ESM_Appendix C Go-Live and Full Operational Capability Definitions Final.docx

DOCX document 20 KB Posted

Attached to
Enterprise Sales and Marketing Solution Federal contract opportunity
Solicitation number
2031JG22R00025
Issued by
Department of the Treasury Departmental Offices

About this file

This document defines criteria for Go-Live and Full Operational Capability milestones for an Enterprise Sales and Marketing Solution. The solution must provide an end-to-end, turnkey retail service for the United States Mint's numismatic program, including contact center functions and equipment, a physical fulfillment warehouse, order management, eCommerce hosting, and integration with internal and external systems. Go-Live criteria include completion of design, testing, and defect resolution; staffed and trained call center and warehouse facilities; and approved plans for switching infrastructure, security certificates, and domain routing. Full Operational Capability requires remediation of all temporary waivers and resolution of all remaining defects.

View the file

Other files for this federal contract opportunity

Other files attached to Enterprise Sales and Marketing Solution, newest first.
File Type Posted
Amendment 002 Solicitation 2031JG22R00025.xlsx XLSX spreadsheet
REVISED United States Mint Request for Prosposal Solicitation 2031JG22R00025 Enterprise Sales and Marketing Solution.pdf PDF
ESM_Attachment 10_Contractor Performance Questionnaire_Final.docx DOCX document
ESM_Attachment C-1_VPAT Template.doc.docx DOCX document
Amendment 001 Solicitation 2031JG22R00025.xlsx XLSX spreadsheet
ESM_Appendix A 1 Functional and Business Requirements Final.docx DOCX document
ESM_Attachment 8 Overall Factor and Sub Factor Weighting Final.pptx PPTX presentation
United States Mint Request for Prosposal Solicitation 2031JG22R00025 Enterprise Sales and Marketing Solution.pdf PDF
United States Mint Request for Proposal ESM Solicitation 2031JG22R00025.doc DOC document
ESM_Appendix D USM Internal and External Systems Interface Descriptions Final.xlsx XLSX spreadsheet
ESM_Attachment 7 Operational Cost Scenario Template Final.xlsx XLSX spreadsheet
ESM_Attachment 11 Contract Release-Form 7510 Final.docx DOCX document
ESM_Attachment 12 Sample Labor Categories and Descriptions Final.docx DOCX document
ESM_Appendix A 2 Functional and Business Requirements Workbook Final.xlsx XLSX spreadsheet
ESM_Appendix B Deliverables and Content Requirements Final.docx DOCX document
ESM_Attachment 5 System Security Control Baselines Final.docx DOCX document
ESM_Attachment 9 Management and Technical Section L and M Final.pptx PPTX presentation
ESM_Attachment 1 Statement of Objectives Final.docx DOCX document
ESM_Attachment 2 Historical Data Final.pptx PPTX presentation
ESM_Attachment 3 Key Performance Indicators Final.docx DOCX document
ESM_Attachment 4 Pay.Gov Technical Overview Final.pdf PDF
ESM_Attachment 6 Pricing Template Final.xlsx XLSX spreadsheet
ESM_Attachment 10 Contractor Performance Questionnaire Final.docx DOCX document
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPENDIX C: Go-Live and Full Operational Capability Definitions

Go-Live shall become the final step upon successful completion of the Physical Design Phase and Transition Phase. The Contractor shall propose Go-Live in accordance with the Performance Work Statement (PWS). At a minimum, Go-Live shall address when the following criteria have been met by the Contractor and approved by the Government:

1. All hardware, software, facilities, and infrastructure are in place to fully service a USM customer.

2. All scheduled testing activities have been completed (test plans, test case execution, test reports, etc.).

3. All Severity 1 and 2 Defect Reports (or equivalents) are resolved, deferred, waivered, or closed.

4. A call center facility is fully staffed and business processes are in place to execute operations. Staff is fully trained and the call center has obtained all necessary telephony infrastructure to include hardware, software, and lines. Plan to switch line routing has been approved by the government.

5. An order fulfillment center is fully staffed and business processes are in place to execute operations. Staff is fully trained and the physical warehouse facility has all the necessary hardware and software for order fulfillment center resources use. Plan to move inventory to facility has been approved by the government.

6. USM personnel have been fully trained on systems they will use.

7. Plan to switch domain routing and security certificate details has been approved by the government. Authorization to Operate is issued by the USM.

The Contractor shall propose Full Operational Capability (FOC) in accordance with the PWS. At a minimum, FOC shall address when the following criteria has been met by the Contractor and approved by the Government:

1. All temporary waivers have been remediated and closed.

2. All Severity 3 and 4 Defect Reports are resolved, deferred, waivered or closed.