Summary: FermiForward Quality Requirements (Section 014200)
This document is a quality requirements specification for service subcontractors working on FermiForward projects. The Service Subcontractor is responsible for managing, controlling, and documenting all work activities—including safety, testing, inspection, and service delivery—to ensure compliance with subcontract documents. This responsibility extends to work performed on-site and off-site by the subcontractor's organization, suppliers, technical laboratories, consultants, and sub-tier contractors.
The quality program consists of two components: (1) a Corporate Quality Assurance Plan that must be submitted with the bid or proposal (failure to submit constitutes non-responsive bidding), and (2) a Project Quality Control (PQC) Plan that must be submitted to the Procurement Administrator within 10 working days of subcontract award for FermiForward review. The PQC Plan must identify personnel, procedures, controls, instructions, tests, records, and forms specific to the project and must be updated to reflect any changes in scope. The Project Quality Control Manager is responsible for implementing the PQC Plan effectively, interfacing with the Task Manager on quality matters, maintaining quality records, attending coordination meetings, performing required QC checks, developing a deficiency/nonconformance list, and preparing quality control reports. Acceptance of the PQC Plan is required before work begins and is conditional on satisfactory performance; FermiForward will review and accept the plan within 5 working days of submittal and reserves the right to require modifications to operations, procedures, or personnel as necessary.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FermiForward Quality Requirements January 2024
QUALITY REQUIREMENTS 014200-1
SECTION 014200 – QUALITY REQUIREMENTS (For Services)
1.1 PURPOSE
The Service Subcontractor is responsible for all activities necessary to manage, control, and document work so as to ensure compliance with the Subcontract documents. The Subcontractor’s responsibility includes ensuring adequate Quality Control services are provided for work accomplished on- and off-site by their organization, suppliers, technical laboratories, and consultants.
The work activities include safety, testing and inspection, and all other functions relating to the requirements for the service being provided. The Subcontractor shall implement a Quality Control program to achieve these goals.
1.2 THE QUALITY PROGRAM
Corporate Quality Assurance Plan: The Subcontractor shall furnish with the bid or proposal a copy of their corporate Quality Assurance Plan. Failure to submit such a document could constitute a non-responsive bid or proposal. See Appendix A for Corporate Quality Assurance Plan guidance.
Project Quality Control Plan: To determine if a Project Quality Control Plan is required for the project, the Design Engineer or Project Manager shall complete the Subcontractor/Vendor Quality Control Plan Checklist (QC Plan Determination Assessment Form). The Subcontractor/Vendor shall furnish a Project Quality Control (PQC) Plan to the Procurement Administrator, for review by FermiForward, not later than 10 working days after receipt of award of Subcontract.
The PQC Plan shall identify personnel, procedures, controls, instructions, test, records, and forms to be used specific to this project at Fermilab. The PQC Plan shall be updated to incorporate any changes in scope of work, due to directed field changes or supplemental agreements, as these changes occur. See Appendix B for Project Quality Control Plan guidance.
1.3 REQUIREMENTS
The PQC Plan shall include, as a minimum, the following information to cover all efforts performed, both onsite and offsite, including work by sub-tier contractors, fabricators, suppliers, and purchasing agents:
The name, qualifications, duties, responsibilities, and authorities of each person assigned a Quality Control function, including the identity of the Project Quality Control Manager:
Depending on the size and complexity of the project, the project superintendent and/or competent person may also serve as the Quality Control Project Manager.
As a minimum, the Project Quality Control Manager shall be responsible for the following:
https://fess-app.fnal.gov/app/SubcontractorSafetyFormQa/ https://fess-app.fnal.gov/app/SubcontractorSafetyFormQa/
QUALITY REQUIREMENTS 014200-2
Ensure the defined Project Quality Control Plan is effectively implemented.
Interface with the Task Manager or designee on all quality matters;
Maintain all quality related records;
Attend any planned coordination meetings;
Assure all required QC checks are performed;
Develop and maintain a deficiency/nonconformance list;
Prepare and submit quality control reports;
1.4 ACCEPTANCE
Acceptance of the Subcontractor's PQC Plan is required prior to starting work.
Acceptance is conditional and will be predicated on satisfactory performance as work proceeds.
FermiForward reserves the right to require the Subcontractor to make modifications to their PQC Plan and operations including personnel as necessary to obtain the quality specified (Subcontract Terms and Conditions). FermiForward review and acceptance will occur within 5 working days of the submittal of the PQC Plan.
END OF SECTION
QUALITY REQUIREMENTS 014200-3
Appendix A – Corporate Quality Assurance (QA) Plan Guidance
The section below describes the elements expected in the Corporate Quality Assurance Plans submitted by Subcontractors.
• Purpose o The Subcontractor is to describe the purpose of the document (Corporate QA Plan) as it relates to their organization.
• Roles, Responsibilities, and Authorities o The Subcontractor is to describe the roles, responsibilities, and authorities relating to the various Quality Assurance processes described within this plan.
• Scope o The Subcontractor is to describe the scope of the Corporate QA Plan.
• Organizational Chart o The Subcontractor is to highlight the QA roles in the organization.
• Requirements Verification o The Subcontractor is to describe how requirements relating to a scope of work are verified.
• Document Control o The Subcontractor is to describe how documentations is controlled.
• Submittals/Procurement o The Subcontractor is to describe their submittal and procurement process.
• Material and Equipment Control o The Subcontractor is to describe how materials and equipment are received, stored, maintained, and released.
• Procedures o The Subcontractor is to describe the various procedures that are used to control the performance of work to ensure requirements for design, materials, installation, etc.
are met.
• Suspect/Counterfeit Items o The Subcontractor is to describe processes that will be in place for monitoring and controlling the use of suspect/counterfeit items.
• Nonconformance Handling o The Subcontractor is to describe processes that will be in place for managing nonconforming goods or processes.
• Lessons Learned o The Subcontractor is to describe their lessons learned process, including identifying, documenting, and sharing lessons.
• Continuous Improvement o The Subcontractor is to describe processes that are in place to identify and implement improvement opportunities.
• Inspection and Testing o The Subcontractor is to describe the inspection and testing requirements and methods for documentation. Additionally, the qualifications of personnel performing inspections and testes should also be described. Also, the managing of testing equipment including calibration requirements should also be described.
• Commissioning o The Subcontractor is to describe the commissioning process that is followed.
QUALITY REQUIREMENTS 014200-4
Appendix B – Project Quality Control Plan Guidance
• Purpose o Describe the purpose of the document as it relates to the specific project that’s been awarded.
• Project Specific Organization o Describe the personnel that will be working directly on the project, highlighting the quality control responsible individuals and their lines of authority. An organizational chart should be provided as well as the names and qualifications of each member.
Describe the duties, responsibilities, and authorities of each person assigned a QC function.
• List the phases for the Project o Provide a list of work phases specific to the project and describe the associated procedures for each.
• QC Procedures/Submittals o Provide the control, verification, and acceptance testing procedures for each test to be performed.
o Include the test name, feature of work to be tested, testing frequency, and responsible party for each test. This includes QC performed both internally and by independent testing agents.
• Turnover Records o The Subcontractor is to describe what documentation will be turned over to the
Owner and at what point in time.
• QC Tracking/Verification o Describe the procedures for identifying and tracking of QC checks required, verification efforts, and acceptance testing.
• Nonconformance Handling o Describe the procedures for tracking deficiencies/nonconformances from identification through corrective action implementation. Establish verification procedures that identified deficiencies/nonconformances have been corrected.
o Include communication process for deficiencies/nonconformances.
• Meetings and Reports o The Subcontractor is to describe what meetings will take place.
Reports/documentation that is generated at each meeting should also be described.
| 1.1 PURPOSE |
| A. The Service Subcontractor is responsible for all activities necessary to manage, control, and document work so as to ensure compliance with the Subcontract documents. The Subcontractor’s responsibility includes ensuring adequate Quality Control se... |
| B. The work activities include safety, testing and inspection, and all other functions relating to the requirements for the service being provided. The Subcontractor shall implement a Quality Control program to achieve these goals. |
| 1.2 THE QUALITY PROGRAM |
| A. Corporate Quality Assurance Plan: The Subcontractor shall furnish with the bid or proposal a copy of their corporate Quality Assurance Plan. Failure to submit such a document could constitute a non-responsive bid or proposal. See Appendix A for C... |
| B. Project Quality Control Plan: To determine if a Project Quality Control Plan is required for the project, the Design Engineer or Project Manager shall complete the Subcontractor/Vendor Quality Control Plan Checklist (QC Plan Determination Assessme... |
| The PQC Plan shall identify personnel, procedures, controls, instructions, test, records, and forms to be used specific to this project at Fermilab. The PQC Plan shall be updated to incorporate any changes in scope of work, due to directed field chan... |
| 1.3 REQUIREMENTS |
| A. The PQC Plan shall include, as a minimum, the following information to cover all efforts performed, both onsite and offsite, including work by sub-tier contractors, fabricators, suppliers, and purchasing agents: |
| 1. The name, qualifications, duties, responsibilities, and authorities of each person assigned a Quality Control function, including the identity of the Project Quality Control Manager: |
| 2. Depending on the size and complexity of the project, the project superintendent and/or competent person may also serve as the Quality Control Project Manager. |
| B. As a minimum, the Project Quality Control Manager shall be responsible for the following: |
| 1. Ensure the defined Project Quality Control Plan is effectively implemented. |
| 2. Interface with the Task Manager or designee on all quality matters; |
| 3. Maintain all quality related records; |
| 4. Attend any planned coordination meetings; |
| 5. Assure all required QC checks are performed; |
| 6. Develop and maintain a deficiency/nonconformance list; |
| 7. Prepare and submit quality control reports; |
| 1.4 ACCEPTANCE |
| A. Acceptance of the Subcontractor's PQC Plan is required prior to starting work. Acceptance is conditional and will be predicated on satisfactory performance as work proceeds. |
| B. FermiForward reserves the right to require the Subcontractor to make modifications to their PQC Plan and operations including personnel as necessary to obtain the quality specified (Subcontract Terms and Conditions). FermiForward review and accept... |