Attachment 1 _Specifications.pdf

PDF 2 MB Posted

Attached to
Provide and Install Antenna Tower at the Back Up Emergency Communications (BUEC) Site, Bakersville, PA
Solicitation number
DTFAEN-16-R-00130
Issued by

About this file

Attachment 1 _Specifications (pdf)

View the file

Other files

File Type Posted
Amendment 0002.pdf PDF
Pre-Proposal Site Visit.pdf PDF
Attachment 2-Wage Rates.pdf PDF
Amendment 0001.pdf PDF
Amendment 0003.pdf PDF
SIR DTFAEN-16-R-00130.pdf PDF
Attachment 4-Supplemental Offer Info.pdf PDF
Attachment 1a-Drawings.pdf PDF
Attachment 1 _Specifications.pdf PDF
Attachment 3-Business Declaration.pdf PDF
Pre-Proposal Site Visit.pdf PDF
SIR DTFAEN-16-R-00130.pdf PDF
Amendment 0001.pdf PDF
Attachment 3-Business Declaration.pdf PDF
Amendment 0002.pdf PDF
Attachment 1a-Drawings.pdf PDF
Attachment 4-Supplemental Offer Info.pdf PDF
Attachment 2-Wage Rates.pdf PDF
Attachment 1a-Drawings.pdf PDF
Attachment 1 _Specifications.pdf PDF
SIR DTFAEN-16-R-00130.pdf PDF
Attachment 2-Wage Rates.pdf PDF
Attachment 3-Business Declaration.pdf PDF
Amendment 0002.pdf PDF
Attachment 4-Supplemental Offer Info.pdf PDF
Amendment 0001.pdf PDF
Attachment 2-Wage Rates.pdf PDF
Attachment 1a-Drawings.pdf PDF
Amendment 0001.pdf PDF
Attachment 4-Supplemental Offer Info.pdf PDF
Attachment 3-Business Declaration.pdf PDF
Attachment 1 _Specifications.pdf PDF
SIR DTFAEN-16-R-00130.pdf PDF
Attachment 1a-Drawings.pdf PDF
Attachment 4-Supplemental Offer Info.pdf PDF
Attachment 3-Business Declaration.pdf PDF
SIR DTFAEN-16-R-00130.pdf PDF
Attachment 2-Wage Rates.pdf PDF
Attachment 1 _Specifications.pdf PDF
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIFICATIONS

U.S. Department of Transportation

Federal Aviation

Administration

DEPARTMENT OF TRANSPORTATION

FEDERAL AVIATION ADMINISTRATION

NEW ENGLAND REGIONAL OFFICE

12 NEW ENGLAND EXECUTIVE PARK

BURLINGTON, MA 01803

TECHNICAL

SPECIFICATIONS

FOR THE

ANTENNA

TOWER INSTALLATION

at the

Back Up Emergency Communications (BUEC) Site

Bakersville, PA (AR1)

DTFAEN-16-R-00130

Attachment 1

PREPARED BY:

Boston Communications AJW-2E13A

DATE: 2 August 2016

DTFAEN-16-R-00130

Attachment 1

Linda Hennequant Stamp for Specs

TABLE OF CONTENTS

SECTION TITLE

DIVISION 1 - GENERAL REQUIREMENTS

1-1 Summary Of Work

1-2 Site Access, Construction Limits, Use of Facilities And Work Hours

1-3 Coordination, Local Permits, and Testing

1-4 Government Furnished Material

1-5 Planned Contract Progress Schedule

1-6 Preconstruction Conference

1-7 Submittals

1-8 Temporary Facilities

1-9 Materials and Equipment

1-10 Contract Close Out

1-11 Safety and Health

DIVISION 2 - SITE WORK

2-2 General Site Work

2-4 Excavating and Backfilling for Utility Systems and Buildings

DIVISION 3 – CONCRETE

3-1 Concrete Formwork

3-2 Concrete Reinforcement

3-3 Cast-In-Place-Concrete

3-4 Finishing and Curing

DIVISION 13 – SPECIAL CONSTRUCTION

13-1 Antenna Tower

13-2

13-3

Demolition

Fencing

DIVISION 16 – ELECTRICAL

16-1

16-3

Electrical Work

Coax Cable Work

R

APPENDIX – A SOIL BORING

APPENDIX - B TOWER DESIGN

APPENDIX – C TACO ANTENNA SPECS

1-1 SUMMARY OF WORK

1-1.1 General.- These specifications, together with the referenced specifications, and standards specified in the Contract Documents, cover the requirements of the Federal Aviation Administration, hereinafter referred to as the Government or FAA, for certain work associated with providing and installing one

50-ft high, self-supporting steel antenna tower with grated work platform and six antenna swing arm mounts, overhead cable tray with Heliax cables, counterpoise grounding and lightning protection.

Work also includes the demolition of one existing 120ft high, 28ft wide cable-supported (guyed) steel

RCL antenna tower, its associated cable anchors and footings, (tower foundations can remain at grade), etc. Work includes the installation of 150 linear feet of 7-ft high security fencing. All work located at the

Bakersville, PA BUEC.

1-1.2 Scope. – The Contractor shall provide the necessary; labor, materials, supplies, and equipment to provide and install: one 50-ft high, self-supporting steel platform antenna tower with 6 antenna swing arm mounts; overhead cable tray with heliax cables, provide and install (12) - 7/8” Heliax coax cables from the shelter to the new antenna tower; excavate and install concrete foundation for the antenna tower, erect the antenna tower along with all associated items; platform, railings, climbing ladder, cable wavequide ladder, heliax cables, antenna swing arm mounts, grounding and lightning protection, install

Obstruction Lighting, etc.; and perform security fencing upgrade and site work as required.

Remove the existing guy cable-supported steel 120-ft high, 28ft wide "H" style tower and all cable guys and anchors and footings (in whole). Remove all communication cables and antenna from the existing tower and above ground cable tray (approx. 10ft span from shelter to tower) and associated supports, connecting to the shelter building. Remove and dispose of the tower in its entirety, including; antenna, cables, conduit, hardware, etc...

Demolition can only begin on the 120ft tower once the newly installed 50-ft tower has been “cut-over” and is "live" and up and running operationally. This "cut-over" and "burn-in" period will be performed by the

FAA personnel. During this timeframe, the Contractor will incur "down-time", before being allowed to proceed with demolition of old tower. Typical timeframe to complete the cut-over and burn-in is two weeks.

Contractor’s basic work flow will consist of:

Site clearing and tree cutting and stump removal

Soil Borings (two), along with soil data/analysis (see Appendix - A)

Install concrete foundation per tower manufacturer’s design drawings.

Install the specified underground counterpoise grounding system for the tower and connect via exothermic cad-welds to existing shelter counterpoise and fencing.

Supply, assemble and erect tower structure per tower design requirements (Appendix - B).

Install overhead cable tray system extending between the existing shelter to the new antenna tower per the contract drawings.

Provide and install one 36” x 36” junction box with angle ground bar, ground cable, and N(F) bulkhead adapters, on the tower platform.

Provide and install cable entry ports thru shelter wall and install heliax cables per drawings.

Provide and install one 36” x 36” shelter junction box with coax surge protection mounted on ground bar, ground cable, and Polyphaser coax surge protectors within shelter interior wall.

Provide and install twelve (12) 7/8” Heliax Andrews cables (PN: AVA5-50FX) from the surge protectors within the shelter j-box to the N(F) bulkhead connectors on tower platform j-box. All

Heliax cables shall be terminated with N(M) connectors. The cables shall be connected to a surge protector/ N(F) bulkhead connector.

Remove the existing steel antenna guyed tower (120ft high, 28ft wide - "H" style).

Remove cable guy wires and their associated concrete anchor foundations (in whole) .

Remove all associated conduits, cables, hardware, etc. above grade at the existing tower.

Install 7-ft high security fencing around new tower and tie into existing fence.

Grade, level and install new topsoil and grass seeding as needed to restore any and all disturbed areas to original conditions / match surrounding conditions.

NOTE: This project will be done in phases; the 1 st phase will be the erection of the new 50ft tower, once completed and fully cabled, the Contractor will have some "down time" (1 to 2 weeks) while the

FAA personnel "cut-over" all equipment and frequencies to the new tower. Once all radios, antenna and frequencies have been cut-over to the new tower from the existing tower and it is up and running on-line (“live”), then the Contractor can proceed with the demolition of the existing tower. The

Contractor should anticipate some “down” time during this process, which may extend for approximately 5 to 10 working days, dependent on weather and air traffic conditions.

Installation Procedure:

During the installation, all work shall be coordinated with the on-site Contracting Officer’s Representative

(COR). A project schedule with anticipated installation and cutover dates shall be submitted to the on-site

COR.

The Contractor will be fully responsible for the immediate repair and cost of any severed or damaged cables during construction.

The Contractor is advised that the BUEC facility is fully operational and any unscheduled interruptions may cause aircraft accidents and loss of life. The facility shall remain operational throughout the entire contract unless a shutdown is scheduled and approved in advance.

1-1.3 Intent of Specifications. - This specification identifies all labor, materials, supplies and equipment to perform the work required to modernize the facility. All work performed and all materials and equipment used shall be subject to the approval of the Contracting Officer (CO) or designated representative. This shall include, but not be limited to, testing, inspection, scheduling, reporting, and submittals.

1.1.4 Contract Documents/Drawings. - These documents form a part of this specification:

Drawing set - - - AR1-1003172--####

1-1.4.1 Measurements: - All dimensions shall be verified, by the Contractor, using actual on-site field measurements. Any discrepancies between the specifications/drawings and the existing field conditions shall be referred to the COR before any work is performed.

1-1.5 Document sources.

1-1.5.1 Federal specifications.- The Federal specifications, standards, supplements, amendments, and indices are prepared and issued by the General Services Administration of the Federal Government. They may be obtained from the Specifications Activity, Printed Materials Supply Division, Building 197, Naval Weapons Plant, Washington, D. C. 20407, or through several online sources.

1-1.5.2 Applicable documents.- The current issues of the following documents that are in effect on the date of issuance of the request for offer form a part of this specification and are applicable herein.

1. AIA American Institute of Architects

2. AISC American Institute of Steel Construction

3. ANSI American National Standards Institute

4. ACI American Concrete Institute

5. FS Federal Specification

6. OSHA Occupational Safety and Health Administration

7. ASTM American Society for Testing and Materials

8. NFPA National Fire Protection Association

9. FAA Order 6950.19A - Lightning, Grounding & Bonding

1-1.5.3 Project Coordination - The Contractor shall be required to coordinate all construction activities with the FAA System Service Center Office (SSC) personnel through the on-site FAA Contracting Officers

Representative (COR). All work which effects FAA or flight operations shall be coordinated and approved by FAA personnel through the COR at least forty eight (48) hours in advance of the scheduled work. Failure to notify and obtain the necessary approval may result in a rescheduling of the work. No claim for delay will be entertained in such case. If weather conditions or aircraft operations preclude a scheduled shutdown of an existing FAA facility or runway, the Contractor shall reschedule the work. The Contractor will be required to coordinate all power shutdowns of existing facilities with the FAA SSC office through the COR at least forty eight (48) hours in advance.

1-1.5.4 Layout of Work - The Contractor shall lay out his/her work from the established base lines and benchmarks indicated on the drawings and shall be responsible for all measurements in connection therewith. The Contractor shall furnish, at his own expense, all stakes, templates, tools, and materials and labor as may be required in laying out any part of the work. The Contractor will be held responsible for the execution of the work to such lines and grades as may be established or indicated by the COR. It shall be the responsibility of the Contractor to maintain and preserve all stakes and other marks previously established until authorized to remove them. If such marks are destroyed by the Contractor, or through his negligence, before authorized removal, they may be replaced at the Contractor’s expense.

1-2 SITE ACCESS, CONSTRUCTION LIMITS, USE OF FACILITIES AND WORK HOURS

1-2.1 General.- Contractor shall be escorted at all times by FAA personnel. Access into the site is via

Security gates and requires an FAA escort for daily access to the site.

1-2.1.2 Damage to site.- Damage to the FAA site or any abutting properties caused by the Contractor's activities must be repaired by the Contractor. All costs of repairs shall be paid by the Contractor. After notice to proceed and prior to the commencement of construction, the Contractor and the COR shall conduct joint inspections of the existing areas to be affected by the construction. Existing conditions shall be noted by both the Contractor and the COR and will be used as the basis for determination of damages caused by the Contractor's operations.

1-2.1.3 Contractor's use of Premises.- as allowed by the FAA.

1-2.1.3.1 Work Hours. Work shall begin no earlier than 7:00 A.M. each morning Monday through

Friday and shall end at approximately 3:30 P.M. Deviation from this work schedule may be discussed prior to the Notice to Proceed date during the Pre-construction Conference. Additional changes/requests to agreed upon work schedule shall be submitted to the COR for approval. All work beyond normal work hours shall be requested in writing to the CO 24 hours in advance. Approval of the request shall be allowed at the CO's discretion.

During construction, if the Contractor plans to stop work, the Contractor shall notify the COR at least 24 hours prior to that time. The Contractor shall notify the COR 48 hours in advance in order to reschedule any on site activity after stopping work.

1-2.1.3.2 Airport Safety. N/A

1-2.1.3.3 Airport Security & Badging. N/A

1-2.1.3.4 Equipment Operation & Permits. N/A

1-2.1.3.5 Work Limitations. Should increased air traffic activity or adverse weather conditions require discontinuance of work that would interfere with air traffic, the Contractor will be required to stop such work promptly and remove any equipment or materials which may constitute interference.

1-2.1.3.6 Runway Safety Area Construction Limitations. – N/A

1-2.1.3.7 Storage Piles. The location of storage piles shall be coordinated with the COR. Storage piles of any material shall be located so as not to interfere with access to the site.

1-2.1.3.8 Vehicles in Airport Operations Area (AOA). N/A

1-2.1.3.9 Radio Communications. N/A

1-2.1.3.10 Man-Hole Access. N/A

1-2.1.3.11 Existing Utilities. N/A

1.2.1.3.12 Excavation. Hand excavation methods shall be used in locating all existing utilities. Hand excavation shall be required within 10-ft or less of any know underground utility or cables. The Contractor at no additional cost to the Government shall immediately repair any damage caused by the Contractor.

Repairs, if necessary, shall be in accordance with the specifications and conditions.

1-2.1.3.13 Housekeeping - The Contractor and subcontractors shall maintain the job site in a neat and orderly condition. This includes the daily removal of rubbish, waste materials, tools, equipment, and any other debris that the COR deems necessary. Contractor shall assume full responsibility for the protection and safekeeping of products stored on the site.

1-3 COORDINATION, LOCAL PERMITS AND TESTING

1-3.1 General.-

1-3.1.1 Scope.- This section covers the requirements for testing and permits, inspections and approvals and coordination of construction required to complete the work.

1-3.2 Applicable Documents.- (not used).

1-3.3 Requirements.-

1-3.3.1 Project Coordination.- The Contractor shall prepare a detailed schedule of work, and arrange the work so as to prevent conflicts between subcontractors. The Contractor shall be responsible for coordination of the work by different trades, and all of the work of this contract. The Contractor shall resolve all coordination conflicts that arise among subcontractors.

1-3.3.2 Permits.- N/A

1-3.3.3 Building Codes.- Construction shall be performed in compliance with the most current editions of

BOCA, UBC Building Codes, the National Electrical Code and the specifications mentioned in this document. If Contract Documents exceed code requirements, the Contract Documents shall govern.

1-3.3.4 Test and inspections.- During the progress of work make all tests for the installation required by these specifications. If applicable, perform all testing required by State or local authorities having jurisdiction of the work. Tests shall be made before systems are concealed or covered. Tests shall be made in the presence of the COR and other authorities requiring tests. Unless specified otherwise, the

Contractor shall pay all costs, inspection charges, and fees required for testing the work or materials.

1-3.4 Existing Utilities.- During the progress of the work, the Contractor shall provide for all existing utilities and services affected. Maintain existing outlets, switches and lighting, whether or not they are shown on the plans. Continue the existence of all impacted electrical and other services in the building as part of the finished product.

1-4 GOVERNMENT FURNISHED MATERIAL

1-4.4 GFM LIST. There are NO Government Furnished Materials for this project. Contractor shall provide all materials and hardware which are necessary to complete the installation shown on these drawings and as stated within the specifications.

1-4.5 Storage Location.- Not Applicable.

1-5 PLANNED CONTRACT PROGRESS SCHEDULE

1-5.1 SCHEDULE.- The Contractor must, within five (5) days after issuance of NTP, prepare and submit to the CO for approval a schedule showing the order in which you propose to perform the work, and the dates you plan to start and finish the important stages of the work (including acquiring materials, plant, and equipment). (Ref. AMS 3.2.2.3-56)

1-5.2 Schedule Milestones.

Site layout

Soil Borings/analysis

Foundation Design (PE certified within the State of installation)

Foundation excavation & installation

Tower Design drawings (PE Certified within continental US)

Tower delivery

Tower erection

Overhead cable tray installation

Heliax cables & j-box installation

Cut-over to new tower (FAA personnel)

Demo old antenna tower

Install Security Fencing

Site grading and repair

PRECONSTRUCTION CONFERENCE The Contractor shall attend a Pre-Construction conference to be conducted by the FAA. Local procedures related to ingress-egress, use of premises, station security, construction work schedule, temporary facilities, material disposal, and the FAA SSC (Service Support

Center) operations will be discussed. The time and location for the Pre-Construction conference shall be established by the CO after contract award. The Contractor’s superintendent and his /her safety representative shall attend this meeting.

1-7 SUBMITTALS

1-7.1 General.-

1-7.1.1 Submittal requirements.- Provide submittals where required in the individual specification sections and as required below.

1-7.1.2 Prior to the Commencement of Work.- Specific submittal data currently listed and required by the various sections of this specification shall be submitted to the CO for approval.

Construction Schedule

Contractor’s Safety and Health Plan

Fall Protection Safety Plan

Crane Set-up/Operation Plan

Soil boring analysis data and foundation recommendations

Tower fabrication drawings, design, layout (continental US Licensed PE)

Foundation Designs (stamped by State of Pennsylvania Licensed PE)

Junction-boxes / type / make-model / size / etc.

Conduits & Heliax cables, connectors, etc. to be supplied

Ice Bridge product to be provided

Security Fencing

Any and all materials to be provided on this project

All others Per CO’s request

(Final approved "Foundation Design" and "Tower Design" (shop drawings, etc.) shall be provided in Micro-station or CAD in addition to hard copies)

1-7.1.3 Procedure.- Two (2) complete sets of all product data shall be submitted and one set will be marked and returned to the Contractor. Each product sheet submitted for approval, shall have in the lower right hand corner, just above the title block, a 4 inch by 4 inch open space in which the FAA can indicate action taken. All submittals shall be accompanied by transmittal letters identifying the contents of the copy.

Submittals shall be delivered within adequate time for FAA review (10 calendar days minimum) and FAA resubmittal review (10 calendar days minimum) before the work, which the respective submittal represents, is fabricated or delivered to the site. Work requiring approval shall not be initiated prior to approval of submittal. Submittals shall be checked by the Contractor and coordinated with the work of other trades involved before they are submitted for approval. Submittals incompleteness or inadequate description will be justification for disapproval. Submittals shall bear the following information:

a. Specification page and paragraph number.

b. Name of project and facility.

c. Name of Contractor and subcontractor or supplier.

d. Clearly identified contents and location of work.

1-7.1.4.- By submitting product sheets, the Contractor thereby represents that he has determined and verified the following:

a. Space limitations.

b. Coordination with equipment furnished under other specification sections.

c. Catalog numbers and similar data.

d. Compliance with requirements of the work and of the contract documents.

e. Compatibility with existing facility materials and sizes.

1-7.1.5 Shop drawing approval.- The checking, marking, or approval of the shop drawings/submittals/ and/or product data by the FAA shall not be construed as a complete check, but will indicate only that the general method of construction and detailing is satisfactory. Submittal approvals will not relieve the

Contractor from the responsibility for any; errors, omissions, incompleteness, inadequacy, incorrect or deficient product or workmanship that may exist or arise. The Contractor shall be responsible for the dimensions and design of adequate connections, details, structural integrity, and satisfactory service of the item.

1-7.1.5.1 Approved as submitted.- If "approved as submitted" is marked by the FAA, each copy of the shop drawings or product data will be identified as having received such approval by being stamped and dated. No substitution will be permitted without written approval by the CO.

1-7.1.5.2 Approved as noted.- If "approved as noted" is marked by the FAA, the shop drawings or product data is satisfactory contingent upon Contractor acceptance of corrections, notations, or both and, if accepted, does not require resubmittal.

1-7.1.5.3 Not approved.- If "not approved" is checked by the FAA, the shop drawing or submittal data does not meet job requirements and the Contractor must resubmit. If shop drawings or submittal data are disapproved, the Contractor shall resubmit the corrected material, in the same quantity as specified for the original submittal.

1-7.1.6 Samples.- The Government reserves the right to request samples of any products or materials proposed for use on this project. Specific samples currently listed under various sections of this specification will be required.

1-7.1.7 Resubmittal.- Resubmit all items marked “disapproved” or “resubmit” within 10 calendar days of receipt. Resubmit construction schedule each 14 days after the original approval with actual dates filled in and dates for any additional submittal or re-submittals.

1-8 TEMPORARY FACILITIES

1-8.1 General.- The Contractor shall provide and pay for all temporary services and facilities as specified below and as necessary for the proper and expeditious execution of the work. Contractor shall make, or have made all connections to existing services and sources of supply as necessary and/or indicated and pay all charges for it. Contractor shall provide all labor, materials, equipment, and appurtenances necessary for the complete installation, operation, and maintenance of all temporary service systems and facilities. All work under this section shall comply with applicable laws, rules, regulations, codes, ordinances, and orders of all federal, state, and local authorities having jurisdiction for the safety of persons, materials, and property.

Contractor shall remove all such temporary installations and connections when no longer necessary for the project work.

1-8.2 Lighting and Power.- Contractor shall be allowed to use the existing dedicated service electrical power located at the BUEC shelter next to the proposed tower site.

1-8.3 Dumpster.- There are no waste disposal units at the project sites. Contractor shall provide a suitable dumpster for construction waste (or remove all trash and debris from the site on a daily basis). Have container emptied with suitable frequency so that trash does not overflow and blow around site and adjacent property. A cover is required on the dumpster in order for the refuse not to blow out. Contractor shall be responsible for the timely, legal disposal of all construction waste. Contractor shall dispose of all removed equipment that is deemed unusable by the FAA. Determination shall be made by the COR. All construction waste shall be legally disposed of offsite by the Contractor.

1-8.4 Toilet Service.- Contractor shall provide a port-a-potty toilet service for the workers during the full schedule of work at the project site.

1-9 MATERIALS AND EQUIPMENT

1-9.1 General.- Material and equipment incorporated into the work shall conform to applicable specifications and standards and comply with size, make, type, and quality specified, or as specifically approved in writing by the COR. Manufactured and fabricated products shall be designed, fabricated, and assembled in accordance with the best engineering and shop practices. Like parts of duplicate units shall be manufactured to standard sizes and gages, and shall be interchangeable. Two or more items of the same kind shall be identical and manufactured by the same manufacturer. Products shall be suitable for service conditions. Equipment capacities, sizes, and dimensions shown or specified shall be adhered to unless variations are specifically approved in writing. Do not use material or equipment for any purpose other than for which it is designed or specified. Furnish and install products specified, under options and conditions for substitution stated in this section.

1-9.1.2 Transportation and handling.- Products shall be delivered in undamaged condition, in manufacturer's original containers or packing, with identifying labels intact and legible. Shipments shall be inspected to ensure compliance with requirements of contract documents and approved submittals, and that products are properly protected and undamaged immediately on delivery. Provide equipment and personnel to handle products by methods to prevent soiling or damage to products or packing.

1-9.2 Asbestos Containing Materials (ACM).- N/A

1-10 CONTRACT CLOSE OUT

1-10.1 Acceptance of work.- The Contractor shall schedule a final inspection with the COR. The

Contractor shall correct discrepancies noted during the final inspection, clean the premises and notify the COR that the work is ready for acceptance.

1-11 SAFETY AND HEALTH

1-11.1 Applicable Publications - The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

1-11.1.1 Code of Federal Regulations (CFR)

1-11.1.2 - OSHA General Industry Safety and Health Standards (29 CFR 1910), Publication V2206;

OSHA Construction Industry Standards (29 CFR 1926). One source of these regulations is OSHA, which includes a combination of both parts 1910 and 1926 as they relate to construction safety and health. It is for sale by the Superintendent of Documents, U.S. Government Printing Office, Washington DC 20402.

1-11.1.3 - National Emission Standards for Hazardous Air Pollutants (40 CFR, Part 61)

1-11.1.4 - Federal Standard (Fed. Std.)

1-11.1.5 - Material Safety Data Sheets; Provide as required for products used on this project.

1-11.2 Work Covered by this Section - This section is applicable to all work covered by this contract.

1-11.3 Definitions of Hazardous Materials - Refer to hazardous and toxic materials/substances included in Subparts H and Z of 29 CFR 1910; and to others as additionally defined in Fed. Std. 313. Those most commonly encountered include asbestos, polychlorinated biphenyl’s (PCBs), explosives, and radioactive material, but may include others, such as lead paint, etc.

1-11.3.1 Spray Painting - Spray painting will be allowed within the construction area with prior approval from COR.

1-11.3.2 Smoking - No smoking will be allowed within the building. Smoking shall be confined to designated areas outside the building.

1-11.4 Quality Assurance - The designated on-site Contractor Foreman along FAA COR shall work collectively to ensure QA is maintained throughout the project.

1-11.4.1 Safety Discussion during Preconstruction Conference - Representatives of the Contractor shall provide the Contractor’s safety and health programs during the preconstruction conference. All safety and health provisions pertinent to the work shall be discussed with the CO and the COR at this time. The Contractor shall be prepared to discuss, in detail, the measures he/she intends to take in order to control any unsafe or unhealthy conditions associated with the planned work. The Contractor’s superintendent and his /her safety representative shall attend this meeting.

1-11.4.2 Compliance with Regulations - All work, including the handling of hazardous materials shall comply with applicable state and municipal safety and health requirements. Where there is a conflict between applicable regulations, the most stringent shall apply.

1-11.4.3 Contractor Responsibility - The Contractor shall assume full responsibility and liability for compliance with all applicable regulations pertaining to the health and safety of personnel during the execution of the work.

1-11.4.4 Inspections, tests and reports – as required by Contract drawings and specifications; provide to COR.

1-11.4.5 Safety Plan - The Contractor shall submit a plan for maintaining a safe working environment for construction workers employed on this project, and for the rest of the personnel working in the building. As a minimum, the plan shall show scheduled inspections of equipment and job conditions to check for potential hazards. The plan shall contain a statement that current OSHA regulations on safety in the construction industry will be followed. The plan shall list the directions by automobile and the telephone number for the nearest hospital emergency room, and police and fire department numbers. The plan will be used by the COR to insure that the work is accomplished in accordance with accepted safety practices.

1-11.5 Submittals – As required by contract drawings and specifications.

1-11.5.1 Accident Reporting - A copy of each accident report, which the Contractor or subcontractors submit to insurance carriers, shall be forwarded through the COR to the CO as soon as possible after the accident occurs.

1-11.5.2 Permits - If hazardous materials are disposed of off site, submit copies of permits from applicable Federal, State, or municipal authorities.

1-11.5.3 Material Safety Data Sheets - The material safety data sheets shall be provided for posting on the job site on every material the Contractor provides including but not limited to construction adhesives, paint, solvents for cleaning and fuel, if applicable. MSDS sheets shall be as printed by the material manufacturer.

1-11.5.4 OSHA Bulletins.- Post the bulletins on construction health and safety as required by law. Post an emergency notice with telephone numbers for medical, Police, Fire, EPA, and Poison Control Center telephone numbers in the stairwell area. Submit this item prior to commencing any work.

1-11.6 Materials and Equipment - Special facilities, devices, equipment, clothing, and similar items used by the Contractor in the execution of work shall comply with the applicable regulations.

1-11.7 Hazardous Materials - The Contractor shall bring to the attention of the COR any material suspected of being hazardous which he/she encounters during execution of the work. A determination will be made by the COR as to whether the Contractor shall perform tests, and/or if the material is found hazardous and additional protective measures are needed, a contract change may be required, subject to applicable provisions of the contract.

1-11.8 Suspension of Work - When the Contractor or his/her subcontractors are notified by the COR of any unsafe conditions caused by noncompliance with the provisions of the contract, the Contractor shall immediately correct the unsafe or unhealthy condition. If the Contractor fails to correct the problem condition(s) to the satisfaction of the COR promptly, all or any part of the work may be suspended by the

CO, in accordance with AMS Clause No. 3.10.1-8, “Suspension of Work”. When, in the opinion of the

COR, satisfactory corrective action has been taken to correct the unsafe and unhealthy condition, a start order will be provided immediately.

1-11.9 Protection - The Contractor shall take all necessary precautions to prevent injury to the public, building occupants or his/her employees. The Contractor shall take all necessary precautions to prevent public or private property damage or loss.

1-11.9.1 - Work shall not be performed in any area occupied by Federal employees unless adequate steps are taken for the protection of Federal employees.

1-11.9.2 -Whenever practicable, the work area shall be fenced, barricaded, or otherwise blocked off to prevent unauthorized entry into the work area. This includes marking off and barricading the perimeter of excavated areas until backfilled.

1-11.9.3 Alternate precautions - When the nature of the work prevents isolation of the work area, alternate precautions such as the posting of signs, the use of signal persons, the erection of barricades or similar protection around particularly hazardous operations shall be used as appropriate.

END OF SECTION 1

2-2 GENERAL SITE WORK

2-2.1 GENERAL: This section covers the requirements of general site work, consisting of excavation, trenching, backfilling, compacting, soil stabilization, grading, graveling, and clean-up.

2-2.1.1 SCOPE: Excavate for the new tower foundation. Restore and re-grade any disturbed areas; add sufficient loam and seed with approved equipment at the site as directed by the COR.

2-2.2 APPLICABLE DOCUMENTS: The following publications of the issues in effect on the date of this solicitation form a part of this section to the extent referenced.

American Society for Testing and Materials (ASTM):

D 2922-81 Test Methods for Density of Soil and Soil

Aggregate in Place by Nuclear Methods (Shallow Depth)

Federal Specification: FAA-C-1391c (Installation and Splicing of Underground Cables).

Federal Standard: FAA-STD-019e (Lightning, Surge Protection, Grounding & Bonding).

2-2.3 MATERIALS:

2-2.3.1 Site Materials: N/A

2-2.3.2 Fill Materials: All fill material shall be free from organic matter, debris, vegetation and other deleterious substances. It shall be of a quality suitable for the purpose intended and shall compact thoroughly without the presence of excessive voids when watered and compacted. Fill shall be non-expansive in nature.

2-2.4 CONSTRUCTION:

2.2.4.3 Excavation: Any interruption or damage to underground cables or utilities will be repaired immediately to the COR’s satisfaction at the Contractor’s expense. Excavation procedures shall adhere to all OSHA and Safety standards (both Federal and State) with respect to slope, use of trench boxes, excavator set back, etc.

The Contractor shall use extreme caution when excavating within 10ft of known underground utilities or cables. Hand digging/excavation will be required in any areas within proximity of 10-ft or less from these known and identified utilities and cables.

2-2.4.4 Trenching: Excavate trenches with caution, hand dig when within 10ft or less of known utilities. Trench to depths as depicted on drawings and as straight as possible avoiding unnecessary bends and turns. Compact backfill in trenches thoroughly in 8inch lifts max, using vibrating compactor as required or deemed necessary by COR.

2-2.4.4.1 Over Excavation: Where excavation is carried to a depth greater than required, backfilling shall be subject to approval by the COR and shall be compacted as required.

2-2.4.4.2 Wet Excavation: No additional compensation will be allowed for any sheeting, shoring, pumping, or draining required to place and keep excavations in dry condition for construction. No water shall be allowed to remain in or around any part of the work.

2-2.4.4.3 Existing Facilities: Contact local FAA personnel through the COR prior to the start of any excavation. Maintain a record of phone conversations and site meetings that take place. Additionally, prior to any excavation or trenching, utilize a cable detector to verify and locate any utilities and cable runs which may be in the vicinity of site work or crossed by the new cable runs. The existing utilities and cable runs shall be exposed by hand digging in these areas and shall be protected from any possible damage. Any damage caused by the Contractor shall be immediately repaired with materials and methods approved by the COR at no additional cost to the Government.

2-2.4.4.4 Connections to Existing Utilities: N/A

2-2.4.4.5 Trench Backfill and Compaction: in 8inch lifts max, compact thoroughly with vibrating compactor to 95% compaction.

2-2.4.4.6 Plastic Marking Tape: Place in trenches over any installed grounding cables or conduits, 1ft below grade. Provide 3inch wide tape full length of trench, appropriate color and type for item being marked.

2-2.4.5 Aggregate Base: N/A

2-2.4.6 Grading: Grade site areas to the lines and grades indicated on the drawings or as directed. Slope graded areas approximately 2% for drainage away from the structures and site area. Areas within the limit of grading shall be finish graded to fill ruts, holes, etc., and to remove surface rocks or boulders.

2-2.4.8 Pavement Removal: (Not Used)

2-2.4.9 Pavement Replacement: (Not Used)

2-2.4.10 ENVIRONMENTAL CONSIDERATIONS.

2-2.4.10.1 General. - All construction operations shall be conducted in such a manner as to prevent the pollution to air, water or land, and shall, within reasonable limits, control noise and the disposal of solid waste material, as well as other pollutants.

2-2.4.10.2 Protection of water resources. - The Contractor shall control the disposal of fuels, oils, bitumens, calcium chloride, acids or harmful materials, both on and off the premises and shall comply with applicable Federal, State, County and Municipal laws concerning pollution of rivers and streams while performing work under this contract. Special measures shall be taken to prevent chemicals, fuels, oils, greases, bituminous materials, herbicides and insecticides, and surface drainage from entering public waters. Water used in on-site material processing, concrete curing, foundation and concrete cleanup, and other waste waters shall not be allowed to re-enter a stream if an increase in the turbidity of the stream could result.

2-2.4.10.3 Dust control. - The Contractor shall maintain all excavations, embankments, stockpiles, access roads, plant sites, waste areas, borrow areas, and all other work areas free from excess dust to such reasonable degree as to avoid causing a hazard or nuisance to the Using Service or to others. Approved temporary methods consisting of sprinkling, chemical treatment, or similar methods will be permitted to control dust. Dust control shall be performed as the work proceeds and whenever a dust nuisance or hazard occurs.

2-2.4.10.4 Erosion control. - Surface drainage from cuts and fills within the construction limits, whether or not completed, and from borrow and waste disposal areas, shall be graded to control erosion within acceptable limits. Temporary control measures shall be provided and maintained until permanent drainage facilities are completed and operative. The area of bare soil exposed at any one time by construction operations should be held to a minimum.

2-2.4.10.5 Post-construction cleanup. - The Contractor shall cleanup and eliminate any and all signs of temporary construction facilities such as haul roads, work areas, structures, foundations of temporary structures, stockpiles of excess or waste materials, and other vestiges of construction prior to final acceptance of the work. These disturbed areas shall be graded and filled and the areas seeded unless otherwise noted on the drawings.

2-2.5 QUALITY ASSURANCE:

2-2.5.1 When excavations are completed, the Contractor shall notify the COR for his inspection and approval prior to placement of concrete or installation of cables, ducts, conduits, or piping.

END OF SECTION 2-2

2-4 EXCAVATING FOR TOWER

2-4 GENERAL

2-4.1 Scope - Excavate all soil necessary for the tower foundation installation per design. Compact bottom of foundation excavation with mechanical driven compactor thoroughly prior to concrete pour.

Distribute and or remove any left over material about the site as directed by the COR.

2-4.2 Related Work In Other Sections N/A

2-4.3 Applicable Documents - The current issues of the following documents in effect on the date of the invitation for bid form a part of this specification and are applicable to the extent specified herein.

2-4.4 American Society For Testing and Materials

ASTM D698 Standard Test Methods for Moisture Density Relations of Soils and Soil Aggregate

Mixtures Using 5.5 lb Rammer and 12-inch Drop

ASTM D1556 Density of Soil in Place by the Sand-Cone Method

ASTM C33 Standard Specification For Concrete Aggregates

2-4.5 Excavation - Excavation shall be unclassified and include the removal of all materials of every name and nature, including all earth and rock of any type and obstructions of any type, either natural or manmade which may be required for the installation of all work described in the various divisions of these specifications.

2-4.6 Structures - Excavate to the depths and dimensions indicated for footings, foundations, slabs on grade and other structures. In the event unsuitable or unstable soil is encountered below this limit, the

COR will determine the depth of removal of such soil. Cut sides and bottom of foundation excavations clean. In all instances, allow sufficient room for installation and inspection of forms. Foundation excavation bottom shall be compacted by mechanical vibrating compactor thoroughly (95% compaction) prior to concrete placement.

2-4.7 Footings and Foundations - Where soil bearing footings and foundations for the new structures will occur, any fill used shall be of the same proportions as specified for footings and foundations; the quality shall also be the same, all as described in division 3 of this specification.

2-4.8 QUALITY ASSURANCE -

2-4.8.1 General - The Contractor shall establish and maintain quality control for operations under this section to assure compliance with contract requirements and maintain records of his quality control for all materials, equipment and construction operations throughout the project.

END OF SECTION 2-4

3-1/01

3 CONCRETE FORMWORK

3.1 General :

3-1.1 Work included.- Unless they are specified elsewhere, provide forms and related work required for cast-in-place concrete, including the following:

Structural concrete:

1. Tower foundation

3-1.2 Related work in other sections.- N/A

3-1.3 Applicable documents.- The current issues of the following documents in effect on the date of the invitation for bid form a part of this specification and are applicable to the extent specified herein.

3-1.4 American Concrete Institute (ACI) Publications.-

301 Specifications for Structural Concrete for Buildings, Chapters 1, 4,18

318 Building Code Requirements of Reinforced Concrete

347 Recommended Practice for Concrete Formwork Chapters 1, 2

SP2 ACI Manual for Concrete Inspection

SP4 Formwork for Concrete, Chapters 6, 7

3-1.5 American Society for Testing and Materials (ASTM).-

As applicable.

3-1.6 U.S. Department of Commerce, National Bureau of Standards.-

PS1-66 Softwood Plywood - Construction and Industrial

3-2 Materials.-

3-2.1 Form framing.- Southern Yellow Pine or Douglas Fir construction grade or better, dressed or rough.

3-2.2 Form sheathing.- as required, structurally sound and clean, braced sufficiently so as not to allow any bowing. Full forms required, at full depth of foundation, above and below grade. Refer to 3-2.4

3-2.3 Boards.- Southern Yellow Pine or Douglas Fir construction grade or better, S4S 1 x 6 boards. Use center matched boards where forms are unlined and concrete will be visible.

3-2.4 Plywood.- Plywood shall comply with U.S. Product Standard PS1-66 and bear grade trademark of the American Plywood Association. B-B Plyform Class 1 exterior, 5/8 inch thick minimum.

Accessories.- Spreaders, etc., of required type, size and finish.

3-1.3.4 Form coating.- Non-staining chemical compound compatible with the direct applied coating required on concrete. Submit brand for approval.

3-1.3.5 Anchor bolts and plates.- Carbon steel: ASTM A307 Grade B, galvanized or better.

3-1.3.6 Compressible filler.- Cork, ASTM D1752, Type II

3-1.4 Installation:

3-1.4.1 Relation with other trades.- N/A

3-1.4.2 Forms for structural concrete: tower foundation forms shall be fully formed with proper boards, sheathing or structural pre-fabed forms to the full depth of the foundation, length and width of the required foundation design, inclusive of both above and below grade. Fully formed foundation is required.

3-1.4.2.1 Tolerances:

3-1.4.2.1.1 General.- Unless otherwise specified, shown, or required to accommodate abutting or adjacent materials, conform to ACI 301 Table 4.3.1 which shall be considered maximum and shall be reduced as necessary to conform to details and to permit the proper installation of adjacent and abutting materials.

3-1.4.2.1.2 Correction.- Correct work outside of required tolerances as directed without limit to extent of work required.

3-1.4.2.2 Support of forms.- The total responsibility for the proper and adequate design, construction, support and bracing of forms to provide the required concrete sections and to support, without deflection, the wet concrete and other construction loads imposed on them rests entirely with the Contractor. The requirements of this Specification are to be considered as minimum only. Re-brace, tighten, etc., any displaced forms as necessary to bring them back to required line and level.

3-1.4.3 Unlined wood forms.- Contact surface shall be free of any; warpage, cupping and large or loose knots. Break joints and double nail.

3-1.4.4 Slabs.- N/A

3-1.4.5 Ties and spreaders.- Lengths shall be as required to provide proper concrete thickness. When practical, locate and space ties and spreaders symmetrically at approximately 3 foot centers both ways, in plumb tiers and level rows.

3-1.4.6 Expansion joints.- N/A.

3-1.4.7 Construction joint.- N/A

3-1.4.7.1 Vertical joints.- N/A

3-1.4.8 Form coating.- Coat the inside of forms in accordance with coating manufacturer's printed installation instructions if necessary for ease of removal.

3-1.4.9 Checking forms.- As concrete is placed, make frequent checks on forms to detect any change in position. Replace, tighten, etc., any displaced forms as necessary to bring them back to required line and level.

3-1.4.10 Equipment pads.- N/A

3-1.5 Quality assurance.-

3-1.5.1 Construction of forms.- Locate and construct forms accurately so that finished concrete will conform to shapes, lines, grades and dimensions shown on the drawings. Joints shall be vertical unless otherwise specified, and sufficiently tight to prevent leakage.

3-1.5.2 Size of forms.- Size forms so that all reinforcing bars, ties, stirrups, etc., shall have the minimum coverage required in the structural general notes on the drawings (minimum 3 inches of coverage at any point). Thickness of concrete coverage shall be measured from face of vertical or horizontal bars and face of stirrups in beams. Coverage not indicated shall conform to ACI 318.

End of Section 3-1

3-2/01

3-2 CONCRETE REINFORCEMENT

3-2.1 General.-

3-2.1.1 Work included.- Fabricate and install reinforcing and the related accessories required for cast-in-place concrete work not specified elsewhere including the following work:

One - 50 foot high self-supporting steel antenna tower foundation

3-2.1.2 Related work in other sections.- N/A

3-2.2 Applicable documents.- The following specifications and standards of the issues currently in force form a part of this section.

3-2.2.1 Federal Specifications.-

QQ-W-461 Wire, Steel, Carbon (Round, Bare and Coated)

3-2.2.2 American Society for Testing and Materials (ASTM) Publications.-

A185 Welded Steel Wire Fabric for Concrete

A615 Deformed and Plain Billet-Steel Bars for Concrete Reinforcement

3-2.2.3 American Concrete Institute (ACI).-

The following ACI standards shall be adhered to and implemented pertaining to this project: ACI 117, 301, 315, 318 & 318R, and 439.

3-2.2.4 Concrete Reinforcing Steel Institute (CRSI MSP).-

Manual of Standard Practice and Recommended Practice for Placing Reinforcing Bars

3-2.3 Materials.-

3-2.3.1 General.- All of the following materials shall be produced and fabricated in the U.S.A.

3-2.3.2 Reinforcing steel / Deformed and Plain Billet Steel.- Carrying rolled-on identifying marks to denote the mill location, bar size and type of steel. ASTM A615/615M – Billet Steel – Minimum Grade

60K psi yield strength shall be used. (or as called out for within the approved PE stamped foundation design drawings).

3-2.3.2 Welded wire fabric.- ASTM A185 cold drawn steel wire welded fabric (grade 60K psi). See

Structural Drawings for size of wires and mesh size.

3-2.3.3 Dowels.- Conform to Paragraph 3-2.3.2

3-2.3.5 Stirrups and ties.- Conform to Paragraph 3-2.3.2

3-2.3.6 Accessories.- Provide spacers, chairs, wire ties, etc., necessary to properly assemble, space and support the reinforcing in place during placement of concrete, as recommended by the Concrete Reinforcing

Steel Institute. Accessories shall be sized to provide required concrete coverage. Position and support bolts, anchors, and other cast-in items with appropriate accessories. Spacers, chairs, wire ties, etc., fabricated of standard bright basic wire. Chairs placed on porous fill shall have 3 x 3 inch 16 gage steel base pads or plates to prevent them from penetrating the supporting surface.

3-2.3.7 Tie wire.-

3-2.3.7.1 For reinforcing steel.- Federal Specification QQ-W-461, 16 gage minimum annealed black steel.

3-2.4 Installation.-

3-2.4.1 Extent of work.- Provide reinforcing for all concrete unless it is definitely specified or noted to be plain or unreinforced.

3-2.4.2 Marking.- Use standard waterproof tags. All designations shall coordinate with the Structural

Drawings.

3-2.4.3 Tolerance.- The following are maximum allowable tolerances:

3.2.4.3.1 Fabrication.-

Sheared length: Plus or minus 1 inch.

Depth of truss bars: Plus 0 or minus 1/2 inch.

Stirrups, ties: Plus or minus 1/2 inch.

All other bends: Plus or minus 1 inch.

3-2.4.3.2 Placement.-

Concrete cover to form surfaces: Plus or minus 1/4 inch.

Minimum spacing between bars: 1/4 inch.

Top bars in slabs: Minimum 3” cover.

Members 8 inches or less deep: Plus or minus 1/4 inch.

Crosswise of members: Space evenly within 2 inches of stated separation.

Lengthwise of members: Plus or minus 2 inches.

Maximum bar movement to avoid interference with other reinforcing steel, conduit or other embedded work: 1 bar diameter.

3-2.4.4 Fabrication of reinforcing bars.-

3-2.4.4.1 Material.- Use deformed bars…

This is the start of the file's text. The full file is on GovTribe.