ESBD_500440_1774465815806_Addendum #1 734-03202026-KM North & South Plant Chiller Replacement.pdf
PDF 144 KB Posted
- Attached to
- North & South Plant Chiller Replacement
- Solicitation number
- 734-03202026-KM
- Issued by
- Johnson County, Beaumont City, Texas
About this file
This Addendum #1 document pertains to a Request for Proposals (RFP) issued by a Texas university for the North & South Plant Chiller Replacement project (RFP #734-03202026-KM). The project involves the replacement of chillers at two plant facilities. Qualifications, pricing, and delivery proposals are due by Tuesday, April 28, 2026 at 2:00 p.m. CST/CDT, with HUB Subcontracting Plans due the following day on Wednesday, April 29, 2026 at 12:00 p.m. CST/CDT. A mandatory voluntary pre-submittal conference and site visit is scheduled for April 9, 2026 at 10:00 a.m., with the deadline for submission of questions and clarifications set for April 14, 2026 at 2:00 p.m. CST/CDT. The successful respondent will be notified on May 7, 2026, with contract execution targeted for May 14, 2026. Construction is scheduled to begin June 1, 2026, with substantial completion expected by March 1, 2027.
The addendum establishes the project timeline and key milestones but does not specify pricing terms, set-asides, incumbent contractor information, or detailed funding requirements within the document provided. The document indicates that chillers will be ordered following contract execution, with the construction phase extending approximately nine months from the June 1, 2026 start date through the March 1, 2027 substantial completion deadline.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSALS
FOR
NORTH & SOUTH PLANT
CHILLER REPLACEMENT
RFP #734-03202026-KM
ADDENDUM 1
Submittal Due Dates:
Qualifications & Pricing and Delivery Proposal:
Tuesday, April 28, 2026
2:00 p.m. CST/CDT
HUB Subcontracting Plan:
Wednesday, April 29, 2026
12:00 p.m. CST/CDT
SECTION 7 – PROJECT PLANNING SCHEDULE
Estimated schedule milestone:
DATE: ACTION:
March 25, 2026: RFP posted to the Electronic State Business Daily (TX Smartbuy/ESBD)
April 9, 2026: Mandatory Voluntary pre-submittal conference/site visit at 10:00 a.m.
April 14, 2026: Deadline for submission of questions and/or clarifications regarding RFP. All questions must be received by 2:00 p.m. CST/CDT to be considered
April 28, 2026: Submissions received by the University on or before 2:00 p.m. CST/CDT
April 29, 2026: HUB Subcontracting Plans received by the University on or before 12:00 p.m.
CST/CDT
May 7, 2026: Notification to successful Respondent(s) - contingent upon execution of contract.
May 14, 2026: Contract Executed
June 1, 2026: Chillers Ordered
November 1, 2026: Construction Begins
March 1, 2027: Substantial Completion
File details come from the government source that posted it. Updated .