
· Construction phasing approach to ensure minimal impact on tenant population and facility functionality during the entire project.
· Use of any fast tracking or multiple construction document packages to achieve best value for the Government.
· Schedules for award of subcontract construction packages, including procurement cycles, submittal approvals, construction delivery, and testing/commissioning.
· Possible labor and/or material shortages.
· Ordering of long-lead delivery materials.
3.1.4.4 DD (60% Design) Submission
Contractor shall provide a DD submission in accordance with the submission requirements listed in P-100 and the following additional requirements.
Contractor shall provide a draft construction specification, including Division 01 General Requirements, and shall include DB Contractor self-performed work and subcontracts, emphasizing project phasing, subcontractor requirements and preliminary project-specific construction management issues. Specifications shall be prepared following the latest Master Format specifications version and shall include Division 01 General Requirements, all developed to a level commensurate with DD Submission. Coordinate Division 01 requirements with GSA.
3.1.5 Construction Documents (CD) Phase
The main purpose of the CD Phase is to finalize the construction documents in order to obtain approval from the Contracting Officer to proceed to the Construction Stage. Contractor shall commence work on the CD Phase work upon receipt of NTP from the Contracting Officer.
The Contractor shall obtain input, review and comments on the CDs from all federal, state and local authorities, companies and personnel who may have jurisdiction, authority, interest in, or approval rights over the design and construction, including any applicable internal GSA offices or divisions (e.g. Fire & Life Safety, IT, etc.), also including those who will operate and maintain the system.
3.1.5.1 Baseline Construction Budget Cost Breakdowns
Prior to the start of the CD Phase, the Contractor shall provide an updated construction work allocation plan with corresponding budget breakdown, a Uniformat Level 3 budget breakdown, and supporting cost estimates, all as prescribed under GSA PBS P-120. The Contractor shall perform cost estimate reconciliation and prepare and submit a cost estimating reconciliation report. The Contractor shall coordinate with GSA as necessary to reach agreement on both budget breakdowns.
3.1.5.2 CD Coordination
3.1.5.2.1 CD Program Review Meetings
Prior to the start of CD Design Stage, the Contractor shall conduct program review meetings. These meetings can be held concurrently with the program review workshop.
3.1.5.2.2 Construction Work Sequencing and Coordination Plan
Based on the updated construction work allocation plan, the Contractor shall prepare and submit a detailed breakdown of the planned construction work sequencing, timing, and required coordination among all trades. The Contractor shall provide a corresponding schedule of planned in-progress and final CD submissions for all work packages. The Contractor shall update the construction work sequencing plan and submission schedule periodically throughout the CD phase.
3.1.5.2.3 CD Coordination (Special Tasks)
The Contractor shall perform the following special tasks:
· Conduct a CD Phase coordination meeting to review system selection options and plans and develop specifications to ensure constructability and future maintainability.
· Identify all manufacturers’ recommended operating, maintenance, and operating practices for major features, systems, and equipment. Coordinate with GSA Property Management Office (PMO) through the Contracting Officer to define specification requirements for service agreements, warranties, and turnover-related training.
· Address integration of safety/security/building automation systems and controls, both internal and external (remote) to the building.
· Coordinate with tenant agencies through the project management team to develop agency-specific construction security requirements.
· Ensure that construction mobilization issues, such as site access, staging, trailers, perimeter security, street closures, permits, etc., are addressed in the construction specifications.
3.1.5.3 In-Progress CD (90% Design) Submission
Contractor shall provide an In-Progress CD (90% Design) design submittal that complies with PBS P-100 submission requirements as they pertain to the scope of the construction work. The submission shall, at a minimum, consist of plans, specifications, cost estimates, and related design narrative including calculations.
The Contractor shall provide an in-progress construction specification package, including Division 01 General Requirements sections emphasizing project phasing, Contractor requirements, and preliminary project-specific construction management issues. The construction specification shall be prepared following the latest MasterSpec version and shall include Division 01 General Requirements developed to a level corresponding to the level of completion of design. The Contractor shall coordinate Division 01 requirements with GSA.
3.1.5.4 Pre-Final CD Submissions
Contractor shall provide a separate Pre-Final CD submission in accordance with PBS P-100 CD document submission requirements as they pertain to the scope of the construction work. The submission shall consist of plans, specifications, cost estimates, and related design narrative, including calculations.
Contractor shall provide a Pre-Final construction specification, including Division 01 General Requirements sections. Specifications shall be prepared following the latest Master Format specifications version and shall include Division 01 General Requirements, all developed to a level corresponding to the level of completion of design. The Contractor shall coordinate Division 01 requirements with GSA. The Contractor shall also include contract specifications for submittal requirements, training requirements, and Operations and Maintenance (O&M) and systems manual requirements. The Contractor shall include requirements for Testing and Commissioning of critical features and equipment.
3.1.5.5 Final CD (100% Design) Submission
GSA will advise the Contractor in writing of any comments, necessary modifications, amendments and additions. After incorporating any of the Government’s comments, modifications, amendments and additions, the Contractor shall submit the Final (100%) Construction Documents for approval to the Contracting Officer.
Contractor’s Final CD submission shall be in accordance with PBS P-100 CD document submission requirements as they pertain to the scope of the construction work.
Contractor shall provide a Final construction specification, including all Division 01 General Requirements sections. Specifications shall be prepared following the latest Master Format specifications version and shall include Division 01 General Requirements, all developed to a level corresponding to the level of completion of design. The Contractor shall coordinate Division 01 requirements with GSA. All specification sections shall be complete as of this submission.
3.1.5.6 Final CD Commissioning Activities
The Contractor shall review and comment on GSA’s updated commissioning plan.
3.1.5.7 GSA CAD Library Coordination
The Contractor shall coordinate with GSA’s Region 10’s CAD librarian and Spatial Data Management coordinators to log the Final CD submissions into GSA’s document library.
3.1.5.8 Final Construction Document Approval & Conformed Set
Following approval of the Final Construction Documents, the Contractor, in order to maintain a fully conformed and accurate version of those documents, shall submit, and clearly label as such, the Final Construction Documents in (1) hard copy version and (1) electronic version. The Final Construction Documents shall affix a stamp or seal of the applicable professional discipline responsible for its design.
3.2 CONSTRUCTION STAGE
Upon receipt of Notice to Proceed for the Construction Stage work, the Contractor shall perform all services as described in this section and contract requirements.
The Contractor shall construct the project in accordance with the SOW requirements, contract requirements, and the Construction Documents prepared by the Contractor. The Contractor shall provide (furnish and install, complete and ready for use) all materials, related services, and other items, as well as the means and methods of construction for all aspects of the project.
3.2.1 Construction Phase BIM Requirements
The Contractor shall use BIM applications where applicable or appropriate for construction coordination. Examples include coordinated electronic product and manufacturer documentation, electronic owner’s manuals, 3D geometric models of equipment layout, collision detection, virtual construction, as-built BIM, model-integrated building automation systems, model-based building monitoring systems, etc. BIM may also be used for construction coordination among various trades and subcontractors, typically with the Contractor in the lead role.
3.2.2 Construction Start Coordination
3.2.2.1 Pre-Construction Conference
The Contractor shall participate in a Pre-Construction conference.
3.2.2.2 Partnering
In lieu of a formal partnering session at the start of the Construction Stage, the Contractor shall host an enhanced project kick-off meeting to cover partnering type concepts.
3.2.2.3 Construction Stage Photographs
The Contractor shall provide color digital images of existing electrical equipment in an as-is (existing) state.
The Contractor shall provide digital images of the project elements in JPEG format with a minimum resolution of 1024x768 pixels. Contractor shall upload images into the project’s Google Team Drive (Drive to be created by GSA and shared after contract award) and into the ePM project repository. All image file names shall include a description of the image.
Images shall be accompanied by a statement signed by the photographer (or his or her authorized representative) allowing GSA to reproduce the images in print and electronic media without additional compensation.
3.2.2.4 Pre-Construction Photographs
Contractor shall provide color digital images of existing electrical equipment in an as-is (existing) state prior to starting Construction Stage activities.
3.2.2.5 Construction Progress Photographs
At weekly intervals during construction, the Contractor shall take digital images of the project’s progress from different points of view documenting progress of the work. The Contractor shall take photographs weekly, adjusting the timing of the photographs each month to coincide with the cut-off date associated with each application for payment. Some photographs shall be taken from the same vantage point each time to best show the status of construction and progress since taking previous photographs.
3.2.3 Construction Administration
In order to administer the construction of the project properly and efficiently, the Contractor shall provide the following services and deliverables.
· Construction Site Office – The GSA may provide a project office with utilities and furnishings; however, this is not a guarantee and any space provided will be limited in size due to the facility's full tenant occupancy.
· The Contractor shall provide to GSA one licensed set of the construction schedule software being used for detailed CPM scheduling.
· Schedule of Values (SOV) – The Contractor shall prepare and submit an SOV based on the awarded contract to GSA for approval. The SOV shall be maintained by the Contractor, with updates submitted to GSA on a regular basis and with each pay application.
· Construction Delivery Phase Record-keeping – Refer to Division 01 specifications.
· Construction Progress Reporting – Refer to Division 01 specifications.
· Construction Safety Program – Refer to Division 01 specifications.
· Project Progress Meetings – GSA shall participate with the Contractor in regularly scheduled progress meetings. Refer to Division 01 specifications.
· Construction Schedules – The Contractor shall provide and maintain construction schedules in accordance with the requirements provided in Division 01 specifications.
· Submittal Processing – The Contractor shall prepare and submit a Submittal Schedule/Registry in accordance with Division 01 specifications. All submittals shall be processed using the ePM system in accordance with the procedures developed and approved by GSA.
· Inspections and Testing – The Contractor shall develop an overall inspections and testing plan in accordance with the SOW and contract. The Contractor shall conduct all inspections and tests as required by the construction specifications.
· The Contractor shall conduct construction safety (OSHA) inspections as required.
· Clarifications/Requests for Information/Change Orders – Using ePM, and in accordance with procedures developed and approved by GSA, the Contractor shall promptly submit to GSA a written request for information (RFI) to request clarification of any owner-related issues, apparent conflicts, ambiguities, or omissions in the DB contract requirements. The Contractor shall ensure that all subcontractors understand, agree to, and conform with their respective roles, responsibilities, and timeliness requirements for RFI processing.
· Each RFI shall include a specific description of the issue requiring clarification, citing the specific related contract documents requiring clarification. RFIs shall only be submitted after performing due diligence to confirm that the contract requirements in question are in fact unclear or otherwise inadequate.
· Upon receipt of the response to each RFI submitted, the Contractor shall coordinate the response with all involved subcontractors to ensure understanding and appropriate action.
· Contractor As-Built Drawings and Specifications – The Contractor shall update the CAD drawings (as-built drawings) and electronic specifications at least monthly in order to document the changes that occur during construction.
3.2.3.1 Payment Requests
The Contractor shall update the construction schedules monthly prior to each payment request and provide an advance copy of the construction progress report to the CMa. The Contractor shall provide documentation evidencing the cost of work performed to be included in the payment request.
Before submitting each payment request, the Contractor shall meet with the CMa and GSA to review the advance copy of the construction progress report. The Contractor shall ensure that the CMa and GSA are in agreement as to the progress of the construction work and the value of the work completed.
Based upon agreed value of work completed, the Contractor shall submit monthly payment requests to GSA.
3.2.4 Construction Delivery Phase Commissioning
During the Construction Delivery Phase, the Contractor shall coordinate its testing, inspection, and quality assurance activities with GSA’s independent testing, inspection, and verification. Elements of the Contractor’s quality control plan for all systems, assemblies, and equipment may overlap elements of the commissioning requirements which will be independently verified by GSA. The Contractor shall perform Construction Delivery Phase commissioning support services as described below.
3.2.4.1 Construction Delivery Phase Commissioning Plan Updates The Contractor shall review and comment on Construction Delivery Phase commissioning plan updates.
3.2.4.2 Commissioning Schedule
The Contractor shall review and comment on the commissioning schedule, coordinating the commissioning work with the Project Delivery Team to ensure that commissioning activities are being incorporated. The Contractor shall integrate commissioning activities into the construction schedule.
3.2.4.3 Construction Delivery Phase Commissioning Coordination The Contractor shall participate in regular commissioning coordination meetings with the Project Delivery Team.
3.2.4.4 Systems Coordination Plans
The Contractor shall prepare and submit systems coordination plans as described in Division 1 of the contract performance specification and the construction specifications.
3.2.4.5 Commissioning Testing and Inspection Procedures
The Contractor shall provide to GSA the information required to perform commissioning tasks, including O&M materials and contractor start-up and checkout procedures. Before systems start-up, the Contractor shall assist GSA in coordinating with contractors and design engineers to obtain information and clarity on control sequences and interlocks as necessary to develop detailed testing procedures and an enhanced systems start-up and initial systems checkout plan.
The Contractor shall review and comment on the step-by-step commissioning test procedures for commissioned systems, including pre-functional test (PFT) procedures, functional performance test (FPT) procedures, and documentation forms and construction checklists for all commissioned equipment and assemblies. Test procedures shall include manual functional testing and energy management control system trending and may include stand-alone data-logger monitoring.
The Contractor shall assist GSA in preparing an enhanced start-u and initial systems checkout plan with contractors for commissioned equipment.
3.2.4.6 Construction Checklists
The Contractor shall complete the construction checklists as the work is accomplished.
3.2.4.7 Commissioning Testing and Inspection
The Contractor shall coordinate with GSA and involved subcontractors as necessary to facilitate performance of independent commissioning testing and inspection, and others deemed necessary, including the following tests:
· Sequence testing of HVAC central plant, condenser water system, and air distribution
· Refrigeration/heating/air handling load test
· HVAC system controls test
· Uninterruptible power supply (UPS) load test if installed as part of EMS
· Smoke management system test for local/NFPA code compliance
The Contractor shall coordinate with GSA and involve subcontractors as necessary to facilitate performance of retesting and reinspection as required if initial testing and inspection indicates performance deficiencies.
The Contractor shall assist GSA in coordinating the scheduling of additional off-site testing and shall review and comment on GSA special testing reports, as appropriate, for building diagnostics tests of critical components and systems.
The Contractor shall assist GSA in verifying proper installation of commissioned components and systems.
The Contractor shall provide GSA with all subcontractor functional testing records for commissioned systems and assemblies.
3.2.4.8 Commissioning Documentation
The Contractor shall perform these duties related to documentation:
· review and comment on GSA commissioning inspection reports
· assemble and review all commissioning test certifications described in the testing and inspection plan
· resolve all failures reported in the commissioning issues log
3.2.4.9 Commissioning Test Certifications
The Contractor shall assist GSA in assembling and reviewing all commissioning test certifications described in the testing and inspection plan.
3.2.4.10 Commissioning Issues Log
The Contractor shall resolve all failures reported in the commissioning issues log prior to acceptance of any installed system..
3.2.5 Turnover Process
3.2.5.1 Substantial Completion
Prior to substantial completion, the Contractor shall assist GSA in conducting a pre-final walk-through.
3.2.5.2 Punch-List
After GSA certification that the work or each designated portion thereof is substantially complete, the Contractor shall assist GSA in conducting a final inspection and preparing a punch-list documenting remaining work.
The Contractor shall participate with GSA in conducting follow-up inspections to administer resolution of punch-list items.
3.2.5.3 Operation and Maintenance (O&M) Manuals Submittals
The Contractor shall prepare and submit complete and properly organized O&M manuals as required in accordance with Division 1 of the contract performance specification and the final construction specifications. The O&M manual shall be presented in a 3-ring binder and digital format.
3.2.5.4 Warranties, Guarantees and Certificates
The Contractor shall prepare and submit warranties, guarantees, and certificates, ensuring that GSA rights and responsibilities are clearly defined.
3.2.5.5 Final As-Built Drawings and Specifications
The Contractor shall prepare and…