EMG Alteration (60 Days) (3) (1).pdf
PDF 109 KB Posted
- Attached to
- Emergency Commercial Demolition: 7601 Rosa Parks
- Solicitation number
- 300000148830391
- Issued by
- Michigan
About this file
This is an Emergency Commercial Alteration project timeline document outlining the critical milestones and procedural phases required for the completion of emergency commercial alterations. The project establishes a structured timeline beginning from the Notice to Proceed (NTP), with specific approval and completion gates established at key intervals. The alteration work commences immediately upon NTP, with an open hole approval required by day 40 of the project timeline. A Certificate of Approval must be obtained by day 50, followed by site finalization activities by day 60. The final pre-invoice approval is scheduled for day 120 from the NTP, indicating a total project duration of approximately four months from initiation to financial closure.
The document provides a sequential process control mechanism for emergency commercial alterations, establishing clear decision points and approval requirements throughout the project lifecycle. The timeline emphasizes expedited processing, with major milestones compressed into the first two months of the project period, followed by extended time for final administrative and financial completion activities. No specific pricing, funding sources, or contract values are detailed in this timeline document, which functions as a procedural roadmap rather than a comprehensive contract specification.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 186769_SUPPLIER.pdf | ||
| 7601 Rosa Parks Blvd EMG letter signed, Parcel, Photos.pdf | ||
| Attachment Fencing Plan- Emergency Commercial_2.22.2024 (3) (1).pdf | ||
| Price Sheet_EMG Demo (Commercial) _7601 Rosa Parks.xlsx | XLSX spreadsheet | |
| RFP Note to Include_EMG Demo_7601 Rosa Parks.docx | DOCX document | |
| Emergency RFQ Notice - 5.24.22 template.dotx | DOTX file | |
| EMG Professional Rate Schedule Demo 02192021.xlsx | XLSX spreadsheet | |
| EMG Professional Rate Schedule Instructions 02192021.docx | DOCX document | |
| OCP, Demolition_Signature_Page 2 25 2020.doc | DOC document | |
| Scope of Services_EMG Demo (Commercial) 8.4.23 (20) (1).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Emergency Commercial
Alteration Timeline
Begin Alteration
Open Hole Approved
Certificate of Approval
Site Finalization
Pre-Invoice Approved
Number of Calendar Days from
NTP
3 40 50 60 120