Glosten Assoc. Specs for Anchor Handling Mods.pdf

PDF 31 KB Posted

Attached to
Drydock and Repairs to NOAA Ship HENRY B. BIGELOW
Solicitation number
EA133M-10-RP-0153
Issued by

About this file

Glosten Associates Specs for Anchor Handling Mods

View the file

Other files

File Type Posted
Amendment 0002 for NOAA Ship Henry B. Bigelow.pdf PDF
HB-100 FH67 Typical Structural Details Model —
Standard Spec AMC-573-1C.pdf PDF
(070)Pumpsmanual-1.pdf PDF
HB-110 FH10 Side Sampling Control Booth.pdf PDF
Amendment 0001 for NOAA Ship Henry B. Bigelow.pdf PDF
HB FY11 Dry Dock Spec - 9-7-10.pdf PDF
SKF Instruction No 81489 SKF OKV Coupling.pdf PDF
ADCP Ocean Surveyor - Shipboard Installlation Guide.pdf PDF
HB-633 FRV40-225-011-010 Cathodic Protection System Marim.pdf PDF
HB-244 01 FRV40-226-006-010 Stern Tube Bearing and Shaft Sea.pdf PDF
Naval Ships Tech Manual Chapter 081 Waterborne Underwater Hull Cleaning.pdf PDF
HB-233 01 FRV40-225-028-010 Diesel Engine Caterpillar 3508B .pdf PDF
HB-562 01 FRV40-224-071-010 High Performance Flap Rudder Wil.pdf PDF
HB-568 FRV40-225-008-010 Bow Thruster Model 40 T3S —
HB-581 01 FRV40-225-004-010 Anchor Windlass —
Tech Manual DT800 Temperature Transducer.pdf PDF
HB-244 01 FRV40-225-005-010 Bearings Line Shaft and Thrust.pdf PDF
HB-591-01 FRV40-225-047-010 Trawling Scientific Winch System Part 1.pdf PDF
NAVSEA Standard Item 009-32 —
HB-243 01 FRV40-225-099-010 Marine Shaft Braking System.pdf PDF
HB-591-02 FRV40-225-048-010 Trawling and Scientific Winch System Part 2.pdf PDF
HB-532 01 FRV40-225-121-010 Heat Exchanger Plate —
SKF C 3184 KM Bearing Dismounting.pdf PDF
HB-572 03 FRV40-225-111-010 Telescoping Boom Crane Model EB7.pdf PDF
ADCP FSB-158 Teledyne RD Instruments Field Service Bulletin.pdf PDF
NAVSEA Std Item 009-32 Cleaning and Painting Requirements.pdf PDF
HB-100 01 FRV40-225-012-010 Centerboard Retractable —
HB-512-1020 Assembly Unit 1020 HVAC A D.pdf PDF
OD-541-001.pdf PDF
HB-532 FP13 Jacket Water Aftercooler System Diagram.pdf PDF
SKF Drawing 25616 Ovako Couplings AB.pdf PDF
HB-593 FP11 Oily Waste Waste Oil System Diagram.pdf PDF
HB-085 FM10 Component Removal Routes.pdf PDF
HB-243 FM01Shafting Layout Details.pdf PDF
HB-461 FE89 Mission Scientific Block Wiring Diagram.pdf PDF
HB-256 FP08 Main Seawater Cooling System Diagram.pdf PDF
HB-512 FV02 HVAC Diagram.pdf PDF
HB-541 FP04 Fuel Service Transfer System Diagram.pdf PDF
OD-512-5020 Assembly Unit 5020 HVAC A D.pdf PDF
OD-581-003 Anchor Handling Modifications.pdf PDF
HB-085 FA04 Docking Drawing.pdf PDF
HB-529 FP01 Bilge and Ballast System Diagram.pdf PDF
HB-524 FP23 Aux Seawater Cooling System Diagram.pdf PDF
HB-612 FH88 Handrails Liferails Lifelines Key Plan Details.pdf PDF
FSCS Wire Diagrams.ppt PPT presentation
HB-524 FP21 Egg Sampling System Diagram.pdf PDF
HB-333 FE14 Deicing System Wiring Diagram.pdf PDF
HB-533 FP03 Fresh Potable Water System Diagram.pdf PDF
HB-085 FA02 General Arrangements.pdf PDF
Show 40 more

Latest 50 of 76 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R/V OSCAR DYSON, Anchor Handling Modifications The Glosten Associates, Inc.

Anchor Handling Spec Page 1 File No. 05056, 21 August, 2006 H:\2005\05056_NOAA_OnCall\08_OscarDysonAnchorHandling\spec\Oscar_Dyson_Anchor_Handling_Mods.DOC

R/V OSCAR DYSON

ANCHOR HANDLING MODIFICATIONS

Work Item: 1

Anchor Handling Modifications

1. GENERAL ................................................................................................................................. 1 5

2. REFERENCES

3. STRUCTURAL

4. MECHANICAL

5. PAINTING AND FINISHING

1. GENERAL

The existing anchors are stowed with their flukes against the side shell. As a result, the anchor shifting against the hull in moderate to heavy sea conditions generates a considerable amount of noise. The post delivery addition of a devil’s claw and turnbuckle arrangement used to cinch up on the anchor chain has not been successful in reducing the anchor movement at sea. 15

The modification described in this specification and in Reference 3 is intended to rectify the problem of anchor movement in the stowed position. This is accomplished two ways: by housing the anchors in anchor pockets set in from the shell plating – somewhat protected from the brunt of the seas; and providing a pocket that restrains the rotation of the anchor head/flukes in the stowed position. The modifications also provide for an improved arrangement of chain stoppers and 20 pelican hooks to facilitate anchor handling.

2. REFERENCES

1. R/V Oscar Dyson Drawings:

a. Dwg. No. M279-070-FC01, L ines

b. Dwg. No. M279-100-FH02, Hul l Forebody Scant l ings 25

c. Dwg. No. M279-180-FH43, Sheet 18, Anchor and Windlass FDN

d. Dwg. No. M279-582-FH20, Anchor Storage and Handl ing

e. Dwg. No. D5600187, General Ar rangement 36mm Windlass

f. Dwg. No. M279-631-FF04, Paint Schedule

2. Glosten Drawing 05124-100-1, Rev. -, Anchor Handling Modifications, 6 shts 30

3. American Bureau of Shipping, “Rules for Building and Classing Steel Vessels Under 90 meters (295 feet) in Length” Current edition.

3. REMOVALS AND RELOCATIONS

The contractor is responsible for all required removals and relocations including, but not limited 35 to, the following:

Anchor Handling Spec Page 2 File No. 05056, 21 August, 2006 H:\2005\05056_NOAA_OnCall\08_OscarDysonAnchorHandling\spec\Oscar_Dyson_Anchor_Handling_Mods.DOC

• The existing port and starboard hawse pipes and associated anchor bolsters are to be removed. The resulting holes in the hull shell plate, and main deck are to be inserted with plate of the appropriate thickness.

• The reinforcement ring and chain guide in the deck at the 01 level are to be removed and 40 the resulting hole inserted with plate of the appropriate thickness. The hull and deck stiffening and framing affected by the hawse pipe removals shall be extended and reconnected using effective brackets.

• The hull shell and main deck plate shall be removed in way of the new anchor pocket port and starboard. The new hawse pipe will require a small amount of deck plate to be 45 removed at the 01 Level.

• A transverse strip of main deck plating must be removed in order to install a new deck insert plate at Frame 3. If an interference exists between the new insert plate or new stanchions and the existing manhole in the main deck, the manhole shall be relocated and the main deck plate inserted. 50

• The existing port and starboard rope scuttles in the 01 level near Frame 0 are to be removed. The deck is to be inserted on the starboard side. The port side 01 level deck shall be prepared for the installation of a new larger scuttle.

• Three ships service transformers in way of the new anchor pockets are to be relocated within the Bosun’s stores. The relocated transformers shall be installed on suitable 55 foundations which incorporate the existing vibration isolation mounts. The transformer relocation may require removal of the storage shelving in the bosun’s stores.

• The ship’s existing anchors shall be removed and returned to the Owner as per his instructions.

• Remove all linings/insulation in way of the port and starboard anchor pocket installations 60 and structural reinforcements.

• The rope bin in the forward section of the bosuns locker shall be removed.

4. STRUCTURE

All structural steel shall be mild steel, certified by ABS. ABS material certificates shall be provided to the Owner prior to proceeding with the steel installation. 65

Fabricate and install two new anchor pockets (port/starboard) and hawse pipes in accordance with Reference 2. All materials and welding are to be in accordance with ABS requirements (Reference 3). The top of the hawse pipes is to be comprised of a pipe elbow, cut and fit to match the 01 level as shown in Reference 2. A new round bar is to be installed on the 01 Level in way of the chain path. 70

A new shell doubler plate shall be installed in Accodance with Reference 2.

Anchor Handling Spec Page 3 File No. 05056, 21 August, 2006 H:\2005\05056_NOAA_OnCall\08_OscarDysonAnchorHandling\spec\Oscar_Dyson_Anchor_Handling_Mods.DOC

Fabricate and install two new chain stopper pedestals on the 01 level in accordance with Reference

2. New foundation structure, stanchions, and other structural reinforcement shall be installed underneath the chain stoppers in accordance with Reference 2.

Fabricate and install new pad eyes and supporting below deck structure port and starboard in 75 accordance with Reference 2.

All welds on the exterior surfaces in way of the chain and anchor path shall be ground smooth.

5. ELECTRICAL

Pull back the existing cables associated with the relocated transformers within the bosun’s locker to the bulkhead penetration at Frame 7, starboard. Reroute the existing cable to the relocated 80 transformers. If the existing cables must be replaced or lengthend, new cables shall be installed between the circuit breaker panel and the transformer as a continuous length of cable. Cable splices are not allowed.

Care shall be taken when installing the new structure below the 01 level so that cables in the existing wireway between Frame 2 and Frame 3 are not damaged. 85

6. MECHANICAL

Modifications to the ship’s mechanical systems are not anticipated.

7. OUTFIT

Two new anchors, with round pin anchor shackles, shall be supplied. The anchors shall be 5,000 lb., stockless type with ABS approvals for compliance with the vessel’s ABS equipment number of 90

660. The existing anchor chain will be re-used.

Two new Ulster Chain Stoppers shall be supplied. The chain stoppers are to be ABS approved and suitable for use with 36mm Gr 3 chain. The chain stopper foundation shown in Reference 2 is designed for a chain stopper with a 20”x11” footprint. The chain stopper foundations must be redesigned if a chain stopper of different dimensions is selected. 95

Two new Pelican Hooks with associated turnbuckles and shackles shall be supplied. The Pelican Hooks shall be suitable for use with 36mm Gr 3 chain.

A new quick acting watertight scuttle with a raised coaming shall be supplied and installed in the 01 Level on the port side as indicated in Reference 2.

New structure and existing structure where coatings are disturbed shall be recoated to original 100 specifications (see Reference 1f).

The bins and shelves removed in item 3 shall be modified and reinstalled to maximize storage space. The installation plan shall be approved by the Owner prior to commencing the work.

Anchor Handling Spec Page 4 File No. 05056, 21 August, 2006 H:\2005\05056_NOAA_OnCall\08_OscarDysonAnchorHandling\spec\Oscar_Dyson_Anchor_Handling_Mods.DOC

8. PAINTING AND FINISHING

Painting of new and disturbed, existing structure shall be completed as described in the vessel’s 105 Paint Schedule, Reference 1f.

The Exterior and interior shell plating affected by the modifications and the exterior and interior surfaces of the anchor pocket shall be coated with Ameron Coatings brand paints. The coatings shall be in accordance with Reference 1f and shall be applied in strict accordance with the manufacturer’s instructions. A local representative shall be consulted for verification of coating 110 application.

9. TESTING

The Owner shall witness all testing. The schedule, procedure and parameters of all testing shall be submitted to the Owner for review.

Upon completion of the modifications and installation of the new anchors, a sea trial shall be conducted to demonstrate successful shipping and unshipping of each anchor.

1. GENERAL
2. REFERENCES
3. REMOVALS AND RELOCATIONS
4. STRUCTURE
5. ELECTRICAL
6. MECHANICAL
7. OUTFIT
8. PAINTING AND FINISHING
9. TESTING