ESBD_381402_1730237861750_SOL_EXH_F.9_24R0022034_Statement of Work Additional Requirements.pdf
PDF 3 MB Posted
- Attached to
- AUTOCLAVE AND NITROGEN GENERATOR PROJECT
- Solicitation number
- 405-24R0022034
- Issued by
- Travis County, Austin City, Texas
About this file
This document provides the construction plans and specifications for the Autoclave and Nitrogen Generator Replacement project for the Department of Public Safety - Building U located at 5800 Guadalupe Street in Austin, Texas. The project includes removing the existing autoclave and nitrogen generator systems and replacing them with new autoclave and nitrogen generator equipment. The construction documents include detailed floor plans, mechanical and electrical plans, and specifications for the new autoclave and nitrogen generator systems. The documents indicate the project is at the 100% Construction Documents phase with a planned completion date of May 6, 2024. The documents provide key details on the required equipment, including the autoclave model, nitrogen generator system specifications, and piping and electrical requirements. The construction requirements, including demolition and installation work, are specified, along with accessibility standards and general notes for the contractor.
The documents do not provide pricing terms, funding details, or information about any procurement process. The incumbent providers and current environment are not specified. The documents focus solely on the technical requirements and construction details for the autoclave and nitrogen generator replacement project.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
# DATE DESCRIPTION
KEY PLAN
CLIENT
PROJECT NO.
Parkhill.com
/6
/2
:4
:2
P
M
42652.24
05/06/2024
100% Construction Documents05/06/2024
5800 Guadalupe Street Austin, Texas 78752
Department of Public Safety
G-001
Cover Sheet & Index
D e p a rt m e n t o f
P u b li c S a fe ty
B u il d in g
U A
U T
O C
L A
V E
A N
D N
IT
R
O G
E N
G E
N E
R A
T O
R R
E P
L A
C E
M E
N T
Department of Public Safety - Building U
Department of Public Safety
5800 Guadalupe Street Austin, Texas 78752
SHEET INDEX
GENERAL
G-001 Cover Sheet & Index
G-002 Accessibility Standards
ARCHITECTURAL
A-101 Second Floor Plan - Autoclave
MECHANICAL
ME001 Mechanical & Electrical Abbreviations & Legends
ME110 Overall Mechanical and Electrical Plans
ME111 Mechanical and Electrical Plan
Autoclave and Nitrogen Generator Replacement
# DATE DESCRIPTION
KEY PLAN
CLIENT
PROJECT NO.
Parkhill.com
/6
/2
:4
:2
P
M
42652.24
05/06/2024
100% Construction Documents05/06/2024
5800 Guadalupe Street Austin, Texas 78752
Department of Public Safety
G-002
Accessibility Standards
D e p a rt m e n t o f
P u b li c S a fe ty
B u il d in g
U A
U T
O C
L A
V E
A N
D N
IT
R
O G
E N
G E
N E
R A
T O
R R
E P
L A
C E
M E
N T
CL CL CL CL CL CL
CL
CL
CL
CL
CL
URINAL
SCREEN
URINAL
SCREEN
WITH
PILASTERS
SIDE
ELEV
CHILDREN'S MOUNTING
HEIGHTS & REACH RANGES
REACH RANGES
RAMPS AND STAIRS
WATER CLOSETS
READING AND STUDY AREAS, AND
FIXED OR BUILT-IN SEATING AND TABLES,
WORK STATIONS
• ACCESSIBILITY GUIDELINE SHEETS ARE BASED ON
THE 2012 TEXAS ACCESSIBILITY STANDARDS (TAS).
• ACCESSIBILITY GUIDELINE SHEETS ARE FOR
INFORMATIONAL PURPOSES ONLY. AND INTENDED
TO SERVE AS A GUIDE FOR CONSTRUCTION
PROFESSIONALS AND OWNERS.
• SOME OF THE INFORMATION AND PICTOGRAPHS
SHOWN MAY NOT BE APPLICABLE TO THIS
PROJECT.
• REFER TO PLUMBING SHEETS FOR PLUMBING
FIXTURE MOUNTING HEIGHTS.
• GRAPHICS SHOWN ARE FOR ADULTS.
ROOM
60" MIN
M
IN
M
IN
M
IN
MIN
MIN
MIN
60 MIN
48 MIN
M
IN 4
M
IN
30 MIN
M
IN
48 MIN
36 MIN
X
60 MIN
X
M
IN
6 MAX
17-25
8 MIN
M
IN
11 MIN
M
IN
4 MAX
X
X
X
M A
X
M
A X
M
IN
MAX
M
A X
M
A X
2O-25
MAX
10 MAX
M
A X
M
IN
M
A X
10 MAX
M
A X
M
A X
>10-24
MAX
M
A X
MAX 48 MIN
MAX
M
IN
M
IN
M
IN
M
IN
Y
M
IN
X
42 MIN
X
42 MIN
X<48
M
A X
M
IN
M
IN
M
IN
12 MIN
M
IN
C
O N
T R
O L
E N
D W
A L
12 MAX 24 MAX24 MIN
M
IN
12 MAX 15 MAX
12 MAX 15 MAX12 MAX 24 MAX24 MIN 36
M
IN
48 MIN 60 MIN
M
IN
M
IN
36 MIN
60 MIN60 MIN
M
IN
M
IN
M
A X
6 MAX6 MAX
M
A X
6 MAX 6 MAX
M
A X
M
A X
6 MAX
15 MAX
CNTRL
AREA
MAX
CONTROL
AREA
M
A X
C O
N T
R O
L A
R E
A
-1
-1
-1
-1
-1
M
IN
33 MIN 33 MIN
M
IN
33 MIN 33 MIN
M
IN
M
IN
M
IN
M
IN
60 MIN60 MIN
4 MAX
M
IN
M
IN
6 MIN
M
IN
M
IN
35-37
ANY AMOUNT
X
X
36 MIN
15 MIN
M
A X
M
A X
M
IN
-9
M
A X
2 FROM
DOOR FRAME
M
A X
17 MIN
M
A X
-3
M
A X
M
A X
M
IN
18 MIN
M
IN
X
Y
M
IN
X
Y
Y
M
IN
22 MIN
Y
M
IN
24 MIN 24 MIN
48 MIN
M
IN
32 MIN
CLEAR
M
A X
M
IN
M
IN
18 MIN
X
M
IN
12 MIN
X
M
IN
MAX
CONTROL
AREA
17-19 16-18 16-18 16-18 16-18
60 MIN
16-18
M
IN
MIN
24 MIN
15 MIN
T O
S H
O U
LD
E
R
T O
S H
O U
L D
E R
-3
M
IN
M
IN
M
IN
M
IN
M
IN
M
IN
M
IN
M
A X
M A
X
M
IN
M
IN
M A
X
M
IN
M
A X
M
IN
CL36 MAX
MAX
54 MIN
42 MIN
-3
T O
P O
F G
R
IP
P
IN
G S
U R
F A
C E
7-9
M
A X
M
IN
M
IN
MIN
IF X>24
X
36 MIN
24 MIN
M
IN
M
A X
M
A X
M
IN
M
A X
-3
T O
P O
F G
R
IP
P
IN
G S
U R
F A
C E
M
IN
C
O N
T R
O L A
R E
A
-3
T O
P O
F G
R
IP
P
IN
G S
U R
F A
C E
M
A X
C O
N T
R O
L A
R E
A
M
IN
C
O N
T R
O L A
R E
A
-3
T O
P O
F G
R
IP
P
IN
G S
U R
F A
C E
M
A X
C O
N T
R O
L A
R E
A
M
IN
C
O N
T R
O L A
R E
A
-3
T O
P O
F G
R
IP
P
IN
G S
U R
F A
C E
M
A X
C O
N T
R O
L A
R E
A
M
IN
C
O N
T R
O L A
R E
A
-3
T O
P O
F G
R
IP
P
IN
G S
U R
F A
C E
M
IN
C
O N
T R
O L
E N
D W
A L
-1
/2 C
L R
MIN
MIN
IF X>24
X
IF X ≤ 24
X
MIN
MIN
MIN
MIN
X
MIN
IF X>24
M
IN
M
IN
H
O L D
MIN
MIN
IF X>24
X
M
A X
/4
/2
FORWARD PARALLEL ELEVATION
TOE CLEARANCE
PLAN
CENTERED
ELEVATION
KNEE CLEARANCE
ALCOVE
FORWARD
ALCOVE
PARALLEL
180 DEG
TURN AROUND
NARROW
PASSAGE
SINGLE
WHEELCHAIR
T-SHAPE
TURN AROUND
CIRCLE
TURN AROUND
BEVELED TRANSITION
VERTICAL TRANSITION
PROTRUDING
OBJECT
UNDER STAIRS
FORWARD REACH RANGES SIDE REACH RANGES
BACK WALLBACK WALL
LENGTH
REMOVABLE SEAT CONTROLS LOCATION FIXED SEAT
REMOVABLE SEAT FIXED SEAT
C O
N T
R O
L W
A L L
BACK
S E
A T
W A
L L
S E
A T
TRANSFER SHOWER ROLL-IN SHOWER ROLL-IN SHOWER
W/ SEAT ROLL-IN SHOWER
W/ SEAT
ALTERNATE
BACK
WALL
CONTROL WALL
WITHOUT SEAT
CONTROL WALL
WITH SEAT
CONTROL WALL
BENCH SEATINGTHEATER SEATING
BENCH SEATINGTHEATER SEATING
LINE OF SIGHT
LINE OF SIGHT
SPORTS ARENA
THEATER/PLAYHOUSE
AUDITORIUM/CONCERT HALL
LECTURE HALLS
MEETING ROOMS
OF TUB
H E
A D
E N
D W
A L L
LENGTH
OF TUB
W A
L L /P
O S
T M
T D
C A
N T
IL
E
V E
R E
D U
N
IT
FORWARD APPROACH
ACCESSIBLE UNIT
PROTRUDING
OBJECT
NOTE:
WIDE SIDE
LEVER ON
250 LBS AND BE CONTINUOUS
GRAB BARS MUST SUPPORT
DOWN TO 27" AFF MIN
APRON THAT EXTENDS
HIGH UNIT SHOULD HAVE
CL
BRACKET MOUNTED
FIRE EXTINGUISHER* CHALKBOARD MOUNTING
* MARKERBOARD MOUNTING
FIRE ALARM
AUDIBLE &
ACCESSIBLE
COAT HOOKS
VISUAL SIGNAL
OUTLET
* TACKBOARD MOUNTING
CABINET
FIRE EXTINGUISHER
TOWELS
MISC MOUNTING (DIMENSIONS SHOWN ARE TO THE HIGHEST OPERABLE PART)
TELEPHONE
THERMOSTAT
TOWELS
SWITCH
OUTLET
CUPS
SOAP
T O
P O
F E
X T
IN
G
U
IS
H E
R
IN
S
ID
E O
F C
A B
IN
E
T
T O
P O
F T
R A
Y
FIN CLG
IF CEILING IS BELOW 90"
MOUNT TOP OF SIGNAL DEVICE
6" BELOW FINISHED CEILING
NOTE:
EQUIPMENT PERMITTED
IN OUTLINED AREA
WASHING MACHINE
TOP LOAD
CONVEYOR
GROCERY
SLIDE
TRAYACCESSIBLE
COAT HOOKS
AMBULATORY ACCESSIBLE TOE CLEARANCE SIDE APPROACH WALL HUNG WATER CLOSET FLOOR MTD WATER CLOSET
CL
H E
A D
E N
D
(REQUIRED) (REQUIRED)
W A
L L
CL
PUSH SIDE
NOTE:
PULL SIDE
FRONT APPROACHES SWINGING DOORS
HAS BOTH A CLOSER AND A LATCH
X = 12" MIN (305mm) IF DOOR
PUSH SIDE
PUSH SIDE
NOTE:
A CLOSER
PULL SIDE
A CLOSER
Y = 54" MIN (1370mm) IF DOOR HAS
NOTE:
PULL SIDE
NOTE: X = 36" MIN IF Y = 60";
X = 42" MIN IF Y = 54"
HINGE SIDE APPROACHES SWINGING DOORS
LATCH SIDE APPROACHES SWINGING DOORS
Y = 48" MIN (1220mm) IF DOOR
HAS BOTH A CLOSER AND A LATCH
Y = 48" MIN IF DOOR HASNOTE:
VESTIBULE DOORS
TWO HINGED DOORS IN SERIES
NOTE:
THE CLEARANCES FOR FRONT APPROACHES
ALL DOORS IN ALCOVES SHALL COMPLY WITH
VESTIBULE DOORS
RECESSED DOOR
DOOR HARDWARE DOOR LITE
CLOSER & LATCH PROVIDED
WALL
CL
14-17 20-25
LOW
HIGH
TOP OF HANDRAIL GRIPPING SURFACE
GRAB BARS
DISPENSER HEIGHT
28 MAX
18-20
KNEE CLEARANCE
HEIGHT OF TABLES OR COUNTERS
24 MIN
26-30 MAX
AGES: 3 AND 4 AGES: 5 THROUGH 8
17-19 25-27
AGES: 9 THROUGH 12
WATER CLOSET CENTERLINE 12-1512 15-18
CLEARANCE AT WATER CLOSET
LAVATORY, URINAL
OR TOILET ACCESSORIES
NOT IN A STALL
CL
IF Y=60 MIN, X=36 MIN
LINE OF SIGHT OVER HEADS
FRONT LOAD
APPROACH ALLOWED
PARALLEL
AGES: 5 & YOUNGER AGES: 6-12
LETTERS & BRAILLE
GRAPHIC SYMBOLS
6x8 PICTOGRAM
MEN
6x8 PICTOGRAM
GRAPHIC SYMBOLS
LETTERS & BRAILLE
WOMEN
& BRAILLE
ROOM NUMBER
8x6 ROOM NAME
SUPERVISOR
MAINTENANCE
& BRAILLE
10x3 ROOM NAME
ADMINISTRATION
6x6 DIRECTIONAL
GRAPHIC SYMBOL
ONLY ONLY
GRAPHIC SYMBOL
6x6 DIRECTIONAL
& BRAILLE
6x6 CHANGEABLE
MESSAGE W/ PERMANENT
ROOM NAME, NUMBER,
ITHJOHN S
OFFICE
REFER TO SIGNAGE PACKAGE OR DETAILS FOR ACTUAL SIGNAGE SPECIFIED
6x8 PICTOGRAM
GRAPHIC SYMBOLS
LETTERS & BRAILLE
STAIR 1
6x8 PICTOGRAM
GRAPHIC SYMBOLS
LETTERS & BRAILLE
STAIR 1
DISPENSERS
IF A WALL HUNG OR FLOOR
MOUNTED FLUSH VALVE
WATER CLOSET IS SPECIFIED,
ENSURE ALL DIMENSIONS
SHOWN ARE MET.
CL
REFER TO KNEE AND
TOE CLEARANCE GRAPHICS
NOT ASSOCIATED
WITH A WATER CLOSET
ONLY TOILET
ASSOCIATED WITH
WATER CLOSETS ARE
ALLOWED WITHIN
FLOOR AREA
ACCESSORIES
28 MAX 28 MAX
NOTE: REFER TO "CHANGES IN LEVEL" DETAILS FOR SHOWER THRESHOLDS
THRESHOLD
SEAT
SEAT
THRESHOLD THRESHOLD
/4
VERTICAL/BEVELED
/4
TRANSITION
M
A X
L
IT
E
O P
E N
IN
G
SURFACE OF MIRROR
TOP OF REFLECTIVE
BOTTOM OF
MIRROR
SURFACE OF
REFLECTIVE
WITH SEAT
CNTRL
AREA
T O
P O
F H
O O
K
CLEAR FLOOR AREA/ACCESSIBLE ROUTE
PROTRUDING OBJECT PROTECTION/REACH RANGES SHOWERS
ASSEMBLY SEATING
TYPICAL WATER CLOSETS
EWC/DRINKING FOUNTAINS
STANDARD ACCESSIBLE MOUNTING HEIGHTS TYPICAL TOILET STALLS
TUBS
TYPICAL DOOR CLEARANCES
GENERAL NOTES
EXAMPLE SIGNAGE - SEE STANDARD ACCESSIBLE MOUNTING HEIGHT
CHANGES IN LEVEL
REFLECTIVE SURFACE
LAVATORIESURINALS
CORRIDOR
CORR.4
STAIR
U-2.2
BIOHAZARD
U-202.01
CORRIDOR
CORR.4
STAIR
U-2.2
BIOHAZARD
U-202.01
# DATE DESCRIPTION
KEY PLAN
CLIENT
PROJECT NO.
Parkhill.com
/6
/2
:4
:2
P
M
42652.24
05/06/2024
100% Construction Documents05/06/2024
5800 Guadalupe Street Austin, Texas 78752
Department of Public Safety
A-101
Second Floor Plan - Autoclave
D e p a rt m e n t o f
P u b li c S a fe ty
B u il d in g
U A
U T
O C
L A
V E
A N
D N
IT
R
O G
E N
G E
N E
R A
T O
R R
E P
L A
C E
M E
N T
1/4" = 1'-0"A4 FLOOR PLAN - AUTOCLAVE DOOR DEMOILITION
1/4" = 1'-0"A6 FLOOR PLAN - AUTOCLAVE DOOR
AS INDICATED BY: #
KEY NOTES
1. REMOVE WALL, GYPSUM BOARD AND STUDS AS NECESSARY TO
REMOVE EQUIPMENT. CONTRACTOR TO VARIFY CONDITIONS BEFORE
BEGINNING DEMOLITION OF WALL.
2. REPLACE PREVIOUSLY DEMOLISHED WALL WITH NEW STUDS, GYPSUM
BOARD, WALL BASE, ETC. TO MATCH SURROUNDINGS. CONTRACTOR
TO COORDINATE FINISHES WITH OWNER.
GENERAL NOTES
1 CONTRACTOR TO VERIFY ALL EXISTING CONDITIONS PRIOR TO
BEGINNING WORK
2 NOTIFY ARCHITECT/OWNER OF ANY DISCREPANCIES PRIOR TO
BEGINNING WORK
3. CONTRACTOR TO VERIFY WITH OWNER ANY FINISH COLORS
NECESSARY TO MATCH SURROUNDING FINISHES
4. CONTRACTOR TO VERIFY ALL HARDWARE/ACCESS CONTROL/KEYING
REQUIREMENTS WITH OWNER
5. CONTRACTOR TO COORDINATE WITH MECHANICAL, ELECTRICAL AND
PLUMBING WORK AS NEEDED
6. THE CONTRACTOR IS REQUIRED TO SAFEGUARD ALL EXISTING
CONSTRUCTION AND EQUIPMENT FROM POTENTIAL HARM CAUSED BY
DUST, DEBRIS, OR DAMAGE RESULTING FROM CONSTRUCTION AND
DEMOLITION ACTIVITIES.
7. THE CONTRACTOR IS EXPECTED TO UPHOLD STRINGENT STANDARDS
OF CLEANLINESS THROUGHOUT THE WORKSPACE. IT IS IMPERATIVE
THAT ALL AREAS AND EQUIPMENT BE THOROUGHLY CLEANED
AND ORGANIZED AT THE CONCLUSION OF EACH WORKDAY.
PLUMBING SYMBOL LEGEND
BUTTERFLY VALVE
BALL VALVE
PRESSURE REDUCING VALVE
CONNECT TO EXISTING
POINT OF DISCONNECT
DOMESTIC COLD WATER
DOMESTIC HOT WATER
DOMESTIC HOT WATER RETURN
SEWER
VENT
CONDENSATE DRAIN
INDICATES DEMOLITION
FLUID FLOW DIRECTION
PIPE TURNED UP
PIPE TURNED DOWN
PIPING LEGEND
EXISTING PIPING IS INDICATED SAME AS ABOVE,
EXCEPT IN A LIGHTER PEN WEIGHT.
P.O.D
MECHANICAL/PLUMBING ABBREVIATIONSSYMBOL LEGEND
AUTOMATIC AIR VENT
MANUAL AIR VENT
P/T PLUG
VENTURI FLOW METER
AUTOMATIC FLOW CONTROL
BUTTERFLY VALVE
BALL VALVE
CHECK VALVE
GLOBE VALVE
GATE VALVE
ANGLE GATE VALVE
PRESSURE REDUCING VALVE
AUTOMATIC VALVE, 2-WAY
AUTOMATIC VALVE, 3-WAY
FLANGE
UNION
STRAINER
GAS METER
AUTOMATIC AIR VENT
ELECTRIC MOTOR
CENTRIFUGAL FAN
THERMOMETER
EXPANSION VALVE
FLOW SWITCH
PRESSURE SWITCH
PUMP
MV
M
FS
PS
AV
BTUH BRITISH THERMAL UNIT PER HOUR
CFM CUBIC FEET PER MINUTE
DEG DEGREE
°F DEGREES FAHRENHEIT
DIA DIAMETER
ID DIAMETER, INSIDE
OD DIAMETER, OUTSIDE
DDC DIRECT DIGITAL CONTROLS
DB DRY BULB TEMPERATURE
EAT ENTERING AIR TEMPERATURE
EWT ENTERING WATER TEMPERATURE
FT FEET
GAL GALLONS
GPD GALLONS PER DAY
GPH GALLONS PER HOUR
GPM GALLONS PER MINUTE
HP HORSEPOWER
IN INCHES
inHG INCHES OF MERCURY inH2O INCHES OF WATER kW KILOWATT
LAT LEAVING AIR TEMPERATURES
MAT MIXED AIR TEMPERATURE
NC NORMALLY CLOSED
NO NORMALLY OPEN
PH PHASE
LBS POUNDS
LBS/HR POUNDS PER HOUR
PSI POUNDS PER SQUARE INCH
PRV PRESSURE REDUCED VALVE
RPZ REDUCED PRESSURE BACKFLOW PREVENTER ASSEMBLY
RH RELATIVE HUMIDITY
RPM REVOLUTIONS PER MINUTE
SEER SEASONAL ENERGY EFFICIENCY RATIO
SQ.FT. SQUARE FEET
SP STATIC PRESSURE
k THERMAL CONDUCTIVITY
R THERMAL RESISTANCE
U U-FACTOR, HEAT TRANSFER COEFFICIENT
VFD VARIABLE FREQUENCY DRIVE
VEL VELOCITY
V VOLTS
WB WET BULB TEMPERATURE
HEATING VENTILATING AND AIR
CONDITIONING SPECIFICATIONS
I. GENERAL
A. NOTE:
1. CONFORM WITH THE APPLICABLE PROVISIONS OF THE GENERAL CONDITIONS,
THE SPECIAL CONDITIONS AND THE GENERAL REQUIREMENTS.
B. SUBMITTALS
1. SUBMIT MANUFACTURER'S DATA AND SHOP DRAWING ON ALL MATERIALS.
C. SCOPE:
1. THIS SECTION OF THE SPECIFICATIONS PERTAINS TO ALL LABOR, MATERIALS,
EQUIPMENT AND SERVICE NECESSARY FOR AND INCIDENTAL TO THE HEATING,
VENTILATING AND AIR CONDITIONING SYSTEM AS SHOWN ON THE DRAWINGS
AND/OR AS SPECIFIED HEREIN.
2. ALL APPURTENANCES AND AUXILIARY EQUIPMENT NECESSARY TO THE
FUNCTION OF ANY SPECIFIED ITEM OF EQUIPMENT SHALL BE FURNISHED WITH
THE ITEM OF EQUIPMENT, WHETHER SPECIFICALLY MENTIONED OR NOT. EACH
ITEM OF EQUIPMENT SHALL PERFORM THE FUNCTION FOR WHICH IT IS
INTENDED, AND ALL WORK NECESSARY TO PROVIDE A COMPLETE FUNCTIONAL
SYSTEM SHALL BE PROVIDED.
3. THIS SPECIFICATION REQUIRES THAT ALL ITEMS OF EQUIPMENT BE COMPLETELY
INSTALLED, FINALLY CONNECTED, TESTED AND PLACED IN SERVICE.
4. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO VERIFY ALL
REQUIREMENTS OF THE EQUIPMENT AND THE CONTRACT AND CERTIFY WITH
THE SUBMITTAL OF THE SHOP DRAWINGS THAT ALL REQUIREMENTS HAVE BEEN
MET, INCLUDING:
a. SPACE REQUIREMENTS
b. ELECTRICAL REQUIREMENTS (VOLTAGE, PHASE, WIRES - NO. AND SIZE)
c. CAPACITIES
d. CLEARANCE FOR MAINTENANCE
e. QUALITY
f. QUANTITY
II. PRODUCTS
A. AUTOCLAVE
1. Model 3AV, CHAMBER SINGLE DOOR STERILIZER BY CONSOLIDATED STERILIZER
SYSTEMS.
2. CONSTRUCTION:
a. CHAMBER SHALL BE CONSTRUCTED FROM 316L STAINLESS STEEL.
b. JACKET SHALL BE CONSTRUCTED FROM STEEL.
c. DOOR SHALL BE VERTICALLY SLIDING AND CONSTRUCTED FROM 316L
STAINLESS STEEL.
3. STANDARD FEATURES:
a. ECOCALENDAR, AUTO IDLE SHUT-OFF
b. ASME U-1 CODE STAMPING
c. UL, CUL LISTED
d. END-OF CYCLE VACUUM DRYING
e. FULLY OPENING FRONT SERVICE PANEL
f. CSS STARTER KIT
4. ADDITIONAL OPTIONS:
a. X1 CONTROLS: TOP MOUNT 7" COLOR TOUCHSCREEN
b. STERINET DATAPORT - USB
c. PASSWORK PROTECTION AND LOCKABLE CYCLE PARAMETERS
d. THERMAL PRINTER
e. 110 VOLT CONTROLS
f. 316L STAINLESS STEEL CHAMBER WITH CARBON STEEL JACKET
g. STANDARD FINISH PASSIVATED CHAMBER
h. PROGEN MODEL INTEGRAL ELECTRICALLY HEATED STEAM GENERATOR -
25 KW
i. GENERATOR: 480 VOLTS, 3 PHASE
j. AUTMATIC GENERATOR BLOWDOWN WITH MOTORIZED BALL VALVE
k. GRAVITY AIR REMOVAL WITH ECONOMY POST-VACUUM DRYING SYSTEM
l. BRASS, BRONZE AND COPPER PIPING
m. EZ-GLIDE VERTICAL SLIDING DOOR WITH NON-STICK GASKET
n. CABINET MOUNTING WITH STAINLESS STEEL FRONT AND SIDE PANELS
o. WATERECO WATER CONSERVATION AND MONITORING SYSTEM
p. AUTOMATIC JACKET BLOWNDOWN FOR LIQUIDS CYCLE
q. WHISPER-QUIET ON-BOARD AIR COMPRESSOR
r. EMERGENCY STOP BUTTON
s. 2 SHELVES - 1 STATIONARY BOTTOM SHELF AND 1 STATIONARY UPPER
SHELF
5. INSTALLATION:
a. MANUFACTURER REP SHALL INCLUDE UNCRATING, SETTING IN PLACE, LEVELING, FINAL ASSEMBLY, FINAL UTILITY CONNECTIONS(5' MAX), START
UP AND END USER TRAINING.
B. NITROGEN GENERATOR SYSTEM
1. PERFORMANCE REQUIREMENTS
a. SYSTEM OPERATING PRESSURE: 130-160 PSI.
b. RESERVIOR PRESSURE: 300 PSI MAX.
c. PURITY: MIN 99%.
d. GENERATION: MIN 1,200 L/MIN.
2. MANUFACTURER
A. ATLAS COPCO
B. BAUER COMPRESSORS
C. SUBSTUTIONS ALLOWED
3. PRODUCTS
a. DESCRIPTION: PACKAGED OIL INJECTED SCREW COMPRESSOR AND
PACKAGED NITROGEN GENERATOR WITH AIR BUFFER TANK AND
NITROGEN PRODUCT TANK.
b. OIL INJECTOR SCREW COMPRESSOR BASIS OF DESIGN: GA30VSD-175.
c. NITROGEN GENERATOR BASIS OF DESIGN: NGP+160-360.
d. ACCESSORIES:
1. PROVIDE ALL MANUFACTURERS RECCOMENDED ACCESSORIES
FOR SYSTEM TO FUNCTION INCLUDING BUT NOT LIMITED TO:
MICROPROCESSOR CONTROLS, PRE-FILTER, AIR DRYER, CARBON
AND PARTICULATE FILTER AFTER DRYER, COMPRESSED AIR
BUFFER TANK AND NITROGEN PRODUCT TANK, SAFETY VALVE,
POWER CORD AND POWER DRAIN FOR BUFFER AND PRODUCT
TANK, POST FILTER AFTER NITROGEN GENERATOR AND PROVIDE
OWNER COMISSIONING AND TRAINING AFTER SETUP.
PLUMBING SPECIFICATIONS
I. GENERAL
A. NOTE:
1. CONFORM WITH APPLICABLE PROVISIONS OF THE GENERAL CONDITIONS,
SPECIAL CONDITIONS, GENERAL REQUIREMENTS, AND SUPPLEMENTAL
CONDITIONS.
B. SUBMITTALS:
1. SUBMIT MANUFACTURER'S DATA ON ALL MATERIALS.
C. SCOPE:
1. THIS SECTION OF THE SPECIFICATIONS REQUIRES THE FURNISHING AND
INSTALLATION OF ALL EQUIPMENT, LABOR, MATERIALS, TRANSPORTATION,
TOOLS AND APPLIANCES AND IN PERFORMING ALL OPERATIONS IN CONNECTION
WITH THE INSTALLATION OF THE PLUMBING SYSTEMS.
II. PRODUCTS
A. MATERIALS:
1. DOMESTIC COLD WATER PIPING: COPPER TUBING, ASTM B 88, TYPE L , HARD
DRAWN. FITTINGS CONFORMING TO ASME B 16.18, CAST COPPER ALLOY OR
ASME B 16.22, WROUGHT COPPER AND BRONZE. JOINTS: SOLDER, LEAD FREE,
ASTM B32, 95-5 TIN-ANTIMONY, OR TIN AND SILVER, WITH MELTING RANGE 430 TO
535 DEGREES F OR BRAZE, AWS A5.8 BCUP ALLOY WITH MELTING RANGE 1,190
TO 1,480 DEGREES F.
2. SANITARY SOIL, WASTE AND DRAIN LINES: PVC-DWV PLASTIC PIPE AND
FITTINGS CONFORMING TO ASTM D-2665-68, ASSEMBLED WITH SOLVENT
CEMENT CONFORMING TO ASTM D-2564-67.
B. HANGERS AND SUPPORTS:
1. SUPPORT ALL PIPES AS REQUIRED BY THE PLUMBING CODE AND AS REQUIRED
TO PREVENT SAGGING. PIPES SHALL BE SUPPORTED ON 8' INTERVALS AS A
MINIMUM. HANGERS SHALL BE CLEVIS TYPE WITH ADJUSTERS.
C. FABRICATION OF PIPE JOINTS:
1. THREADED PIPES: REAM AND DEBURR PIPE AFTER IT IS CUT AND BEFORE IT IS
THREADED. STAND EACH PIPE ON ONE END AND HAMMER TO REMOVE ALL
FOREIGN MATERIAL. FULL CUT THREADS, BUT NOT MORE THAN 3 PIPE THREADS
SHALL REMAIN EXPOSED WHEN JOINT IS COMPLETED. MAKE UP JOINTS WITH
GRAPHITE AND OIL OR AN APPROVED GRAPHITE COMPOUND APPLIED TO MALE
THREADS ONLY. CAULKING OF THREADED JOINTS TO STOP OR PREVENT LEAKS
IS PROHIBITED.
2. COPPER TUBING: CUT TUBING SQUARE, REAM AND DEBURR. CLEAN INSIDES OF
FITTINGS AND OUTSIDES OF TUBING WITH SAND CLOTH BEFORE ASSEMBLY.
EXERCISE CARE TO PREVENT ANNEALING OF FITTINGS AND HARD DRAWN
TUBING. MAKE ALL JOINTS WITH HIGH TEMPERATURE SOLID STRING OR WIRE
SOLDER, 95% TIN, 5% ANTIMONY, USING NON-CORROSIVE PASTE FLUX OF THE
PROPER TYPE FOR ALL COPPER TUBING. LOW TEMPERATURE SOLDER SUCH AS
50/50 OR 40/60 WILL NOT BE PERMITTED.
D. REPAIR OF LEAKS:
1. ALL LEAKS IN PIPING SYSTEMS SHALL BE CORRECTED AS FOLLOWS:
a. REPAIR LEAKS IN SOLDER JOINTS BY REMAKING THE JOINT; NO
SOLDERING OR BRAZING OVER EXISTING JOINTS WILL BE PERMITTED.
b. REPAIR LEAKS IN SCREWED JOINTS BY TIGHTENING THE JOINT; REMAKE
THE JOINT IF THE TIGHTENING FAILS TO STOP THE LEAK.
c. REPAIR LEAKS IN PVC PIPE BY REMAKING THE JOINT.
2. WHEN ANY DEFECT IS REPAIRED, RETEST THAT SECTION OF THE SYSTEM.
E. INSULATION:
1. ANY INSULATION WHICH IS NOT APPLIED IN A WORKMANLIKE MANNER WILL BE
REJECTED AND REPLACED. ALL COVERINGS SHALL BE SMOOTH, FLUSH,
DRESSED TO LINE AND TIGHT. MASTIC SHALL BE NEATLY APPLIED AND TOOLED.
ARCHITECT RESERVES THE RIGHT TO REJECT ANY INSULATION WHOSE
APPEARANCE IS DEEMED UNACCEPTABLE.
2. APPLY INSULATION AND PIPE COVERING AFTER ALL WORK HAS BEEN TESTED,
FOUND TO BE TIGHT AND ACCEPTED AS SUCH BY THE ARCHITECT.
THOROUGHLY CLEAN AND DRY ALL SURFACE TO BE COVERED.
3. FACTORY-APPLIED VAPOR-BARRIER JACKETS SHALL BE ONE OF THE
FOLLOWING:
a. AN ALL SERVICE JACKET (ASJ) LAMINATED OF FLAME RESISTANT WHITE
KRAFT PAPER, GLASS SCRIM REINFORCEMENT, AND KRAFT PAPER.
b. FOIL REINFORCED KRAFT (FRK) JACKET LAMINATED OF FLAME
RESISTANT 0.001" ALUMINUM FOIL, GLASS SCRIM REINFORCEMENT AND
KRAFT PAPER.
4. INSULATE VALVES AND FITTINGS WITH TWO FIBERGLASS INSERTS AND
PREFORMED MANVILLE "ZESTON" COVERS WITH TAPED SEAMS.
5. THE FOLLOWING DESCRIBES MATERIALS, THICKNESSES AND FINISHES FOR
INSULATION AND COVERINGS.
6. DOMESTIC COLD WATER LINES: INSULATE WITH 1" THICK OWENS-CORNING
FIBERGLAS ASJ/SSL-II MOLDED SECTIONAL GLASS FIBER PIPE COVERING WITH
AN ALL SERVICE JACKET (ASJ). INSULATE CONCEALED VALVES AND FITTINGS
WITH PREFORMED "ZESTON" PVC COVERS OVER FIBERGLASS INSULATION.
INSULATE EXPOSED VALVES AND FITTINGS WITH HAMFAB INSULATION FITTINGS.
F. TESTING:
1. TEST ALL PIPES BEFORE THEY ARE CONCEALED IN FURRINGS OR CHASES,
INSULATED, PAINTED, OR OTHERWISE COVERED UP OR RENDERED
INACCESSIBLE. ACCOMPLISH TESTING BY SECTIONS OF LINES OR SYSTEMS, AS
REQUIRED BY CONDITIONS DURING CONSTRUCTION. CLEAN ALL PIPING AND
EQUIPMENT BEFORE TESTING.
2. DOMESTIC WATER LINES INTERIOR: HYDROSTATICALLY TEST FOR 6 HOURS AT
150 PSIG. THERE SHALL BE NO LEAKS WHATSOEVER.
3. OTHER TESTS: PERFORM ALL TESTS REQUIRED TO DEMONSTRATE THAT EACH
SYSTEM IS OPERATING PROPERLY.
END OF SECTION
1. GENERAL NOTES ON THIS SHEET ARE APPLICABLE TO EACH DRAWING OF THIS SET OF
CONSTRUCTION DOCUMENTS. NOTES SPECIFIC TO INDIVIDUAL DRAWINGS WILL BE SHOWN
ON THE RESPECTIVE MECHANICAL DRAWING.
2. THE CONTRACTOR SHALL PROVIDE A COMPLETE SYSTEM TO INCLUDE ALL LABOR,
MATERIALS, TOOLS AND EQUIPMENT FOR A COMPLETE AND FUNCTIONAL SYSTEM
INCLUDING ALL NECESSARY APPURTENANCES CUSTOMARILY INCLUDED IF NOT
SPECIFICALLY CALLED OUT.
3. ENTIRE INSTALLATION, INCLUDING MATERIALS, EQUIPMENT AND WORKMANSHIP SHALL
CONFORM WITH ALL APPLICABLE LAWS, CODES AND REGULATIONS.
4. THIS PROJECT SHALL CONFORM TO APPLICABLE ASHRAE, NFPA AND SMACNA STANDARDS
AND OTHER REGULATORY BODIES HAVING JURISDICTION OVER THE CLASS OF WORK.
5. MATERIAL AND EQUIPMENT SHALL HAVE STAMPS OR SEALS OF AHRI, ASME, UL OR ASTM.
6. THE CONTRACTOR SHALL MAKE TESTS FOR ACCEPTANCE AND APPROVAL AS REQUIRED BY
CODE AND THE REQUIREMENTS OF APPLICABLE REGULATORY AGENCIES. REQUIRED TESTS
SHALL BE PERFORMED IN THE PRESENCE OF THE ENGINEER OF RECORD AND/OR OWNER
UNLESS OTHERWISE WAIVED IN WRITING.
7. THE CONTRACTOR SHALL OBTAIN AND PAY FOR ALL PERMITS, LICENSES, DOCUMENTS AND
SERVICES RELATED TO INSTALLATION OF THE WORK.
8. THE CONTRACTOR SHALL COORDINATE HIS WORK WITH THE OTHER TRADES IN ORDER TO
RESOLVE ANY CONFLICTS THAT MIGHT ARISE DUE TO THE LOCATION OF EQUIPMENT OR
THE USE OF SPACE.
9. EQUIPMENT OF DIFFERENT ELECTRICAL CHARACTERISTICS MAY BE FURNISHED PROVIDED
SUCH PROPOSED EQUIPMENT IS APPROVED IN WRITING AND CONNECTING ELECTRICAL
SERVICE, CIRCUIT BREAKERS AND CONDUIT ARE APPROPRIATELY MODIFIED AT NO COST TO
THE OWNER.
10. DO NOT INSTALL EQUIPMENT, PIPING OR DUCTWORK OVER ANY ELECTRICAL EQUIPMENT
OR ELECTRICAL SERVICE SPACE.
11. LAYOUT OF PIPING AND DUCTWORK IS DIAGRAMMATIC.
12. INSTALL MECHANICAL EQUIPMENT TO FACILITATE SERVICING, MAINTENANCE AND REPAIR
OR REPLACEMENT OF ELECTRICAL COMPONENTS. AS MUCH AS PRACTICAL, CONNECT
EQUIPMENT FOR EASE OF DISCONNECTING, WITH A MINIMUM OF INTERFERENCE WITH
OTHER INSTALLATIONS, PIPING SHALL NOT INTERFERE WITH FILTER PULL.
13. MECHANICAL CONTRACTORS SHALL PROVIDE AUTOMATIC CONTROL DEVICES SUCH AS
STARTERS, VARIABLE FREQUENCY DRIVES (VFD), TEMPERATURE SENSORS, RELAYS,
PRESSURE SWITCHES THAT ARE ASSOCIATED WITH MECHANICAL EQUIPMENT AND
ASSOCIATED CONTROL WIRING FROM CONTROL POWER LOCATION TO THE CONTROL
DEVICE/ ELECTRICAL CONTRACTOR SHALL PROVIDE CONDUIT AND WIRING FROM POWER
SOURCE TO DISCONNECT SWITCH, FROM DISCONNECT SWITCH TO STARTER OR VFD, AND
FROM STARTER OR VFD TO THE EQUIPMENT.
14. LOCATE SENSORS 48" ABOVE FINISHED FLOOR.
15. BEFORE INSTALLATION, EQUIPMENT AND DEVICES INCLUDING, BUT NOT LIMITED TO, ANY
DEVICE WITH ELECTRICAL CONNECTIONS, DUCTWORK, INSULATION, PIPING, VALVES, AIR
DEVICES, ETC., SHALL NOT BE STORED DIRECTLY ON GRADE OR ON A SLAB OR FLOOR.
BEFORE AND AFTER INSTALLATION, SUCH EQUIPMENT AND DEVICES SHALL BE PROTECTED
FROM ENTRY OF DIRT, TRASH, WATER (EXCEPT AS REQ'D), VERMIN, ETC.
16. CONTRACTOR SHALL NOT CUT, DRILL, OR ALTER ANY ELEMENT OF A WALL, FLOOR, CEILING, ROOF, SLAB, ETC., WITHOUT FIRST RECEIVING INSTRUCTIONS FROM ARCHITECT. ALL CUTS
SHALL BE MADE WITH A CUTTING TOOL.
17. PATCHING OR SEALING OF CUTS, PENETRATIONS, ETC., SHALL BE DONE BY CONTRACTOR
PER INSTRUCTIONS FROM AND TO FINAL APPROVAL OF ARCHITECT. COORDINATE WITH
GENERAL CONTRACTOR.
18. NOT ALL SYMBOLS OR ABBREVIATIONS ARE USED.
GENERAL NOTES
ELECTRICAL SPECIFICATIONS
CODE COMPLIANCE/WORKMANSHIP
1. CONTRACTOR SHALL COMPLY WITH ALL NATIONAL, STATE AND LOCAL CODES
AND ACCEPTED GOOD PRACTICE.
2. ALL WORK SHALL BE PERFORMED BY LICENSED AND QUALIFIED PERSONNEL.
EXISTING CONDITIONS
1. CONTRACTOR SHALL FIELD VERIFY ALL EXISTING CONDITIONS PRIOR TO
SUBMITTING BID. BY SUBMITTING BID, CONTRACTOR STATES THAT HE HAS
EXAMINED ALL EXISTING CONDITIONS. IF CONTRACTOR ENCOUNTERS EXISTING
CONDITIONS WHICH NEED CLARIFICATION, CONTACT ENGINEER FOR
RESOLUTION OR CLARIFICATION.
PERMITS AND FEES
1. CONTRACTOR SHALL OBTAIN ALL PERMITS AND PAY ALL FEES AND CHARGES
REQUIRED (INCLUDING UTILITY COMPANY CHARGES).
GUARANTEE AND WARRANTIES
1. ALL WORK PERFORMED UNDER THIS CONTRACT SHALL HAVE ONE (1) YEAR
WRITTEN GUARANTEE FOR ALL MATERIALS AND WORKMANSHIP.
MATERIALS
1. ALL MATERIALS SHALL BE NEW AND SPECIFICATION GRADE.
OWNERS MANUAL
1. AT COMPLETION OF PROJECT, CONTRACTOR SHALL DELIVER TO OWNER ALL
DOCUMENTS (INCLUDING BUILDING PERMITS, OPERATION AND MAINTENANCE
MANUALS, WARRANTY ETC.).
CONDUIT
1. ALL INTERIOR CONDUIT SHALL BE EMT. ALL EXTERIOR AND ABOVE GRADE
CONDUIT SHALL BE RIGID GALVANIZED STEEL. MINIMUM SIZE OF CONDUIT SHALL
BE 3/4". ALL CONDUIT SHALL BE ROUTED PERPENDICULAR TO BUILDING LINES
WHERE EXPOSED TO VIEW.
WIRE
1. ALL WIRE SHALL BE THHN/THWN COPPER UNLESS OTHERWISE INDICATED ON
THE DRAWINGS. MINIMUM SIZE OF WIRE SHALL BE #12. FOR 20A CIRCUITS
LONGER THAN 100', MINIMUM WIRE SIZE SHALL BE #10 AWG.
DISCONNECT SWITCHES
1. ALL DISCONNECT SWITCHES SHALL BE HEAVY DUTY WITH NEMA CONFIGURATION
AS INDICATED ON DRAWINGS OR AS REQUIRED BY N.E.C. PROVIDE FUSES IN
SWITCHES AS INDICATED ON THE DRAWINGS.
RECEPTACLES
1. ALL RECEPTACLES SHALL BE SPECIFICATION GRADE (HUBBELL 5352 OR
APPROVED EQUAL). COLOR OF ALL RECEPTACLES AND COVERPLATES SHALL BE
WHITE. MOUNTING HEIGHT OF RECEPTACLES SHALL COMPLY WITH A.D.A.
REQUIREMENTS UNLESS SPECIFIC OR SPECIAL MOUNTING HEIGHT IS SHOWN ON
DRAWINGS OR REQUIRED BY EQUIPMENT.
SUBMITTALS AND SUBSTITUTIONS
1. CONTRACTOR SHALL FURNISH SUBMITTAL DATA TO ENGINEER FOR APPROVAL
ON ALL FIXTURES AND EQUIPMENT PRIOR TO ORDERING ANY ITEMS.
CONTRACTOR MAY OFFER SUBSTITUTIONS ON ITEMS FOR APPROVAL BY
ENGINEER. SUBSTITUTIONS MUST BE EQUAL IN ALL RESPECTS TO ITEMS
SCHEDULED OR SPECIFIED.
# DATE DESCRIPTION
KEY PLAN
CLIENT
PROJECT NO.
Parkhill.com
/6
/2
:4
:2
P
M
42652.24
05/06/2024
100% Construction Documents05/06/2024
5800 Guadalupe Street Austin, Texas 78752
Department of Public Safety
ME001
Mechanical & Electrical Abbreviations & Legends
D e p a rt m e n t o f
P u b li c S a fe ty
B u il d in g
U A
U T
O C
L A
V E
A N
D N
IT
R
O G
E N
G E
N E
R A
T O
R R
E P
L A
C E
M E
N T
R
05/06/2024
05/06/2024
J
J
J
J
J
A. REFER TO GENERAL NOTES ON M-001.
/ME111A4
/ME111C4
# DATE DESCRIPTION
KEY PLAN
CLIENT
PROJECT NO.
Parkhill.com
/6
/2
:4
:2
P
M
42652.24
05/06/2024
100% Construction Documents05/06/2024
5800 Guadalupe Street Austin, Texas 78752
Department of Public Safety
ME110
Overall Mechanical and Electrical Plans
D e p a rt m e n t o f
P u b li c S a fe ty
B u il d in g
U A
U T
O C
L A
V E
A N
D N
IT
R
O G
E N
G E
N E
R A
T O
R R
E P
L A
C E
M E
N T
GENERAL NOTES
3/32" = 1'-0"A2 OVERALL MECHANICAL PLAN- 1ST FLOOR
3/32" = 1'-0"D2 OVERALL MECHANICAL PLAN- 2ND FLOOR
NORTH
NORTH
05/06/2024
J
J
J
J
A. REFER TO GENERAL NOTES ON M-001.
CORRIDOR
CORR.4
STAIR
U-2.2
ACS-1
BIOHAZARD
U-202.01
1 1/2"
ACS-2
1/2"
1"
1 1/2"
1/2"
1 1/2"
CORRIDOR
CORR.4
STAIR
U-2.2
BIOHAZARD
U-202.01
P.O.D
LOADING
DOCK
U-103.01
CYLINDER
STORAGE
U-103.02
CORRIDOR
CORR.1.5
VEHICLE
SEARCH BAY
U-103.04
CYLINDER
STORAGE
U-103.02
CORRIDOR
CORR.1.5
LOADING
DOCK
U-103.01
VEHICLE
SEARCH BAY
U-103.04
# DATE DESCRIPTION
KEY PLAN
CLIENT
PROJECT NO.
Parkhill.com
/6
/2
:4
:2
P
M
42652.24
05/06/2024
100% Construction Documents05/06/2024
5800 Guadalupe Street Austin, Texas 78752
Department of Public Safety
ME111
Mechanical and Electrical Plan
D e p a rt m e n t o f
P u b li c S a fe ty
B u il d in g
U A
U T
O C
L A
V E
A N
D N
IT
R
O G
E N
G E
N E
R A
T O
R R
E P
L A
C E
M E
N T
AS INDICATED BY: #
KEY NOTES
GENERAL NOTES
1 REMOVE ALL EXISTING PIPING SERVING EXISTING BOILER AND AUTOCLAVE
MACHINE. REMOVE UP TO DESCALAR DEVICE. PREPARE PIPING FOR
CONNECTION TO NEW PIPING.
2 REMOVE EXISTING NITROGEN GENERATOR SYSTEM.
3 REMOVE EXISTING BOILER AND AUTOCLAVE SYSTEM.
4 ROUTE AUTOCLAVE SYSTEM DRAIN PIPING TO FLOOR SINK. TERMINATE WITH A
90 DEGREE FITTING OVER FLOOR SINK .
5 PROVIDE NEW AUTOCLAVE MACHINE. INSTALL PER MANUFACTURERS
REQUIREMENTS. SEE SPECS ON SHEET M-001 FOR MORE INFORMATION.
6 PROVIDE OXYGEN DEFICIENCY MONITOR. INTERLOCK TO NITROGEN
GENERATOR CONTROL SYSTEM. PROVIDE CONTROL TO SHUTDOWN NITROGEN
GENERATOR WHEN OXYGEN LEVEL IN THE SPACE FALLS BELOW 19.5%.
EXAMPLE: AMI MODEL 221R.
7 PROVIDE NEW NITROGEN GENERATOR SYSTEM. INSTALL PER
MANUFACTURERS REQUIREMENTS. MODIFY AND EXTEND PIPING AS REQURIED
TO CONNECT TO NEW UNIT. BASIS OF DESIGN IS ATLAS COPCO MODEL
GA30VSDP. REFER TO SPECIFICATIONS FOR PERFORMANCE REQUIREMENTS.
8 JUNCTION BOX FOR SENSOR. 120V/1P, 20A IN 3/4" CONDUIT. EXTEND AND
CONNECT (2) #12 AWG + #12 GND TO 120/208V PANEL SERVING THIS AREA.
COORDINATE WITH MECHANICAL FOR EXACT LOCATION ON SENSOR AND
HEIGHT.
9 PROVIDE A NEW CIRCUIT WITH (3) #4 AWG + #8 GND IN 1 1/4" CONDUIT TO
EXISTING PANEL CURRENTLY SERVING PREVIOUS NITROGEN GENERATOR.
PROVIDE A NEW 70A/3P CIRCUIT BREAKER IN EXISTING PANEL. NEW CIRCUIT
BREAKER SHALL MATCH EXISTING TYPE AND AIC RATING. PROVIDE A NEW
100A/3P DISCONNECT, WITH 70 AMP FUSES LOCATED ADJACENT TO
EQUIPMENT.
10 REQUIREMENTS FOR CONTROL SYSTEM. 120V, 10A NON GFCI RECEPTACLE
OUTLET. EXTEND 3/4" CONDUIT AND CONNECT TO 120/208V PANEL SERVING
THIS AREA. COORDINATE WITH MECHANICAL FOR EXACT LOCATION AND
HEIGHT.
11 EXTEND AND RECONNECT TO EXISTING 480V PANEL CIRCUIT FOR THE
AUTOCLAVE. COORDINATE ALL REQUIREMENTS WITH UNIT MANUAL AND
MECHANICAL FOR EXACT LOCATION.
12 PROVIDE POWER FOR CONTROLS. EXTEND (2) #12 AWG + # 12 GND IN 3/4"
CONDUIT AND CONNECT TO EXISTING 120/208V PANEL SERVING THIS
AREA.PROVIDE A NEW 20A/1P BREAKER OR UTILIZE SPARE IF AVAILABLE.
MATCH EXITING AIC RATING.
1/4" = 1'-0"C4 MECHANICAL FLOOR PLAN- AUTOCLAVE
1/4" = 1'-0"C1 DEMOLITION MECHANICAL FLOOR PLAN - AUTOCLAVE
1/4" = 1'-0"A1 DEMOLITION MECHANICAL FLOOR PLAN- NITROGEN GENERATOR
1/4" = 1'-0"A4 MECHANICAL FLOOR PLAN- NITROGEN GENERATOR
NORTHNORTH
NORTH NORTH
05/06/2024
| Sheets |
| G-001 - Cover Sheet & Index |
| G-002 - Accessibility Standards |
| A-101 - Second Floor Plan - Autoclave |
| ME001 - Mechanical & Electrical Abbreviations & Legends |
| ME110 - Overall Mechanical and Electrical Plans |
| ME111 - Mechanical and Electrical Plan |
File details come from the government source that posted it. Updated .