531-24-106 Spec Section 23 05 93.pdf
PDF 68 KB Posted
- Attached to
- Z1DA--531-24-106 Replace AHU-2 Building 85 Federal contract opportunity
- Solicitation number
- 36C26026R0019
About this file
This document is a technical specification section (Section 23 05 93) for Testing, Adjusting, and Balancing (TAB) of HVAC systems for the AHU-2 Replacement project at Building 85, Boise VAMC (VA Medical Center), with project number 531-24-106. The specification outlines comprehensive requirements for TAB processes, including detailed procedures for verifying and balancing air and water distribution systems, with specific focus on ensuring proper HVAC system performance, energy efficiency, and documentation.
Key requirements include engaging a certified TAB agency and specialist within 60 days of project commencement, submitting multiple reports (Design Review, Systems Inspection, Duct Air Leakage Test, Systems Readiness), and performing rigorous testing across various system modes including variable volume, economizer, and emergency modes. The specification mandates precise tolerances for air and water flow rates, requires vibration testing for rotating equipment, and stipulates that all HVAC adjustment device settings be permanently marked after final approval. The TAB work must follow specific standards from AABC, NEBB, or TABB and coordinate with the project's phasing and commissioning requirements.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C26026R0019 0006.docx | DOCX document | |
| 531-24-106 Spec Section 23 31 00.pdf | ||
| 36C26026R0019 0005.docx | DOCX document | |
| Request for Information and Site Visit - VA Response.pdf | ||
| 36C26026R0019 0004.docx | DOCX document | |
| 36C26026R0019 0003.docx | DOCX document | |
| 36C26026R0019 0002.pdf | ||
| site visit sign in AHU_2 B.85 24OCT2025.pdf | ||
| 36C26026R0019 0001.pdf | ||
| 36C26026R0019 RFP.pdf | ||
| Drawings - Boise AHU-2 100 Percent.pdf | ||
| S02 EXHIBIT A Past Performance Reference Form.docx | DOCX document | |
| SOW CON 531-24-106 REPLACE AHU2 B 85.pdf | ||
| 36C26026R0019.docx | DOCX document | |
| Specifications - Boise AHU-2 CD Set.pdf | ||
| WD ID20250104 Building.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
03-01-23
AHU-2 REPLACEMENT, BUILDING 85, BOISE VAMC (CD SET)
PROJECT # 531-24-106
23 05 93 - 1
SECTION 23 05 93
TESTING, ADJUSTING, AND BALANCING FOR HVAC
PART 1 - GENERAL
1.1 DESCRIPTION
A. A complete listing of common acronyms and abbreviations are included in
Section 23 05 11, COMMON WORK RESULTS FOR HVAC.
B. Testing, adjusting, and balancing (TAB) of heating, ventilating and air conditioning (HVAC) systems. TAB includes the following:
1. Planning systematic TAB procedures.
2. Design Review Report.
3. Systems Inspection Report.
4. Duct Air Leakage Test Report.
5. Systems Readiness Report.
6. Balancing air and water distribution systems; adjustment of total system to provide design performance; and testing performance of equipment and automatic controls.
7. Vibration and sound measurements.
8. Recording and reporting results.
9. Document critical paths of flow on reports.
C. Definitions:
1. Basic TAB used in this Section: Chapter 39, "Testing, Adjusting and
Balancing" of ASHRAE Handbook "HVAC Applications".
2. TAB: Testing, Adjusting and Balancing; the process of checking and adjusting HVAC systems to meet design objectives.
3. AABC: Associated Air Balance Council.
4. NEBB: National Environmental Balancing Bureau.
5. TABB: Testing Adjusting and Balancing Bureau.
6. SMACNA: Sheet Metal and Air Conditioning Contractors’ National
Association.
7. Hydronic Systems: Includes chilled water, and heating hot water.
8. Air Systems: Includes all outside air, supply air, return air, exhaust air and relief air systems.
9. Flow Rate Tolerance: The allowable percentage variation, minus to plus, of actual flow rate from values (design) in the contract documents.
23 05 93 - 2
1.2 RELATED WORK
A. Section 01 00 00, GENERAL REQUIREMENTS.
B. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
C. Section 23 05 11, COMMON WORK RESULTS FOR HVAC.
D. Section 23 05 41, NOISE AND VIBRATION CONTROL FOR HVAC PIPING AND
EQUIPMENT.
E. Section 23 07 11, HVAC AND BOILER PLANT INSULATION.
F. Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.
G. Section 23 09 23, DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC.
1.3 APPLICABLE PUBLICATIONS
A. The following publications form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only. Where conflicts occur these specifications and the VHA standards will govern.
B. American Society of Heating, Refrigerating and Air Conditioning
Engineers, Inc. (ASHRAE):
2019....................ASHRAE Handbook – HVAC Applications, Chapter
39, Testing, Adjusting, and Balancing and
Chapter 49, Noise and Vibration Control
C. Associated Air Balance Council (AABC):
2016....................National Standards for Total System Balance, 7th
Edition
D. National Environmental Balancing Bureau (NEBB):
2019....................Procedural Standard for Testing, Adjusting, and
Balancing of Environmental Systems, 9th Edition
2015....................Procedural Standard for the Measurement of
Sound and Vibration, 2nd Edition
S110-2019...............Whole Building Technical Commissioning of New
Construction, 2nd Edition
E. Sheet Metal and Air Conditioning Contractors National Association
(SMACNA):
2002....................HVAC Systems Testing, Adjusting and Balancing, 3rd Edition
2003....................TAB Procedural Guide 1st Edition
23 05 93 - 3
1.4 SUBMITTALS
A. Submittals, including number of required copies, shall be submitted in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND
SAMPLES.
B. Information and material submitted under this section shall be marked
“SUBMITTED UNDER SECTION XX XX XX, SECTION TITLE”, with applicable paragraph identification.
C. Submit names and qualifications of TAB agency and TAB Specialists within 60 days after the notice to proceed. Submit information on three recently completed projects and a list of proposed test equipment.
D. For use by the COR staff, submit one complete set of applicable AABC, NEBB or TABB publications that will be the basis of TAB work.
E. Submit the following for review and approval:
1. Design Review Report within 90 days for conventional design projects after the system layout on air and water side is completed by the
Contractor.
2. Systems inspection report on equipment and installation for conformance with design.
3. Duct Air Leakage Test Report.
4. Systems Readiness Report.
5. Intermediate and Final TAB reports covering flow balance and adjustments, performance tests, vibration tests and sound tests.
6. Include in final reports uncorrected installation deficiencies noted during TAB and applicable explanatory comments on test results that differ from design requirements.
7. Include in each report the critical path for each balanced branch
(air and hydronic). Every branch shall have at least one terminal device damper 100 percent open.
F. Prior to request for Final or Partial Final inspection, submit completed Test and Balance report for the area with noted critical paths.
1.5 QUALITY ASSURANCE
A. Refer to paragraphs QUALITY ASSURANCE and SUBMITTALS, in Section 23 05
11, COMMON WORK RESULTS FOR HVAC and Section 23 08 00, COMMISSIONING OF
HVAC SYSTEMS.
B. Qualifications:
23 05 93 - 4
1. TAB Agency: The TAB agency shall be a subcontractor of the General
Contractor and shall report to and be paid by the General
Contractor.
2. The TAB agency shall be either a certified member of AABC, NEBB, or
TABB to perform TAB service for HVAC, water balancing and vibrations and sound testing of equipment. The certification shall be maintained for the entire duration of duties specified herein. If, for any reason, the agency loses subject certification during this period, the General Contractor shall immediately notify the COR and submit another qualified TAB firm for approval. Any agency that has been the subject of disciplinary action by either the AABC, TABB or
NEBB within the five (5) years preceding Contract Award shall not be eligible to perform any work related to the TAB. All work performed in this Section and in other related Sections by the TAB agency shall be considered invalid if the TAB agency loses its certification prior to Contract completion, and the successor agency’s review shows unsatisfactory work performed by the predecessor agency.
3. TAB Specialist: The TAB Specialist shall be either a member of AABC or TABB or an experienced technician of the Agency certified by
NEBB. The certification shall be maintained for the entire duration of duties specified herein. If, for any reason, the Specialist loses subject certification during this period, the General Contractor shall immediately notify the COR and submit another TAB Specialist for approval. Any individual that has been the subject of disciplinary action by either the AABC or the NEBB within the five
(5) years preceding Contract Award shall not be eligible to perform any duties related to the HVAC systems, including TAB. All work specified in this Section and in other related Sections performed by the TAB Specialist shall be considered invalid if the TAB Specialist loses its certification prior to Contract completion and shall be performed by an approved successor.
4. TAB Specialist shall be identified by the General Contractor within sixty (60) days after the Notice to Proceed. The TAB Specialist will be coordinating, scheduling, and reporting all TAB work and related activities and will provide necessary information as required by the
COR. The responsibilities shall specifically include:
23 05 93 - 5
a. Directly supervising all TAB work.
b. Sign the TAB reports that bear the seal of the TAB standard. The reports shall be accompanied by report forms and schematic drawings required by the TAB standard, AABC, TABB or NEBB.
c. Following all TAB work through its satisfactory completion.
d. Providing final markings of settings of all HVAC adjustment devices.
e. Permanently mark location of duct test ports.
f. Documenting critical paths from the fan or pump. These critical paths are ones in which are 100 percent open from the fan or pump to the terminal device. This will show the least amount of restriction is being imposed on the system by the TAB firm.
5. All TAB technicians performing actual TAB work shall be experienced and shall have done satisfactory work on a minimum of three (3) projects comparable in size and complexity to this project.
Qualifications shall be certified by the TAB agency in writing. The lead technician shall be certified by AABC, TABB or NEBB.
C. Test Equipment Criteria: The instrumentation shall meet the accuracy/calibration requirements established by AABC National
Standards, TABB/SMACNA International Standards, or by NEBB Procedural
Standard for Testing, Adjusting and Balancing of Environmental Systems and instrument manufacturer. Provide calibration history of the instruments to be used for test and balance purpose. All equipment shall remain in calibration, or be re-calibrated if certification expires, during the TAB procedures.
D. TAB Criteria:
1. One or more of the applicable AABC, NEBB, TABB or SMACNA publications, supplemented by Chapter 39, "Testing, Adjusting and
Balancing" of ASHRAE Handbook "HVAC Applications" and requirements stated herein shall be the basis for planning, procedures, and reports.
2. Flow Rate Tolerance: Following tolerances are allowed. For tolerances not mentioned herein follow Chapter 39, "Testing, Adjusting and Balancing" of ASHRAE Handbook "HVAC Applications" as a guideline. Air Filter resistance during tests, artificially imposed, if necessary, shall be at least 100 percent of manufacturer
23 05 93 - 6 recommended change over pressure drop values for pre-filters and after-filters.
a. Air handling unit and all other fans, cubic meters/min (cubic feet per minute): Minus 5 percent to plus l0 percent.
b. Air Terminal Units (maximum values): Minus 5 percent to plus l0 percent
c. Exhaust Hoods/Cabinets: 0 percent to plus l0 percent.
d. Minimum Outside Air: 0 percent to plus 10 percent.
e. Individual room air outlets and inlets, and air flow rates not mentioned above: Minus 5 percent to plus l0 percent except if the air to air space is 100 CFM or less the tolerance will be minus 5 to plus 5 percent.
f. Heating Hot Water Pumps and Hot Water Coils: Minus 5 percent to plus 5 percent.
g. Chilled Water and Condenser Water Pumps: Minus 5 percent to plus
5 percent.
h. Chilled Water Coils: Minus 5 percent to plus 5 percent.
3. Systems shall be adjusted for energy efficient operation as described in PART 3.
4. Typical TAB procedures and critical path results shall be demonstrated to the COR for one air distribution system (including all fans, 3 terminal units, 3 rooms randomly selected by the COR, one of which shall be a critical path) and 1 hydronic system (pumps and 3 coils) as follows:
a. When field TAB work begins.
b. During each partial final inspection and the final inspection for the project if requested by VA.
PART 2 - PRODUCTS
2.1 PLUGS
A. Provide plastic plugs to seal holes drilled in ductwork for test purposes.
2.2 INSULATION REPAIR MATERIAL
A. See Section 23 07 11, HVAC and BOILER PLANT INSULATION. Provide for repair of insulation removed or damaged for TAB work.
PART 3 - EXECUTION
3.1 GENERAL
A. Refer to TAB Criteria in Paragraph QUALITY ASSURANCE.
23 05 93 - 7
B. Obtain applicable contract documents and copies of approved submittals for HVAC equipment and automatic control systems.
3.2 DESIGN REVIEW REPORT
A. The TAB Specialist shall review the contract documents and advise the
COR of any design deficiencies that would prevent the HVAC systems from effectively operating in accordance with the sequence of operation specified or prevent the effective and accurate TAB of the system. The
TAB Specialist shall provide a report individually listing each deficiency and the corresponding proposed corrective action necessary for proper system operation.
3.3 SYSTEMS INSPECTION REPORT
A. Inspect equipment and installation for conformance with design.
B. The inspection and report shall be done after air distribution and hydronic equipment is onsite, and duct and piping installation has begun, but well in advance of performance testing and balancing work.
The purpose of the inspection is to identify and report deviations from design and ensure that systems will be ready for TAB at the appropriate time.
C. Reports: Follow checklist format developed by AABC, NEBB or SMACNA
(TABB), supplemented by narrative comments, with emphasis on air-handling units and fans. Check for conformance with submittals.
Verify that diffuser and register sizes are correct. Check air terminal unit installation including their duct sizes and routing.
3.4 DUCT AIR LEAKAGE TEST REPORT
A. TAB Agency shall perform the leakage test as outlined in "Duct Leakage
Tests and Repairs" in Section 23 31 00, HVAC DUCTS and CASINGS for TAB agency’s role and responsibilities in witnessing, recording and reporting of deficiencies.
3.5 SYSTEM READINESS REPORT
A. The TAB Contractor shall measure existing air and water flow rates associated with existing systems utilized to serve renovated areas as indicated in the contract documents. Submit report of findings to COR.
B. Inspect each system to ensure that it is complete including installation and operation of controls. Submit report to COR in standard format and forms prepared and/or approved by the CxA.
23 05 93 - 8
C. Verify that all items such as ductwork piping, dampers, valves, ports, terminals, connectors, etc., that are required for TAB are installed.
Provide a report to the COR.
3.6 TAB REPORTS
A. Submit an intermediate report for 25 percent of systems and equipment tested and balanced to establish satisfactory test results.
B. The TAB Contractor shall provide raw data immediately in writing to the
COR if there is a problem in achieving intended results before submitting a formal report.
C. If over 20 percent of readings in the intermediate report fall outside the acceptable range, the TAB report shall be considered invalid and all contract TAB work shall be repeated after engineering and construction have been evaluated and re-submitted for approval at no additional cost to the owner.
D. Do not proceed with the remaining systems until intermediate report is approved by the COR.
3.7 TAB PROCEDURES
A. EXISTING SYSTEM VERIFICATION
1. Before commencing any demolition, repair, or replacement of existing
HVAC equipment, the Contractor shall engage a qualified testing, adjusting, and balancing agency to measure and document the current operating performance of AHU-2 supply airflow (hot and cold deck), exhaust airflow, return airflow, and outside airflow.
2. The Contractor shall submit TAB reports to the Engineer for review prior to performing any work that alters the existing system conditions.
3. The intent of this requirement is to establish baseline system performance for verification and comparison following completion of the work.
B. TAB shall be performed in accordance with the requirement of the
Standard under which TAB agency is certified by either AABC, TABB or
NEBB. Balancing shall be done proportionally to all applicable systems.
1. At least 1 trunk damper shall be 100 percent open.
2. At least 1 branch damper shall be 100 percent open per trunk.
3. At least 1 terminal device duct be 100 percent open per branch.
23 05 93 - 9
4. At least one hydronic balancing valve shall be 100 percent open per hydronic system.
C. General: During TAB all related system components shall be in full operation. Fan and pump rotation, motor loads and equipment vibration shall be checked and corrected as necessary before proceeding with TAB.
Set controls and/or block off parts of distribution systems to simulate design operation of variable volume air or water systems for test and balance work.
D. Coordinate TAB procedures with existing systems and any phased construction completion requirements for the project. Provide TAB reports for pre-construction air and water flow rate and for each phase of the project prior to partial final inspections of each phase of the project. Return existing areas outside the work area to pre-constructed conditions.
E. Allow 21 days’ time in construction schedule for TAB and submission of all reports for an organized and timely correction of deficiencies.
F. Air Balance and Equipment Test: Include air-handling unitsand fans.
1. Artificially load air filters by partial blanking to produce static air pressure drop of manufacturer’s recommended pressure drop.
2. Adjust fan speeds to provide design air flow. V-belt drives, including fixed pitch pulley requirements, are specified in Section
23 05 11, COMMON WORK RESULTS FOR HVAC.Provide new drive sets as required to adjust fan speeds.
3. Test and balance systems in all specified modes of operation, including variable volume, economizer, and fire emergency modes.
Verify that dampers and other HVAC controls function properly.
4. Variable Air Volume (VAV) Systems:
a. Coordinate TAB, including system volumetric controls, with
Section 23 09 23, DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC.
b. Check and readjust ATU flow rates if necessary to meet design criteria. Balance air distribution from ATU on full cooling maximum scheduled cubic meters per minute (cubic feet per minute). Reset room thermostats and check ATU operation from maximum to minimum cooling, to the heating mode, and back to cooling. Record and report the heating coil leaving air temperature when the ATU is in the maximum heating mode. Record and report outdoor air flow rates under all operating conditions
23 05 93 - 10
(The test shall demonstrate that the minimum outdoor air ventilation rate shall remain constant under all operating conditions).
c. Adjust operating pressure control setpoint to maintain the design flow to each space with the lowest setpoint. Confirm static pressure reset is operational and functioning properly.
5. Record final measurements for air handling equipment performance data sheets.
6. Record final damper settings for all manual volume dampers.
G. Water Balance and Equipment Test: Include circulating pumps, convertors, coils, coolers and condensers:
1. Adjust flow rates for equipment. Set coils and evaporator to values on equipment submittals, if different from values in the contract documents.
2. Primary-Secondary (variable volume) Systems: Coordinate TAB with
Section 23 09 23, DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC. Balance systems at design water flow and then verify that variable flow controls function as designed.
3. Record final measurements for hydronic equipment on performance data sheets. Include entering and leaving water temperatures for heating and cooling coils, and for convertors. Include entering and leaving air temperatures (DB/WB for cooling coils) for air-handling units and reheat coils. Make air and water temperature measurements at the same time.
4. On coils with automatic flow limiting valves (automatic balancing valves) measure and report Delta P across valve and measure Delta P across 100 percent open temperature control valve and using control valve CV calculate and report gpm.
5. Record final valve setting for all balancing valves.
3.8 VIBRATION TESTING
A. Furnish instruments and perform vibration measurements as specified in
Section 23 05 41, NOISE and VIBRATION CONTROL FOR HVAC PIPING and
EQUIPMENT. Field vibration balancing is specified in Section 23 05 11, COMMON WORK RESULTS FOR HVAC. Provide measurements for all rotating
HVAC equipment of 373 watts (1/2 horsepower) and larger, including centrifugal/screw compressors, cooling towers, pumps, fans and motors.
23 05 93 - 11
B. Record initial measurements for each unit of equipment on test forms and submit a report to the COR. Where vibration readings exceed the allowable tolerance Contractor shall be directed to correct the problem. The TAB agency shall verify that the corrections are done and submit a final report to the COR.
3.9 MARKING OF SETTINGS
A. Following approval of TAB Final Report, the setting of all HVAC adjustment devices including valves, splitters and dampers shall be permanently marked by the TAB Specialist so that adjustment can be restored if disturbed at any time. Style and colors used for markings shall be coordinated with the COR.
3.10 IDENTIFICATION OF TEST PORTS
A. The TAB Specialist shall permanently and legibly identify the location points of duct test ports. If the ductwork has exterior insulation, the identification shall be made on the exterior side of the insulation.
All penetrations through ductwork and ductwork insulation shall be sealed to prevent air leaks and maintain integrity of vapor barrier.
3.11 PHASING
A. Phased Projects: Testing and Balancing Work to follow project with areas shall be completed per the project phasing. Upon completion of the project all areas shall have been tested and balanced per the contract documents.
B. Existing Areas: Systems that serve areas outside of the project scope shall not be adversely affected. Measure existing parameters where shown to document system capacity.
3.12 CRITICAL FLOW PATH
A. Provide a documented critical path for all fluid flows. There shall be at least one (1) terminal device that can be traced back to the fan or pump where there is no damper or valves that are less than 100 percent open.
3.13 COMMISSIONING
A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.
B. Components provided under this section of the specification will be tested as part of a larger system.
- - E N D - -