The document is the NFPA 409-26 Aircraft Hangars 2016 Edition Chapter 11, detailing inspection, testing, and maintenance requirements for fire protection systems in aircraft hangars. The comprehensive document provides a detailed matrix (Table 11.1.1) outlining specific inspection and testing frequencies for various fire protection system components, including sprinkler heads, piping, valves, pumps, detectors, and other critical equipment. Inspection frequencies range from weekly visual checks to comprehensive operational tests with actual discharge performed every 5 years.

The related federal contract opportunity is a U.S. Coast Guard solicitation (70Z03325Q201900001) for an Annual Fire Protection System Inspection at Air Station Port Angeles, Washington. The small business set-aside contract is for a firm fixed-price purchase order to inspect fire protection systems across multiple buildings, including an aircraft hangar, in compliance with NFPA standards. Key details include: quote submission deadline of 06/11/25 at 3pm PST, award will be based on lowest-priced technically acceptable (LPTA) criteria, quotes must be submitted on SF 1449 with cost breakdown, and contractors must be registered in the System Award Management (SAM).

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NFPA 409-26 AIRCRAFT HANGARS

2016 Edition Chapter 11 Inspection, Testing, and Maintenance

11.1 Fire Protection Systems.

11.1.1 Inspection, testing, and maintenance of fire protection systems in aircraft hangars shall be performed in accordance with NFPA 11, NFPA 25, NFPA 70, NFPA 72, or NFPA 80 as applicable and as supplemented by Table 11.1.1.

11.1.2 The 5-year discharge test for piping required in Table 11.1.1 shall not be required if an internal inspection in accordance with NFPA 25 indicates that the pipe is in good condition and free of obstructions, mechanical damage, leakage, and corrosion.

11.1.3 Records of inspections, tests, and test results shall be maintained.

Table 11.1.1 Inspection and Testing of Hangar Fire Protection Systems

Type and Frequency of Inspections and Tests

System ComponentsWeekly Monthly Quarterly Semi- Annually Every5
AnnuallyYears
Sprinkler heads————V—
Piping————VD
Pipe hangers————V —
Sprinkler alarm valve—VO1———
Deluge valve—V——OD
Pre-action system—V——D—
Dry pipe systems—V——D—
Shutoff valves—V——F—
Fire pumpsF2———D—
Water reservoirs—V————
Hose stations—V———D
Strainer filter baskets————V—
Foam concentrate————F—
Concentrate storage tanks—V————
Concentrate pumpsF2———OD
Concentrate control valve (automatic) —V——OD
Concentrate shutoff valve—V——F—
Foam proportioning device—V———D
Water-powered monitor nozzle—V——D—
Electric-powered monitor nozzle—V——FD

Water-powered high-expansion-foam (HEF) Generator — V — — D D Electric-powered high-expansion-foam (HEF)

Generator—V——FD
Pneumatic detector———FO3—
Electric detector———FO3—
Optical detectorV——FO3—
Control panels—V—FO—
Alarm transmission (local and remote) —F————
Tamper switch (supervisory switch valve) ——F———
Flow indication switch————O—
Low air pressure supervisory switch ———FO—
Supervisory alarms———F——
Manual actuation stations———F——
Hangar floor drain system and separators —V———D
Fire doors—V——F—
Gas detectors—V—F——
Ventilation system in pits, tunnels, and ducts ———F——
Grounding equipment—————F

V: Visual inspection. D: Operational test with actual discharge. O: Operational test with flow, no discharge. F: Functional test, no flow.

1For the purposes of this test, the inspector’s flow valve is acceptable.

2Churn test.

3At this time it is necessary to check that the set points are the same as the original.

Table 11.1.1 Inspection and Testing of Hangar Fire Protection Systems

Type and Frequency of Inspections and Tests

System Components Every 5 Years

PipingD: Operational test with actual discharge.
Deluge valveD: Operational test with actual discharge.
Hose stationsD: Operational test with actual discharge.
Concentrate pumpsD: Operational test with actual discharge.
Concentrate control valve (automatic)D: Operational test with actual discharge.
Foam proportioning deviceD: Operational test with actual discharge.
Electric-powered monitor nozzleD: Operational test with actual discharge.

Water-powered high-expansion-foam (HEF) Generator D: Operational test with actual discharge.

Electric-powered high-expansion-foam (HEF)

GeneratorD: Operational test with actual discharge.
Hangar floor drain system and separatorsD: Operational test with actual discharge.
Grounding equipmentF: Functional test, no flow.

V: Visual inspection. D: Operational test with actual discharge. O: Operational test with flow, no discharge. F: Functional test, no flow.

1For the purposes of this test, the inspector’s flow valve is acceptable.

2Churn test.

3At this time it is necessary to check that the set points are the same as the original.