Amendment A005 - changes in SCR's

View the file

Other files

File Type Posted
A004_Rainier.pdf PDF
WA 2009-1 NPS MORA Rt 013 —
P1300051.jpg JPG image
WA 2009-1 NPS MORA Rt 013 —
P1300055.jpg JPG image
WA 2009-1 NPS MORA Rt 013 —
P1300059.jpg JPG image
Amendment A003 —
Amendment A002 —
Plans Req form _Rainier_.pdf PDF
A001_Rainier.pdf PDF
Mt Rainier ERFO Complete Plans.pdf PDF
RFP_Rainier.pdf PDF
FBO Synopsis —
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

N/A

PAGE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)

A005 05/18/09 N/A WA NPS ERFO 2009(1)-42(2)

Mount Rainier Emergency Repairs

6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A

Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.

X

DTFH70-09-R-00019

9B. DATED (SEE ITEM 11)

April 10, 2009

10A. MODIFICATION OF CONTRACT/ORDER NO.

N/A

10B. DATED (SEE ITEM 13)

CODE: N/A FACILITY CODE: N/A N/A

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers (__ ) is extended, ( X ) is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

N/A

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN

ITEM 10A.

N/A

B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

N/A

C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

N/A

D OTHER (Specify type of modification and authority) N/A

E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

WA NPS ERFO 2009(1)-42(2), Mount Rainier Emergency Repairs

See Page 2

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

N/A

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITION NOT USABLE

30-105 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

Amendment No. A005, dated 5/18/09 WA NPS ERFO 2009(1)-42(2) Solicitation No. DTFH70-09-R-00019 Mount Rainier Emergency Repairs

REVISIONS ARE AS FOLLOWS:

Offeror’s are reminded that faxed modifications to submitted offers is acceptable as stated on page A-2 of the solicitation:

“Offers may be modified or withdrawn by facsimile, if such notice is received by the time specified for receipt of bids. The Government will not be responsible for any failure attributable to the transmission or receipt of facsimile data. FAX 360.619.7932.”

SPECIAL CONTRACT REQUIREMENTS

Page E-17, Subsection 108.01, Commencement, prosecution, and Completion of Work.

Adds (g), (h), and (i)

ENCLOSURES

Pages:

E-17

E-17

Special Contract Requirements Project: WA NPS ERFO 2009(1)-42(2), Mount Rainier Emergency Repairs

03USC02/13/09

Section 108.— PROSECUTION AND PROGRESS

108.01 Commencement, Prosecution, and Completion of Work. Amend as follows:

Delete the text of the second paragraph and substitute the following:

A preconstruction conference will be held after the task order is awarded and before beginning work.

Provide a work plan according to Section155.

Add the following:

Furnish at least 48 hours advance notice before changing the current work schedule. Work schedule changes that include additional shifts require 14 days notice.

Perform work under this contract according to the following:

(a) Complete work according to 108.04:

(b) Do not perform construction operations from sunset to sunrise as determined by the National Oceanic and Atmospheric Administration (NOAA).

(c) Limit work as provided in Subsection 107.10.

(d) Limit work as provided in Subsection 156.03

(e) Do not perform construction operations on any holiday or between sunset on Friday and sunrise the following Tuesday of Memorial Day weekend.

(f) Limit work as provided in Subsection 201.

(g) No trucks are allowed to haul through the park between the Nisqually-Paradise Road site at MP 12.3 and the Stevens Canyon Site at MP 14.1. Material for the Stevens Canyon Road site must come in from SR 123. Material for the Nisqually-Paradise Road site must come in from SR 706 direction.

(h) For the Nisqually-Paradise Road site, trucks over 30 feet in length must be piloted between the Longmire Museum and 1 mile East of Christine Falls Bridge.

(i) For the Nisqually-Paradise Road site, loaded trucks may be staged at Ricksecker Point just prior to dumping at the project site.

108.01A Labor. (Added Subsection.)

Follow the requirements of FAR Clause 52.222-6 Davis Bacon Act.

Adjacent or virtually adjacent work sites are defined to be work sites within ½ mile of the project.

Application of the Davis-Bacon Act for work sites beyond ½ mile of the project will be determined by the CO.

108.04 Failure to Complete Work on Time. Delete the text and table of this Subsection and substitute the following:

Follow the requirements of FAR Clause 52.211-12 Liquidated Damages — Construction.

Revised by Amendment A005