This document is a Project Implementation Plan (PIP) prepared for the Texas Juvenile Justice Department (TJJD) and the Texas Facilities Commission (TFC) by the project management firm Kitchell. The plan outlines the details for the planning, design, construction, and activation of two new juvenile justice facilities in Texas, aiming to add at least 200 state-level beds. The key milestones include site selection in the Houston, San Antonio, and Dallas areas, procurement of the Architect/Engineer of Record and the Construction Manager at Risk, and a project timeline targeting substantial completion in September 2027 and occupancy in February 2028.
The current $200 million budget allocation is deemed insufficient to meet the project's requirements, and TFC and TJJD will collaborate to secure an additional $75 million in supplemental appropriations. The project team includes CBRE for site acquisition, Kleinfelder Engineering for site due diligence, and Broaddus Planning for program requirements. The procurement will include Historically Underutilized Business (HUB) subcontracting plan requirements, and the contract is expected to be awarded by January 16, 2025.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NEW FACILITIES
PROJECT IMPLEMENTATION PLAN (PIP)
PREPARED FOR
Texas Juvenile Justice Department
Texas Facilities Commission
KITCHELL REPORT
October 21, 2024 - Rev 0 updated for AE Solicitation
Phase: Planning & Site Selection
New Facility Project Implementation Plan (PIP)
(Updated for AE Solicitation)
2 | P a g e
Final Rev 0 for AE Solicitation – 10/21/2024
Executive Summary
This document represents the initial (Revision 0) of the Project Implementation Plan
(PIP), which is designed to guide the Planning, Design, Construction, and Activation of two new Juvenile Justice Facilities in Texas, adding at least 200 state-level beds.
The PIP serves as the primary Project Management tool to ensure seamless and efficient execution of every project phase.
This Project Implementation Plan is a dynamic and evolving document designed to keep all stakeholders informed and aligned. By adhering to this plan, we aim to deliver state-of-the-art juvenile justice facilities that meet the highest standards of safety, functionality, and efficiency.
Key Challenge
A critical issue we are encountering is the current budget allocation. As described in more detail in Section III, the allocated $200 million is insufficient to achieve the goal of delivering 200 new beds. Therefore, we recommend seeking an additional funding in the range of $75 million in supplemental appropriations to fulfill the project's requirements.
Key Accomplishments
Site Selection
• Sites in the Houston, San Antonio, and Dallas area are all in different stages of site acquisition including, due diligence, negotiations, and research.
Procurement
• Site Acquisition Representation: CBRE has been contracted by the Texas Juvenile
Justice Department (TJJD) as the Site Acquisition Buyer’s Representative.
• Project Management Services: Kitchell has been contracted by the Texas
Facilities Commission (TFC) to provide comprehensive Project Management
Services.
• Site Due-Diligence: Kleinfelder Engineering has been selected from TFC’s IDIQ to provide site surveys, investigation, phase 1 environmental, and soil evaluation.
• Program of Requirements: Broaddus Planning has been selected to provide an updated specific program, site fit and updated estimate.
• The Pre-solicitation notifications for the project have been posted by TFC to achieve the 60-day minimum requirements.
• Solicitation documents for the Architect/Engineer of Record and the
Construction Manager at Risk are being drafted and reviewed.
(Updated for AE Solicitation)
3 | P a g e
Final Rev 0 for AE Solicitation – 10/21/2024
Next Steps
Site Investigation and Closing
• Property Closing: TFC aims to complete property closings by the end of 2024 / early 2025.
Procurement
• Drafting and Releasing Contracts: Solicitations and contracts will be drafted, reviewed, and released to procure the Architect of Record and the Construction
Manager at Risk.
Budgeting & Programming
• Additional Fund Appropriation: TFC and Kitchell will collaborate with TJJD to secure the additional funds needed to construct at least 200 new state-level beds.
• Facility Programming and Criteria Documents: TFC and Kitchell will prepare comprehensive Facility Programming and Criteria Documents based on TJJD’s needs and requirements. These documents will be utilized to do an updated budget estimate and confirm the construction cost budget for the project.
Additionally, these documents will ensure that the Architect of Record can perform an expedited program confirmation and start design work immediately upon contracting.
Project Management Overview
a) Background – 88th Legislature Appropriation:
Construction of Facilities. Included in the amounts appropriated is $200,000,000 in General Revenue in fiscal year 2024 in Strategy B.3.1, Construct and Renovate
Facilities, for the Texas Juvenile Justice Department (TJJD) to construct a minimum of 200 beds in new state facility capacity. Newly constructed facilities may include services and appropriate physical features to serve youth with acute mental health needs, youth exhibiting highly aggressive or violent behavior, and female youth.
It is the intent of the legislature that these new facilities be located as close as practical to population centers which have existing workforce capacity to hire
Juvenile Correctional Officers (JCOs) and provide necessary mental health, counseling, therapy and other services to rehabilitate youth and to provide appropriate workforce development training for youth as appropriate. The selection of sites for the new facilities shall be contingent on approval from the
Legislative Budget Board. TJJD shall coordinate with the Texas Facilities
Commission for the construction of the facilities.
(Updated for AE Solicitation)
4 | P a g e
Final Rev 0 for AE Solicitation – 10/21/2024
b) Team
i. TJJD – (Client and Facility Operator) Responsible for partnering with counties to promote public safety; provide a continuum of services for justice-involved youth; and produce positive outcomes for youth, families, and communities. The core values guiding board and staff actions are public safety, accountability, and transparency.
ii. TFC – (Close the land, Design and Build the Facilities) The Commission strives to provide the highest quality of service to all its fellow agency clients and consistently works with agencies to help them develop, design and construct new facilities.
iii. CBRE – (Site Acquisition Buyer’s Representative) Experts in real estate transactions throughout Texas.
iv. Kitchell – (Project Management Firm supporting TFC and TJJD) Experts in
Project Management and Juvenile Justice Facility Delivery.
v. Kleinfelder Engineering – (Site Due-Diligence) Experts in site investigation with statewide services in Houston, San Antonio and Dallas.
vi. Broaddus Planning – (Program of Requirements) Expert planners and programmers.
c) Team Goals
i. Collaborative Communication – have the difficult conversations.
ii. Accuracy & Credibility – gain the confidence of all stakeholders.
iii. Sustainable for the Future of TJJD – not just a moment in time.
iv. HUB Firm Participation – endeavor to meet and exceed the State’s HUB goals for the projects.
v. Transparency and Accountability – reporting and process achieving State requirements.
(Updated for AE Solicitation)
5 | P a g e
Final Rev 0 for AE Solicitation – 10/21/2024
Master Schedule
The following pages present the Initial Project Master Schedule based on the best information we have to date. At this stage, the schedule does not differentiate between the two site locations. However, as the development of the schedule progresses, we will establish a baseline and track activities for both sites separately.
Despite this distinction, the overall timeline for the project is expected to remain consistent across both locations.
We will continue to update and communicate the schedule on a monthly basis to ensure we are on track and/or need to make adjustments or course corrections along the way.
d) Current Milestone Summary
- August 2024 – TJJD report to Legislature
- Q4 2024 / Q1 2025 – Close on Properties
- February 2025 – Design Notice to Proceed
- September 2025 – Construction Notice to Proceed (early package)
- September 2027 – Construction Substantial Completion
- February 2028 – TJJD Occupancy and Use
e) Master Schedule
i. Planning & Site Selection Phase – (September 2023- November 2024)
ii. Land Acquisition – (March 2024 – January 2025)
iii. Design & Construction Procurement (June 2024 – March 2025)
iv. Design Phase (February 2025 – December 2025)
v. Construction Phase (September 2025 – September 2027)
vi. Owner Occupancy Phase (October 2027 – February 2028)
ID Task Name % Complete Duration Start Finish
1 TFC TJJD New Facility Master Schedule 14% 1327 days Fri 9/1/23 Mon 10/2/28
2 Major Milestones 0% 1066 days Fri 8/30/24 Mon 10/2/28
3 TJJD Report to Legislature 0% 0 days Fri 8/30/24 Fri 8/30/24
4 Program of Requirements Complete 0% 0 days Mon 12/16/24 Mon 12/16/24
5 Close on New Propert(ies) 0% 0 days Mon 12/23/24 Mon 12/23/24
6 Design Notice to Proceed (NTP) 0% 0 days Thu 2/6/25 Thu 2/6/25
7 Construction Notice to Proceed (NTP) 0% 0 days Thu 9/18/25 Thu 9/18/25
8 Construction Substanial Completion 0% 0 days Thu 9/30/27 Thu 9/30/27
9 Facility Owner (TJJD) Occupany 0% 0 days Thu 2/10/28 Thu 2/10/28
10 Warranty Phase Completion 0% 0 days Mon 10/2/28 Mon 10/2/28
11 TJJD Board Meetings 100% 55 days Fri 5/24/24 Fri 8/9/24
12 TJJD Board Meeting 100% 0 days Fri 5/24/24 Fri 5/24/24
13 TJJD Board Meeting 100% 0 days Fri 8/9/24 Fri 8/9/24
14 TFC Commission Meetings 0% 85 days Thu 6/20/24 Thu 10/17/24
15 TFC Commission Meeting 100% 0 days Thu 6/20/24 Thu 6/20/24
16 TFC Commission Meeting 100% 0 days Thu 8/15/24 Thu 8/15/24
17 TFC Commission Meeting 0% 0 days Thu 10/17/24 Thu 10/17/24
18 Planning & Site Selection Phase 99% 261 days Fri 9/1/23 Fri 8/30/24
19 Feasability Study 100% 133 days Fri 9/1/23 Tue 3/5/24
20 Feasability Study 100% 133 days Fri 9/1/23 Tue 3/5/24
TFC TJJD New Facility Master Schedule
Major Milestones
TJJD Report to Legislature
Program of Requirements Complete
Close on New Propert(ies)
Design Notice to Proceed (NTP)
Construction Notice to Proceed (NTP)
Construction Substanial Completion
Facility Owner (TJJD) Occupany
Warranty Phase Completion
TJJD Board Meetings
TJJD Board Meeting
TJJD Board Meeting
TFC Commission Meetings
TFC Commission Meeting
TFC Commission Meeting
TFC Commission Meeting
Planning & Site Selection Phase
Feasability Study
Feasability Study
Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul
2023 2024 2025 2026 2027 2028 2029
TFC TJJD New Facility
Master Schedule
8.26.2024
21 New Facility Project Implementation Plan (PIP) 97% 73 days Wed 5/22/24 Fri 8/30/24
22 Kick-off and Alignment Meeting 100% 0 days Wed 5/22/24 Wed 5/22/24
23 PIP Check In Meeting #1 100% 0 days Wed 6/5/24 Wed 6/5/24
24 PIP Check In Meeting #2 100% 0 days Fri 6/21/24 Fri 6/21/24
25 TFC/Kitchell Prepare PIP Draft 100% 28 days Wed 5/22/24 Fri 6/28/24
26 TFC/Kitchell Submit Draft PIP to TJJD 100% 0 days Fri 6/28/24 Fri 6/28/24
27 TJJD PIP Review 100% 11 days Fri 6/28/24 Fri 7/12/24
28 TJJD PIP Comments Due 100% 0 days Fri 7/12/24 Fri 7/12/24
29 PIP Updates/Revisions 100% 14 days Mon 7/15/24 Thu 8/1/24
30 Final PIP issue to TJJD 100% 0 days Mon 8/26/24 Mon 8/26/24
31 TJJD Incorporate PIP into Legislative Report 90% 22 days Thu 8/1/24 Fri 8/30/24
32 Land Acquisition 42% 212 days Fri 3/1/24 Mon 12/23/24
33 Setup Real Estate Broker 100% 32 days Fri 3/1/24 Mon 4/15/24
34 Site Selection Kick-off Meeting 100% 0 days Wed 5/1/24 Wed 5/1/24
35 Site Work Group Meeting 100% 1 day Tue 5/28/24 Tue 5/28/24
36 Site Work Group Meeting 100% 1 day Wed 6/19/24 Wed 6/19/24
37 Review Preliminary Slate of Site Market Options 100% 17 days Tue 5/28/24 Wed 6/19/24
38 Site Shortlist Established 100% 5 days Thu 6/20/24 Wed 6/26/24
39 Site Visits 100% 30 days Mon 6/24/24 Fri 8/2/24
40 Letter of Interest (LOI) Process for Potential Sites 100% 24 days Tue 7/23/24 Fri 8/23/24
New Facility Project Implementation Plan (PIP)
Kick-off and Alignment Meeting
PIP Check In Meeting #1
PIP Check In Meeting #2
TFC/Kitchell Prepare PIP Draft
TFC/Kitchell Submit Draft PIP to TJJD
TJJD PIP Review
TJJD PIP Comments Due
PIP Updates/Revisions
Final PIP issue to TJJD
TJJD Incorporate PIP into Legislative Report
Land Acquisition
Setup Real Estate Broker
Site Selection Kick-off Meeting
Site Work Group Meeting
Site Work Group Meeting
Review Preliminary Slate of Site Market Options
Site Shortlist Established
Site Visits
Letter of Interest (LOI) Process for Potential Sites
Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul
2023 2024 2025 2026 2027 2028 2029
TFC TJJD New Facility
Master Schedule
41 Site(s) Contracted 10% 22 days Fri 8/23/24 Mon 9/23/24
42 Contract Option Period 0% 60 days Tue 9/24/24 Mon 12/16/24
43 Close on New Propert(ies) 0% 0 days Mon 12/23/24 Mon 12/23/24
44 Site Due Diligence 4% 55 days Tue 8/20/24 Mon 11/4/24
45 Site 1 (Rosharon) - Survey, Utility, Environmental, Soil 10% 30 days Tue 8/20/24 Mon 9/30/24
46 Site 2 - Survey, Utility, Environmental, Soil 0% 20 days Tue 9/24/24 Mon 10/21/24
47 Appraisal 0% 30 days Tue 9/24/24 Mon 11/4/24
48 Design/Construction Procurement 8% 451 days Thu 6/20/24 Thu 3/12/26
49 Determine Delivery Method (CMAR) 100% 2 days Thu 6/20/24 Fri 6/21/24
50 Prepare Draft RFQ Solicitations 100% 30 days Tue 7/9/24 Mon 8/19/24
51 Architect/Engineer of Record Procurement 0% 90 days Tue 8/20/24 Mon 12/23/24
52 CMAR Contractor Procurement 0% 90 days Tue 10/1/24 Mon 2/3/25
53 Commissioning Agent Procurement 0% 60 days Fri 3/7/25 Thu 5/29/25
54 Construction Material Testing Agency (CMT) Procurement 0% 60 days Fri 3/7/25 Thu 5/29/25
55 FF&E Procurement 0% 60 days Fri 12/19/25 Thu 3/12/26
56 Design Phase 0% 351 days Thu 8/15/24 Thu 12/18/25
57 Program of Requirements 0% 88 days Thu 8/15/24 Mon 12/16/24
58 Program of Requirements Complete 0% 0 days Mon 12/16/24 Mon 12/16/24
59 Program Validation 0% 20 days Fri 2/7/25 Thu 3/6/25
60 Schematic Design 0% 45 days Fri 3/7/25 Thu 5/8/25
Site(s) Contracted
Contract Option Period
Close on New Propert(ies)
Site Due Diligence
Site 1 (Rosharon) - Survey, Utility, Environmental, Soil
Site 2 - Survey, Utility, Environmental, Soil
Appraisal
Design/Construction Procurement
Determine Delivery Method (CMAR)
Prepare Draft RFQ Solicitations
Architect/Engineer of Record Procurement
CMAR Contractor Procurement
Commissioning Agent Procurement
Construction Material Testing Agency (CMT) Procurement
FF&E Procurement
Design Phase
Program of Requirements
Program of Requirements Complete
Program Validation
Schematic Design
Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul
2023 2024 2025 2026 2027 2028 2029
TFC TJJD New Facility
Master Schedule
61 Design Development 0% 60 days Fri 5/9/25 Thu 7/31/25
62 Site/Civil/Equipment Early Release Package 0% 35 days Fri 6/20/25 Thu 8/7/25
63 Construction Documents 0% 100 days Fri 8/1/25 Thu 12/18/25
64 Construction Phase 0% 711 days Fri 3/21/25 Mon 12/13/27
65 Preconstruction 0% 195 days Fri 3/21/25 Thu 12/18/25
66 Early Release Package Procurement 0% 30 days Fri 8/8/25 Thu 9/18/25
67 Site Work Construction 0% 80 days Fri 9/19/25 Thu 1/8/26
68 Foundation/Structure Construction 0% 160 days Fri 1/9/26 Thu 8/20/26
69 Envelope Construction 0% 160 days Fri 6/26/26 Thu 2/4/27
70 Interior Construction 0% 180 days Fri 12/11/26 Thu 8/19/27
71 Building Security Testing & Startup 0% 30 days Fri 8/20/27 Thu 9/30/27
72 Building Final Commissioning 0% 30 days Fri 8/20/27 Thu 9/30/27
73 Substantial Completion 0% 0 days Thu 9/30/27 Thu 9/30/27
74 Final Completion 0% 0 days Mon 12/13/27 Mon 12/13/27
75 Owner Occupancy Phase 0% 95 days Fri 10/1/27 Thu 2/10/28
76 FF&E Deliveries & Install 0% 35 days Fri 10/1/27 Thu 11/18/27
77 TJJD Move In & Training 0% 60 days Fri 11/19/27 Thu 2/10/28
78 Resident Move In 0% 0 days Thu 2/10/28 Thu 2/10/28
79 Warranty Phase 0% 262 days Fri 10/1/27 Mon 10/2/28
80 Warranty Phase 0% 262 days Fri 10/1/27 Mon 10/2/28
Design Development
Site/Civil/Equipment Early Release Package
Construction Documents
Construction Phase
Preconstruction
Early Release Package Procurement
Site Work Construction
Foundation/Structure Construction
Envelope Construction
Interior Construction
Building Security Testing & Startup
Building Final Commissioning
Substantial Completion
Final Completion
Owner Occupancy Phase
FF&E Deliveries & Install
TJJD Move In & Training
Resident Move In
Warranty Phase
Warranty Phase
Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul
2023 2024 2025 2026 2027 2028 2029
TFC TJJD New Facility
Master Schedule
| Exhibit F - PIP for AE |
| TFC TJJD Kitchell Master Project Schedule 8.26.24 |