Exhibit 1 Technical Specifications.Revised.doc
DOC document 94 KB Posted
- Solicitation number
- S-73000-00013172
- Issued by
- Umatilla County, Oregon
About this file
Exhibit 1 Technical Specifications.Revised.doc is a technical document related to the Oregon state procurement for the ESB La Grande Maintenance Station Wash Bay Overhead Door Replacement project. The solicitation is a Request for Competitive Quote (RFCQ) issued on March 20, 2025, with a submission deadline of April 8, 2025. The project scope includes comprehensive removal and replacement of existing overhead doors, gutters, siding, linear panel, track, and operator systems, with specific requirements to widen rough openings for new overhead doors at the maintenance station. The technical specifications provide detailed guidelines for contractors interested in bidding on this facility infrastructure upgrade.
The project appears to be a state-level procurement without explicitly stated set-aside designations. While no specific budget range is provided, the technical specifications (92KB) and accompanying drawings (250KB) suggest a complex project requiring specialized knowledge in industrial door installation and facility infrastructure modifications. Bidders will need to submit detailed cost breakdowns using the Competitive Quote Pricing Form, demonstrating technical expertise and the capability to complete the overhead door replacement project efficiently and in compliance with state specifications. The evaluation criteria are likely to focus on technical compliance, proposed pricing, and the contractor's ability to meet the specified technical requirements outlined in the documentation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00013172 Preliminary Results.xlsx | XLSX spreadsheet | |
| Exhibit 1 Technical Specifications.doc | DOC document | |
| ESB_RFCQ_Attachments_279C.Revised.docx | DOCX document | |
| 00013172 Intent To Award.xlsx | XLSX spreadsheet | |
| Exhibit 2 Drawings.pdf | ||
| PrebidMeetingTopics.doc | DOC document | |
| Competitive Quote Pricing Form~3.xlsx | XLSX spreadsheet | |
| ESB_RFCQ_Attachments_279C.Final.docx | DOCX document | |
| PrebidSignInRoster.pdf | ||
| 256015 Notice Intent to Award.pdf | ||
| Competitive Quote Pricing Form Revised.xlsx | XLSX spreadsheet | |
| ESB_RFCQ_279C.Final.docx | DOCX document | |
| Addendum 1~17.docx | DOCX document |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT 1 – TECHNICAL SPECIFICATIONS
ESB LAGRANDE MAINTENANCE OVERHEAD DOOR REPLACEMENT
PROJECT INFORMATION AND SPECIFICATIONS
Brand Name used in Specifications:
Any brand name listed in the specifications as “equivalent” or “equal” shall establish minimum requirements for quality, durability, function, etc. Other brands may be offered that are equal to or better than the brand named in the specifications.
Project Description:
The La Grande Maintenance Station wash bay doors are undersized and have experienced significant wear and tear over the years. This project includes removing the existing gutters, siding, liner panel, overhead door, track, and operator to widen the rough openings for the overhead doors. Contractor must provide design, engineering, and installation of a new 16’ x 13’9” overhead door per specifications. Contractor is also responsible to work with city of La Grande throughout plan review and the construction process; contractor must also apply and pay for any permit or review required by the AHJ. Proposed materials must mitigate salt corrosion, as the wash bay is consistently exposed to salt. Prior to construction, ODOT project managers need to review and approve plans.
Base Bid: Remove and dispose of two existing 14'x14' overhead doors, reframe end walls for installation of two new 16'x14' overhead doors, supply and install new overhead doors
· Two (2) overhead doors to be replaced and walls reframed per engineering:
· Temporarily support trusses with post and beam shoring.
· Install new glulam beam, double trimmers, hold downs, etc. per engineering.
· New overhead door rough openings: 16’-0” x 13’-9”.
· ¾” plywood sheeting, interior and exterior with house wrap.
· Custom cee jamb wrap, white, 24ga, no splices preferred.
· New J-trim, interior and exterior, no splices preferred.
· Install new siding at exterior and liner panel at interior walls.
· 24 gauge, match existing profile and colors.
· Reinstall existing outside corner metal, gutters, & downspouts.
· 16’-2” x 13’-9” ThermaSeal (TM200) Commercial Raynor Garage Door or approved equal.
· Stucco surface texture, white
· 2” thick sections.
· 26ga, insulated w/R18.3 Polyurethane foam.
· 2 rows of 4 aluminum full view windows in sections #3 and #4.
· Double end stiles, struts, seals, & pusher bumpers.
· Normal headroom, 3” track, 15” radius
· 3” car wash rollers, sealed nylon roller, stainless steel 7-1/4” stem.
· Commercial Raynor Operator COH411 or approved equal
· ControlHoist2.0, gear drive
· Waterproof NEMA-4
· Lift Master receiver and (7) remotes, N12 inside 3-button
· N4 outside 3-button opener – Remove existing surface mounter conduit and stub out wire in new wall prior to cover.
· NEMA-4 photo eyes
Add Alternate Specifications:
Add Alternate 1: Replace four existing sealed LED fixtures with similar new LED fixtures, provide EMT surface mounted conduit for any new wiring.
· Add 4 new sealed LED light fixtures to wash-bay.
· Match existing sealed LED fixtures or similar
· Provide EMT surface mounted conduit for any new wiring.
· Electrical work shall be done by a licensed electrician.
Add Alternate 2: Provide and install new metal liner panel on ceiling of wash-bay
· Ceiling panels can be 26 gauge, ¾” rib height, & white in color.
· Install J trim around perimeter
· Install 2 X 12 backing at the 8 locations for the overhead wash system prior to cover.
· Contractor shall include in their price Purchasing and installing zee metal and flat stock metal to finish walls up to ceiling height. Metal shall be 26 gauge and white in color. Contractor has the option to use matching liner panel on the gable end wall.
Revision: 5/7/24