A001_E24.pdf

PDF 97 KB Posted

Attached to
CO FLAP 102(1) and FTFW 112(2) Brainard Lake Road and Bridge
Solicitation number
DTFH6817B00019
Issued by

About this file

Amendment A001 attachment (page E-24)

View the file

Other files

File Type Posted
Bid_Opening_Summary_10.11.17.pdf PDF
2017-10-02_Q&A.pdf PDF
Pawnee_Campground_Water_System_As-Builts.pdf PDF
Amendment_A004.pdf PDF
Amendment_A003.pdf PDF
2017-09-29_Q&A.pdf PDF
A003_E_Section.pdf PDF
Option_Y_Waterline_Plans_Updated_92917.pdf PDF
2017-09-28_Q&A.pdf PDF
Amendment_A002.pdf PDF
2017-09-22_Q&A.pdf PDF
3D_ALICO102(1).dgn —
XSECO102(1)_Final.dgn —
CO_102(1)_ExistingGround.xml XML file
2017-09-20_Q&A.pdf PDF
2017-09-18_Q&A.pdf PDF
SF_30_Amendment_Form.pdf PDF
Brainard_Lake_Bridge_Replacment_03_1987.pdf PDF
DTFH6817B00019_IFB.pdf PDF
CO_FLAP_102(1)_Brainard_Lake_Road_Pavements_Report_2-25-2015.pdf PDF
Century_Link_Records_for_Brainard_Road.pdf PDF
Brainard_Lake_Bridge_Replacment_03_1987_3.pdf PDF
CO_102(1)_PDF.pdf PDF
CO_102(1)_PDF_XS.pdf PDF
Brainard_Lake_Bridge_Replacment_03_1987_4.pdf PDF
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

E-24

CO FLAP 102(1)

Brainard Lake Road Amendment A001

From October 20th to February 28th, at the CO’s sole discretion, the CO may allow the road to be closed to the public traffic when major work activities are occurring during the following times:

Monday 8:00 a.m. to 4:00 p.m.

Tuesday 8:00 a.m. to 4:00 p.m.

Wednesday 8:00 a.m. to 4:00 p.m.

Thursday 8:00 a.m. to 4:00 p.m.

Friday 8:00 a.m. to Noon

Do not delay public traffic during other times in this date range. Consolidate operations to the greatest extent possible.

From March 1st to June 28th, when work is being performed the road may be closed to the public traffic at all times.

During all other times of year, limit construction-caused delays to public traffic to a maximum of 60 minutes per passage through the project, Monday at 8:00 a.m. to Friday noon. With CO approval, establish set times when the public are allowed passage. One example of this is: “Westbound traffic will be allowed passage on-the-hour. Eastbound traffic will be allowed passage 15-minutes-past-the-hour.” After June 28th, do not delay traffic from Friday noon to Monday at 8:00 a.m.

For all areas (Schedule A and Option X):

Allow residents living within the project limits, USFS staff, USFS Concessionaire staff, Town of Ward staff, and Boulder County Staff to pass through the project with a maximum delay of 20 minutes at all times, regardless if the road is closed to public traffic. Allow emergency response vehicles to pass through the project at all times.

Notify the CO of all closures or construction-caused delays to public traffic 14 days in advance of intended use. Notify the CO prior to suspending work. Designate a Public Information Officer (PIO). The PIO is to prepare a stakeholder list and inform the stakeholders of public traffic delays and closures before and during project work.

Add the following:

(k) Limit the length of area affected as approved by the CO. See Subsection 108.01 for limitations on work.

Section 157. — SOIL EROSION AND SEDIMENT CONTROL

157.04 General. Add the following:

Do not designate the project superintendent as the Erosion Control Supervisor.