AK NPS DENA 10(41), REPAVE DENALI PARK ROAD, MP 3.4 TO 14.9,
Denali National Park and Preserve, Denali Borough, Alaska
The work consists of subexcavation, reclamation, paving and other small items of work.
Project length: 11.5 Miles
Tentative Fixed Completion Date: Schedule A - Fall 2016, Schedules B and C - Fall 2017.
(Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)
Estimated Price Range: Schedule A $3 million to $5 million Schedule B $5 million to $7 million Schedule C $7 million to $10 million
Location: Denali National Park and Preserve, Alaska
DESCRIPTION OF WORK in US
CUSTOMARY UNITS
FP-14
Sc h Na m e
_A
Sc h
Na m e
B_
Na m e
C_
DIVISION 150 – Project Requirements 152 Construction Survey & Staking (yes/no) Yes Yes Yes 153 Contractor Quality Control and Assurance
(yes/no) Yes Yes Yes 154 Contractor Sampling & Testing (yes/no) Yes Yes Yes 155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes Yes Yes 157 Soil Erosion & Sediment Control (erosion control devices) Silt fence – lnft Stabilized Construction Exit - each
DIVISION 200 – Earthwork 204 Excavation & Embankment – cuyd - 510 510 204 Subexcavation – cuyd 30,500 30,500 30,500 207 Earthwork Geosynthetics Geotextile - sqyd Geogrid – sqyd
44,565 138,700
44,565 137,700
44,565 138,700
DIVISION 300 – Aggregate and Base Courses 302 Minor Crushed Aggregate - ton 61,100 62,700 62,700 303 Ditch Reconditioning – lnft 700 700 700 306 Full Depth Reclamation With Asphalt - 44,600 97,750
DESCRIPTION OF WORK in US
CUSTOMARY UNITS
FP-14
Sc h
Na m e _A
Na m e
B_
Na m e
C_
DIVISION 400 – Asphalt Pavements & Surface Treatments 401 Asphalt Concrete Pavement By Gyratory Mix Design Method - ton - 7,900 16,000 403 Asphalt Concrete (Type 1) – ton 4,010 4,010 4,010 412 Asphalt Tack Coat (asphalt surface treatment) – ton - 25 48
DIVISION 600 – Incidental Construction 605 Underdrains – lnft 1,900 1,900 1,900 622 Rental Equipment (yes) Yes Yes Yes 623 General Labor (yes) Yes Yes Yes 633 Permanent Traffic Control (traffic control devices) Remove & reset signs – each 6 11 11 634 Permanent Pavement Markings (traffic pavement markings) Pavement markings – lnft 23,000 61,800 80,800 635 Temporary Traffic Control – Flagger fxhr 2,700 3,175 3,650 635 Temporary Traffic Control – Traffic Control supervisor – day Traffic signal system – Each Temporary pavement markings - lnft
63,360
63,360
63,360 636 Traffic Signal, Traffic Counter, Lighting, & Electrical Systems Traffic detector system – each 1 1 1 637 Facilities & Services Residential housing Vehicles
| DIVISION 200 – Earthwork |
| 412 Asphalt Tack Coat (asphalt surface treatment) – ton |