Enclosure F. AMS-Form-001.docx
DOCX document 30 KB Posted
- Attached to
- Trane CH-3 Centrifugal Chiller
- Solicitation number
- JF481976
- Issued by
-
Department of Energy Office of Science
About this file
This is a Subcontracting Plan Waiver form (AMS-Form-001, Revision 6) from Brookhaven National Laboratory's Procurement and Property Management Division. The form documents an exemption from the Small Business Subcontracting Plan requirement under Public Law 95-507 for a federal contract. The waiver applies to negotiated contracts exceeding $750,000 (or construction contracts exceeding $1,500,000) and any single action modifications, tasks, or change orders meeting those thresholds.
The form indicates that the contractor has certified exemption from the subcontracting plan requirement, with two primary exemption categories available: performance of work entirely outside the United States and its territories, or certification that no subcontracting will be conducted under the contract. The document requires contractor certification, validation by the buyer or contract specialist, and approval by the Small Business Liaison Administrator. As a template form, it does not contain specific details regarding the products or services required for any particular procurement but serves as the administrative mechanism for documenting subcontracting plan waivers at Brookhaven National Laboratory. The form was approved on November 14, 2023.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROCUREMENT AND PROPERTY MANAGEMENT DIVISION
BROOKHAVEN NATIONAL LABORATORY
Managed by Brookhaven Science Associates, LLC under contract to the U.S. Department of Energy
ACQUISITION MANAGEMENT SYSTEM FORM
Form No. AMS-Form-001
Revision No. 6
APPROVED BY:
Paul Pierson 11/14/2023
PPM Manager/Date
Subcontracting Plan Waiver
Public Law 95-507 requires that all negotiated contracts in excess of $750,000 or contracts for the construction of a public facility in excess of $1,500,000, and any single action Modification, Task, or Change Order over those thresholds, have an approved Small Business Subcontracting Plan. The work covered by this Subcontracting Plan Waiver for proposed Contract No. is with in the total amount of $ AND/OR Modification, Task, or Change Order No. in the increased amount of $ . The scope of work covers .
The proposed Contractor has certified that they are exempt from submission of the Small Business Subcontracting Plan for the following reasons:
(|_|) The contract including all subcontracts there under will be performed entirely outside of the United States, its possessions or territories, the District of Columbia, and the Commonwealth of Puerto Rico.
(|_|) The Contractor has certified that subcontracting will not be conducted under this contract. Contractors’ reasons for no subcontracting opportunities required:
I hereby certify that the above statement is true, to the best of my knowledge.
Certification:
Contractor
Date:
DETERMINATION
On the basis of the above findings and pursuant to P.L. 95-507, I hereby determine that the Small Business Subcontracting Plan is not applicable to this procurement.
Validated:
Buyer / Contract Specialist / Manager
Date:
Approved:
Small Business Liaison Administrator
Date:
Date Printed 8/28/2026 1 of 1 Date Approve 11/14/2023