ESBD_500440_1774465815806_Addendum #1 734-03202026-KM North & South Plant Chiller Replacement.pdf

PDF 144 KB Posted

Attached to
North & South Plant Chiller Replacement
Solicitation number
734-03202026-KM
Issued by
Johnson County, Beaumont City, Texas

About this file

This Addendum #1 document pertains to a Request for Proposals (RFP) issued by a Texas university for the North & South Plant Chiller Replacement project (RFP #734-03202026-KM). The project involves the replacement of chillers at two plant facilities. Qualifications, pricing, and delivery proposals are due by Tuesday, April 28, 2026 at 2:00 p.m. CST/CDT, with HUB Subcontracting Plans due the following day on Wednesday, April 29, 2026 at 12:00 p.m. CST/CDT. A mandatory voluntary pre-submittal conference and site visit is scheduled for April 9, 2026 at 10:00 a.m., with the deadline for submission of questions and clarifications set for April 14, 2026 at 2:00 p.m. CST/CDT. The successful respondent will be notified on May 7, 2026, with contract execution targeted for May 14, 2026. Construction is scheduled to begin June 1, 2026, with substantial completion expected by March 1, 2027.

The addendum establishes the project timeline and key milestones but does not specify pricing terms, set-asides, incumbent contractor information, or detailed funding requirements within the document provided. The document indicates that chillers will be ordered following contract execution, with the construction phase extending approximately nine months from the June 1, 2026 start date through the March 1, 2027 substantial completion deadline.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR PROPOSALS

FOR

NORTH & SOUTH PLANT

CHILLER REPLACEMENT

RFP #734-03202026-KM

ADDENDUM 1

Submittal Due Dates:

Qualifications & Pricing and Delivery Proposal:

Tuesday, April 28, 2026

2:00 p.m. CST/CDT

HUB Subcontracting Plan:

Wednesday, April 29, 2026

12:00 p.m. CST/CDT

SECTION 7 – PROJECT PLANNING SCHEDULE

Estimated schedule milestone:

DATE: ACTION:

March 25, 2026: RFP posted to the Electronic State Business Daily (TX Smartbuy/ESBD)

April 9, 2026: Mandatory Voluntary pre-submittal conference/site visit at 10:00 a.m.

April 14, 2026: Deadline for submission of questions and/or clarifications regarding RFP. All questions must be received by 2:00 p.m. CST/CDT to be considered

April 28, 2026: Submissions received by the University on or before 2:00 p.m. CST/CDT

April 29, 2026: HUB Subcontracting Plans received by the University on or before 12:00 p.m.

CST/CDT

May 7, 2026: Notification to successful Respondent(s) - contingent upon execution of contract.

May 14, 2026: Contract Executed

June 1, 2026: Chillers Ordered

November 1, 2026: Construction Begins

March 1, 2027: Substantial Completion

File details come from the government source that posted it. Updated .