DS 27-0004 Q & A Columbus Oil and Gas.docx
DOCX document 31 KB Posted
- Solicitation number
- DS 761 270000000004 2
- Issued by
- Michigan
About this file
This is a Question and Answer document related to a turn-key well plugging project in Cass County, Michigan, administered by the Michigan Department of Environment, Great Lakes, and Energy (EGLE). The project involves the plugging of 22 oil and gas wells of varying depths, with the Hawkes & Adams 1-18 well at approximately 900 feet (previously drilled to 2,998 feet and plugged back with a cast iron bridge plug) and the remaining 21 wells at approximately 700 to 1,000 feet. The scope of work includes well plugging according to EGLE's provided instructions, removal of partial surface piping infrastructure with installation of blind flanges near master gate valves, and removal of associated electrical infrastructure at well pads. Bidders must provide a per-well turn-key price and a grand total for all 22 wells. No project start date or required completion date has been established, though winter work is permitted and seasonal weight restrictions will temporarily halt plugging activities with time excluded from the contractor's timeline. Seeding may be performed in the next planting season following plugging completion.
Bidders should base pricing on compliance with EGLE's plugging instructions and attached procedures, with minor variations in cement quantities and similar changes considered the contractor's responsibility rather than change orders. The State will pay 100 percent of invoiced amounts upon verification of accuracy and completion of pay certifications, contrary to the standard 20 percent holdback referenced in initial questions. Salvage and scrap proceeds belong to the State of Michigan, with the contractor responsible for arranging transportation and loading of purchased items off-site. The project does not require bid, performance, or payment bonds. Davis Bacon wage determinations apply to truck drivers performing labor-type tasks but not to drivers engaged in de minimus activities such as dropping off and picking up items. The wells present very low levels of hydrogen sulfide and do not require a third-party H2S safety trailer, though personal air monitors must be available for rig crew evaluation. All well fluids and materials must be containerized in steel tanks, with earthen pits prohibited. Certified payrolls must be submitted weekly using the WH-347 form via email. Soil disturbance from plugging activities should be addressed through filling, leveling, and seeding with standard grass mix unless the site is an agricultural field, with pricing to reflect removal and disposal of up to 5 cubic yards of soil per well location.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Columbus Oil Pre-Bid Meeting.docx | DOCX document | |
| DS 270000000004 SCHEDULE B - PRICING MATRIX Columbus Oil Project.xlsx | XLSX spreadsheet | |
| Revised DS 270000000004 Columbus Oil and Gas Well Plugging Project.docx | DOCX document | |
| DS 270000000004 Columbus Oil and Gas Well Plugging Project.docx | DOCX document | |
| Columbus Oil Project 36806 FY25 308 Response.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q & A DS No. 270000000004 Columbus Oil and Gas Plugging Project
1. Schedule B asks for one turn-key price per well and a grand total for 22 wells. The wells vary a lot in depth. Hawkes & Adams 1-28 is recorded at about 2,998 ft and the others at about 700 to 1,000 ft. Should we enter one average price per well, or may we attach a separate turn-key price for each well? If a well is removed from or added to the project after award, how will the contract amount be adjusted?
Answer: The Hawkes & Adams 1-18 was originally drilled to 2998’, then subsequently plugged back with a cast iron bridge plug (CIBP) to 900’ and perforated in the Traverse Lime at 728’-778’. Plugging of the well will commence from placing cement on top of the CIBP and proceed according to the well plugging instructions. Wells will not be added.
2. The pricing matrix has a Quantity column that feeds a Grand Total. Should bidders enter estimated quantities, so the matrix total supports the turn-key price, or enter unit prices only and leave quantities blank? Which number is used to compare bids: the turn-key grand total on DS page 50 or the matrix Grand Total?
Answer: Please tabulate a per well price and a grand total of plugging 22 wells and completing the tasks described in the scope of work document.
3. The master contract says salvage is sold through at least three bids, the proceeds go to the State, and the contractor may not bid on it. For this turn-key project, does salvage and scrap value belong to the contractor, so it can be credited in the turn-key price? Or does the master contract salvage process apply? If the State keeps the salvage, is the work to inventory it, take bids and load it out part of the turn-key price?
Answer: If items are to be sold, we attempt to get multiple price offers/bids. In the event we only get one bid, we generally require the bidder to meet the minimum price of what we would get at the scrap yard, if the item was scrapped. Proceeds from all salvage and scrap go to the State of Michigan in the form of a check. It is the responsibility of the bidder to make all necessary arrangements for items purchased to be loaded out and transported off site. This is not the responsibility of the contractor.
4. The contract holds back 20% of each invoice until final State acceptance. On this 22-well project, is final acceptance and release of the 20% done well by well, or only after all 22 wells and all site restoration are complete? Can we invoice a well at the turn-key price once it is plugged, or only after its site is restored? If seeding must wait until spring, is the 20% held until then?
Answer: The State of Michigan will pay 100% of invoiced amounts pending they are accurate, correct, and pay certifications are complete and correct.
5. We did not find a bid bond, performance bond or payment bond requirement in the DS or in Schedule A of the master contract. Please confirm that no bond of any kind is required for this project.
Answer: A bid bond is not required.
6. The project wage determination expires 11/28/2026. Proposals are due 11/17/2026 and the start date is TBD. If the contract is not in place by 11/28/2026 and a new determination is issued, will the new rates apply? If the new rates are higher, will EGLE allow a matching price adjustment?
Answer: A project award will be made before 11/28/2026, thus making the existing wage determinations good for the life of the project.
7. The wage determination has no Truck Driver classification. Which classification should bidders use for drivers of the pole truck, tractor and lowboy, and dump trucks? Will EGLE ask DOL for an added (conformed) classification before award, so all bidders price the same rate?
Answer: Truck drivers that are generally dropping off and picking up items from the site, fall under “de minimus” status, and are not subject to DBPW. In the event truck drivers are performing labor type tasks, they must adhere to Davis Bacon provisions.
8. The attached well records describe these wells as potentially sour. Does EGLE have any measured H2S readings for any of the 22 wells? Is a third-party H2S safety company required on site every day for every well, or is gas monitoring enough unless H2S is found? Should H2S services be in the turn-key price, or billed at the rated items in lines 40 to 42 only if needed?
Answer: These wells are very low level H2S and will not require a 3rd party H2S safety trailer. Personal air monitors of the rig crew can evaluate for the presence of H2S. If H2S exceeds levels above health and safety requirements, then the State will re-evaluate, get H2S safety trailer, and or engineered controls to mitigate the H2S risks. This would be a legitimate change order.
9. Our reading of the records shows a bridge plug at about 900 ft in a well drilled to about 2,998 ft, with a lost-circulation zone in the Traverse Lime. Will the plugging instructions require drilling out that bridge plug and plugging to total depth, or plugging from the existing bridge plug up? The DS cover also lists drilling and re-drilling. Is drilling or re-drilling expected on any of the 22 wells?
Answer: See Question 1 above. The Hawkes & Adams 1-18 was originally drilled to 2998’, then subsequently plugged back with a cast iron bridge plug (CIBP) to 900’ and perforated in the Traverse Lime at 728’-778’. Plugging of the well will commence from placing cement on top of the CIBP and proceed according to the well plugging instructions. No, we are not anticipating drilling or re-drilling on any of the 22 wells.
10. Is the former Growhowski central production facility (tanks, vessels, buildings, containment) part of this project, or only equipment inside the 22 well pad areas? If any tanks or vessels hold oil, will the oil be sold to escrow as the master contract describes? Are tank cleanout, sludge removal and steam cleaning part of the turn-key price?
Answer: No, the Growhowski facility is not part of this project. This scope of work only includes the plugging of 22 wells, removing partial surface piping infrastructure to install blind flanges near the master gate valves, and removal of associated electrical infrastructure at the well pads.
11. The DS says to cut flowlines 4 ft below grade and cap them at the well location. The master contract says lines less than 3 ft deep are purged and removed. For this project, are flowlines only cut and capped at each well, or must full runs be purged and removed? Does EGLE have flowline maps or approximate lengths and depths?
Answer: Flow lines and related surface piping at the well locations will be blind flanged above grade as close as possible to the master gate valve nearest the ground. They will not be purged. In the event that we encounter a buried flowline tied into the well during installation of the cellar, we will install a steel cap on that line to secure the line.
12. Are the poles and transformers at the well pads owned by the electric utility or by the former operator? If the utility owns them, will EGLE arrange the disconnect and removal with the utility, or is the contractor responsible for that coordination and any utility charges?
Answer: It is assumed that the electric utility owns the poles and transformers. The Contractor is to make arrangements (with assistance of the State of Michigan, if needed) with the utility owner to schedule removal and/or de-energizing activities.
13. When does EGLE expect work to start, and is there a required completion date? Will winter work be allowed? If seasonal road weight limits restrict access, will that time be excluded from the contractor's timeline? May final seeding be done in the next planting season?
Answer: The State of Michigan currently does not have a project start date and there is no required completion date. Winter work is allowed. We will temporarily shut down plugging activities during seasonal weight restrictions, and this time can be excluded from the contractor’s timeline due to the fact that no site work will be conducted while seasonal weight restrictions are on.
14. Is there an approved disposal well or facility EGLE expects bidders to use for plugging fluids? If NORM above allowed levels is found on tubulars, equipment or soil, is its handling and disposal a change order at the rated items, or part of the turn-key price?
Answer: Any oilfield permitted disposal well could be utilized for fluid disposal, pending approval of the EGLE-GRMD UIC Unit. The State of Michigan will assist the contractor in setting up this approval. In the event a disposal well could not be readily procured for this work, the contractor could alternately use an environmental disposal company for disposing of well fluids, etc.
NORM is not expected. If NORM impacted materials are encountered, a change order will be considered.
15. Will EGLE issue the plugging instructions and permits, with landowner access already arranged for all 22 sites? Does EGLE expect any local permits, such as soil erosion permits? Are there any water wells at these sites that must be plugged under this project?
Answer: The plugging instructions are attached to the bid document and EGLE has access to the sites. There will be no permitting needed for soil erosion and there are no known water wells that need to be plugged.
16. The turn-key price per well is based on EGLE's plugging procedures for each well. If conditions in the hole are different from the records (for example stuck or parted tubing, rods or packers, casing that will not come free at the free point, lost circulation, or cement above the procedure volumes), will that added work be paid as a change order at the Schedule B rated items? Or is it the contractor's risk inside the turn-key price? If casing cannot be recovered after a reasonable attempt, may it be left in place and cemented as the EGLE inspector directs?
Answer: Pricing should reflect the work necessary to comply with the plugging instructions and bid documents. Change orders will not be given for minor changes to plugging plans, such as increase or decrease in number of sacks needed to plug. Casing can be left in the hole and cemented. This will be evaluated on a case-by-case basis.
17. The Hawkes & Adams 1-28 procedure shows two cases, one of which cuts and pulls the 8-5/8 casing. Which case should bidders use for the turn-key price? If the other case applies in the field, will the difference be handled at rated items? For Growhowski 1-33, can EGLE confirm the production casing size (4-1/2 or 5-1/2)?
Answer: It is up to the bidder to decide which of the two cases they want to include in their price.
18. The wage decision says each wellbore will be cleaned out and electronically logged. Please confirm which logs EGLE requires on each well (for example gamma ray, CCL and free point). Is a cement bond log or any check of cement tops required on any well?
Answer: Logs will not be necessary for this project.
19. Is digging out and disposing of stained or oil-soaked soil at the well pads part of the turn-key price, or is it paid at line 43 B as a change order? What cleanup standard will EGLE use, and who does any confirmation sampling?
Answer: Price should reflect removal and disposal of up to 5 cubic yards of soil per well location. Sampling and confirmation are not necessary.
20. Will lined earthen pits be allowed for returns and wash-up, or must all fluids be held in tanks? Because the wells are listed as potentially sour, does EGLE require an enclosed (sealed) tank for returns on every well, or only where H2S is found?
Answer: Earth pits are not allowed. All fluids and materials must be containerized in steel tanks. Sealed tanks are not required.
21. Who decides when gravel removal is necessary, and when? May clean gravel be left for the landowner or spread on site, and where should removed gravel go? For seeding, is there a required seed mix, mulch, fertilizer or topsoil, and what growth must be in place before EGLE accepts a site?
Answer: All lease roads and well pads are to remain in place. Areas disturbed during the project such as cellar area and electrical equipment removal areas will need to be filled, leveled and perhaps seeded with standard grass mix unless in an agricultural field.
22. How will EGLE weigh the proposed timeline against price in the best-value decision? Would a schedule using two rigs at once be scored more favorably? After award, is the proposed timeline binding, and are there liquidated damages or other penalties if it runs over for weather or access? Is Saturday work allowed?
Answer: EGLE uses multiple factors to determine best value to the state, the timeline is just one factor and there are no penalties or liquidated damages related to the proposed timeline. Generally, work is conducted Monday through Friday.
23. How should certified payrolls be submitted to EGLE (form WH-347 by email, an online system such as LCPtracker, or another way), and how often? When our own drivers haul the rig and equipment to and from the project area, does EGLE treat that hauling as covered work under the wage decision?
Answer: The state currently uses the WH-347 form via email with weekly submittal. The state is looking to obtain an online program such as LCP tracker but does not have access at this time. If drivers work for our vendor they are subject to Davis Bacon provisions.
24. Does EGLE require a written H2S contingency plan or site safety plan for this project? If so, is it due with the proposal or at the pre-construction meeting?
Answer: No. It is the Contractor’s responsibility to know and understand the health and safety risks and industry standards for H2S and how to mitigate those risks.
25. Will EGLE post in writing on SIGMA VSS any clarifications given at the 11/4 pre-bid meeting, along with the attendee sign-in sheet?
Answer: Yes, see revised RFP document posted to SIGMA.
26. Can Class A or Type 1L cement be used instead of 50/50 Poz on the bottom hole plug.
Answer: Type 1L or Class A cement can be permitted for use on a bottom hole plug on a case-by-case basis. These wells have very low to non-detect levels of hydrogen sulfide.
27. Are earthen pits permitted during well plugging?
Answer: Earthen pits are not permitted during well plugging activities. All fluids including well plugging fluids will be containerized in tanks (half round tanks, etc.).
28. Do all flowline stub-ups have to be removed at the well locations?
Answer: The flowline network in this field is complex and is tied into common flowlines related to another active operator. As such, flow-line stub-ups will be blind flanged at the closest above grade master gate valve to where the line stubs up from the ground, and will also allow adequate room for installing the cellar at each well location. The blind flange must be securely bolted and be adequate to handle operating pressure from the field.