These mechanical design documents detail a project to replace the Air Handling Unit (AHU-2) at Building 85 of the Department of Veterans Affairs Boise VAMC (Veterans Affairs Medical Center), located at 500 W Fort St, Boise, ID. The 100% submittal, dated 30 April 2025, includes detailed technical drawings for a new air handling unit with specific specifications: a supply fan wall (FW-101) with 4,352 CFM airflow, a primary heating coil (PHC-101) with 1,053,066 BTUH capacity using 30% glycol, a secondary heating coil (HC-101) with 1,209,750 BTUH capacity, and a cooling coil (CC-101) with 1,079,126 BTUH capacity using water. The design includes comprehensive control schematics, sequences of operation, and electrical diagrams for the replacement of the existing air handling system, with provisions for variable frequency drives, static pressure control, and specific operational modes including occupied, unoccupied, and warm-up modes.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DA--531-24-106 Replace AHU-2 Building 85, newest first.
File Type Posted
36C26026R0019 0006.docx DOCX document
36C26026R0019 0005.docx DOCX document
531-24-106 Spec Section 23 31 00.pdf PDF
531-24-106 Spec Section 23 05 93.pdf PDF
Request for Information and Site Visit - VA Response.pdf PDF
36C26026R0019 0004.docx DOCX document
36C26026R0019 0003.docx DOCX document
36C26026R0019 0002.pdf PDF
site visit sign in AHU_2 B.85 24OCT2025.pdf PDF
36C26026R0019 0001.pdf PDF
36C26026R0019 RFP.pdf PDF
WD ID20250104 Building.pdf PDF
SOW CON 531-24-106 REPLACE AHU2 B 85.pdf PDF
36C26026R0019.docx DOCX document
S02 EXHIBIT A Past Performance Reference Form.docx DOCX document
Specifications - Boise AHU-2 CD Set.pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

324 S. State St., Suite 400 Salt Lake City, UT 84111

800-678-7077 801-328-5151 fax: 801-328-5155 www.spectrum-engineers.com

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

SHEET TO BE VIEWED AND PRINTED IN COLOR

BUILDING 85

531-24-106

BOISE, ID 83702

C :\U se rs

\M ik e.

Sm ith 1\

D oc um en ts \2

5- El ec C en tra l_ M

IK

E.

SM

IT

H 3X

N 6J

.rv t

4/

/2

3:

:5

PM

G001

COVER SHEET REPLACE AHU-2 BUILDING 85

VAMC

30 APRIL 2025 WNF PMS

SHEET INDEX

SHEET NUMBER SHEET NAME

G001 COVER SHEET

M0.00 MECHANICAL COVER SHEET

M1.11 EXISTING AIR HANDLING UNIT

M1.12 EXISTING AIR HANDLING UNIT

M1.21 NEW AIR HANDLING UNIT

M1.22 NEW AIR HANDLING UNIT

M2.01 MECHANICAL SCHEDULES

E6.01 ONE-LINE DIAGRAM

DIRECTOR

ASSOCIATE DIRECTOR / ADMINISTRATIVE OPERATIONS

CHIEF OF STAFF

ASSOCIATE DIRECTOR / PATIENT SERVICES

ASSOCIATE DIRECTOR / CLINICAL OPERATIONS

FINANCIAL MANAGEMENT SERVICE

REPLACE AHU-2REPLACE AHU-2

BUILDING 85 VAMCBUILDING 85 VAMC

531-24-106531-24-106

DEPARTMENT OF VETERANS AFFAIRS BOISE VAMC

500 W FORT ST,

BOISE, ID 83702-4501

100% SUBMITTAL

30 APRIL 2025

SCALE: NTS

SITE PLAN1

Revisions: Date:

100% CONSTRUCTION

DOCUMENTS

2025.04.30

324 S. State St., Suite 400 Salt Lake City, UT 84111

800-678-7077 801-328-5151 fax: 801-328-5155 www.spectrum-engineers.com

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

BUILDING 85

531-24-106

C U s e rs

\G a b e

.B is h o p \D o c u m e n ts

\2

M e c h

C e n tr a l (R

G a b e .B is h o p

.r v t

/2

/2

:5

:3

P

M

M0.00

MECHANICAL COVER SHEET REPLACE AHU-2, BUILDING 85

VAMC

Boise, ID 83702

CLD GPB

100% CONSTRUCTION

DOCUMENTS

13 FEB 2025

1. THE MECHANICAL DRAWINGS SHOW THE GENERAL DESIGN, ARRANGEMENT,

& EXTENT OF THE MECHANICAL SYSTEM. BECAUSE OF THE SMALL SCALE OF

THE DRAWINGS, THESE DRAWINGS DO NOT SHOW ALL OFFSETS, BENDS, OR

ELBOWS NECESSARY FOR THE COMPLETE INSTALLATION IN THE SPACE

PROVIDED. CONTRACTOR SHALL MAKE ALTERATIONS AS MAY BE

NECESSARY TO MAKE THE SYSTEM COMPLETE & OPERATIONAL IN

ACCORDANCE WITH THE DESIGN INTENT.

2. MAJOR DEVIATIONS SUCH AS CHANGES IN SIZES, WEIGHTS, QUANTITIES, OR

MATERIAL REQUIRE PRIOR APPROVAL BY THE DESIGN ENGINEER AND

OWNER.

3. THE DRAWINGS & SPECIFICATIONS HAVE BEEN PREPARED TO SUPPLEMENT

EACH OTHER & SHALL BE INTERPRETED AS AN INTEGRAL UNIT WITH THE

ITEMS SHOWN ON ONE & NOT THE OTHER BEING FURNISHED & INSTALLED

AS THOUGH SHOWN AND CALLED OUT IN BOTH DOCUMENTS. THE

SPECIFICATIONS SHALL SUPERCEDE THE DRAWINGS WHEN IN CONFLICT.

4. THE ENTIRE MECHANICAL INSTALLATION SHALL CONFORM TO THE

REQUIREMENTS OF THE MOST RECENTLY ADOPTED BUILDING CODES,

MECHANICAL CODE, PLUMBING CODE, ELECTRICAL CODE, & ALL OTHER

APPLICABLE CITY, COUNTY, STATE, & FEDERAL CODES & REGULATIONS IN

EFFECT.

5. THE ENTIRE MECHANICAL INSTALLATION SHALL CONFORM TO ALL CODES,

RULES, REGULATIONS, & REQUIREMENTS OF THE BUILDING OWNER.

6. ALL MECHANICAL COMPONENTS AND EQUIPMENT SHALL BE INSTALLED TO

CONFORM WITH ANY APPLICABLE LOCAL SEISMIC REQUIREMENTS.

7. PRIOR TO FABRICATION & INSTALLATION OF ANY MECHANICAL COMPONENT

THE CONTRACTOR SHALL COORDINATE THE INSTALLATION OF ALL

MECHANICAL WORK WITH ALL OTHER BUILDING TRADES, INCLUDING

BUILDING TRADES HIRED DIRECTLY BY THE OWNER. WHERE CONFLICTS

MAY OCCUR, THEY SHALL BE RESOLVED PRIOR TO INSTALLATION.

8. VERIFY ALL REQUIRED SERVICE CONNECTIONS, INCLUDING ELECTRICAL

CHARACTERISTICS, FOR ALL EQUIPMENT PRIOR TO ORDERING OR

FABRICATING MECHANICAL EQUIPMENT AND COMPONENTS.

9. THE SPACE ABOVE CEILINGS IS LIMITED. CAREFUL COORDINATION IS

REQUIRED WITH ALL TRADES BEFORE ANY PIPE, DUCT, OR EQUIPMENT IS

ORDERED &/OR INSTALLED. ANY CONFLICTS &/OR CHANGES FOUND DURING

INSTALLATION THAT RESULTS FROM THE LACK OF COORDINATION BY THE

CONTRACTORS DURING THE SHOP DRAWING PROCESS ARE THE

RESPONSIBILITY OF THE CONTRACTOR.

10. ALL MECHANICAL INFORMATION IS NOT SHOWN ON THE MECHANICAL

DRAWINGS. THE CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATION

OF ALL INFORMATION ON ALL OTHER CONSTRUCTION DOCUMENTS.

11. THE CONTRACTOR SHALL BE RESPONSIBLE TO REVIEW & USE, WHERE

APPROPRIATE, ALL THE MECHANICAL DETAILS SHOWN ON THE DRAWINGS.

DETAILS MAY OR MAY NOT BE CALLED OUT ON THE DRAWINGS WITH

SYMBOLS OR KEYED NOTES. ANY CHANGES RESULTING FROM FAILURE TO

INSTALL THE MECHANICAL SYSTEM WITHOUT USING THE INCLUDED DETAILS

SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR.

12. ALL EQUIPMENT SHALL BE INDEPENDENTLY SUPPORTED FROM

STRUCTURAL MEMBERS. STRUCTURAL ELEMENTS SHOWN IN DETAILS MAY

OR MAY NOT PERTAIN TO ANY PORTION OF THE BUILDING. COORDINATE ALL

MOUNTING REQUIREMENTS WITH ARCHITECTURAL & STRUCTURAL

DRAWINGS AND SPECIFICATIONS.

13. ALL MECHANICAL COMPONENTS AND EQUIPMENT SHALL BE INSTALLED IN

ACCORDANCE WITH ALL MANUFACTURER RECOMMENDATIONS.

14. ALL SIMILAR EQUIPMENT SHALL BE OF THE SAME MANUFACTURER. AIR

INLETS & OUTLETS OF SIMILAR TYPES SHALL BE OF THE SAME

MANUFACTURER.

15. ANY PART OF THE MECHANICAL INSTALLATION THAT FAILS, IS DEEMED

UNFIT, OR BECOMES DAMAGED DURING CONSTRUCTION SHALL BE

REPLACED BY THE CONTRACTOR AT NO ADDITIONAL COST TO THE OWNER.

THE CONTRACTOR SHALL BE RESPONSIBLE FOR EQUIPMENT CHECK-IN,

SAFEKEEPING, & DAMAGE.

16. COORDINATE WITH ARCHITECTURAL REFLECTED CEILING PLAN FOR EXACT

LOCATION OF ALL CEILING DIFFUSERS & GRILLES.

17. CONTRACTOR SHALL OPERATE INSTALLED &/OR MODIFIED SYSTEMS &

DEMONSTRATE ALL ASPECTS OF THE SYSTEM TO THE ENGINEER &/OR

OWNER TO PROVE ALL ASSOCIATED SYSTEMS ARE OPERATIONAL.

18. DURING CONSTRUCTION THE CONTRACTOR SHALL MAINTAIN A SET OF AS-

BUILT REDLINED RECORD DRAWINGS AT THE PROJECT SITE. ALL CHANGES

OR DEVIATIONS IN LAYOUT, ROUTING, EQUIPMENT, COMPONENTS, &

ACCESSORIES SHALL BE RECORDED. THESE REDLINED DRAWINGS SHALL

BE GIVEN TO THE ARCHITECT / ENGINEER AFTER THE FINAL INSPECTION IN

ACCORDANCE WITH PROJECT SPECIFICATIONS.

19. ALL DUCT ELBOWS SHALL BE LONG RADIUS, UNLESS NOTED OTHERWISE.

MECHANICAL GENERAL NOTESABBREVIATIONS

NOTE: ALL ABBREVIATIONS MAY NOT BE USED.

(E) EXISTING

(F) FUTURE

AC AIR CONDITION(-ING,-ED)

APD AIR PRESSURE DROP

BD BALANCING DAMPER

BHP BRAKE HORSE POWER

BTU BRITISH THERMAL UNIT

BTUH BTU/HOUR

CFH CUBIC FEET PER HOUR

CFM CUBIC FEET PER MINUTE

CV CONTROL VALVE

DB DRY BULB TEMPERATURE

DCW DOMESTIC COLD WATER

DHW DOMESTIC HOT WATER

DHWR DOMESTIC HOT WATER RECIRC

DP DEPTH, DEEP, OR DROP IN PRESSURE

EA EXHAUST AIR

EER ENERGY EFFICIENCY RATIO

EFF EFFICIENCY

ELEC ELECTRIC

ELEV ELEVATION

ENT ENTERING

EVAP EVAPORAT(-E, -ING, -ED, -OR)

EWT ENTERING WATER TEMPERATURE

EXT EXTERNAL

FD FIRE DAMPER

FLA FULL LOAD AMPS

FPI FINS PER INCH

FPM FEET PER MINUTE

FPS FEET PER SECOND

FSD FIRE SMOKE DAMPER

GE GREASE EXHAUST

GPH GALLONS PER HOUR

GPM GALLONS PER MINUTE

HD HEAD

HG MERCURY

HP HORSEPOWER

HR HOUR

HTG HEATING

HZ HERTZ (FREQUENCY)

IN INCH

KW KILOWATT

LAT LEAVING AIR TEMPERATURE

LBS POUNDS

LH LATENT HEAT

LRA LOCKED ROTOR AMPS

LVG LEAVING

LWT LEAVING WATER TEMPERATURE

MBH THOUSAND BTU PER HOUR

MCA MINIMUM CIRCUIT AMPS

MFR MANUFACTUR(-ER, -ED)

NC NORMALLY CLOSED OR NOISE CRITERIA

NIC NOT IN CONTRACT

NO NORMALLY OPEN

NPSH NET POSITIVE SUCTION HEAD

NTS NOT TO SCALE

OA OUTSIDE AIR

OD OUTSIDE DIAMETER

OZ OUNCE

PD PRESSURE DROP OR DIFFERENCE

PG PROPOLENE GLYCOL

PH PHASE

PPM PARTS PER MILLION

PSF POUNDS PER SQUARE FOOT

PSI POUNDS PER SQUARE INCH

PSIA PSI ABSOLUTE

PSIG PSI GAUGE

RA RETURN AIR

RECIRC RECIRCULATE (-ER, -ED, -ING)

REFR REFRIGERATION

REQD REQUIRED

RLA RATED LOAD AMPS

RPM REVOLUTIONS PER MINUTE

SA SUPPLY AIR

SCFM STANDARD CUBIC FEET PER MINUTE

SCW SOFT COLD WATER

SH SENSIBLE HEAT

SP STATIC PRESSURE

SPEC(S) SPECIFICATION(S)

SQ SQUARE

SS SANITARY SEWER, SOIL, WASTE

STD STANDARD

TA TRANSFER AIR

TD TEMP. DROP OR DIFF.

TEMP TEMPERATURE

TOT TOTAL

TSTAT THERMOSTAT

TYP TYPICAL

V VOLT, VOLTAGE OR VENT

VAC VACUUM

VAV VARIABLE AIR VOLUME

VEL VELOCITY

VENT VENT, VENTILATION

VERT VERTICAL

VFD VARIABLE FREQUENCY DRIVE

VOL VOLUME

VTR VENT THROUGH ROOF

WB WET BULB TEMP

WC WATER COLUMN

WG WATER GAUGE

WPD WATER PRESSURE DROP

WTR WATER

PIPING LEGEND

DESCRIPTIONABBREVIATION

NOTE: ALL ABBREVIATIONS MAY NOT BE USED.

CONDENSER WATER SUPPLY

CONDENSER WATER RETURN

FIRE PROTECTION

HEATING HOT WATER SUPPLY

HEATING HOT WATER RETURN

NITROUS OXIDE

REFRIGERANT LIQUID

REFRIGERANT GAS

SNOW MELT RETURN

SNOW MELT SUPPLY

CHILLED WATER SUPPLY

CHILLED WATER RETURN

COMPRESSED AIR

CONDENSATE DRAIN

GLYCOL SUPPLY

GLYCOL RETURN

MEDICAL AIR

LIQUID PROPANE GAS

NATURAL GAS

OXYGEN

VACUUM

CHWR

CHWS

CA

CD

CWR

CWS

FP

GR

GS

HHWR

HHWS

LPG

MA

NG

NO

O

RL

RG

SMR

SMS

VAC

FUEL OIL SUPPLY

FUEL OIL RETURN

FUEL OIL VENT

FOR

FOS

FOV

MEDIUM PRESSURE CONDENSATE

HIGH PRESSURE CONDENSATEHPC

MPC

HIGH PRESSURE STEAM

LOW PRESSURE CONDENSATELPC

HPS

LOW PRESSURE STEAM

MEDIUM PRESSURE STEAMMPS

LPS

PUMPED CONDENSATEPC

C02 CARBON DIOXIDE

SQUARE OR RECTANGULAR

SUPPLY DIFFUSER

SYMBOL LEGEND - MECH

DESCRIPTIONSYMBOL

NOTE: ALL ABBREVIATIONS MAY NOT BE USED.

DUCT HIGH EFFICIENCY TAKE OFF

WITH BALANCING DAMPER

SQUARE OR RECTANGULAR

RETURN DIFFUSER

SQUARE OR RECTANGULAR

EXHAUST DIFFUSER

ROUND DIFFUSER

SIDEWALL GRILLE OR REGISTER

BALANCING DAMPER

FIRE DAMPER

FIRE / SMOKE COMBINATION

DAMPER

LINEAR SLOT GRILLE OR DIFFUSER

FLEXIBLE DUCT

T S H THERMOSTAT - SENSOR - HUMIDISTAT

SYMBOL LEGEND - MISC

DESCRIPTIONSYMBOL

VIEW OR DETAIL INDICATOR: # INDICATES DETAIL NUMBER,

SHEET INDICATES DRAWING SHEET WHERE VIEW OR DETAIL

IS SHOWN.

REFERENCE LINES AND SYMBOLS

ELEVATION OR SECTION INDICATOR: # INDICATES VIEW

NUMBER, SHEET INDICATES DRAWING SHEET WHERE VIEW IS

SHOWN.

NAME

### ROOM / SPACE INDICATOR

# KEYNOTE INDICATOR

# REVISION INDICATOR

XX-##

XX-##

TAG

CFM

PLUMBING FIXTURE INDICATOR

EQUIPMENT INDICATOR

REGISTER, GRILLE, OR DIFFUSER INDICATOR

BREAKLINE

MATCHLINE INDICATOR

CONTRACT LIMIT LINE: DASHDOT, WIDE LINE

NEW CONNECTION TO EXISTING

POINT OF DEMOLITION

OR

MATCH LINE

SEE XX/XXX

MECHANICAL SHEET INDEX

M0.00 MECHANICAL COVER SHEET

M1.11 EXISTING AIR HANDLING UNIT

M1.12 EXISTING AIR HANDLING UNIT

M1.21 NEW AIR HANDLING UNIT

M1.22 NEW AIR HANDLING UNIT

M2.01 MECHANICAL SCHEDULES

Revisions: Date:

30 APRIL 2025

PRE-FILTER RACK

PRESSURE GAUGE

PRE-HEAT COIL (116"L x 59"T x 20"D)

MIXING BOX

FILTER RACK

PRESSURE GAUGE

PRIMARY HEATING COIL

(116"L x 104"T x 6"D)

FAN SECTION

39,170 cfm @ 5.3" S.P.

HW COIL (116L x 50"T) COOLING COIL(116L x 71"T)

EXISTING

INTAKE LOUVER

EXTERIOR WALL

EXTERIOR WALL

EXISTING FLOOR DRAIN

EXISTING

EXHAUST LOUVER

E X

IS

T

IN

G

E X

H A

U S

T A

IR

E X

IS

T

IN

G

R E

T U

R N

A

IR

E X

IS

T

IN

G

R E

T U

R N

A

IR

EXISTING RETURN AIR

324 S. State St., Suite 400 Salt Lake City, UT 84111

800-678-7077 801-328-5151 fax: 801-328-5155 www.spectrum-engineers.com

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

BUILDING 85

531-24-106

C U s e rs

\G a b e

.B is h o p \D o c u m e n ts

\2

M e c h

C e n tr a l (R

G a b e .B is h o p

.r v t

/2

/2

:5

:3

P

M

M1.11

EXISTING AIR HANDLING UNIT REPLACE AHU-2, BUILDING 85

VAMC

Boise, ID 83702

CLD GPB

100% CONSTRUCTION

DOCUMENTS

13 FEB 2025

SCALE: 1/2" = 1'-0"1

EXISTING AIR HANDLING UNIT PLAN DETAIL

SHEET KEYNOTES

1 REMOVE EXISTING 60 HP MOTOR AND FAN ASSEMBLY AND ALL RELATED WIRING

AND CONTROLS. FIELD VERIFY EXISTING CONDITIONS BEFORE ANY WORK

SHOULD BEGIN.

Revisions: Date:

EXISTING DOOR

(60.5"T x 20.5"W)

EXISTING DOOR

(84.5"T x 20.5"W)

EXISTING DOOR

(62"T x 26"W)

EXISTING DOOR

("T x 26"W)

4 5 4

HOT DECK

COLD DECK

EXISTING

INTAKE LOUVER

RETURN DUCT

EXISTING DOOR

(60.5"T x 20.5"W)HOT DECK

COLD DECK

RETURN DUCT

324 S. State St., Suite 400 Salt Lake City, UT 84111

800-678-7077 801-328-5151 fax: 801-328-5155 www.spectrum-engineers.com

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

BUILDING 85

531-24-106

C U s e rs

\G a b e

.B is h o p \D o c u m e n ts

\2

M e c h

C e n tr a l (R

G a b e .B is h o p

.r v t

/2

/2

:5

:3

P

M

M1.12

EXISTING AIR HANDLING UNIT REPLACE AHU-2, BUILDING 85

VAMC

Boise, ID 83702

CLD GPB

100% CONSTRUCTION

DOCUMENTS

13 FEB 2025

SHEET KEYNOTES

1 REMOVE EXISTING PRIMARY HEATING COIL. FIELD VERIFY EXISTING CONDITIONS

BEFORE ANY WORK SHOULD BEGIN.

2 REMOVE EXISTING HEATING COIL. FIELD VERIFY EXISTING CONDITIONS BEFORE

ANY WORK SHOULD BEGIN.

3 REMOVE EXISTING COOLING COIL. FIELD VERIFY EXISTING CONDITIONS BEFORE

ANY WORK SHOULD BEGIN.

4 REMOVE EXISTING SERVICE DOOR. FIELD VERIFY EXISTING CONDITIONS AND

EXACT SIZE OF DOOR BEFORE ANY WORK SHOULD BEGIN.

5 REMOVE EXISTING SERVICE DOOR AND FILL IN WITH NEW DOUBLE WALL SHEET

METAL PANEL. FIELD VERIFY EXISTING CONDITIONS BEFORE ANY WORK SHOULD

BEGIN.

6 REMOVE EXISTING WALL INSIDE AHU BETWEEN THE FAN SECTION AND THE COIL

SECTION. FIELD VERIFY EXISTING CONDITIONS BEFORE ANY WORK SHOULD

BEGIN.

7 REMOVE EXISTING CONTROLS CABINET AND WILL BE RELOCATED. FIELD VERIFY

EXISTING CONDITIONS BEFORE ANY WORK SHOULD BEGIN.

8 REMOVE ALL EXISTING STEAM PIPING AND EQUIPMENT THAT IS IN THIS AREA TO

PERFORM NEW WORK.

Revisions: Date:

SCALE: 1/2" = 1'-0"1

EXISTING AIR HANDLING UNIT FRONT ELEVATION DETAIL

SCALE: 1/2" = 1'-0"2

EXISTING AIR HANDLING UNIT BACK ELEVATION DETAIL

PRE-FILTER RACK

PRESSURE GAUGE

PRE-HEAT COIL (116"L x 59"T x 20"D)

MIXING BOX

FILTER RACK

EXISTING

INTAKE LOUVER

EXTERIOR WALL

EXTERIOR WALL

PHC-101

HC-101

CC-101

FW-101 4

EXISTING FLOOR DRAIN

EXISTING

EXHAUST LOUVER

E X

IS

T

IN

G

E X

H A

U S

T A

IR

E X

IS

T

IN

G

R E

T U

R N

A

IR

E X

IS

T

IN

G

R E

T U

R N

A

IR

EXISTING RETURN AIR

324 S. State St., Suite 400 Salt Lake City, UT 84111

800-678-7077 801-328-5151 fax: 801-328-5155 www.spectrum-engineers.com

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

BUILDING 85

531-24-106

C U s e rs

\G a b e

.B is h o p \D o c u m e n ts

\2

M e c h

C e n tr a l (R

G a b e .B is h o p

.r v t

/2

/2

:5

:3

P

M

M1.21

NEW AIR HANDLING UNIT REPLACE AHU-2, BUILDING 85

VAMC

Boise, ID 83702

CLD GPB

100% CONSTRUCTION

DOCUMENTS

13 FEB 2025

SCALE: 1/2" = 1'-0"1

NEW AIR HANDLING UNIT TOP DETAIL

Revisions: Date:

SHEET KEYNOTES

1 NEW PRIMARY HEATING COIL. CONNECT TO EXISTING PIPING AS REQUIRED.

FIELD VERIFY EXISTING CONDITIONS AND EXACT SIZE OF COIL BEFORE ANY

WORK SHOULD BEGIN.

2 NEW HEATING COIL. CONNECT TO EXISTING PIPING AS REQUIRED. FIELD VERIFY

EXISTING CONDITIONS AND EXACT SIZE OF COIL BEFORE ANY WORK SHOULD

BEGIN.

3 NEW COOLING COIL. CONNECT TO EXISTING PIPING AS REQUIRED. FIELD VERIFY

EXISTING CONDITIONS AND EXACT SIZE OF COIL BEFORE ANY WORK SHOULD

BEGIN.

4 NEW FAN WALL. INSTALL NEW FANS AS REQUIRED PER MANUFACTURERS

RECOMMENDATIONS. FIELD VERIFY EXISTING CONDITIONS BEFORE ANY WORK

SHOULD BEGIN.

5 PROVIDE DRAIN DOWN LOW AT COIL SECTION FOR CLEANING PURPOSES. ROUTE

PIPING CLOSE TO AHU AND OVER TO FLOOR DRAIN.

6 SEAL AROUND FAN WALL AIR TIGHT TO SIDE OF INTERIOR WALL OF AHU.

7 RELOCATE EXISTING AHU CONTROLS HERE.

GENERAL SHEET NOTES

1. FIX ALL METAL ON AHU THAT IS SHOWING FATIGUE.

2. INSTALL LIGHTS IN ALL SERVICE SECTIONS INCLUDING FILTER SECTIONS. REFER

TO ELECTRICAL DRAWINGS FOR MORE INFORMATION. ALL LIGHTS NEED TO BE

WIRED TO A SINGLE CIRCUIT.

3. PROVIDE NEW FILTER SECTION DOORS, HANDLES, HINGES AND SEALS AT EXISTING

LOCATIONS.

4. DEMO ALL EXISTING STEAM PIPING ON EXTERIOR OF AHU. FIELD VERIFIY EXISTING

CONDITIONS BEFORE ANY WORK SHALL BEGIN.

5. INSTALL CLEANING SERVICE DRAIN AT EACH COIL SECTION. ROUTE PIPING FROM

COIL SECTION OVER TO FLOOR DRAIN NEXT TO AHU.

6. REPAIR OR REPLACE ANY DAMAGED INSULATION ON EXTERIOR OF AHU. REFER TO

DRAWINGS FOR AREAS.

7. AROUND EACH ACCESS DOOR REPAIR OR REPLACE INSULATION 1'-0" BEYOND

DOOR OPENING.

8. VERIFY THAT THE EXISTING DRAIN AT THE CHILLED WATER COIL FUNCTIONS

PROPERLY. REPAIR IF NEEDED TO WORKING ORDER. DEMONSTRATE WORKING

DRAINAGE TO OWNER.

NEW DOOR

(60.5"T x 20.5"W)

NEW DOOR

(84.5"T x 20.5"W)

NEW DOOR

(62"T x 26"W)

NEW DOOR

(62"T x 26"W)

PHC-101

CC-101

HC-101

FW-101

NEW DOOR

(62"T x 26"W)

RETURN DUCT

HOT DECK

COLD DECK

NEW DOOR

(49"T x 20.5"W)

NEW DOOR

(72.5"T x 20.75"W)

HOT DECK

COLD DECK

HC-101

CC-101

FW-101 PHC-101

NEW DOOR

(49"T x 20.5" W)

NEW DOOR

(72.25"T x 20.75" W)

NEW DOOR

(60.5"T x 20.5" W)

RETURN DUCT

8 8

324 S. State St., Suite 400 Salt Lake City, UT 84111

800-678-7077 801-328-5151 fax: 801-328-5155 www.spectrum-engineers.com

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

BUILDING 85

531-24-106

C U s e rs

\G a b e

.B is h o p \D o c u m e n ts

\2

M e c h

C e n tr a l (R

G a b e .B is h o p

.r v t

/2

/2

:5

:3

P

M

M1.22

NEW AIR HANDLING UNIT REPLACE AHU-2, BUILDING 85

VAMC

Boise, ID 83702

CLD GPB

100% CONSTRUCTION

DOCUMENTS

13 FEB 2025

SHEET KEYNOTES

1 PROVIDE AND INSTALL NEW SERVICE DOORS. PROVIDE WITH NEW HINGES,

LATCHES AND DOOR SEAL. FIELD VERIFY EXISTING CONDITIONS AND EXACT SIZE

OF DOOR BEFORE ANY WORK SHOULD BEGIN.

2 NEW FAN WALL. INSTALL NEW FANS AS REQUIRED PER MANUFACTURERS

RECOMMENDATIONS. FIELD VERIFY EXISTING CONDITIONS BEFORE ANY WORK

SHOULD BEGIN.

3 NEW PRIMARY HEATING COIL. CONNECT TO EXISTING PIPING AS REQUIRED.

FIELD VERIFY EXISTING CONDITIONS AND EXACT SIZE OF COIL BEFORE ANY

WORK SHOULD BEGIN.

4 NEW HEATING COIL. CONNECT TO EXISTING PIPING AS REQUIRED. FIELD VERIFY

EXISTING CONDITIONS AND EXACT SIZE OF COIL BEFORE ANY WORK SHOULD

BEGIN.

5 NEW COOLING COIL. CONNECT TO EXISTING PIPING AS REQUIRED. FIELD VERIFY

EXISTING CONDITIONS AND EXACT SIZE OF COIL BEFORE ANY WORK SHOULD

BEGIN.

6 SEAL AROUND FAN WALL AIR TIGHT TO SIDE OF INTERIOR WALL OF AHU.

7 RELOCATE EXISTING AHU CONTROLS HERE.

8 REPAIR EXISTING INSULATION SO THAT IT IS TIGHT TO AHU AROUND DOOR TO

MIN OF 12" OUT.

Revisions: Date:

SCALE: 1/2" = 1'-0"1

NEW AIR HANDLING UNIT FRONT ELEVATION DETAIL

SCALE: 1/2" = 1'-0"2

NEW AIR HANDLING UNIT BACK ELEVATION DETAIL

GENERAL SHEET NOTES

1. FIX ALL METAL ON AHU THAT IS SHOWING FATIGUE.

2. INSTALL LIGHTS IN ALL SERVICE SECTIONS INCLUDING FILTER SECTIONS. REFER

TO ELECTRICAL DRAWINGS FOR MORE INFORMATION. ALL LIGHTS NEED TO BE

WIRED TO A SINGLE CIRCUIT.

3. PROVIDE NEW FILTER SECTION DOORS, HANDLES, HINGES AND SEALS AT EXISTING

LOCATIONS.

4. DEMO ALL EXISTING STEAM PIPING ON EXTERIOR OF AHU. FIELD VERIFIY EXISTING

CONDITIONS BEFORE ANY WORK SHALL BEGIN.

5. INSTALL CLEANING SERVICE DRAIN AT EACH COIL SECTION. ROUTE PIPING FROM

COIL SECTION OVER TO FLOOR DRAIN NEXT TO AHU.

6. REPAIR OR REPLACE ANY DAMAGED INSULATION ON EXTERIOR OF AHU. REFER TO

DRAWINGS FOR AREAS.

7. AROUND EACH ACCESS DOOR REPAIR OR REPLACE INSULATION 1'-0" BEYOND

DOOR OPENING.

8. VERIFY THAT THE EXISTING DRAIN AT THE CHILLED WATER COIL FUNCTIONS

PROPERLY. REPAIR IF NEEDED TO WORKING ORDER. DEMONSTRATE WORKING

DRAINAGE TO OWNER.

AI

DI

DI AIDO AO AI AIAOAI AI

DI

DI AIDO

NC

NC

NO

CSR

CSR

OUTSIDE AIR

RELIEF AIR RETURN AIR

PT

TT

TT

D

DA

HOT DECK SUPPLY AIR

PTPDT

D

DA

D

DA

VFD

T E

M P

E R

A T

U R

E

T E

M P

E R

A T

U R

E

S T

A T

U

S PS

P R

E S

S U

R E

T E

M P

E R

A T

U R

E

M O

D U

L A

T

IN

G

M O

D U

L A

T

IN

G

P R

E S

S U

R E

A

IR

F L O

W

VFD

S T

A T

U S

RETURN AIR

SMOKE DETECTORS PROVIDED AND

WIRED BY ELECTRICAL CONTRACTOR,

INSTALLED BY MECHANICAL

CONTRACTOR

LOCATED ON SUPPLY AIR. SEE

PLANS FOR EXACT LOCATIONS.

TUBING PROVIDED WITH RTU,

INSTALLED BY THE CONTROLS

CONTRACTOR

PRESSURE TO

VFD SAFETY STRIP

T O

V F

D S

A F

E T

Y S

T R

IP

R

.A

D U

C T

S M

O K

E D

E T

E C

T O

R

AIR HANDLING UNIT SEQUENCE OF OPERATION:

1. GENERAL:

THE VARIABLE AIR VOLUME ROOFTOP UNIT SHALL CONSIST OF A MIXED AIR SECTION, RETURN FAN, MODULATING POWER EXHAUST FAN, OUTDOOR AIR MODULATING DAMPERS, FILTERS, CHILLED WATER COILS, SUPPLY AIR FAN WALL W/VFD, WATER SIDE ECONOMIZER, OSA PRE-HEAT COIL. THE ROOFTOP UNIT SHALL BE PROVIDED WITH AN INDIVIDUAL DDC CONTROLLER LOCATED AT THE UNIT.

2. OPERATION:

WARM-UP MODE OF OPERATION SHALL ALLOW THE BUILDING TO ADJUST FROM UNOCCUPIED SETPOINTS TO THE OCCUPIED SETPOINTS WITHOUT CONDITIONING THE OUTSIDE AIR. THIS WARM-UP MODE SHALL START 20 MINUTES PRIOR TO THE START OF THE OCCUPIED MODE. UNLESS ECONOMIZER COOLING IS AVAILABLE THE OUTSIDE AIR DAMPERS SHALL BE CLOSED DURING THE WARM-UP MODE.

OCCUPIED MODE OF OPERATION SHALL SEE THE SUPPLY FAN RUN CONTINUOUSLY. THE AIR HANDLING UNIT SHALL HAVE THE OUTSIDE AIR DAMPER SET TO THE MINIMUM POSITION AS NOTED IN THE AIR

HANDLING UNIT SCHEDULE.

THE FAN SHALL START AND STOP ON THE MASTER WEEKLY AND HOLIDAY SCHEDULE SET AT THE DDC SYSTEM. WHEN THE FAN IS SCHEDULED ON, ALL VAV BOXES SHALL GO TO OCCUPIED MODE. IN OTHER WORDS THE VAV BOXES SHALL HAVE THEIR OCCUPIED SCHEDULE AS A SLAVE TO THE MASTER SCHEDULE.

INTERNAL AIR HANDLING UNIT CONTROLS SHALL MODULATE TO MAINTAIN THE DESIRED SUPPLY AIR TEMPERATURE. A DISCHARGE AIR SENSOR SHALL MAINTAIN A CONSTANT DISCHARGE AIR

TEMPERATURE OF 55° F OR AS RESET BELOW (ADJUSTABLE).

WHEN ALL THE VAV BOXES ARE AT OR BELOW 75% OF THE DESIGN CFM OR ARE IN THE HEATING MODE THE SUPPLY AIR SETPOINT SHALL RESET FROM 55 F TO 58 F. WHEN THE SAME CONDITIONS NOTED ABOVE ARE MET AGAIN THE SUPPLY AIR SETPOINT SHALL BE RESET FROM 58 F TO 62 F. AS THE COOLING DEMANDS IN THE BUILDING INCREASE THE RESET SCHEDULE SHALL SEQUENCE IN REVERSE.

UNOCCUPIED MODE OF OPERATION SHALL HAVE THE FANS OFF, THE OUTSIDE AIR DAMPER SHALL BE CLOSED AND THE POWER EXHAUST FANS TURNED OFF.

IN THE UNOCCUPIED MODE THE AIR HANDLING UNIT SUPPLY FAN WILL BE STOPPED. IF SPACE TEMPERATURE WERE TO RISE ABOVE OR FALL BELOW THE UNOCCUPIED SPACE SET POINTS THE AIR HANDLING SUPPLY FAN WILL START AND HEATING OR COOLING WILL BE ENABLED TO MAINTAIN THE SPACE TEMPERATURE AT THE UNOCCUPIED SPACE TEMPERATURE SETPOINT, THE

OUTSIDE AIR DAMPERS SHALL REMAIN CLOSED.

3. STATIC PRESSURE CONTROL:

A DUCT STATIC PRESSURE DIFFERENTIAL TRANSMITTER LOCATED WHERE SHOWN ON THE PLANS, SHALL SENSE DUCT STATIC PRESSURE AND SIGNAL THE UNIT DDC CONTROLLER WHICH SHALL MODULATE THE VARIABLE FREQUENCY DRIVE (VFD) OF THE SUPPLY FAN TO MAINTAIN THE DUCT STATIC PRESSURE OF 1.0" (ADJUSTABLE, CONFIRM WITH FACILITIES

ENGINEER). THE STATIC PRESSURE SENSOR SHUT DOWN THE VFD ON HIGH PRESSURE.

THE BUILDING STATIC PRESSURE SHALL BE CONTROLLED THROUGH MODULATING POWER EXHAUST FAN TO MAINTAIN A POSITIVE ROOM STATIC PRESSURE OF 0.02" (ADJUSTABLE). THE BUILDING

STATIC PRESSURE SENSOR SHALL BE LOCATED AT THE LOBBY'S AS NOTED ON THE PLANS.

4. FAN SAFETIES:

A LOW LIMIT DUCT THERMOSTAT SHALL BE INSTALLED ON THE DISCHARGE SIDE OF THE AIR HANDLING UNIT. WHENEVER THE LOW LIMIT DUCT THERMOSTAT SENSES DISCHARGE AIR TEMPERATURES BELOW ITS 35° F SET POINT THE SUPPLY AND POWER EXHAUST FANS SHALL STOP, AND THE OUTSIDE AIR DAMPER SHALL CLOSE.

WHENEVER THE FIRE ALARM CONTROL PANEL GOES INTO ALARM ALL FANS SHALL STOP, AND THE OUTSIDE AIR DAMPER SHALL CLOSE.

THE HIGH STATIC SWITCH, LOW STATIC SWITCH, AND FREEZE STAT SHALL BE WIRED DIRECTLY INTO THE VFD TERMINAL SAFETY STRIP.

T E

M P

E R

A T

U R

E

P R

E S

S U

R E

T E

M P

E R

A T

U R

E

P R

E S

S U

R E

PDT

TT

PT PT

LOCATED ON SUPPLY AIR. SEE

PLANS FOR EXACT LOCATIONS.

TUBING PROVIDED WITH RTU,

INSTALLED BY THE CONTROLS

CONTRACTOR

COLD DECK SUPPLY AIR

HOT DECK SUPPLY AIR

COLD DECK SUPPLY AIR

AO AO AI

AO AI AI AI AI

AI

PDT

P R

E S

S U

R E

AI

PDT

P R

E S

S U

R E

M O

D U

L A

T

IN

G

DI

DI AIDO

CSR

EXHAUST AIR EXHAUST AIR

VFD

S T

A T

U S

AO

BUILDING EXHAUST FAN

324 S. State St., Suite 400 Salt Lake City, UT 84111

800-678-7077 801-328-5151 fax: 801-328-5155 www.spectrum-engineers.com

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

BUILDING 85

531-24-106

C U s e rs

\G a b e

.B is h o p \D o c u m e n ts

\2

M e c h

C e n tr a l (R

G a b e .B is h o p

.r v t

/2

/2

:5

:3

P

M

M2.01

MECHANICAL SCHEDULES REPLACE AHU-2, BUILDING 85

VAMC

Boise, ID 83702

CLD GPB

100% CONSTRUCTION

DOCUMENTS

13 FEB 2025

REMARKS: ALTERNATE MANUFACTURERS MUST BE REVIEWED BY ENGINEER BEFORE APPROVAL.

AHU HYDRONIC SECONDARY HEATING COIL SCHEDULE

LABEL

OPERATING

CONDITIONS

HYDRONIC HEATING

MANUFACTURER MODEL REMARKS

TOTAL

CAPACITY

(BTUH)

FLUID TYPE GPM

NO. OF

ROWS

MAXIMUM

AIR PD

(IN-WC)

MAXIMUM

WATER PD

(FT)

EWT

(°F)

LWT

(°F)

CONTROL

VALVE

HC-101 / 0 OSA, EDB, EWB 1,209,750 30% GLYCOL 127 3 0.28 16.1 140 120 NORTEK COIL SOLUTIONS 5WC-4-51X116X3-10AL

REMARKS: ALTERNATE MANUFACTURERS MUST BE REVIEWED BY ENGINEER BEFORE APPROVAL.

AHU SUPPLY FANS SCHEDULE

LABEL

DESCRIPTION

SUPPLY FANS

MANUFACTURER

Model REMARKS

TOTAL

AIRFLOW

(CFM)

ESP

(IN-WC)

QTY VOLTS PHASE Hz

MOTOR

HP

FLA

VFD

PROVIDED BY

(ELEC/MECH)

FW-101 SUPPLY FAN WALL 4,352 2.25 9 460 3 60 2.5 3.5 MECH NORTEK COIL SOLUTIONS 18-90-145T-32X36X26-C3

REMARKS: ALTERNATE MANUFACTURERS MUST BE REVIEWED BY ENGINEER BEFORE APPROVAL.

AHU HYDRONIC COOLING COIL SCHEDULE

LABEL

OPERATING

CONDITIONS

HYDRONIC COOLING

MANUFACTURER MODEL REMARKS

TOTAL

CAPACITY

(BTUH)

FLUID

TYPE

GPM

NO. OF

ROWS

MAXIMUM

AIR PD

(IN-WC)

MAXIMUM

WATER PD

(FT)

EWT

(°F)

LWT

(°F)

CONTROL

VALVE

CC-101 / 95 OSA, 80 EDB, 62 EWB 1,079,126 WATER 143 6 0.94 18.8 45 60 NORTEK COIL SOLUTIONS 5WC-8-72X116X6-10AL

REMARKS: ALTERNATE MANUFACTURERS MUST BE REVIEWED BY ENGINEER BEFORE APPROVAL.

AHU HYDRONIC PRIMARY HEATING COIL SCHEDULE

LABEL

OPERATING

CONDITIONS

HYDRONIC HEATING

MANUFACTURER MODEL REMARKS

TOTAL

CAPACITY

(BTUH)

FLUID TYPE GPM

NO. OF

ROWS

MAXIMUM

AIR PD

(IN-WC)

MAXIMUM

WATER PD

(FT)

EWT

(°F)

LWT

(°F)

CONTROL

VALVE

PHC-101 / 0 OSA, EDB, EWB 1,053,066 30% GLYCOL 110 2 0.12 6.3 140 120 NORTEK COIL SOLUTIONS 5WC-2-57X116X2-6AL

Revisions: Date:

SCALE: NTS1

AIR HANDLING UNIT CONTROL SCHEMATIC

13 FEB 202530 APRIL 2025

23C

VFD

5C

30/3

20A

VFD

8C

60/3

40A

23C

VFD

5C

30/3

20A

VFD

8C

60/3

40A

VFD

23C

30A/3P

FRS-30

150/3

FANWALL

(NEW)

FANWALL

23C

30A/3P

FRS-30

FANWALL

(NEW)

FANWALL

23C

30A/3P

FRS-30

FANWALL

(NEW)

FANWALL

23C

30A/3P

FRS-30

FANWALL

(NEW)

FANWALL

23C

30A/3P

FRS-30

FANWALL

(NEW)

FANWALL

23C

30A/3P

FRS-30

FANWALL

(NEW)

FANWALL

(NEW) VFD-1

60HP, 61kVA 480V, 3Ø

77A FLA

150A MOCP

5C

RF-1

(NEW)

RF-1

23C

EF-1

(NEW)

EF-1

(NEW)

(NEW) (NEW) (NEW) (NEW) (NEW) (NEW)

(NEW) (NEW) (NEW) (NEW) (NEW) (NEW) (NEW) (NEW)

TYP

(NEW) VFD-2

5HP, 6.1kVA

480V, 3Ø

7.3A FLA

20A MOCP

8C

TO

MCCB

5HP

3.7kW

480V, 3Ø

FLA: 6.80A

15HP

11kW

480V, 3Ø

FLA: 19.0A

TO

MCCB

23C

30A/3P

FRS-30

FANWALL

(NEW)

FANWALL

23C

30A/3P

FRS-30

FANWALL

(NEW)

FANWALL

23C

30A/3P

FRS-30

FANWALL

(NEW)

FANWALL

(NEW) (NEW) (NEW)

(NEW) (NEW) (NEW)

VFD

VFD

FEEDER BY DIVISION 26 FACTORY WIRING W/ EQUIP

SINGLE POINT FEED BY

DIVISION 26

AIR HANDLER WITH

FANWALL SYSTEM

MOTOR PROTECTION

BY OTHERS (TYP)

TYPICAL FANWALL, FAN QUANTITY

AS INDICATED IN SCHEDULE;

WIRING BY OTHERS

TYPICAL FANWALL, FAN QUANTITY

AS INDICATED IN SCHEDULE;

WIRING BY OTHERS

MOTOR CIRCUIT

PROTECTOR

480V/3Ø SUPPLY

BY DIVISION 26

VFD FULLY RATED FOR

ENTIRE FANWALL. VFD

SHOULD ALTERNATE

AUTOMATICALLY

BASED ON RUNTIME. IF

VFD FAILS, ALTERNATE

VFD WILL START.

CUSTOM BUILT DUAL REDUNDANT

VFD CABINET BY DIVISION 26

150/3

23C

30A/3P

FRS-30

FAN

(DEMO)

FAN

(DEMO) VFD-1

60HP, 61kVA 480V, 3Ø

77A FLA

150A MOCP

5C

RF-1

(DEMO)

RF-1

23C

EF-1

(NEW)

EF-1

(DEMO)

(DEMO)

(DEMO) (DEMO) (DEMO)

(DEMO) VFD-2

5HP, 6.1kVA

480V, 3Ø

7.3A FLA

20A MOCP

(DEMO) VFD-3

15HP, 16.7kVA

480V, 3Ø

20.1A FLA

40A MOCP

8C

TO

MCCB

5HP

3.7kW

480V, 3Ø

FLA: 6.80A

15HP

11kW

480V, 3Ø

FLA: 19.0A

TO

MCCB

324 S. State St., Suite 400 Salt Lake City, UT 84111

800-678-7077 801-328-5151 fax: 801-328-5155 www.spectrum-engineers.com

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

SHEET TO BE VIEWED AND PRINTED IN COLOR

BUILDING 85

531-24-106

BOISE, ID 83702

C :\U se rs

\M ik e.

Sm ith 1\

D oc um en ts \2

5- El ec C en tra l_ M

IK

E.

SM

IT

H 3X

N 6J

.rv t

4/

/2

3:

:5

PM

E6.01

ONE-LINE DIAGRAM REPLACE AHU-2 BUILDING 85

VAMC

30 APRIL 2025 WNF PMS

GENERAL SHEET NOTES

1 PROVIDE NEMA 3R ENCLOSURES FOR EQUIPMENT LOCATED OUTDOORS. REFER

TO PLANS FOR EQUIPMENT LOCATIONS.

2 REFER TO PLANS FOR CONSTRAINTS ON PHYSICAL DIMENSIONS AND CLEARANCE

REQUIREMENTS OF EQUIPMENT. PROVIDE EQUIPMENT DIMENSIONS THAT FALL

WITHIN THE CONSTRAINTS OF EACH SPECIFIC LOCATION.

3 ALL EQUIPMENT SHALL BE CONSTRUCTED AND BRACED FOR THE SEISMIC

CONDITIONS OF THE PROJECT. REFER TO ELECTRICAL SPECIFICATIONS FOR

REQUIREMENTS.

4 PROVIDE PERFORMANCE TESTING FOR GROUND-FAULT PROTECTION SYSTEMS ON

SITE WITH A WRITTEN RECORD OF THIS TEST SUBMITTED TO THE AUTHORITY

HAVING JURISDICTION PER NEC 230.95(C).

1. CONDUCTORS SHOWN ARE SHOWN FOR EACH CONDUIT WITH MODIFICATIONS

AS NOTED IN NOTE 5. ALL CONDUCTORS SHOWN ARE THWN UNLESS

OTHERWISE NOTED.

2. PROVIDE EQUIPMENT GROUND CONDUCTORS PER TABLE 250-122 WHEN

CIRCUIT BREAKERS ARE SIZED GREATER THAN AMPERE RATING SHOWN IN

TABLE.

3. PROVIDE #10 NEUTRALS FOR MULTIWIRE BRANCH CIRCUITS SERVING

COMPUTERS.

4. GROUND (G) CONDUCTOR MAY BE DELETED ON SERVICE ENTRANCE

CONDUCTORS.

5. SYMBOL SUBSCRIPTS:

EQUIPMENT NAMEPLATE

SCHEDULE

EQUIPMENT ID SCHEME

LABEL FORMAT [NAME]

[SYSTEM]

[VOLTAGE]

[FED FROM]

[SOURCE(S)]

LABEL EXAMPLE PANEL "4LA1"

STANDBY POWER

120/208V

FED FROM

BUS-A / XFMR 4TA

BUSWAY

OTHER

COLOR SCHEME

SYSTEM EQUIPMENT

NORMAL POWER ALL GEAR NOT INCLUDED BELOW

TEXT BACKGROUND

NAMEPLATE COLOR

STANDBY POWER

EMERGENCY POWER

LEGALLY-REQUIRED

STANDBY POWER

UPS "A" POWER

UPS "B" POWER

LABEL BUSWAY EVERY 6' WHERE EXPOSED TO VIEW AND

EVERY 15' WHERE NOT EXPOSED TO VIEW

WHITE

WHITE

WHITE

RED

WHITE

BLACK

BLACK

ORANGE

RED

WHITE

BLUE

YELLOW

MDPS1 AND ALL DOWNSTREAM GEAR,

EXCEPT UPS GEAR AS NOTED

GDP1, GDP2, ATS-E AND ALL

DOWNSTREAM GEAR

ATS-S AND ALL DOWNSTREAM

GEAR

UPSA AND ALL DOWNSTREAM

GEAR

UPSB AND ALL DOWNSTREAM

GEAR

FIRST DIGIT - BUILDING LEVEL (0, 1, 2, ETC)

SECOND DIGIT - PANEL TYPE

M - MECHANICAL

H - (277/480) L - (120/208)

E - EMERGENCY

S - STANDBY

Q - EQUIPMENT

U - UPS

K - KITCHEN (120/208)

THIRD DIGIT - BUILDING AREA (A, B, C, ETC)

FOURTH DIGIT - SEQUENCE # (1,2,3,...) SHEET KEYNOTES

1 EXISTING 60HP SUPPLY FAN TO BE REPLACED. ELECTRICAL CONTRACTOR SHALL

DEMOLISH BRANCH CIRCUIT TO SOURCE. PROVIDE NEW FEEDERS, DISCONNECTS,

AND A NEW MOTOR. COORDINATE WITH MECHANICAL CONTRACTOR PRIOR TO

ROUGH-IN.

2 PROVIDE NEW VFD FOR NEW FAN-WALL REPLACEMENT. ELECTRICAL CONTRACTOR

SHALL DEMOLISH EXISTING VARIABLE FREQUENCY DRIVES AND EXISTING

FAN-WALL TO SOURCE. COORDINATE EXACT REQUIREMENTS WITH MECHANICAL

CONTRACTOR AND OWNER PRIOR TO ROUGH-IN. VFD TO BE CONTROLLED BY PLC,

SEE MECHANICAL CONTROL DRAWINGS FOR MORE DETAIL.

CIRCUIT

AMPACITY/VOLTAGE

CIRCUIT

LENGTH

CONDUCTOR SIZE

(PHASE, NEUTRAL AND GR) CONDUIT SIZE

20A/120V 0' - 60' #12 AWG 0.75" Ø

20A/120V 60' - 95' #10 AWG 0.75" Ø

20A/120V 95' - 150' #8 AWG 1" Ø

20A/120V 150' - 240' #6 AWG 1.25" Ø

20A/277V 0' - 140' #12 AWG 0.75" Ø

20A/277V 140' - 220' #10 AWG 0.75" Ø

20A/277V 220' - 350' #8 AWG 1" Ø

20A/277V 350' - 550' #6 AWG 1.25" Ø

1.

2.

3.

NOTES:

WIRE SIZING IS BASED ON COPPER CONDUCTORS SUPPLYING A 20A, 120V

CIRCUIT AT THE INDICATED VOLTAGE, ASSUMED TO BE 80% LOADED (16A),

WITH MAXIMUM VOLTAGE DROP OF 3% AT THE LOAD.

DOWN-SIZED WIRE AT DEVICE/LOAD AS REQUIRED AND TERMINATE

CONDUCTORS IN A SAFE AND CODE COMPLIANT MANNER.

CONDUIT SIZE IS BASED ON A MAXIMUM OF 3 CIRCUITS PER CONDUIT, EACH

WITH A SEPARATE NEUTRAL CONDUCTOR.

BRANCH CIRCUIT CONDUCTOR

AND CONDUIT SIZING TABLE

SCALE: NTSF5 ONE-LINE DIAGRAM - FOR REFERENCE ONLY

6. RACEWAY ONLY. CONDUCTORS PROVIDED BY UTILITY.

IG

(E.G.)

COPPER CONDUCTOR AND

CONDUIT SCHEDULE

SUBSCRIPT (NOTE 5)

SCHEDULE NUMBER

5C

"2N": INCLUDE TWO NEUTRAL CONDUCTORS SIZED AS SCHEDULED FOR

PHASE AND NEUTRAL CONDUCTORS WHERE THE CONDUCTOR IS #1/0

OR LARGER. INCLUDE A SINGLE 200% RATED CONDUCTOR THAT IS

TWICE THE AMPACITY OF THE SCHEDULED PHASE AND NEUTRAL

CONDUCTOR WHERE THE CONDUCTOR IS BELOW #1/0 IN SIZE.

"CI": PROVIDE CIRCUIT INTEGRITY CABLE; TYPE TWO-HOUR FIRE

RESISTIVE CABLES IN CONDUIT OR PROVIDE FEEDER ENCASED IN

CONCRETE.

"FG" FULL SIZE GROUND, SIZE EQUIPMENT GROUNDING CONDUCTOR TO

BE SAME SIZE AS THE PHASE CONDUCTORS.

"HH": NEUTRAL CURRENTS EXIST DUE TO HIGH HARMONIC "NONLINEAR"

LOADS. CURRENT CARRYING CONDUCTORS DERATED

ACCORDINGLY. PROVIDE THE IG/HH SIZE FOR THE EQUIPMENT

GROUNDING CONDUCTOR.

"IG": INCLUDE IG (INSULATED/ISOLATED GROUND CONDUCTOR)

SCHEDULED ALONG WITH THE GROUND OF EQUIPMENT GROUND

CONDUCTOR.

"MC": PROVIDE FEEDER IN METAL-CLAD CABLE; TYPE MC IN PLACE OF

SINGLE CONDUCTORS IN CONDUIT.

"SE": SUBSTITUTE "SE" CONDUCTOR FOR "G" CONDUCTOR SHOWN, WHICH

IS SIZED FOR THE GROUNDING OF THE SECONDARY OF THE

SEPARATELY DERIVED SYSTEM.

"SER": PROVIDE SERVICE-ENTRANCE CABLE; TYPE SE OR SER IN PLACE OF

SINGLE CONDUCTORS IN CONDUIT.

CONDUCTOR AND CONDUIT SCHEDULE NOTES

SYM AMP

HH

AMPS

CONDUIT

SIZE

CONDCUTOR (NOTE 1)

IG/HH SE NOTESQTY SIZE G

1C 20 - 0.75 2 12 12 12 8 2 2C 20 - 0.75 3 12 12 12 8 2 3C 20 24 0.75 4 12 12 12 8 2 4C 30 - 0.75 2 10 10 10 8 2 5C 30 - 0.75 3 10 10 10 8 2 6C 30 32 0.75 4 10 10 10 8 2 7C 40 - 1 2 8 10 8 6 2 8C 40 - 1 3 8 10 8 6 2 9C 40 44 1 4 8 10 8 6 2 10C 55 - 1 2 6 10 8 4 2 11C 55 - 1 3 6 10 8 4 2 12C 55 60 1.25 4 6 10 8 4 2 13C 70 - 1 2 4 8 4 2 2 14C 70 - 1.25 3 4 8 4 2 2 15C 70 76 1.25 4 4 8 4 2 2 16C 85 - 1.25 2 3 8 3 2 2 17C 85 - 1.25 3 3 8 3 2 2 18C 85 92 1.25 4 3 8 3 2 2 19C 95 - 1.25 3 2 8 2 2 2 20C 95 104 1.5 4 2 8 2 2 2 21C 130 - 1.5 3 1 6 2 2 2 22C 130 116 1.5 4 1 6 2 2 2 23C 150 - 2 3 1/0 6 2 1/0 2 24C 150 136 2 4 1/0 6 2 1/0 2 28C 200 180 2.5 4 3/0 6 2 2/0 2 29C 230 - 2.5 3 4/0 4 2 2/0 2 30C 230 208 2.5 4 4/0 4 2 2/0 2 34C 310 280 3 4 350 3 1/0 3/0 2 35C 380 - 3.5 3 500 3 3/0 3/0 2

37C 400 - 2 EA 2 3 3/0 3 3/0 3/0 2

38C 400 360 2 EA 2.5 4 3/0 3 3/0 3/0 2

41C 620 - 2 EA 3 3 350 1/0 4/0 3/0 2

42C 620 560 2 EA 3 4 350 1/0 4/0 3/0 2

52C 1240 1120 4 EA 3 4 350 3/0 4/0 3/0 4

53C 1675 1520 5 EA 4 4 400 4/0 4/0 4/0 4

55C 2660 2408 7 EA 4 4 500 350 350 350 4

SCALE: NTS

TYPICAL DUAL REDUNDANT VFD

SCHEMATIC FOR FANWALL AIR

HANDLER SYSTEM1A5

Revisions: Date:

SCALE: NTSF1 ONE-LINE DIAGRAM - DEMOLITION - FOR REFERENCE ONLY

100% CONSTRUCTION

DOCUMENTS

G001 - COVER SHEET
100% Mechanical
M0.00 - MECHANICAL COVER SHEET
M1.11 - EXISTING AIR HANDLING UNIT
M1.12 - EXISTING AIR HANDLING UNIT
M1.21 - NEW AIR HANDLING UNIT
M1.22 - NEW AIR HANDLING UNIT
M2.01 - MECHANICAL SCHEDULES
100% Electrical
E6.01 - ONE-LINE DIAGRAM