ETHYLENE-PROPYLENE-DIENE-MONOMER (EPDM) ROOFING 07 53 23 -1
FEDERAL AVIATION ADMINISTRATION
DENVER ATCT (DEN) ROOF REPLACEMENT PROJECT
SECTION 07 53 23 - ETHYLENE-PROPYLENE-DIENE-MONOMER (EPDM)
ROOFING PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Adhered EPDM membrane roofing system.
2. Roof insulation.
1.2 DEFINITIONS
A. Roofing Terminology: See ASTM D 1079 and glossary of NRCA's "The NRCA Roof-ing and Waterproofing Manual" for definitions of terms related to roofing work in this Section.
1.3 PERFORMANCE REQUIREMENTS
A. General Performance: Installed membrane roofing and base flashings shall withstand specified uplift pressures, thermally induced movement, and exposure to weather with-out failure due to defective manufacture, fabrication, installation, or other defects in construction. Membrane roofing and base flashings shall remain watertight.
B. Material Compatibility: Provide roofing materials that are compatible with one another under conditions of service and application required, as demonstrated by membrane roofing manufacturer based on testing and field experience.
C. Roofing System Design: Provide membrane roofing system that is identical to systems that have been successfully tested by a qualified testing and inspecting agency to resist uplift pressure calculated according to ASCE/SEI 7. Refer also to Structural Drawings.
D. FM Approvals Listing: Provide membrane roofing, base flashings, and component ma-terials that comply with requirements in FM Approvals 4450 and FM Approvals 4470 as part of a membrane roofing system, and that are listed in FM Approvals' "RoofNav" for Class 1 or noncombustible construction, as applicable. Identify materials with FM Approvals' markings.
1. Fire/Windstorm Classification: Class 1A-90.
2. Hail-Resistance Rating: SH
E. Energy Performance: Provide roofing system with 3-year aged solar reflectance not less than
0.55 and emissivity not less than 0.75 when tested according to CRRC-1.
1.4 SUBMITTALS
ETHYLENE-PROPYLENE-DIENE-MONOMER (EPDM) ROOFING 07 53 23 -2
A. Product Data: For each type of product indicated.
B. Shop Drawings : For roofing sys tem. Include plans, elevations, sections, details, and attachments to other work.
1. Base flashings and membrane terminations.
2. Tapered insulation, including slopes.
C. Samples for Verification: For the following products, in manufacturer's standard sizes:
1. Sheet roofing, of color specified, including T-shaped side and end lap seam.
2. Roof insulation.
3. Walkway pads or rolls.
D. Qualification Data: For qualified Installer and manufacturer.
E. Manufacturer Certificate: Signed by roofing manufacturer certifying that membrane roofing system complies with requirements specified in "Performance Requirements" Article.
1. Submit evidence of complying with performance requirements.
F. Field quality-control reports.
G. Maintenance Data: For membrane roofing system to include in maintenance manuals.
H. Warranties: Sample of standard and special warranties.
1.5 QUALITY ASSURANCE
A. Manufacturer Qualifications: A qualified manufacturer that is FM Approvals approved for membrane roofing system identical to that used for this Project.
B. Installer Qualifications: A qualified firm that is approved, authorized, or licensed by membrane roofing system manufacturer to install manufacturer's product and that is eli-gible to receive manufacturer's special warranty.
C. Source Limitations: Obtain components including roof insulation and fasteners for membrane roofing system from same distributor as membrane roofing.
D. Fire-Resistance Ratings: Where indicated, provide fire-resistance-rated roof assemblies identical to those of assemblies tested for fire resistance per ASTM E 119 by a qualified testing agency. Identify products with appropriate markings of applicable testing agen-cy.
E. Preinstallation Roofing Conference: Conduct conference at Project site.
07 53 23 ETHYLENE-PROPYLENE-DIENE-MONOMER (EPDM)
ROOFING
SACRAMENTO (SMF) NEW ATCT AND ADMINISTRATIVE BASE BUILDING
1. Meet with Resident Engineer, testing and inspecting agency representative, roofing Installer, roofing system manufacturer's representative, deck Installer, and installers whose work interfaces with or affects roofing, including install-ers of roof accessories and roof-mounted equipment.
2. Review methods and procedures related to roofing installation, including man-ufacturer's written instructions.
3. Review and finalize construction schedule and verify availability of materials, Installer's personnel, equipment, and facilities needed to make progress and avoid delays.
4. Examine deck substrate conditions and finishes for compliance with require-ments, including flatness and fastening.
5. Review structural loading limitations of roof deck during and after roofing.
6. Review base flashings, special roofing details, roof drainage, roof penetra-tions, equipment curbs, and condition of other construction that will affect roofing system.
7. Review governing regulations and requirements for insurance and certificates if applicable.
8. Review temporary protection requirements for roofing system during and after installation.
9. Review roof observation and repair procedures after roofing installation.
1.6 DELIVERY, STORAGE, AND HANDLING
A. Deliver roofing materials to Project site in original containers with seals unbroken and labeled with manufacturer's name, product brand name and type, date of manu-facture, approval or listing agency markings, and directions for storing and mixing with other components.
B. Store liquid materials in their original undamaged containers in a clean, dry, protect-ed location and within the temperature range required by roofing system manufac-turer. Protect stored liquid material from direct sunlight.
1. Discard and legally dispose of liquid material that cannot be applied within its stated shelf life.
C. Protect roof insulation materials from physical damage and from deterioration by sunlight, moisture, soiling, and other sources. Store in a dry location. Comply with insulation manufacturer's written instructions for handling, storing, and protecting during installation.
D. Handle and store roofing materials and place equipment in a manner to avoid per-manent deflection of deck.
1.7 PROJECT CONDITIONS
A. Weather Limitations: Proceed with installation only when existing and forecasted weather conditions permit roofing system to be installed according to manufacturer's written instructions and warranty requirements.
1.8 WARRANTY
A. Special Warranty: Manufacturer's standard or customized form, without monetary limitation, in which manufacturer agrees to repair or replace components of mem-brane roofing system that fail in materials or workmanship within specified warran-ty period.
1. Special warranty includes membrane roofing, base flashings, roof insulation, fasteners, cover boards, substrate board, roof pavers, and other components of membrane roofing system.
2. Warranty Period: 20 years from date of Substantial Completion.
B. Special Project Warranty: Submit roofing Installer's warranty, on warranty form at end of this Section, signed by Installer, covering Work of this Section, including all components of membrane roofing system such as membrane roofing, base flashing, roof insulation, fasteners, cover boards, substrate boards, vapor retarders, and walk-way products, for the following warranty period:
1. Warranty Period: Two years from date of Substantial Completion.
PART 2 - PRODUCTS
2.1 EPDM MEMBRANE ROOFING
A. EPDM: ASTM D 4637, Type II, scrim or fabric non-reinforced, uniform, flexible
EPDM sheet.
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following :
a. Carlisle SynTec Incorporated.
b. Firestone Building Products.
c. GenFlex Roofing Systems.
d. Johns Manville.
2. Thickness: 60 mils (1.5 mm), nominal.
3. Exposed Face Color: White w/ SRI of 78 min.
2.2 AUXILIARY MEMBRANE ROOFING MATERIALS
A. General: Auxiliary membrane roofing materials recommended by roofing system manufacturer for intended use and compatible with membrane roofing.
1. Liquid-type auxiliary materials shall comply with VOC limits of authorities having jurisdiction.
2. Adhesives and sealants that are not on the exterior side of weather barrier shall comply with the following limits for VOC content when calculated according to 40 CFR 59, Subpart D (EPA Method 24):
a. Plastic Foam Adhesives: 50 g/L.
b. Gypsum Board and Panel Adhesives: 50 g/L.
c. Multipurpose Construction Adhesives: 70 g/L.
d. Fiberglass Adhesives: 80 g/L.
e. Contact Adhesive: 80 g/L.
f. Single-Ply Roof Membrane Sealants: 450 g/L.
g. Nonmembrane Roof Sealants: 300 g/L.
h. Sealant Primers for Nonporous Substrates: 250 g/L.
i. Sealant Primers for Porous Substrates: 775 g/L.
j. Other Adhesives and Sealants: 250 g/L.
B. Sheet Flashing: White, 60-mil- (1.5-mm-) thick EPDM, partially cured or cured, ac-cording to application.
C. Protection Sheet: Epichlorohydrin or neoprene non-reinforced flexible sheet, 55- to 60-mil- (1.4- to 1.5-mm-) thick, recommended by EPDM manufacturer for re-sistance to hydrocarbons, non-aromatic solvents, grease, and oil.
D. Bonding Adhesive: Manufacturer's standard.
E. Seaming Material: Single-component, butyl splicing adhesive and splice cleaner.
F. Lap Sealant: Manufacturer's standard, single-component sealant, colored to match membrane roofing.
G. Water Cutoff Mastic: Manufacturer's standard butyl mastic sealant.
H. Metal Termination Bars: Manufacturer's standard, predrilled stainless-steel or alu-minum bars, approximately 1 by 1/8 inch (25 by 3 mm) thick; with anchors.
I. Metal Battens: Manufacturer's standard, aluminum-zinc-alloy-coated or zinc-coated steel sheet, approximately 1 inch wide by 0.05 inch thick (25 mm wide by 1.3 mm thick), prepunched.
J. Miscellaneous Accessories: Provide pourable sealers, preformed cone and vent sheet flashings, preformed inside and outside corner sheet flashings, EPDM securement strips, T-joint covers, in-seam sealants, termination reglets, cover strips, and other accessories.
K. Liquid coating, specifically formulated for coating EPDM membrane roofing, as fol-lows:
1. Type: Hypalon.
2. Color: White.
2.3 SUBSTRATE BOARDS
A. Substrate Board: ASTM C 1177/C 1177M, glass-mat, water-resistant gypsum sub-strate, 1/4 inch (6 mm) thick.
1. Products: Subject to compliance with requirements, provide the following :
a. Georgia-Pacific Corporation; Dens Deck.
B. Fasteners: Factory-coated steel fasteners and metal or plastic plates complying with corrosion- resistance provisions in FM Approvals 4470, designed for fastening sub-strate panel to roof deck.
2.4 VAPOR RETARDER
A. Polyethylene Film: ASTM D 4397, 6 mils (0.15 mm) thick, minimum, with maxi-mum permeance rating of 0.13 perm (7.5 ng/Pa x s x sq. m).
1. Tape: Pressure-sensitive tape of type recommended by vapor-retarder manu-facturer for sealing joints and penetrations in vapor retarder.
2. Adhesive: Manufacturer's standard lap adhesive, FM Approvals approved for vapor- retarder application.
B. Laminated Sheet: Kraft paper, two layers, laminated with asphalt and edge rein-forced with woven fiberglass yarn with maximum permeance rating of 0.50 perm (29 ng/Pa x s x sq. m) and with manufacturer's standard adhesive.
C. Glass-Fiber Felts: ASTM D 2178, Type IV, asphalt impregnated.
2.5 ROOF INSULATION
A. General: Preformed roof insulation boards manufactured or approved by EPDM membrane roofing manufacturer, of R-30 value or higher, selected from manufactur-er's standard sizes suitable for application, of thicknesses indicated and that produce FM Approvals-approved roof insulation.
B. Polyisocyanurate Board Insulation: ASTM C 1289, Type II, Class 1, Grade 2, felt or glass-fiber mat facer on both major surfaces.
C. Tapered Insulation: Provide factory-tapered insulation boards fabricated to slope of 1/4 inch per 12 inches (1:48) unless otherwise indicated.
D. Provide preformed saddles, crickets, tapered edge strips, and other insulation shapes where indicated for sloping to drain. Fabricate to slopes indicated.
2.6 INSULATION ACCESSORIES
A. General: Furnish roof insulation accessories recommended by insulation manufac-turer for intended use and compatibility with membrane roofing.
B. Fasteners: Factory-coated steel fasteners and metal or plastic plates complying with corrosion- resistance provisions in FM Approvals 4470, designed for fastening roof insulation and cover boards to substrate, and acceptable to roofing system manufac-turer.
C. Full-Spread Applied Insulation Adhesive: Insulation manufacturers recommended spray- applied, low-rise, two-component urethane adhesive formulated to attach roof insulation to substrate or to another insulation layer.
D. Cover Board: ASTM C 1177/C 1177M, glass-mat, water-resistant gypsum sub-strate, 1/4 inch (6 mm) thick.
1. Products: Subject to compliance with requirements, provide the following :
a. Georgia-Pacific Corporation; Dens Deck.
2.7 WALKWAYS
A. Flexible Walkways: Factory-formed, nonporous, heavy-duty, solid-rubber, slip-resisting, surface-textured walkway pads or rolls, approximately 3/16 inch (5 mm) thick, and ac-ceptable to membrane roofing system manufacturer. Walkways shall be near-white color or finished white following installation. Furnish 8 additional walkway pads as spare stock.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present, for compliance with the following requirements and other conditions affecting performance of roof-ing system:
1. Verify that roof openings and penetrations are in place and curbs are set and braced and that roof drain bodies are securely clamped in place.
2. Verify that wood blocking, curbs, and nailers are securely anchored to roof deck at penetrations and terminations and that nailers match thicknesses of in-sulation.
3. Verify that surface plane flatness and fastening of steel roof deck complies with requirements in Section 05 3100, STEEL DECKING.
4. Verify that minimum concrete drying period recommended by roofing system manufacturer has passed.
5. Verify that concrete substrate is visibly dry and free of moisture. Test for ca-pillary moisture by plastic sheet method according to ASTM D 4263.
6. Verify that concrete curing compounds that will impair adhesion of roofing components to roof deck have been removed.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Clean substrate of dust, debris, moisture, and other substances detrimental to roofing installation according to roofing system manufacturer's written instructions. Re-move sharp projections.
B. Prevent materials from entering and clogging roof drains and conductors and from spilling or migrating onto surfaces of other construction. Remove roof-drain plugs when no work is taking place or when rain is forecast.
C. Complete terminations and base flashings and provide temporary seals to prevent water from entering completed sections of roofing system at the end of the workday or when rain is forecast. Remove and discard temporary seals before beginning work on adjoining roofing.
3.3 SUBSTRATE BOARD
A. Install substrate board with long joints in continuous straight lines, perpendicular to roof slopes with end joints staggered between rows. Tightly butt substrate boards together.
3.4 INSULATION INSTALLATION
A. Coordinate installing membrane roofing system components so insulation is not ex-posed to precipitation or left exposed at the end of the workday.
B. Comply with membrane roofing system and insulation manufacturer's written in-structions for installing roof insulation.
C. Install tapered insulation under area of roofing to conform to slopes indicated.
D. Install insulation under area of roofing to achieve required thickness. Where overall insulation thickness is 2.7 inches (68 mm) or greater, install two or more layers with joints of each succeeding layer staggered from joints of previous layer a minimum of 6 inches (150 mm) in each direction.
1. Where installing composite and noncomposite insulation in two or more lay-ers, install noncomposite board insulation for bottom layer and intermediate layers, if applicable, and install composite board insulation for top layer.
E. Trim surface of insulation where necessary at roof drains so completed surface is flush and does not restrict flow of water.
F. Install insulation with long joints of insulation in a continuous straight line with end joints staggered between rows, abutting edges and ends between boards. Fill gaps exceeding 1/4 inch (6 mm) with insulation.
1. Cut and fit insulation within 1/4 inch (6 mm) of nailers, projections, and penetra-tions.
G. Adhered Insulation: Install each layer of insulation and adhere to substrate as follows:
1. Set each layer of insulation in a uniform coverage of full-spread insulation ad-hesive, firmly pressing and maintaining insulation in place.
H. Mechanically Fastened Insulation: Install each layer of insulation and secure to deck using mechanical fasteners specifically designed and sized for fastening specified board-type roof insulation to deck type.
1. Fasten insulation according to requirements in FM Approvals' "RoofNav" for specified Windstorm Resistance Classification.
2. Fasten insulation to resist uplift pressure at corners, perimeter, and field of roof.
I. Install cover boards over insulation with long joints in continuous straight lines with end joints staggered between rows. Offset joints of insulation below a minimum of 6 inches (150 mm) in each direction. Loosely butt cover boards together and fasten to roof deck.
1. Fasten cover boards according to requirements in FM Approvals' "RoofNav" for specified Windstorm Resistance Classification.
2. Fasten cover boards to resist uplift pressure at corners, perimeter, and field of roof.
3.5 ADHERED MEMBRANE ROOFING INSTALLATION
A. Adhere membrane roofing over area to receive roofing according to membrane roof-ing system manufacturer's written instructions. Unroll membrane roofing and allow to relax before installing.
B. Start installation of membrane roofing in presence of membrane roofing system manufacturer's technical personnel.
C. Accurately align membrane roofing and maintain uniform side and end laps of min-imum dimensions required by manufacturer. Stagger end laps.
D. Bonding Adhesive: Apply to substrate and underside of membrane roofing at rate required by manufacturer and allow to partially dry before installing membrane roof-ing. Do not apply to splice area of membrane roofing.
E. In addition to adhering, mechanically fasten membrane roofing securely at termina-tions, penetrations, and perimeters.
F. Apply membrane roofing with side laps shingled with slope of roof deck where possi-ble.
G. Adhesive Seam Installation: Clean both faces of splice areas, apply splicing cement, and firmly roll side and end laps of overlapping membrane roofing according to manufacturer's written instructions to ensure a watertight seam installation. Apply lap sealant and seal exposed edges of membrane roofing terminations.
1. Apply a continuous bead of in-seam sealant before closing splice if required by membrane roofing system manufacturer.
H. Tape Seam Installation: Clean and prime both faces of splice areas, apply splice tape, and firmly roll side and end laps of overlapping membrane roofing according to manufacturer's written instructions to ensure a watertight seam installation. Apply lap sealant and seal exposed edges of membrane roofing terminations.
I. Repair tears, voids, and lapped seams in roofing that does not comply with require-ments.
J. Spread sealant or mastic bed over deck drain flange at roof drains and securely seal membrane roofing in place with clamping ring.
3.6 BASE FLASHING INSTALLATION
A. Install sheet flashings and preformed flashing accessories and adhere to substrates according to membrane roofing system manufacturer's written instructions.
B. Apply bonding adhesive to substrate and underside of sheet flashing at required rate and allow to partially dry. Do not apply to seam area of flashing.
C. Flash penetrations and field-formed inside and outside corners with cured or uncured sheet flashing.
D. Clean splice areas, apply splicing cement, and firmly roll side and end laps of over-lapping sheets to ensure a watertight seam installation. Apply lap sealant and seal exposed edges of sheet flashing terminations.
E. Terminate and seal top of sheet flashings.
3.7 COATING INSTALLATION
A. Apply coatings to membrane roofing and base flashings according to manufacturer's written recommendations, by spray, roller, or other suitable application method.
3.8 WALKWAY INSTALLATION
A. Flexible Walkways: Install walkway products in locations indicated. Adhere walk-way products to substrate with compatible adhesive according to roofing system manufacturer's written instructions.
B. Roof-Paver Walkways: Install walkway roof pavers according to manufacturer's written instructions in locations indicated, to form walkways. Leave 3 inches (75
mm) of space between adjacent roof pavers.
3.9 FIELD QUALITY CONTROL
A. Testing Agency: Engage a qualified independent third party testing agency, hired by the Contractor, to perform inspections.
B. Final Roof Inspection: Arrange for roofing system manufacturer's technical person-nel to inspect roofing installation on completion.
C. Repair or remove and replace components of membrane roofing system where in-spections indicate that they do not comply with specified requirements.
D. Additional inspections, at Contractor's expense, will be performed to determine compliance of replaced or additional work with specified requirements.
3.10 PROTECTING AND CLEANING
A. Protect membrane roofing system from damage and wear during remainder of con-struction period. When remaining construction will not affect or endanger roofing, inspect roofing for deterioration and damage, describing its nature and extent in a written report, with copies to Architect and Owner.
B. Correct deficiencies in or remove membrane roofing system that does not comply with requirements, repair substrates and repair or reinstall membrane roofing system to a condition free of damage and deterioration at time of Substantial Completion and according to warranty requirements.
C. Clean overspray and spillage from adjacent construction using cleaning agents and procedures recommended by manufacturer of affected construction.
END OF SECTION 07 53 23
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .