About this file

This is a Response to Questions document submitted to Texas A&M University-Texarkana (TAMUT) regarding Request for Proposals RFP-1423_112025 for the Anita & Truman Arnold University Center Servery Remodel project. The project involves a comprehensive remodel of the food service area within the Anita & Truman Arnold University Center, encompassing demolition of existing spaces and installation of new modular casework, equipment, finishes, and building systems across multiple functional areas including market storage, serving lines, back-of-house kitchen, walkway coolers, and various service stations such as pizza, grill, salad bar, and deli/dessert zones. The Request for Proposals process included a pre-bid conference on October 28, 2025, with proposal submissions due November 9, 2025 at 11:30 PM. Potential candidate interviews were scheduled for November 11-13, 2025, with contract award expected on November 14, 2025. The project must be completed by January 9, 2026, with liquidated damages of $5,000 per day assessed for any delays beyond this deadline.

The estimated project cost is $150,000, which covers all demolition work, installation of materials outlined in the Scope of Work, and coordination of equipment installation. Equipment procurement and installation are the responsibility of Chartwells, with equipment preordered and scheduled for delivery to TAMUT by December 9, 2025. The university emphasizes utilization of Historically Underutilized Businesses (HUB) in the contracting process, requiring respondents to submit a HUB Subcontracting Plan. Contractors must provide comprehensive documentation including company background, current workload, litigation history, project execution plans, team organization, and relevant project examples. The project funding is sourced through university capital improvement resources and is being delivered through a Guaranteed Maximum Price Construction Build delivery method.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RESPONSES TO QUESTIONS

TAMUT RFP 1423_112025

Anita & Truman Arnold University Center Servery Remodel

1. Is there an estimated cost available for the Anita & Truman Arnold University Center Servery Remodel project?

a. $150,000 (which should include all the scope of work in the demolition, installation of the material within the SO, and the coordination of the equipment installation. The equipment and its installation is covered directly by Chartwells. That equipment is preordered and scheduled to be delivered to TAMUT by 12/9/2025.)