AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
N/A
PAGE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)
A003 July 29, 2010 N/A ID PFH 60(5)
SALMON RIVER ROAD
CONNECTION/EXTENSION
6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A
Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.
X DTFH70-10-B-00015
9B. DATED (SEE ITEM 11)
June 28, 2010
10A. MODIFICATION OF CONTRACT/ORDER NO.
N/A
10B. DATED (SEE ITEM 13)
CODE: N/A FACILITY CODE: N/A
N/A
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
(___) is extended, ( X ) is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
N/A
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN
ITEM 10A.
N/A
B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
N/A
C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
N/A
D OTHER (Specify type of modification and authority) N/A
E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
ID PFH 60(5), SALMON RIVER ROAD CONNECTION/EXTENSION
REVISIONS ARE AS FOLLOWS:
SPECIAL CONTRACT REQUIREMENTS
Page E-59. Section 157.11 Temporary Turf Establishment - Deletes subsection
ENCLOSURE:
Page: E-59
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
N/A
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITION NOT USABLE
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
E-59
Special Contract Requirements Project: ID PFH 60(5), Salmon River Road Connection/Extension
(p) Construct stabilized construction entrances where dirt or mud can be tracked from unpaved construction areas onto paved public roads.
157.09 Diversions. Add the following:
Construct stream diversions which maintain stream flow at all times.
Maintain passage for adult and juvenile forms of all salmonid species throughout the construction period.
When stream diversions require a pump system, provide adequately sized pumps and lines to accommodate flows during the diversion. Pumping under Section 157 is not paid for under Section 622. Maintain pumps and lines throughout the period of the diversion.
When machine placed sandbags are used to isolate a work area adjacent to or along the edge of the river, use additional hand placed sandbags and plastic sheeting to prevent sediment from entering the stream.
Provide the CO with 3 copies of the proposed diversion plans for all live streams and sediment containment plans for all in-water work along the river 14 days before beginning work for acceptance or rejection by the CO. If rejected, submit a revised plan within 7 days. Include proposed materials and methods of stream diversion, sediment containment, or both for each site.
Include manufacturers literature for all products used.
157.12 Inspection and Reporting. Delete the text of the first paragraph and substitute the following:
Inspect all erosion control facilities and BMPs at least once every 7 calendar days OR at least once every 14 calendar days and within 24 hours of the end of a storm event of 13 millimeters or greater. Record inspections as directed in Subsection 157.04(l).
During winter shutdown, perform BMP inspections once every month if the entire site is temporarily stabilized or runoff is unlikely due to winter conditions.
Perform immediately necessary repairs, replacements, additions or adjustments to the erosion control measures.
Revised by Amendment A003