Q A_1_12_16.pdf

PDF 121 KB Posted

Attached to
AK NPS DENA 10(41) Repave Denali Park Road MP 3. 4 to 14. 9
Solicitation number
DTFH70-15-B-00015
Issued by

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

# General Technical Question Answer Date

1 x Sheet C.5 refers to Roadway

Aggregate, method 2 (Crushed

Aggregate) as part of the entire (12”, 24”, 36”) subbase fill. Is there to be a delineation where Roadway Aggregate, method 2 is a 6‐8” top layer and the rest is NFS material of some kind?

All subexcavation locations are backfilled with rdwy_agg, method 2 to top of subgrade.

The last lift will vary in thickness due to the supering of the roadway.

12/4/2015

2 x

In the Standard Underdrain System , the backfill is referred to as Granular

Backfill . The specification (703.03a) has no identification other than AASHTO M

80 Size Number 3, 4, 5, 57, 67, or 7.

Assuming the material has to be screened and washed, what is the gradation of the granular backfill?

Refer to the ASSHTO M 80 specification 12/4/2015

3 x

The bid schedule pay item Temp Traffic

Control, Warning Light Type A has no reference in any of the plan sheets.

Where are these signs to be placed and what are these signs?

Refer to the MUTCD Manual and use as required 12/4/2015

4 x

The contract specifications say to have two lanes open by 8:00am unless otherwise approved by the CO and the plan sheets show possible lane closures using a temporary traffic signals. How often will the traffic signals be able to be used and when?

A Traffic Control Plan must be provided to the Project Engineer before commencing work.

12/4/2015

5 x

Can you please confirm the plan for the underdrain system. From what we see, there are no drain outlets from STA 208+00 to

214+50, only perforated drain pipe running along both LT and RT sides of the project? Are there outlets on either end of the drain system?

See G.2 12/8/2015

6 x

We have a couple of questions regarding the plans for the Denali Park Road Repave job concerning the standard under drain and outlet system referenced on sheet G.2.

1. The standard under drain with outlet pipe detail shows the standard under drain on project right, Note: 1 references 453+20 to

459+00 Project Left. Please clarify

Per stations given the underdrain system is either on the RT or the LT. It is not necessary to show every situation with a generic detail, the STANDARD

UNDERDRAIN WITH OUTLET PIPE is a typical for either side. Sheet C.5 shows an example of the underdrain placement either RT or LT.

12/11/2015

Check General or Technical

AK NPS DENA 10(41)

Repave Denali Park Road MP 3.4 to 14.9

Check General or Technical

AK NPS DENA 10(41)

Repave Denali Park Road MP 3.4 to 14.9

7 x

We have a couple of questions regarding the plans for the Denali Park Road Repave job concerning the standard under drain and outlet system referenced on sheet G.2.

2. Subsequently, if we are to install cross drains, this would make an additional length of pipe exceeding 1883LF (According to stationing the math checks for the bid quantity). Please clarify.

See FP‐14 605.08, the measurement of the 1883LF is the linear foot, from Station to Station, of the system and not the individual parts.

12/11/2015

8 x

Spec 107.11 (d) states “do not turn around vehicles, equipment or loads longer than 22 feet inside the park boundaries except at locations designated by the CO.” Can WFLD provide at least one turn around location after MP 7 pit for turning trucks around and calculating haul distances?

See plan sheet A.3, beyond the locations noted there are no additional locations at this time.

12/11/2015

9 x

Is asphalt oil grade PG 52‐40 incidental/subsidiary to bid items 40301‐0000 and 40101‐5600? Or should it have it’s own bid item like the anti strip and the AC oil for the reclaiming/foaming?

Incidental

12/17/2015

10 x

We have a question about the Traffic Control

Supervisor Bid Schedule days versus the project description days. The bid schedule for Schedule

A, B, C has 102, 125, 154 days respectively. The

Project Description has listed for Schedule A, B, and C ‐ 84, 158, 218 days respectively. Please clarify which contains the intended Traffic

Control Supervisor bid quantity.

The Traffic Control Supervisor is required even if the contractor is not working

12/18/2015

11 x

According to the tabulations of quantities included in the plans, It appears that the bid item for antistrip accounts for only the antistrip needed in the asphalt concrete pavement, gyratory mix. Is anti strip required for the asphalt concrete pavement (type 1) in schedule

A? Is antistrip required for the PG 52‐28 needed for the foamed asphalt (full depth reclamation)

Antistrip only for the 401 item. The ACP mix is provided by the Contractor

1/5/16

Check General or Technical

AK NPS DENA 10(41)

Repave Denali Park Road MP 3.4 to 14.9

12 x

What is the required gradation for the Roadway

Aggregate Method 2? Section 302 of the specs calls it a minor crushed aggregate and refers you to Section 703.06. This section only states that it is a crushed 1” minus. Are there any other requirements on any of the other sieves, a max passing the No. 200?

Just 703.06

1/6/16

13 x

Are items in 637 (housing & vehicles) to be available through winter shutdown or can contractor use dates of shutdown (October 1, 2016 – June 1, 2017)?

The contractor may use the same winter shutdown dates for housing and vehicle items. 1/7/16

14 x

Can excess material be left at Mile 5 and Mile 7

Pits after screening or does it need to be removed from the Park per 204.14?

YES. Excess material can be left at MP 5 and 7 after project completion.

1/7/16

15 x

Does excess material at Mile 5 pit need to be removed by July 31?

NPS will move the material to 7 Mile Pit after the wolfs leave, see 107.10 (e) for wolf restrictions 1/7/16

16 x

Can scales be setup at Mile 5 or Mile 7 Pit or at another location within the Park? Yes 1/7/16

17 x

Is it the intent of the Contract to use sub excavation material, after screening, as the roadway aggregate? Spec 703.06 calls for

“crushed material” but has no fracture specification Refer to 703.06 in the SCRs 1/7/16

File details come from the government source that posted it. Updated .