Drawings 565-21-101 Halls and Walls B and 1 Floors (4).pdf
PDF 32 MB Posted
- Solicitation number
- 36C24623B0041
About this file
This document outlines a federal contract opportunity to renovate halls and walls in a Veteran Affairs medical center. The solicitation number is 36C24623B0041 and is being issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 6 to renovate the basement and first floor of the Fayetteville Veteran Affairs Medical Center located in Fayetteville, North Carolina. The work includes renovating the halls and walls on these floors. No further details are provided on pricing, response dates, or other requirements.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
B
IM
/2
.9
V
A F a y e tt e v ill e H a lls
W a lls
/2 .9
A v
.r v t
/1
/2
:5
:3
P
M
AI911
INTERIOR RENDERINGS
GUIDON
1221 N. PENNSYLVANIA STREET
INDIANAPOLIS, IN 46202
317.800.6388
HALLS & WALLS 1ST FLOOR
BLDG. 1
2300 RAMSEY ST.
565-21-101
BLDG 1
07/14/2022 DB BA
100% BID DOCUMENTS
FULLY SPRINKLERED
FIRST FLOOR - MAIN ELEVATOR LOBBY
FIRST FLOOR D-WING ELEVATOR LOBBY BASEMENT A-WING ELEVATOR LOBBY
Revisions: Date:
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
B
IM
/2
.9
V
A F a y e tt e v ill e H a lls
W a lls
/2 .9
A v
.r v t
/1
/2
:5
:3
P
M
AI912
INTERIOR RENDERINGS
GUIDON
1221 N. PENNSYLVANIA STREET
INDIANAPOLIS, IN 46202
317.800.6388
HALLS & WALLS 1ST FLOOR
BLDG. 1
2300 RAMSEY ST.
565-21-101
BLDG 1
07/14/2022 DB BA
100% BID DOCUMENTS
FULLY SPRINKLERED
FIRST FLOOR - WAITING AREA
FIRST FLOOR - CONNECTOR
FIRE PROTECTION GENERAL NOTES
1. THE NEW SPRINKLER SYSTEM SHALL BE SIZED IN ACCORDANCE WITH NFPA 13 AND SHALL BE HYDRAULICALLY CALCULATED TO MEET THE REQUIREMENTS OF INTERNATIONAL BUILDING CODE, NFPA, AND APPROVED BY ALL AUTHORITIES HAVING JURISDICTION. THE CONTRACTOR SHALL BE RESPONSIBLE
FOR PROVIDING FLOW TEST DATA TO PERFORM AS A BASIS OF THEIR CALCULATIONS.
2. THE SYSTEM SHALL BE DESIGNED AND BUILT IN A WORKMANLIKE MANNER, IN ACCORDANCE WITH DETAILED DRAWINGS TO BE SUBMITTED FOR APPROVAL. THE WORK SHALL INCLUDE ALL COMPONENTS
REQUIRED TO PROVIDE A COMPLETE SYSTEM.
3. THE FIRE PROTECTION CONTRACTOR SHALL PROVIDE A SET OF SHOP DRAWINGS THAT INCLUDE ALL PIPE SIZES, ELEVATIONS, HEAD LOCATIONS, DIMENSIONS, VALVES, INSPECTOR TESTS, FLOW SWITCHES, TAMPER SWITCHES, ETC.
4. THE FIRE PROTECTION CONTRACTOR SHALL PROVIDE SPRINKLER LAYOUT INCLUDING LOCATION OF
PENDANT HEADS FOR ALL LOCATION IN THIS SCOPE OF WORK.
5. THE SHOP DRAWINGS AND CALCULATIONS IF REQUIRED, SHALL BE SUBMITTED TO OWNER ’ S ENGINEER
AND THESE CALCULATIONS AND DRAWINGS SHALL BE SUBMITTED TO ALL AUTHORITIES HAVING
JURISDICTIONS.
6. SPRINKLER HEADS AND ASSOCIATED MAIN/BRANCH PIPING SHALL BE PROVIDED AND LOCATED IN
ACCORDANCE WITH NFPA 13 AND ALL PREVAILING LOCAL CODES. IT IS THE CONTRACTOR ’ S
RESPONSIBILITY TO CONFIRM LOCATIONS FOR COMPLIANCE WITH THE CODE REQUIREMENTS.
7. THE FIRE PROTECTION CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS AT THE PROJECT SITE.
8. SPRINKLER PIPING SHOULD BE ROUTED AS HIGH AS POSSIBLE WHILE STILL COORDINATING WITH OTHER
TRADES. ELEVATION OF SPRINKLER PIPING AND HEAD MUST BE DETERMINED BY PROPOSED OR
EXISTING CEILING HEIGHTS.
9. ALL MATERIAL AND ITS INSTALLATION SHALL BE IN COMPLETE COMPLIANCE WITH ALL APPLICABLE SECTIONS OF THE LATEST EDITION OF NFPA. AND FACTORY MUTUAL GUIDELINES. THE FIRE PROTECTION CONTRACTOR SHALL BE REQUIRED TO COMPLY WITH ALL SPECIAL CONDITIONS SET FORTH BY THE
INSURANCE UNDERWRITER IF AND WHEN REQUIRED BY THE OWNER.
10. THE FIRE PROTECTION CONTRACTOR SHALL FURNISH ALL LABOR, MATERIAL AND EQUIPMENT; AND, PERFORM ALL OPERATIONS NECESSARY FOR THE INSTALLATION OF A COMPLETE FIRE PROTECTION SYSTEM THAT IS READY FOR USE WITHIN THE INTENT OF AND AS INDICATED ON THE DRAWINGS, SPECIFICATIONS AND AS HEREIN SPECIFIED.
11. PROVIDE CUTTING AND PATCHING OF BUILDING AS REQUIRED TO INSTALL NEW WORK.
12. SMALL ITEMS NOT SHOWN OR SPECIFIED, BUT OBVIOUSLY REQUIRED BY GOOD GENERAL PRACTICE TO
COMPLETE THE WORK SHALL BE FURNISHED AND INSTALLED THE SAME AS IF BOTH SHOWN AND
SPECIFIED.
13. BY SUBMITTING A PROPOSAL FOR THIS WORK, THE CONTRACTOR WILL BE HELD TO HAVE EXAMINED THE SITE AND SATISFIED THEMSELVES AS TO EXISTING CONDITIONS UNDER WHICH THEY WILL BE OBLIGED
TO OPERATE OR THAT WILL IN ANY MANNER AFFECT THEIR WORK UNDER THIS CONTRACT. NO
ALLOWANCES SHALL BE MADE SUBSEQUENTLY IN THIS CONTRACT IN BEHALF OF CONTRACTOR OF ANY
ERROR OR NEGLIGENCE ON THEIR PART.
14. WHERE SO INDICATED ON THE PLANS AS PART OF THE PROJECT SCOPE OF WORK, THE FIRE PROTECTION CONTRACTOR SHALL MAKE CONNECTION INTO THE NEW/EXISTING FIRE SERVICE WATER
SYSTEM.
15. THE FIRE PROTECTION CONTRACTOR SHALL SCHEDULE WITH THE VA COR ALL TIE-INS TO EXISTING
SYSTEMS AND PERFORM REQUIRED SHUTDOWN AND RE-INITIALIZATION OF THE EXISTING FIRE
SPRINKLER SYSTEM; THESE SERVICES WILL INCLUDE DRAIN AND REFILL OF THE FIRE SPRINKLER
SYSTEMS IN THE AFFECTED AREAS OF THIS PROJECT WORK SCOPE.
16. ALL FIRE PROTECTION WORK SHALL BE MADE IN ACCORDANCE WITH RULES AND REGULATIONS OF ALL GOVERNING AUTHORITIES, THE OWNER INSURANCE UNDERWRITER AND NFPA 13 AND NFPA 25. THE ENTIRE FIRE PROTECTION SYSTEM FOR THE WORK SCOPE SHOWN ON THESE DESIGN DRAWINGS SHALL BE MADE BY THIS CONTRACTOR IN THE PRESENCE OF AN INSPECTOR FROM THE AUTHORITY HAVING JURISDICTION AND AN OWNER ’ S REPRESENTATIVE. THE FIRE PROTECTION SYSTEM SHALL BE TESTED
AS REQUIRED BY NFPA 13.
17. THROUGH PENETRATION ASSEMBLIES SHALL BE PROVIDED AT EACH OPENING WHERE EXPOSED SPRINKLER PIPING PASS THROUGH RATED WALLS, FLOORS AND PARTITIONS. ALL PIPING PENETRATIONS MUST BE SEALED IN ACCORDANCE WITH “ UL ” LISTING SEALING METHOD AND/OR AS DETAILED IN THESE
CONTRACT DRAWINGS OR SPECIFICATIONS.
18. ALL APPLIANCES AND APPURTENANCES SHALL BEAR LABEL OF UL/FM APPROVED AND LABELED FOR ITS
INTENDED USE.
19. ALL MATERIALS AND EQUIPMENT SHALL BE INSTALLED AND COMPLETED IN A FIRST-CLASS
WORKMANLIKE MANNER AND IN ACCORDANCE WITH THE BEST MODERN METHODS AND PRACTICES.
ANY MATERIALS WHICH SHALL NOT PRESENT AN ORDERLY AND REASONABLY NEAT AND/OR
WORKMANLIKE APPEARANCE SHALL BE REMOVED AND REPLACED WHEN SO DIRECTED BY THE
ARCHITECT OR ENGINEER OF RECORD. THE REMOVAL AND REPLACEMENT OF THIS WORK SHALL BE
DONE WHEN DIRECTED IN WRITING BY THE ARCHITECT, AT THE CONTRACTOR ’ S EXPENSE.
20. PIPE HANGERS SHALL BE OF TYPE FM APPROVED AND UL LISTED.
21. ALL HANGERS SHALL BE FASTENED BY MEANS OF BEAM CLAMPS, CONCRETE INSERTS OR OTHER
APPROVED DEVICES INSTALLED BY THIS CONTRACTOR.
22. SPRINKLER HEAD RATINGS, SPRAY TYPE, AND FINISH SHALL BE AS SPECIFIED ON PROJECT PLANS.
WHERE NOT SPECIFICALLY IDENTIFIED ON PLANS, SPRINKLER HEADS SHALL QUICK RESPONSE TYPE UPRIGHT PENDANT WITH PAINTED COVER PLATE OR AS REQUIRED BY THE OWNER. REGULAR PENDANT HEADS IN FINISHED SPACES SHALL BE CHROME PLATED WITH CHROME PLATED CEILING PLATES UNLESS
OTHERWISE NOTED. NEW HEADS SHALL MATCH EXISTING.
23. THE FIRE PROTECTION CONTRACTOR WILL BE REQUIRED TO COORDINATE ACCEPTANCE FOR VARIATION OF EQUIPMENT LOCATIONS AND EQUIPMENT CONFIGURATIONS WITH THE FIRE MARSHAL, THE LOCAL
JURISDICTION, THE OWNER, AND THE GENERAL CONTRACTOR.
24. THE FIRE PROTECTION CONTRACTOR IS RESPONSIBLE FOR COORDINATING CHANGES IN ELECTRICAL
REQUIREMENTS WITH THE ELECTRICAL CONTRACTOR.
25. VARIATION FROM SPECIFIED PHYSICAL EQUIPMENT APPEARANCE WILL NEED TO BE APPROVED
THROUGH THE ARCHITECT.
26. SYSTEM PIPING WILL BE SUPPORTED AND BRACED WITH HANGERS AND LISTED EARTHQUAKE BRACE ASSEMBLIES IN ACCORDANCE WITH THE INTERNATIONAL BUILDING CODE, ASCE 7 AND NFPA 13.
27. AUTOMATIC SPRINKLER SYSTEM SHALL BE SUPERVISED AND INTERFACE WITH FIRE ALARM SYSTEMS.
28. ONE SET OF STAMPED, APPROVED DRAWINGS SHALL BE ON SITE AT ALL TIMES AND MADE AVAILABLE TO
THE INSPECTOR AND/OR ARCHITECT/OWNER UPON DEMAND.
29. FIRE PROTECTION SYSTEMS SHALL BE INSTALLED BY A CONTRACTOR LICENSED TO PERFORM SUCH
WORK IN THE PROJECT JURISDICTION.
30. AVOID DAMAGING EXISTING SURFACES AND EQUIPMENT AND ASSOCIATED MATERIALS FROM THE SITE.
REPAIR ANY DAMAGE CAUSED DURING WORK AT NO EXTRA COST TO THE OWNER.
31. REPAIR FIRE AND SMOKE RATED PARTITIONS SURROUNDING FIRE ALARM WORK AS SPECIFIED. REFER
TO ARCHITECTURE PLANS FOR LOCATIONS OF SMOKE AND FIRE PARTITIONS.
32. THREADED BUSHING SHALL NOT BE USED.
33. ANY SPRINKLER REMOVED FROM SERVICE FOR ANY REASON (E.G., REMOVED, RELOCATED, ETC.) SHALL BE REPLACED WITH A NEW SPRINKLER HEAD IN ACCORDANCE WITH NFPA 25, SECTION 5.4.1.1.
34. NEW ARMOVERS SHALL BE PROVIDED TO EITHER RELOCATED OR NEW SPRINKLERS AS REQUIRED BY
NFPA 13.
35. SPRINKLER SYSTEM SHOP DRAWINGS SHALL INCLUDE ALL MATERIALS REQUIRED BY NFPA 13 CHAPTER 23.
36. CONTRACTOR SHALL BE RESPONSIBLE FOR ALL CUTTING AND PATCHING OF WALLS AND CEILING AS
MAY BE REQUIRED FOR THE INSTALLATION OF THE NEW FIRE SUPPRESSION SYSTEM.
37. INTERRUPTIONS IN OPERATION OF THE FIRE SUPPRESSION SYSTEM MUST BE SCHEDULED WITH THE OWNER AT LEAST ONE(1) WEEK IN ADVANCE; WITH PROPER NOTICE PROVIDED TO THE EMERGENCY
RESPONSE TEAMS - BOTH INSIDE AND OUTSIDE OF THE FACILITY.
38. WHEN WORK IS BEING PERFORMED IN AREAS THAT MUST CONTINUE OPERATION, CONTRACTOR SHALL KEEP THE AREAS CLEAN AND CLEAR OF OBSTRUCTIONS, AS MUCH AS POSSIBLE, PROVIDE WARNING
SIGNS AS NECESSARY FOR PROTECTION OF OCCUPANTS FROM ASSOCIATED RISKS. REMOVE ALL
DEBRIS AS WORK PROGRESSES.
39. UPON COMPLETION OF THE WORK, THE CONTRACTOR SHALL PRESENT THE OWNER WITH A REPORT CONFIRMING PROPER TESTING OF ALL NEW AND EXISTING DEVICES IN THE PROJECT ZONE; ALONG WITH APPROPRIATE SELECTED TESTING OF THE MAIN FIRE SUPPRESSION SYSTEM TO CONFIRM CONTINUED PROPER OPERATION. A CERTIFICATE OF APPROVAL FROM THE APPROPRIATE AGENCY INSPECTION
AGENT WILL BE REQUIRED PRIOR TO FINAL ACCEPTANCE OF THE PROJECT.
40. THE PIPING SCHEMATIC INDICATED BY THE DRAWINGS REPRESENTS THE SCOPE AND INTENT OF THE FIRE PROTECTION SYSTEM; HOWEVER THE SPRINKLER CONTRACTOR SHALL PROVIDE A COMPLETE SPRINKLER SYSTEM PER NFPA 13 AND LOCAL AUTHORITY HAVING JURISDICTION REQUIREMENTS.
41. LIGHT FIXTURES AND HVAC DIFFUSERS TAKE SPACE PREFERENCE, ADD ADDITIONAL SPRINKLER HEADS AS
REQUIRED TO MEET "COVERAGE REQUIREMENTS".
42. CONTRACTOR SHALL MAINTAIN A CLEAN WORK PREMISE AT ALL TIMES AND SHALL CLEAN CONSTRUCTION
SITE OF ALL HIS DEBRIS AT THE END OF THE DAY AND BEFORE FINAL PAYMENT IS MADE.
43. COORDINATE PLACEMENT OF SPRINKLER HEADS WITH ALL MECHANICAL DUCTS, DIFFUSERS AND
ELECTRICAL LIGHT FIXTURES.
44. THE FIRE PROTECTION CONTRACTOR SHALL INDICATE ON THEIR SHOP DRAWINGS; CEILING TILE
LOCATIONS WITH ALL CEILING MOUNTED FIRE PROTECTION DEVICES.
45. WALL PENETRATIONS THROUGH NON-RATED PARTITIONS SHALL BE PROVIDED WITH A NON-SHRINKING
GROUT OR CAULKING MATERIAL.
46. THE FIRE PROTECTION SYSTEM / AREA OF PROTECTION INDICATED ON THE PLANS IS FOR COORDINATION AND BIDDING PURPOSES ONLY. THE FIRE PROTECTION CONTRACTOR SHALL BE RESPONSIBLE FOR THE
COMPLETE DESIGN
47. ALL PIPING SYSTEMS THAT ARE NOT INTENDED TO BE REUSED SHALL BE REMOVED AND PIPES SHALL BE
CAPPED AS CLOSE TO MAINS AS POSSIBLE.
48. IT IS THE INTENTION OF THE SPECIFICATION AND DRAWINGS TO CALL FOR A COMPLETE AND FUNCTIONAL SYSTEM, INSTALLED AS PER THE APPLICABLE CODES WITH ALL FINISHED WORK TESTED AND READY FOR
OPERATION.
49. THE FIRE PROTECTION CONTRACTOR SHALL NOTIFY THE OWNER, OWNER’S REPRESENTATIVE, FIRE ALARM CONTRACTOR, ARCHITECT AND GENERAL CONTRACTOR ONE WEEK PRIOR TO ANY SHUTDOWN OR
INTERRUPTION OF SERVICE.
50. ALL MATERIALS, PIPING, FITTINGS, VALVES, AND APPLIANCES HEREINAFTER SPECIFIED AND THOSE WHICH ARE ESSENTIAL BUT HAVE NOT BEEN SPECIFIED SHALL BE NEW AND OF THE HIGHEST GRADE AND
QUALITY, FREE FROM DEFECTS AND SUCH AS BREAKS, FLAWS, AND IMPERFECTIONS.
51. CORE DRILL MASONRY WALLS FOR NEW PIPING. SEAL PENETRATIONS AS NECESSARY TO MAINTAIN
INTEGRITY OF EXISTING WALLS.
52. CONTRACTOR SHALL BE RESPONSIBLE FOR ALL CUTTING AND PATCHING OF WALLS AND CEILING AS MAY
BE REQUIRED FOR THE INSTALLATION OF THE NEW FIRE SUPPRESSION SYSTEM.
53. ALL APPLIANCES AND APPURTENANCES SHALL BEAR LABEL OF UL/FM APPROVED AND LABELED FOR ITS
INTENDED USE.
54. LONG RUNS OF PIPE SHALL BE PROVIDED WITH A SUITABLE MEANS TO PERMIT FREE MOVEMENT RESULTING FROM EXPANSION AND CONTRACTION OF PIPE. REDUCTION IN PIPE SIZES SHALL BE MADE
WITH ONE-PIECE REDUCTION FITTINGS.
55. THE FIRE PROTECTION CONTRACTOR IS TO MAINTAIN A SET OF UP TO DATE CONSTRUCTION DOCUMENTS AVAILABLE AT THE PROJECT SITE AT ALL TIMES DURING CONSTRUCTION. THE FIRE PROTECTION CONTRACTOR IS TO INSTRUCT THE OWNER’S REPRESENTATIVE(S) IN THE OPERATION AND MAINTENANCE REQUIREMENTS OF THE COMPLETED BUILDING FIRE PROTECTION SYSTEM AT A TIME AGREED ON BY THE OWNER. THE OWNER’S REPRESENTATIVE(S) SHALL BE PROVIDED WITH AN UP TO DATE CONSTRUCTION
DOCUMENTS AND A COPY OF NFPA 25 PRIOR TO INSTRUCTION BY THIS CONTRACTOR.
56. COORDINATE WITH OTHER WORK, INCLUDING HVAC, PLUMBING PIPING, ELECTRICAL AS NECESSARY TO INTERFACE COMPONENTS OF FIRE SPRINKLER PIPING PROPERLY WITH OTHER WORK. SYSTEM PIPING WILL BE SUPPORTED AND BRACED WITH HANGERS AND LISTED EARTHQUAKE BRACE ASSEMBLIES IN
ACCORDANCE WITH THE NORTH CAROLINA BUILDING CODE, ASCE 7 AND NFPA 13.
57. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO REMOVE AND LEGALLY DISPOSE OF
DEMOLISHED MATERIALS UNLESS NOTED OTHERWISE IN THE DRAWINGS.
58. ALL WALL AND FLOOR PENETRATIONS SHALL BE CORE-DRILLED AND SLEEVED.
59. CONTRACTOR SHALL MAINTAIN A CLEAN WORK PREMISE AT ALL TIMES AND SHALL CLEAN CONSTRUCTION
SITE OF ALL HIS DEBRIS AT THE END OF THE DAY AND BEFORE FINAL PAYMENT IS MADE.
60. UNLESS INDICATED OTHERWISE IN THE DRAWINGS OR SPECIFICATIONS, FIRE SUPPRESSION CONTRACTOR IS RESPONSIBLE FOR SEALING ALL FIRE RATED WALL PARTITIONS WITH U.L. LISTED MATERIAL AND
METHODS.
61. WALL PENETRATIONS THROUGH NON-RATED PARTITIONS SHALL BE PROVIDED WITH A NON-SHRINKING
GROUT OR CAULKING MATERIAL AND APPROVED ASSEMBLY.
62. BEFORE SUBMITTING A PROPOSAL FOR THE WORK, EACH BIDDER WILL BE HELD RESPONSIBLE TO HAVE EXAMINED THE EXISTING SITE CONDITIONS FOR THE WORK INCLUDED UNDER THIS CONTRACT. NO ALLOWANCE WILL BE MADE SUBSEQUENTLY IN THIS CONNECTION ON BEHALF OF THE CONTRACTOR FOR
ANY ERROR OR NEGLIGENCE ON HIS PART.
63. THE FIRE SUPPRESSION CONTRACTOR SHALL BE RESPONSIBLE FOR THE COMPLETE DESIGN OF THE FIRE PROTECTION SYSTEM AND SHALL PROVIDE SEALED SHOP DRAWINGS. SPRINKLER SYSTEM PLANS AND CALCULATIONS SHALL BE SEALED BY AN PROFESSIONAL ENGINEER REGISTERED IN THE STATE WHERE THE WORK IS TO OCCUR, OR SEALED BY A NICET LEVEL III OR LEVEL IV SPRINKLER DESIGNER CERTIFIED IN "WATER BASED SYSTEMS LAYOUT". DRAWINGS SHALL BE SEALED IN ACCORDANCE WITH REQUIREMENTS
OF THE LOCAL AUTHORITY HAVING JURISDICTION.
64. ALL HANGERS MUST BE APPROVED TYPE BY NFPA 13. NO SPRINKLER PIPING IS TO BE SUPPORTED FROM ANY MECHANICAL OR ELECTRICAL DEVICES. ALL PIPE SHALL BE SUPPORTED FROM THE BUILDING STRUCTURE IN A NEAT AND WORKMANLIKE MANNER. VERTICAL RISERS SHOULD BE SUPPORTED AT EACH FLOOR LEVEL WITH STEEL PIPE CLAMPS. HANGING PIPES FROM OTHER PIPES WILL BE NOT PERMITTED.
PIPING SHALL BE CAREFULLY COORDINATED BEFORE INSTALLATION WITH OTHER SYSTEMS AND
EQUIPMENT IN CHASES AND OTHER CONGESTED AREAS.MAXIMUM DISTANCES BETWEEN PIPE SUPPORTS SHALL MEET THE REQUIREMENT STATED IN NFPA 13, SECTION 9.2.2 AND TABLE 9.2.2.1(A). TITLED "MAXIMUM
DISTANCE BETWEEN HANGERS (FT-IN)."
65. WATER FLOW IN ONE ZONE SHALL NOT CAUSE FIRE ALARMS IN OTHER ZONES. PROVIDE WATER FLOW
ALARM SWITCHES WITH RETARD MECHANISM.
66. THE CONTROL VALVE UTILIZED IN THE STAIRWELLS ON EACH FLOOR SHOULD BE OF THE INDICATING TYPE THAT IS READILY VISIBLE TO AN OBSERVER AT FLOOR LEVEL AS TO WHETHER THE VALVE IS OPEN OR
CLOSED.
67. PROVIDE A 2" TEST OUTLET ON SHOP DRAWING REMOTE AREA. SEE ENGINEERING DRAWINGS FOR
SUGGESTED LOCATION. COORDINATE EXACT LOCATION WITH FIRE MARSHALL.
68. VERIFY THAT ALL TAMPER SWITCHES AND FLOW SWITCHES ARE CONNECTED TO A U.L. APPROVED FACP
BY THE FIRE DETECTION CONTRACTOR.
69. ALL VALVES SHALL BE MADE TAMPER RESISTANT. ELECTRICAL SUPERVISION SHALL BE REQUIRED ON ALL SPRINKLER CONTROL VALVES. INDICATOR VALVES SHALL BE MADE EASILY READABLE AND READILY
ACCESSIBLE.
70. EACH SPRINKLER ZONES IS TO BE PROVIDED WITH A DEDICATED CONTROL VALVE, TAMPER SWITCH AND
AN INSPECTOR'S TEST.
71. TAMPER SWITCHES ON OS&Y TYPE VALVES MUST NOT DISTORT OR CHANGE SWITCH SETTINGS AS THEIR
BOLTS ARE SECURELY FASTENED. NO "J-BOLT" MOUNTS WILL BE PERMITTED.
72. MAINTAINABILITY
A. EXTERNAL AND INTERNAL PARTS SHALL BE ARRANGED SO THAT WHEN INSTALLED, ALL PARTS REQUIRING MANIPULATION, OBSERVATION, AND/OR MAINTENANCE ARE READILY ACCESSIBLE AND
SAFE FOR OPERATION AND MAINTENANCE PERSONNEL. WHEREVER PRACTICAL, VALVES AND
INSTRUMENTS SHALL BE LOCATED SUCH THAT THEY CAN BE OPERATED AND EASILY ACCESSED FROM
GRADE LEVEL.
B. MAINTAINABILITY SHALL BE INCORPORATED INTO THE DESIGN OF ALL CONTRACTOR SUPPLIED EQUIPMENT. THE PRIMARY MAINTAINABILITY OBJECT SHALL BE TO MINIMIZE THE COMPLEXITY AND TIME REQUIRED FOR MAINTENANCE. THE FOLLOWING GENERAL CRITERIA SHALL BE FOLLOWED TO
ACHIEVE THIS OBJECTIVE:
a. CONTRACTOR SUPPLIED EQUIPMENT SHALL BE LOW MAINTENANCE DESIGN AND SHALL BE EASILY
MAINTAINABLE.
b. CONTRACTOR SUPPLIED EQUIPMENT SHALL BE DESIGNED TO BE MAINTAINED IN PLACE, IF
POSSIBLE, WITH MINIMUM DISASSEMBLY OF SURROUNDING EQUIPMENT AND MINIMUM USAGE OF
TEMPORARY SCAFFOLDING AND HANDLING EQUIPMENT.
73. DEVICES SHOWN ON THIS PLAN ARE NEW, UNLESS OTHERWISE NOTED.
74. DRAWING ARE DIAGRAMMIC AND ARE NOT INTENDED TO SHOW EACH AND EVERY SPRINKLER HEAD, BRANCH PIPING, DEVICES, FITTINGS, VALVES OR COMPLETE DETAIL OF ALL THE WORK TO BE PERFORMED, BUT ARE FOR THE PURPOSES OF ILLUSTRATING THE TYPE OF SYSTEM AND CONDITIONS NECESSARY FOR AN EXPERIENCED TRADESMAN TO LAYOUT HIS WORK. THE CONTRACTOR SHALL BE RESPONSIBLE FOR MAKING SUCH SITE OBSERVATIONS AND MEASUREMENTS AS NECESSARY TO PROPERLY COMPLETE THE
WORK.
76. ADEQUATE HOUSING SHALL BE PROVIDED FOR ALL MATERIAL STORED ON THE JOB. ALL MATERIALS FURNISHED FOR THE PROJECT SHALL BE NEW WITH LISTINGS AND LABELS BY A TESTING AGENCY
APPROVED BY THE STATE OF WHERE THE WORK IS TO BE PERFORMED.
77. INTERRUPTIONS IN OPERATION OF THE FIRE SUPPRESSION SYSTEM MUST BE SCHEDULED WITH THE OWNER AT LEAST ONE(1) WEEK IN ADVANCE; WITH PROPER NOTICE PROVIDED TO THE EMERGENCY
RESPONSE TEAMS - BOTH INSIDE AND OUTSIDE OF THE FACILITY.
78. WHERE WORK IS BEING PERFORMED IN AREAS THAT MUST CONTINUE NORMAL OPERATION, CONTRACTOR SHALL KEEP THE AREAS CLEAN AND CLEAR OF OBSTRUCTIONS, AND AS MUCH AS POSSIBLE, PROVIDE WARNING SIGNS AS NECESSARY FOR PROTECTION OF OCCUPANTS FROM ASSOCIATED RISKS. REMOVE
ALL DEBRIS AS WORK PROGRESSES.
79. UPON COMPLETION OF THE WORK, THE CONTRACTOR SHALL PRESENT THE OWNER WITH A REPORT CONFIRMING PROPER TESTING OF ALL NEW AND EXISTING DEVICES IN THE PROJECT ZONE; ALONG WITH APPROPRIATE SELECTED TESTING OF THE MAIN FIRE SUPPRESSION SYSTEM TO CONFIRM CONTINUED PROPER OPERATION. A CERTIFICATE OF APPROVAL FROM THE APPROPRIATE AGENCY INSPECTION AGENT
WILL BE REQUIRED PRIOR TO FINAL ACCEPTANCE OF THE PROJECT.
80. THE PIPING SCHEMATIC INDICATED BY THE DRAWINGS REPRESENTS THE SCOPE AND INTENT OF THE FIRE PROTECTION SYSTEM; HOWEVER THE SPRINKLER CONTRACTOR SHALL PROVIDE A COMPLETE SPRINKLER
SYSTEM PER NFPA 13 AND LOCAL AUTHORITY HAVING JURISDICTION REQUIREMENTS.
81. REFER TO ARCHITECTURAL REFLECTED CEILING PLAN FOR COORDINATION OF SPRINKLER LOCATIONS WITH CEILING HEIGHTS AND TYPES. LOCATE SPRINKLER HEADS THROUGHOUT ALL AREAS AS REQUIRED BY NFPA 13 AND LOCAL AUTHORITY HAVING JURISDICTION. COORDINATE SPRINKLER HEAD LOCATIONS WITH ALL OTHER TRADES BUT NOT LIMITED TO THE FOLLOWING: LIGHTS, STRUCTURAL SUPPORTS, BOOM, SPECIAL SYSTEMS, SMOKE DETECTORS,FIRE ALARM INDICATION DEVICES, HVAC DIFFUSERS, ETC. OBTAIN
ARCHITECT'S, ENGINEER AND/OR APPROVAL OF ALL SPRINKLER HEAD LOCATIONS.
82. ALL SPRINKLER HEAD PIPE ROUTING AND ELEVATIONS SHALL BE COORDINATED WITH ALL OTHER TRADES INCLUDING BUT NOT LIMITED TO THE FOLLOWING: CEILINGS, STRUCTURAL STEEL AND SUPPORTS, HVAC
DUCTWORK, CABLE TRAYS, CONDUIT, SPECIAL SYSTEMS, CONTROLS, ETC.
83. THE AUTOMATIC SPRINKLER CONTRACTOR IS TO PROVIDE ALL NECESSARY OFFSETS, RISES OR DROPS IN THE PIPING AND AUXILIARY DRAINS AS REQUIRED TO INSTALL COMPLETELY COORDINATED SPRINKLER
SYSTEM.
84. HYDRAULIC CALCULATIONS SHALL BE ORIGINATED AT THE FIRE PUMP AS A MINIMUM FOR FACILITIES THAT
POSSES A FIRE PUMP OR AT LOCATION OF FIRE HYDRANT FLOW TEST.
85. SPRINKLER HEADS SHALL BE LOCATED A MINIMUM OF TWO (2) FOOT DISTANCE FROM A SIDE WALL- MOUNTED OR CEILING MOUNTED DIFFUSER USING AN ORDINARY TEMPERATURE SPRINKLER HEAD.
SPRINKLER HEADS SHALL BE LOCATED A MINIMUM OF THREE (3) FOOT DISTANCE FROM THE FRONT OF A
WALL-MOUNTED HOT AIR DIFFUSER.
86. SPRINKLER HEADS SHALL BE LOCATED A MINIMUM OF 18 INCHES FROM ANY LIGHT FIXTURE USING AN ORDINARY TEMPERATURE SPRINKLER HEAD. IT IS PREFERRED THAT THE CONTRACTOR MAINTAINS A TWO
(2) FOOT SPACING BETWEEN THE LIGHT FIXTURE AND SPRINKLER HEAD.
87. SPRINKLER PLANS AS SHOWN ARE FOR BIDDING PURPOSES ONLY. SPRINKLER CONTRACTOR IS TO OBTAIN CURRENT HYDRANT TEST DATA AND PROVIDE HYDRAULIC CALCULATIONS FOR SYSTEM PIPE SIZING IN ACCORDANCE WITH NFPA 13. CONTRACTOR IS TO SUBMIT SHOP DRAWINGS INDICATING HYDRAULIC CALCULATIONS, PIPING LAYOUT & SIZING. ALL WORK IS TO BE DONE IN ACCORDANCE WITH ALL STATE, LOCAL, GOVERNING AND APPLICABLE CODES.
88. SPRINKLER CONTRACTOR SHALL MAINTAIN SUPERVISION OF EXISTING SPRINKLER SYSTEM AT ALL TIMES
AND SHALL COORDINATE TRANSFER OF SYSTEM WITH OWNER AND ENGINEER OF RECORD.
89. THIS CONTRACTOR IS RESPONSIBLE FOR SUBMISSION OF CONTRACTOR'S MATERIAL AND TEST CERTIFICATE FOR ABOVEGROUND PIPING MEEITNG NFPA 13, FIGURE 28.1 TO THE VA COR AND THE
ENGINEER OF RECORD FOR REVIEW AND COMMENT.
90. THE FIRE PROTECTION CONTRACTOR SHALL NOTIFY THE VA FIRE MARSHAL, THE ENGINEER, THE
ARCHITECT, CONTRACTOR AND GENERAL CONTRACTOR ONE WEEK PRIOR TO ANY SHUTDOWNS OR
INTERRUPTIONS OF SERVICE.
91. THE FIRE SUPPRESSION CONTRACTOR SHALL LOCATE SPRINKLER HEADS IN CEILING AS FOLLOWS. ALL HEADS SHALL BE LOCATED IN THE CENTER OF THE TILES (2'X2') OR IN THE CENTER OF ONE QUADRANT (2'X4') IN GYP/. BOARD CEILING. SPRINKLER HEADS SHALL BE LOCATED IN SYMMETRICAL PATTERN
RELATIVE TO OTHER DEVICES LOCATED IN THE CEILING.
92. THE FIRE PROTECTION CONTRACTOR SHALL NOTIFY THE COR, COR’S REPRESENTATIVE, FIRE ALARM
CONTRACTOR, ARCHITECT AND GENERAL CONTRACTOR ONE WEEK PRIOR TO ANY SHUTDOWN OR
INTERRUPTION OF SERVICE.
93. ALL MATERIALS FURNISHED FOR THE PROJECT SHALL BE NEW WITH LISTINGS AND LABELS BY A TESTING
AGENCY APPROVED BY THE STATE OF WHERE THE WORK IS TO BE PERFORMED.
94. CONFLICTS BETWEEN NATIONALLY RECOGNIZED CODES AND THE VA DESIGN REQUIREMENTS SHOULD A CONFLICT EXIST BETWEEN THE VA REQUIREMENTS AND THE VA ADOPTED CODES, THE REQUIREMENTS OF
NFPA ARE TO BE USED AND NOT THE MOST STRINGENT.
95. ALL MAINS AND CONTROL VALVES, INCLUDING THE WATER SUPPLY CONTROL VALVES, SHALL HAVE A SIGN INDICATING THE PORTION OF THE SYSTEM THAT IS CONTROLLED BY THE VALVE AND THE VALVE SHALL HAVE A IDENTIFICATION / VALVE TAG NUMBER. ALL ISOLATION VALVES SHALL BE ELECTRONICALLY
SUPERVISED BY TAMPER/WATER FLOW SWITCHES AND THEY SHALL INTERFACE WITH THE FIRE
ALARM/FIRE DETECTION SYSTEM.
96. WET PIPE SYSTEMS SHALL MEET THE FOLLOWING REQUIREMENTS:
A. WET PIPE SYSTEM SPRINKLER PIPES SHALL BE PERMITTED TO BE INSTALLED LEVEL MEETING THE
REQUIREMENTS OF NFPA 13, 2022 EDITION, SECTION 16.10.2.
B. ANY TRAPPED PIPING WHERE THE BRANCH LINES OR MAINS ARE LOCATED AT A LEVEL THAT CAN NOT
BE DRAINED AT THE WET PIPE ASSEMBLY DRAIN VALVE(S) SHALL MEET THE REQUIREMENTS OF NFPA 13, 2022 EDITION, SECTION 16.10.5 AND VA FIRE PROTECTION DESIGN MANUAL, SECTION 6.1.P.
C. PROVIDE AUXILIARY DRAIN WITH DRUM DRIP IN AN ACCESSIBLE LOCATION; WHERE, 2-INCH MINIMUM DRAIN SHALL BE PROVIDED AND SLOPED 1/2-INCH PER 10 FEET PER NFPA 13 AND VA FIRE PROTECTION
DESIGN MANUAL REQUIREMENTS.
97. ALL SPRINKLER HEADS SHALL BE QUICK RESPONSE PENDENT TYPE HEADS AND IF IN THE EXISTING BUILDING THERE IS A DIFFERENT TYPE THEN ALL SPRINKLER HEADS SHALL BE OF QUICK RESPONSE TYPE.
CONTRACTOR SHALL VERIFY EXISTING SPRINKLER HEAD TYPE BEFORE WORK BEGINS.
98. THIS CONTRACTOR IS RESPONSIBLE FOR SUBMISSION OF CONTRACTOR'S MATERIAL AND TEST CERTIFICATE FOR ABOVEGROUND PIPING MEEITNG NFPA 13, FIGURE 28.1 TO THE VA COR AND THE
ENGINEER OF RECORD FOR REVIEW AND COMMENT.
99. THE FIRE PROTECTION CONTRACTOR SHALL NOTIFY THE VA FIRE MARSHAL, THE ENGINEER, THE
ARCHITECT, CONTRACTOR AND GENERAL CONTRACTOR ONE WEEK PRIOR TO ANY SHUTDOWNS OR
INTERRUPTIONS OF SERVICE.
100. THE FIRE SUPPRESSION CONTRACTOR SHALL LOCATE SPRINKLER HEADS IN CEILING AS FOLLOWS. ALL HEADS SHALL BE LOCATED IN THE CENTER OF THE TILES (2'X2') OR IN THE CENTER OF ONE QUADRANT (2'X4') IN GYP/. BOARD CEILING. SPRINKLER HEADS SHALL BE LOCATED IN SYMMETRICAL PATTERN
RELATIVE TO OTHER DEVICES LOCATED IN THE CEILING.
101. THE FIRE PROTECTION CONTRACTOR SHALL NOTIFY THE COR, COR’S REPRESENTATIVE, FIRE ALARM
CONTRACTOR, ARCHITECT AND GENERAL CONTRACTOR ONE WEEK PRIOR TO ANY SHUTDOWN OR
INTERRUPTION OF SERVICE.
102. ALL MATERIALS FURNISHED FOR THE PROJECT SHALL BE NEW WITH LISTINGS AND LABELS BY A TESTING
AGENCY APPROVED BY THE STATE OF WHERE THE WORK IS TO BE PERFORMED.
103. CONFLICTS BETWEEN NATIONALLY RECOGNIZED CODES AND THE VA DESIGN REQUIREMENTS SHOULD A CONFLICT EXIST BETWEEN THE VA REQUIREMENTS AND THE VA ADOPTED CODES, THE REQUIREMENTS OF
NFPA ARE TO BE USED AND NOT THE MOST STRINGENT.
104. ALL MAINS AND CONTROL VALVES, INCLUDING THE WATER SUPPLY CONTROL VALVES, SHALL HAVE A SIGN INDICATING THE PORTION OF THE SYSTEM THAT IS CONTROLLED BY THE VALVE AND THE VALVE SHALL HAVE A IDENTIFICATION / VALVE TAG NUMBER. ALL ISOLATION VALVES SHALL BE ELECTRONICALLY
SUPERVISED BY TAMPER/WATER FLOW SWITCHES AND THEY SHALL INTERFACE WITH THE FIRE
ALARM/FIRE DETECTION SYSTEM.
105. WET PIPE SYSTEMS SHALL MEET THE FOLLOWING REQUIREMENTS:
A. A.WET PIPE SYSTEM SPRINKLER PIPES SHALL BE PERMITTED TO BE INSTALLED LEVEL MEETING THE
REQUIREMENTS OF NFPA 13, 2022 EDITION, SECTION 16.10.2.
B. ANY TRAPPED PIPING WHERE THE BRANCH LINES OR MAINS ARE LOCATED AT A LEVEL THAT CAN NOT
BE DRAINED AT THE WET PIPE ASSEMBLY DRAIN VALVE(S) SHALL MEET THE REQUIREMENTS OF NFPA 13, 2022 EDITION, SECTION 16.10.5 AND VA FIRE PROTECTION DESIGN MANUAL, SECTION 6.1.P.
C. PROVIDE AUXILIARY DRAIN WITH DRUM DRIP IN AN ACCESSIBLE LOCATION; WHERE, 2-INCH MINIMUM DRAIN SHALL BE PROVIDED AND SLOPED 1/2-INCH PER 10 FEET PER NFPA 13 AND VA FIRE PROTECTION
DESIGN MANUAL REQUIREMENTS.
106. ALL SPRINKLER HEADS SHALL BE QUICK RESPONSE PENDENT TYPE HEADS AND IF IN THE EXISTING BUILDING THERE IS A DIFFERENT TYPE THEN ALL SPRINKLER HEADS SHALL BE OF QUICK RESPONSE TYPE.
CONTRACTOR SHALL VERIFY EXISTING SPRINKLER HEAD TYPE BEFORE WORK BEGINS.
FIRE PROTECTION ABBREVIATIONS
WET PIPE
WIREGUARD
WELDED
WATER FLOW SWITCH
VOLTS
VALVE
US DEPT OF VETERANS AFFAIRS
UNDERGROUND
UNLESS NOTED OTHERWISE
UPRIGHT
UNDERWRITERS LABORATORY
TO BE DETERMINED
TYPICAL
TAMPER SWITCH
THREADED
TOP OF STEEL
TOP OF CONCRETE
STEEL
SQUARE FEET
SPECIAL
SPECIFICATION
SIDEWALL
SCREWED
SCHEDULE
ROOM
RESIDUAL
REDUCER
POUNDS PER SQUARE INCH
PRESSURE SWITCH
POST INDICATING VALVE
PHASE
PLUMBING
PENDANT
PLUMBING CONTRACTOR
PRE-ACTION VALVE
PRE-ACTION
ORDINARY HAZARD 2
ORDINARY HAZARD I
OUTSIDE SCREW AND YOKE
NATIONAL PIPE THREAD
NOT TO SCALE
NON RISING STEM
NOT APPLICABLE
NOT IN CONTRACT
NORMALLY OPENED
NORMALLY CLOSED
NATIONAL FIRE PROTECTION ASSOCIATION
MALLEABLE IRON
MEZZANINE
MECHANICAL JOINT
LEVEL
LIGHT HAZARD
LIGHTING
INSPECTOR TEST CONNECTION
INSPECTOR
INTERIOR
HEATING VENTING AND AIR CONDITIONING
HOSE CABINET
HOSE VALVE
HOSE REEL
WP
WG
WLD
FS
V
VAL
VA
UNO
UPR
UL
UG
TBD
TYP
TS
THRD
TOS
TOC
STL
SF
SP
SPEC
SW
SCR
SCH
RM
RES
RED
PSI
PS
PIV
PH
PLB
PEND
PC
PAV
PA
OH2
OH1
OS&Y
NPT
NTS
NRS
NA
NIC
NO
NC
NFPA
MI
MEZZ
MJ
LVL
LH
LTG
ITC
INSP
INT
HVAC
HC
HV
HR
HORSEPOWER
HYDRANT
GROOVED
GALLONS PER MINUTE
GROUND
GRADE
GENERAL CONTRACTOR
GALVANIZED
GAUGE
GALLONS
FLOW SWITCH
FIRE PROTECTION
FLOOR
FIRE ALARM
FLANGE
FINISH
FIRE HOSE VALVE
FIRE DEPARTMENT CONNECTION
FIRE ALARM
FACTORY MUTUAL GLOBAL
EXTINGUISHER
EXTERIOR
EXISTING
EXTRA HAZARD 2
EXTRA HAZARD 1
ELEVATION
ELECTRIC
ECCENTRIC
EXTENDED COVERAGE
ELBOW
EACH
EXISTING
DUCTILE IRON
DRY PIPE
DEPT OF DEFENSE
DEPARTMENT
DRAWING
DEGREE
DIAMETER
DRY
DOWN
CONCENTRIC
CONCRETE
CONTINUATION
CHECK
CEILING
CLASS
CAST IRON
BLACK
BUILDING
BOTTOM OF BEAM
BASEMENT
BACKFLOW PREVENTER
BELOW FINISH FLOOR
BELOW
ABOVE FINISHED GRADE
ABOVE FINISHED FLOOR
ABOVE CONCRETE
AUTOMATIC
AUTHORITY HAVING JURISDICTION
AMERICANS WITH DISABILITIES ACT
ABOVE
HP
HYD
GVD
GPM
GND
GR
GC
GALV
GA
GAL
FS
FP
FL
FA
FLG
FIN
FHV
FDC
FA
FM
EXT
EX
EXIST
EH2
EH1
EL
ELEC
ECC
EC
EL
EA
(E)
DI
DP
DOD
DEPT
DWG
DEG
DIA
D
DN
CON
CR
CONT
CHK
CLG
CL
CI
BLK
BLDG
BOB
BSMT
BFP
BFF
BEL
AFG
AFF
A/CONC
AUTO
AHJ
ADA
ABV
SPRINKLER NOTE
STATE, LOCAL, GOVERNING AND APPLICABLE CODES.
ALL WORK IS TO BE DONE IN ACCORDANCE WITH ALL
CERTIFICATION IN WATER BASED SYSTEM LAYOUT.
PROFESSIONAL ENGINEER OR A NICET LEVEL III OR IV
CALCULATIONS ARE TO BE SIGNED & SEALED BY A
LAYOUT & SIZING. SHOP DRAWINGS AND
INDICATING HYDRAULIC CALCULATIONS, PIPING
CONTRACTOR IS TO SUBMIT SHOP DRAWINGS
PIPE SIZING IN ACCORDANCE WITH NFPA 13.
PROVIDE HYDRAULIC CALCULATIONS FOR SYSTEM
OBTAIN CURRENT HYDRANT TEST DATA AND
. SPRINKLER CONTRACTOR IS TOONLYPURPOSES
SPRINKLER PLANS AS SHOWN ARE FOR BIDDING
1. INTERNATIONAL BUILDING CODE, 2021 EDITION
2. NFPA 13 - STANDARD FOR THE INSTALLATION OF SPRINKLER SYSTEMS 2022 EDITION
3. NFPA 25 - STNADARD FOR THE INSPECTION, TESTING, AND MAINTENANCE OF WATER-
BASED FIRE PROTECTION SYSTEMS, 2020 EDITION
4. NFPA 72 - NATIONAL FIRE ALARM & SIGNALING CODE, 2022 EDITION
5. NFPA 101 - LIFE SAFETY CODE, 2021 EDITION
6. NFPA 241 - STANDARD FOR SAFEGAURGING CONSTRUCTION, ALTERATION AND
DEMOLITION OPERATIONS, 2022 EDITION
7. NFPA 291 - RECOMMENDED PRACTICE FOR WATER FLOW TESTING VA FIRE PROTECTION
DESIGN MANUAL, EIGHTH EDITION
8. ANSI A117.1 STANDARD, ACCESSIBLE AND USUABLE BUILDING AND FACILITIES, 2017
EDITION
9. VA FIRE PROTECTION DESIGN MANUAL, EIGHTH EDITION
10. VA FIRE SAFETY REPRESENTATIVE
11. ALL AUTHORITIES HAVING JURISDICTION
ON THIS PROJECT:
SHALL BE REFERENCED FOR THE DESIGN OF THE FIRE PROTECTION SYSTEM
THE FOLLOWING PUBLICATIONS AND AUTHORITIES HAVING JURISDICTION
DESIGN CODES, STANDARDS & PARTIES OF REFERENCE
FIRE PROTECTION DESIGN CRITERIA
LIGHT HAZARD - OFFICES, CUSTOMARY ACCESS AREAS AND
RESTROOMS, AND IT TELECOMMUNICATION ROOMS
0.10GPM/SQ.FT
HYDRAULICALLY MOST DEMANDING AREA:
1/2INCH
225SQ.FT
100GPM
DESIGN DENSITY:
1,500SQ.FT
SPRINKLER ORIFICE:
MAXIMUM COVERAGE/SPRINKLER HEAD:
HOSE STREAM ALLOWANCE INSIDE/OUTSIDE:
K FACTOR: 5.6GPM/(PSI)
½
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
Engineering Discipline:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
B
IM
/2
.9
V A
F a y e tt e v ill e H a lls
W a lls
/2 .9
M E
P v
.r v t
/1
/2
:1
:3
P
M
FX001
FIRE SUPPRESSION - SYMBOLS,
LEGENDS, NOTES AND DRAWING INDEX
CHARLOTTE ENGINEERS, LLP
5838 MONROE ROAD, SUITE 100
CHARLOTTE, NC 28212
704-531-3000
MICHAEL EAVES
GUIDON
1221 N. PENNSYLVANIA STREET
INDIANAPOLIS, IN 46202
HALLS & WALLS
FAYETTEVILLE, NC
565-21-101
BLDG 1
07/14/2022 JRC ERF
100% BID DOCUMENTS
FULLY SPRINKLERED
317-800-6388
FIRE SUPRESSION - DRAWING INDEX
Sheet
Number Sheet Name
FX001 FIRE SUPPRESSION - SYMBOLS, LEGENDS, NOTES AND DRAWING INDEX
FX002 FIRE SUPPRESSION - DETAILS
FX003 FIRE SUPPRESSION - TEMPORARY AND IMPAIRMENT PROCEDURES
FX100A FIRE SUPPRESSION - BASEMENT RENOVATION PLAN - A WING
FX100B FIRE SUPPRESSION - BASEMENT RENOVATION PLAN - B & C WING
FX100C FIRE SUPPRESSION - BASEMENT RENOVATION PLAN - D WING
FX101A FIRE SUPPRESSION - FIRST LEVEL RENOVATION PLAN - A WING
FX101B FIRE SUPPRESSION - FIRST LEVEL RENOVATION PLAN - B & C WING
FX101C FIRE SUPPRESSION - FIRST LEVEL RENOVATION PLAN - D WING
NOTE :
CL
SUSPENDED CEILING TILE
(TYPE & COLOR BY ARCH.)
SPRINKLER HEAD
DRY PENDENT TYPE
WET SYSTEM WITH
DRY PENDENT
BRANCH REMOVE DROP NIPPLE
AND EXISTING
SPRINKLER. REPIPE
PIPING
CONFIGURATION
TYPICAL SPRINKLER HEAD RELOCATION
PIPE
AS SHOWN
ALTERNATE
SPRINKLER HEADS
NTS
SPRINKLER HEAD LOCATION
PIPE SUPPORT AND SEISMIC RESTRAINT -
HORIZONTAL PIPING
SEISMIC RESTRAINT COMPONENTS
(TYPICAL APPLICATIONS)
LC
1'-0"
CLAMP
BAR JOISTS
(AT 45 )
SEISMIC
TRANSVERSE
BRACE
PIPE
CLEVIS HANGER
NOTE:
ON WOOD ROOF
TRUSSES - USE
A CEILING FLANGE
OR ANGLE BRACKET
PROVIDE SEISMIC RESTRAINTS FOR PIPING AS FOLLOWS:
1" & 1-1/2" PIPES: 20 FT. ON CENTER
3/8" THREADED
ROD
BAR JOISTS
2" & 2-1/2" PIPES: 30 FT. ON CENTER
3" , 4" & 6" PIPES: 40 FT. ON CENTER
8" MIN
PART'L ACOUSTIC
CEILING TILE.
PENDANT TYPE
SP. HEAD
2'x2' ACOUSTIC
CEILING TILE.
SP. HEAD
PENDANT TYPE
2'x4' ACOUSTIC
CEILING TILE.
PENDANT TYPE
SP. HEAD
SP. HEAD
PENDANT TYPE
CEILING TILE.
2'x4' ACOUSTIC
1'-0"
1'-0"
1'-0"
2'-0"
1'-0"
1'-0"
TOLCO BAND HANGERS FIG. 200, 2NFPA,
TOLCO FIG. 25 SURGE RESTRAINER
TYPE 1- FOR USE WITH 1" AND 1 1/4"
PIPE AND HANGER.
TYPE 2- FOR USE WITH 1 1/2" AND 2"
PIPE AND HANGER
TOLCO FIG. 25 IS DESIGNED TO BE USED ONLY
TO RESTRICT UPWARD MOVEMENT OF PIPE WITHIN
THE HANGER AS IT OCCURS DURING SPRINKLER
HEAD ACTIVATION OR EARTHQUAKE TYPE ACTIVITY
TOLCO FIG.
909 OR 910
TOLCO U.L. LISTED ATTACHMENTS.
TOLCO FIG. 1000 FAST CLAMPS UNDERWRITERS
LBORATORIES LISTED, MUST BE USED WITH
PROVIDE TOLCO RESTRAINTS OR APPROVED
EQUAL AS REQUIRED.
SHOWN FLAT
TORQUE-TIGHTEN HEX
MINIMUM REQUIRED
NUTS UNTIL LEAF
NOTE: TO ASSURE
SPRING IS FLAT
NOTE:
BAND HANGER
TOLCO
USED IN LONGITUDINAL BRACE
PIPE CLAMP (TOLCO FIG. 4A)
(OPTIONAL METHOD)
LATERAL (TRANSVERSE)
BRACE
TOLCO
TOLCO FIG. 1000
LEAF SPRING
FAST CLAMP
FIG. 1000
909 OR 908
TOLCO FIG.
909 OR 910
TOLCO FIG.
CONFIGURATION AND
NUTS ARE TIGHTENED
ORIENTATION BEFORE
LEAF SPRING
LATERAL (TRANSVERSE) BRACE
FAST CLAMP
TOLCO FIG. 1000
LONGITUDINAL/4 WAY BRACE
(OPTIONAL METHOD)
909 OR 910
TOLCO FIG.
TOLCO FIG. 907
MAX.
TOLCO FIG. 1000
909 OR 910
TOLCO FIG.
3"
(2) FAST CLAMP
TOLCO FIG. 1000
TOLCO FIG. 1000
FASTCLAMP RISER BRACE
TOLCO FIG.
909 OR 910
1'-0"
CLAMP
BAR JOISTS
(AT 45 )
SEISMIC
TRANSVERSE
BRACE
PIPE
CLEVIS HANGER
ON WOOD ROOF
TRUSSES - USE
A CEILING FLANGE
OR ANGLE BRACKET
PROVIDE SEISMIC RESTRAINTS FOR PIPING AS FOLLOWS:
1" & 1-1/2" PIPES: 20 FT. ON CENTER
3/8" THREADED
ROD
BAR JOISTS
2" & 2-1/2" PIPES: 30 FT. ON CENTER
3" , 4" & 6" PIPES: 40 FT. ON CENTER
8" MIN
PART'L ACOUSTIC
CEILING TILE.
PENDANT TYPE
SP. HEAD
2'x2' ACOUSTIC
CEILING TILE.
SP. HEAD
PENDANT TYPE
2'x4' ACOUSTIC
CEILING TILE.
PENDANT TYPE
SP. HEAD
SP. HEAD
PENDANT TYPE
CEILING TILE.
2'x4' ACOUSTIC
1'-0"
1'-0"
2'-0"
1'-0"
WITH TOLCO BAND HANGERS FIG. 200, 2NFPA,
TOLCO FIG. 25 SURGE RESTRAINER
TYPE 1- FOR USE WITH 1" AND 1 1/4"
PIPE AND HANGER.
TYPE 2- FOR USE WITH 1 1/2" AND 2"
PIPE AND HANGER
TO RESTRICT UPWARD MOVEMENT OF PIPE WITHIN
THE HANGER AS IT OCCURS DURING SPRINKLER
HEAD ACTIVATION OR EARTHQUAKE TYPE ACTIVITY
TOLCO FIG.
909 OR 910
TOLCO U.L. LISTED ATTACHMENTS.
TOLCO FIG. 1000 FAST CLAMPS UNDERWRITERS
LBORATORIES LISTED, MUST BE USED WITH
PROVIDE TOLCO RESTRAINTS OR APPROVED
EQUAL AS REQUIRED.
SHOWN FLAT
TORQUE-TIGHTEN HEX
BAND HANGER
TOLCO
USED IN LONGITUDINAL BRACE
PIPE CLAMP (TOLCO FIG. 4A)
(OPTIONAL METHOD)
LATERAL (TRANSVERSE)
BRACE
TOLCO
TOLCO FIG. 1000
LEAF SPRING
FAST CLAMP
FIG. 1000
909 OR 908
TOLCO FIG.
909 OR 910
TOLCO FIG.
CONFIGURATION AND
NUTS ARE TIGHTENED
ORIENTATION BEFORE
LEAF SPRING
LATERAL (TRANSVERSE) BRACE
FAST CLAMP
TOLCO FIG. 1000
LONGITUDINAL/4 WAY BRACE
(OPTIONAL METHOD)
909 OR 910
TOLCO FIG.
TOLCO FIG. 907
MAX.
TOLCO FIG. 1000
909 OR 910
TOLCO FIG.
3"
(2) FAST CLAMP
TOLCO FIG. 1000
TOLCO FIG. 1000
FASTCLAMP RISER BRACE
TOLCO FIG.
909 OR 910
BEAM PIPE HANGER
R C
A B
-1
/2
COMPONENTS:
1. HEX NUT
2. LOCK WASHER
3. HANGER ROD
4. ADJUSTABLE HANGER RING
5. STEEL BEAM OR BAR JOIST
INCHES INCHES INCHES
NOMINAL
PIPE
SIZE
MINIMUM
A DIMENSION
HANGER
TAKEOUT
ROD
DIAMETER
1/2 3 +1/4 3/8
3/4 3 +1/4 3/8
1 3 +1/4 3/8
1 1/4 3 1/4 +0 3/8
1 1/2 3 1/2 +0 3/8
2 3 3/4 -1/4 3/8
2 1/2 4 3/4 -3/4 3/8
3 5 1 3/8
4 5 3/4 -1 1/2 3/8
5 6 1/2 -2 1/4 1/2
6 7 1/2 -3 1/2
8 9 -4 1/2 1/2
DESIGN DATA FOR BEAM HANGER
NTS
NTS
NTS
NTS
STANDARD C-CLAMP PIPE HANGER
DESIGN DATA FOR C-CLAMP HANGER
A
C R
1-1/8" or Bar Joist
6. Steel Beam
Ring
5. Adjustable Hanger
4. Hanger Rod
3. Lock Nut
2. Set Screw
1. C-Clamp
Components:
1/2-69 1/48
1/2-4 1/27 3/46
1/2-3 3/46 3/45
3/8-364
3/8-2 1/25 1/23
3/8-2 1/452 1/2
3/8-1 3/44 1/42
3/8-1 1/241 1/2
3/8-1 1/23 3/41 1/4
3/8-1 1/43 1/21
3/8-1 1/43 1/23/4
3/8-1 1/43 1/21/2
Diameter
Rod
Takeout
Hanger
A Dimension
Minimum
Size
Pipe
Nominal inchesinchesinches
NTS
PIPE SUPPORT AND SEISMIC RESTRAINT -
HORIZONTAL PIPING
BEAM PIPE HANGER
DETAIL OF SPRINKLER BRANCH
PIPING MODIFICATION
CONCRETE PIPE HANGER
CLAMP
BAR JOISTS
(AT 45 )
SEISMIC
TRANSVERSE
BRACE
PIPE
CLEVIS HANGER
NOTE:
ON WOOD ROOF
TRUSSES - USE
A CEILING FLANGE
OR ANGLE BRACKET
PROVIDE SEISMIC RESTRAINTS FOR PIPING AS FOLLOWS:
1" & 1-1/2" PIPES: 20 FT. ON CENTER
3/8" THREADED
ROD
BAR JOISTS
2" & 2-1/2" PIPES: 30 FT. ON CENTER
3" , 4" & 6" PIPES: 40 FT. ON CENTER
R C
A B
-1
/2
Components:
1. Hex Nut
2. Lock Washer
3. Hanger Rod
4. Adjustable Hanger
Ring
5. Steel Beam or Bar Joist inches inches inches
Nominal
Pipe
Size
Minimum
A Dimension
Hanger
Takeout
Rod
Diameter
1/2 3 +1/4 3/8
3/4 3 +1/4 3/8
1 3 +1/4 3/8
1 1/4 3 1/4 +0 3/8
1 1/2 3 1/2 +0 3/8
2 3 3/4 -1/4 3/8
2 1/2 4 3/4 -3/4 3/8
3 5 1 3/8
4 5 3/4 -1 1/2 3/8
5 6 1/2 -2 1/4 1/2
6 7 1/2 -3 1/2
8 9 -4 1/2 1/2
DESIGN DATA FOR BEAM HANGER
BRANCH PIPE
CEILING
REMOVE EXISTING PIPING
AND REPLACE WITH NEW
OR CUT BACK OR EXTEND
PIPING AS INDICATED ON
PLAN
COMPONENTS
1. DROP-IN ANCHOR
2. SPRING CLIP CEILING
PLATE (OPTIONAL)
3. HANGER ROD
4. ADJUSTABLE HANGER RING
5. CONTRACTOR IS RESPONSIBLE
FOR OBTAINING A LICENSED
STRUCTURAL ENGINEER ON ALL
HANGERS THAT PENETRATE
CONCRETE STRUCTURES AND THIS
CONTRACTOR SHALL SUBMIT
CALCULATIONS AND COMPLIANCE
LETTER MEETING NFPA 13
REQUIREMENTS WITH THE
PROFESSIONAL ENGINEER'S SEAL,
SIGNATURE AND DATE. ENGINEER
SHALL BE LICENSED AS A
PROFESSIONAL ENGINEER IN THE
STATE WHERE THE WORK SHALL
OCCUR.
B=5/8"
A
R
C
NOMINAL
PIPE SIZE
MINIMUM A
DIMENSION
INCHES
HANGER
TAKEOUT
ROD
DIAMETER QTY ITEMS
FASTENERS
* DRILL BIT SIZES REQUIRED: 1/2" FOR THE 3/8" ANCHOR AND 5/8" FOR THE 1/2"
ANCHOR. A MINIMUM CONCRETE SLAB THICKNESS OF 4" IS RECOMMENDED.
DESIGN DATA FOR CONCRETE HANGERS
6 1/2 7 1/2
-3 -3 3/4 -5 1/4
1/2
1 1/2" DROP-IN
ANCHOR -
HILTI HDI 1/2*
1/2 3/4 1 1/4 1 1/2 2 1/2
3 1/4 3 1/2 3 3/4 4 3/4 5 3/4
-1/2 -1/2 -1/2 -3/4 -1 -1 1/4 -1 3/4 -2 -2 1/2
3/8
3/8" DROP-IN
ANCHOR -
HILTI HDI 3/8*
ARM OVER WITH RECESSED
PENDENT HEAD
TYPICAL RETURN BEND DETAIL
1"
VARIES
VARIES
VARIES
1"
PER
MANUFACTURER'S
INSTRUCTIONS
CEILING
THREADED
STEEL
PIPING
RECESSED
PENDENT
HEAD WITH CHROME
FINISH AND WHITE
ESCUTCHEON
BRANCH
MAIN
QUICK RESPONSE RECESSED DRY PENDENT FOR ALL DRY SPRINKLER
AREAS OR AS NOTED. PROVIDE CHROME HEAD AND CHROME
ESCUTCHEON.
CEILING
BRANCH PIPE
CEILING
ON PLAN
PIPING AS INDICATED
OR CUT BACK OR EXTEND
AND REPLACE WITH NEW
REMOVE EXISTING PIPING
DETAIL OF SPRINKLER BRANCH PIPING
MODIFICATION
NTS
NTS
NTS
NTS
NTS
NTS
NTS
CEILING TILE
SUSPENDED T-BAR GRID
ADJUSTABLE HUB
1" NPT THREADS TO
ANSI B1.20.1
TYPE 304 SS
SCH. 40 PIPE
TYPE 304 SS CORRUGATED
HOSE, 1" TRUE-BORE
INTERNAL DIAMETER, TYPE
304 SS BRAID SLEEVE
TYPE 304 SS OUTLET SPUD WITH
1/2" INCH THREAD FEMALE NPT
THREADS TO ANSI B1.20.1
QUICK RESPONSE TYPE
RECESSED PENDENT
FOR LAY-IN CEILINGS
TYPICAL RECESSED SPRINKLER FLEX
RETURN BEND DETAIL
BRANCH
LINE
FLEXHEAD
SPRINKLER
DROP
CEILING GRID
MOUNTING
BRACKET
NTS
BRANCH PIPE
CEILING
ON PLAN
PIPING AS INDICATED
OR CUT BACK OR EXTEND
AND REPLACE WITH NEW
REMOVE EXISTING PIPING
DETAIL OF SPRINKLER BRANCH PIPING
MODIFICATION
NTS
SPRINKLER HEAD DETAIL
REDUCER
1" DROP NIPPLE
NEW SPRINKLER HEAD
CEILING PLATE
SUSPENDED CEILING
EXISTING
BRANCH
LINE
INCREASER
REMOVE EXISTING
SPRINKLER HEAD
AND
REPIPE AS
SHOWN
NTS
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
Engineering Discipline:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
B
IM
/2
.9
V A
F a y e tt e v ill e H a lls
W a lls
/2 .9
M E
P v
.r v t
/1
/2
:1
:3
P
M
FX002
FIRE SUPPRESSION - DETAILS
CHARLOTTE ENGINEERS, LLP
5838 MONROE ROAD, SUITE 100
CHARLOTTE, NC 28212
704-531-3000
MICHAEL EAVES
GUIDON
1221 N. PENNSYLVANIA STREET
INDIANAPOLIS, IN 46202
HALLS & WALLS
FAYETTEVILLE, NC
565-21-101
BLDG 1
07/14/2022 JRC ERF
100% BID DOCUMENTS
FULLY SPRINKLERED
317-800-6388
PROCEDURES FOR DRAINING WET
PIPE SYSTEM
1. TO DRAIN A WET PIPE SYSTEM THE PROCEDURE TO BE PERFORMED AND
SUBMITTED TO THE ARCHITECT, ENGINEER, AND OWNER'S
REPRESENTATIVE SHOULD INCLUDE BUT NOT LIMITED TO THE
FOLLOWING.
1.1. CLOSE ALL SPRINKLER CONTROL VALVES.
1.2. TAG ALL CLOSED VALVES.
1.3. OPEN MAIN DRAIN VALVES AND AUXILIARY DRAINS ALLOWING THE
SYSTEM FOR 100% COMPLETE DRAINAGE.
1.4. WHEN THE WATER HAS BEEN COMPLETELY DRAINED, CLOSE THE
MAIN DRAIN AND AUXILIARY DRAIN VALVES. WHEN THE WATER
HAS STOPPED FLOWING, CHECK ALL CONTROL VALVES TO BE
SURE THEY ARE TIGHTLY SHUT; ANY MALFUNCTION CONTROL
VALVES SHOULD BE REPAIRED AND/OR REPLACED IMMEDIATELY
AS DEEMED APPLICABLE.
1.5. CHECK FOR WATER TRAPPED AT ALL LOW POINTS IN PIPING THAT
LACK AUXILIARY DRAINS; REMOVE DRAIN AND REPLACE SUCH
PIPING.
1.6. ONCE ABOVE ITEM ARE CONFIRMED WITH 100% CERTAINTY THE
CONTRACTOR SHALL PERFORM ALL NEW INSTALLATIONS.
1. MINIMUM REQUIREMENTS
A. THE CONTRACTOR SHALL ENACT MEASURES THAT SHALL BE TAKEN DURING THE IMPAIRMENT
TO ENSURE THAT INCREASED RISKS ARE MINIMIZED AND THE DURATION OF THE IMPAIRMENT IS
LIMITED.
B. THE CONTRACTOR SHALL NOTIFY IN WRITING TO THE ARCHITECT, ENGINEER, OWNER AND ANY
JURISDICTION HAVING AUTHORITY OF THE PLANNED IMPAIRMENT, PROCEDURES DURING THE
IMPAIRMENT, TESTING RE-COMMISSIONING OF THE PRE-ACTION FIRE PROTECTION/FIRE ALARM
SYSTEMS FOR PROTECTION OF THE AFFECTED LOCATIONS WITHIN THE SCOPE OF WORK
SUITE.
C. THE CONTRACTOR THROUGH THE OWNER SHALL PREPARE AND SUBMIT TO THE OWNER FOR
OWNER'S DISTRIBUTION TO THE EMPLOYEES IN THE AREA OF THE IMPAIRMENT SHALL BE
PROVIDED WITH INFORMATION ON ALTERNATE FIRE PROTECTION THAT WILL BE AVAILABLE.
D. THE SUSPENSION OF ALL NON-ESSENTIAL HOT WORK PERMITS UNTIL THE CONCLUSION AND
REACTIVATION OF THE PRE-ACTION FIRE SUPPRESSION SYSTEM AND INTERFACING FIRE
DETECTION SYSTEM.
2. FIRE PROTECTION IMPAIRMENT PLAN
A. A FIRE PROTECTION IMPAIRMENT PLAN SHOULD BE DEVELOPED AND IMPLEMENTED BEFORE
AUTHORIZATION IS GIVEN, THE IMPAIRMENT COORDINATOR SHOULD VERIFY THAT THE
FOLLOWING PROCEDURES HAVE BEEN IMPLEMENTED:
• THE EXTENT AND EXPECTED DURATION OF THE IMPAIRMENT THAT HAS BEEN DETERMINED.
• THE AREA OF THE BUILDING THAT WILL BE AFFECTED HAS BEEN INSPECTED AND THE
INCREASED RISKS DETERMINED.
• RECOMMENDATIONS HAVE BEEN SUBMITTED TO THE ARCHITECT, ENGINEER AND OWNER
OR OWNER'S REPRESENTATIVE TO MITIGATE ANY INCREASED RISKS.
• WHERE A REQUIRED FIRE PROTECTION SYSTEM IS OUT OF SERVICE FOR MORE THAN TEN
HOURS IN A 24 HOUR PERIOD THE CONTRACTOR & OWNER SHALL ARRANGE FOR THE
FOLLOWING:
• AN APPROVED FIRE WATCH.
• ESTABLISHMENT AND IMPLEMENTATION OF AN APPROVED PROGRAM TO ELIMINATE
POTENTIAL IGNITION SOURCES AND LIMIT OF THE AMOUNT OF COMBUSTIBLES IN THE
AREA OF CONSTRUCTION.
• ASSIGN PERSONNEL TO TRANSMIT FIRE ALARMS TO THE OWNER'S HOSPITAL
COORDINATOR WHERE THE MAIN FIRE ALARM PANEL IS BEING MONITORED FOR 24/7
COVERAGE.
3. TAG IMPAIRMENT SYSTEM
A. A TAG SHALL BE USED TO INDICATE THAT A SYSTEM OR PART THERE OF, HAS BEEN REMOVED
FROM SERVICE. THE CONTRACTOR SHALL PLACE TAGS ON ALL AFFECTED COMPONENTS, E.G.,
TAMPER SWITCHES, VALVES, FIRE ALARM ANNUNCIATOR DEVICES, ETC., PRIOR TO THE
COMMENCEMENT OF ANY WORK.
B. THE TAG SHALL BE POSTED AT EACH FIRE PROTECTION CONNECTION AND SYSTEM CONTROL
VALVE AND OTHER LOCATION REQUIRED BY THE OWNER'S REPRESENTATIVE OR ANY AND ALL
AUTHORITIES HAVING JURISDICTION, INDICATING WHICH SYSTEM, OR PART THERE OF, HAS
BEEN REMOVED FROM SERVICE.
• THE SUPERVISORS IN THE AREA TO THE AFFECTED AREA HAS BEEN NOTIFIED.
• THE FIRE DEPARTMENT HAS BEEN NOTIFIED.
• A TAG IMPAIRMENT SYSTEM HAVE BEEN IMPLEMENTED.
• ALL NECESSARY TOOLS, EQUIPMENT, MATERIAL AND APPURTENANCES ARE LOCATED AND
ASSEMBLED ON THE IMPAIRMENT SITE.
4. RESTORING SYSTEMS TO SERVICE
A. WHEN ALL IMPAIRED EQUIPMENT IS RESTORED TO NORMAL WORKING ORDER, THE ARCHITECT/
ENGINEER SHALL VERIFY THAT THE CONTRACTOR HAS IMPLEMENTED THE FOLLOWING
PROCEDURES:
• ALL NECESSARY INSPECTION HAVE BEEN CONDUCTED FOLLOWING NFPA 13, 25 AND 72
REQUIREMENTS IN ORDER TO VERIFY THAT THE AFFECTED SYSTEM ARE OPERATION.
CONTRACTOR SHALL SUBMIT ALL REQUIRED RECORDS AND RECORDS SHALL INDICATE THE
PROCEDURE PERFORMED, THE ORGANIZATION THAT PERFORMED THE WORK, RESULTS
AND THE DATE.
• OPEN ALL VALVES THAT WERE SECURED DURING THE IMPAIRMENT.
• REMOVE IMPAIRMENT TAG ONCE VALVES ARE OPEN.
• CONDUCT A DRAIN TEST IN THE WIDE OPEN POSITION.
• ENSURE THE FIRE PROTECTION SYSTEM IS PLACED BACK TO "AUTOMATIC" SERVICE.
• RESET FIRE ALARM SYSTEM AND NOTIFY OWNER'S REPRESENTATIVE AND FIRE ALARM
COMPANY THAT MONITORS THE OWNER'S MAIN FIRE ALARM PANEL ON 24/7 COVERAGE.
• ARCHITECT, ENGINEER AND OWNERS REPRESENTATIVE HAVE BEEN ADVISED THAT THE
FIRE PROTECTION AND FIRE DETECTION SYSTEM THAT WAS IMPAIRED HAS BEEN
RESTORED.
• THE OWNER'S REPRESENTATIVE OR DESIGNATED REPRESENTATIVE, FIRE ALARM COMPANY
WHO MONITORS THE MAIN FIRE ALARM PANEL FOR 24/7 COVERAGE AND ALL OTHER
JURISDICTIONS HAVE BEEN ADVISED THAT BOTH FIRE PROTECTION SYSTEMS IS RESTORED.
• THE IMPAIRMENT TAG HAS BEEN REMOVED.
PROCEDURES FOR IMPAIRMENT TO THE FIRE PROTECTION
SYSTEM
FIRE WATCH PROCEDURES AND REQUIREMENTS
A. THE FIRE WATCH PERSONNEL SHALL BE TRAINED TO UNDERSTAND THE INHERENT HAZARDS OF THE
WORK SITE AND OF THE HOT WORK TO OCCUR.
B. THE FIRE WATCH SHALL ENSURE THAT SAFE CONDITIONS ARE MAINTAINED DURING OUTAGE OF THE
FIRE ALARM/FIRE SUPPRESSION SYSTEM AND/OR DURING THE OCCURRENCE OF HOT WORK
OPERATION.
C. THE FIRE WATCH SHALL HAVE THE AUTHORITY TO STOP HOT WORK OPERATIONS IF UNSAFE
OPERATIVE DEVELOPS.
D. THE FIRE WATCH SHALL HAVE FIRE EXTINGUISHING EQUIPMENT READILY AVAILABLE AND TRAINED IN
ITS USE, E.G., FIRE EXTINGUISHERS.
E. THE FIRE WATCH SHALL BE FAMILIAR WITH OWNER'S FACILITIES AND PROCEDURES FOR SOUNDING
AN ALARM IN THE EVENT OF A FIRE.
F. THE FIRE WATCH SHALL WATCH FOR FIRES IN ALL EXPOSED AREAS AND TRY TO EXTINGUISH A FIRE ONLY WHEN THE FIRES ARE OBVIOUSLY WITHIN THE CAPACITY OF THE AVAILABLE EXTINGUISHING EQUIPMENT. IF THE FIRE WATCH DETERMINES THAT THE FIRE IS NOT WITHIN THE CAPACITY OF THE EQUIPMENT THE FIRE WATCH SHALL SOUND AN ALARM IMMEDIATELY (E.G.,INITIATE A MANUALLY ACTUATED ALARM INDICATING DEVICE THAT IS OUTSIDE OF THE CONSTRUCTION AREA DURING THE DISRUPTION OF THE FIRE ALARM/DETECTION WITHIN THE CONSTRUCTION WORK SCOPE OR WITHIN THE CONSTRUCTION WORK SCOPE IF THE FIRE ALARM/DETECTION SYSTEM HAS BEEN ACTIVATED).
G. BEFORE STARTING ANY HOT WORK, CONTRACTORS AND THEIR OWNERS SHALL DISCUSS THE
PLANNED PROJECT COMPLETELY INCLUDING THE TYPE OF HOT WORK TO BE CONDUCTED AND THE HAZARDS IN THE AREA WITH THE ASSOCIATED PLAN OF ACTION, IN ORDER, TO PROVIDE EQUIVALENT
SAFETY MEASURES TAKEN DURING THE FIRE DETECTION OR FIRE SUPPRESSION IMPAIRMENT.
FIRE PROTECTION DEMOLITION GENERAL NOTES
A. EXISTING FIRE SPRINKLERS SHALL REMAIN IN SERVICE AS LONG AS POSSIBLE, WHILE DEMOLITION WORK IS IN PROGRESS. ANY DISRUPTIONS IN THE FIRE SPRINKLER SYSTEM SERVICE SHALL BE
PROVIDED WITH AN APPROVED FIRE WATCH OR STANDBY PERSONNEL.
B. REMOVE ALL EXISTING FIRE SPRINKLERS IN THE AREAS INDICATED ON THIS SHEET AND CUT AND CAP THE PIPING BACK TO THE CONNECTION OF THE ARM OVER . FOR FLEXIBLE HOSE CONNECTIONS, REUSE OF THE FLEXIBLE HOSE IS AT THE CONTRACTOR'S RISK; CAP THE OPEN PIPE AT THE FLEXIBLE HOSE
CONNECTION TO THE SPRINKLER PIPING.
C. EXISTING FIRE SPRINKLER SYSTEM SHALL REMAIN IN SERVICE AS LONG AS POSSIBLE WHILE THE
DEMOLITION WORK IS IN PROGRESS.
D. FIRE SUPPRESSION SPRINKLERS SHALL BE REPLACED, RELOCATED AND/OR ADDED IN ACCORDANCE
WITH THE REQUIREMENTS FOR NFPA 13.
E. EXISTING FIRE SUPPRESSION SUPPLY SHALL BE DRAINED PRIOR TO ANY DEMOLITION WORK ON THE WET PIPE SPRINKLER SUPPLY FROM THE INDIVIDUAL FLOOR CONTROL VALVE TO THE MOST REMOTE
SPRINKLER HEAD.
F. EXISTING FLOOR CONTROL VALVE SHALL BE SECURED / CLOSED FOR DEMOLITION AND NEW WORK.
G. ALL WORK SHALL BE PERFORMED SO AS TO NOT INTERRUPT SERVICE TO THE ENTIRE AFFECTED FLOOR.
THE CONTRACTOR SHALL PROPERLY NOTIFY THE VA COR AS APPLICABLE A MINIMUM OF 1 WEEK IN
ADVANCE BEFORE PROCEEDING WITH THIS WORK.
H. REMOVE ALL UNUSED AND DEMOLISHED EQUIPMENT AND ASSOCIATED MATERIAL FROM THE SITE.
ABANDONING UNUSED PORTIONS WILL NOT BE ACCEPTABLE. VA COR SHALL HAVE THE RIGHT OF REFUGE OWNERSHIP OF ALL DEMOLISHED AND UNUSED PORTION OF EQUIPMENT AND MATERIALS.
I. AVOID DAMAGING EXISTING SURFACES AND EQUIPMENT AND ASSOCIATED MATERIALS FROM THE SITE.
REPAIR ANY DAMAGE CAUSED DURING WORK AT NO EXTRA COST TO THE VA COR.
J. ALL SYSTEMS ARE TO BE LEFT IN SERVICE PRIOR TO THE END OF EACH WORKDAY.
K. REMOVE ANY CEILING TILES, GRID, AND LIGHT FIXTURES REQUIRED TO ACCOMPLISH THE WORK.
REPLACE SAME AFTER THE INSTALLATION IS COMPLETE. IT IS THE CONTRACTOR’S RESPONSIBILITY TO
REPLACE ANY ITEMS DAMAGED DURING CONSTRUCTION.
L. MODIFY EXISTING SPRINKLER SYSTEM, RELOCATE AND/OR PROVIDE ADDITIONAL SPRINKLERS, PIPING, HANGERS, ETC., COORDINATE WITH WALLS, CEILINGS, LIGHTS, DIFFUSERS, STRUCTURE, OBSTRUCTIONS, ETC., IN AREAS AFFECTED BY THE SCOPE OF WORK.
M. REMOVE ALL ABANDONED PIPING, WET SPRINKLERS, FITTINGS, HANGERS, ETC., FROM THE PROJECT
LOCATION. DISPOSE OF ALL MATERIAL LEGALLY TO AN APPROVED DISPOSAL SITE.
N. THE CONTRACTOR SHALL FIELD VERIFY ALL EXISTING ELECTRICAL LINES, PLUMBING LINES, DUCTWORK OR MECHANICAL PIPING LOCATED IN THE CEILING SPACE, WALLS OR FLOOR PRIOR TO SAW CUTTING OR ANY CORE DRILLING. IT IS THE CONTRACTOR’S RESPONSIBILITY TO REPAIR SUCH ITEMS DAMAGED.
O. FIRE SPRINKLER SYSTEM(S) NOT ASSOCIATED WITH THE DEMOLITION SHALL BE LEFT IN SERVICE AS
APPLICABLE.
P. COORDINATE SPRINKLER SYSTEM MODIFICATIONS TO MINIMIZE SYSTEM IMPAIRMENT. PROVIDE FIRE WATCH AND INTERIM FIRE PROTECTION MEASURES WHERE REQUIRED BY THE AUTHORITY HAVING
JURISDICTION OR THE VA COR.
Q. ALL SHUTDOWNS SHALL BE COORDINATED AND APPROVED THROUGH THE COR'S REPRESENTATIVE AND SHALL REQUIRE A MINIMUM OF 15 DAYS ADVANCED NOTICE, THIS TIME LENGTH MAY BE LONGER OF
SHORTER FOR SOME SHUTDOWNS AND SHALL BE AT THE VA COR'S DISCRETION. DRAINING AND
REFILLING OF THE EXISTING SYSTEM IS A RESPONSIBILITY OF THE CONTRACTOR.
R. ALL DISRUPTIONS IN THE FIRE SUPPRESSION SYSTEM SHALL BE COMPENSATED WITH AN APPROVED
FIRE WATCH AND STANDBY PERSONAL.
TEMPORARY FIRE ALARM, FIRE EXTINGUISHERS AND FIRE SUPPRESSION REQUIREMENTS
A. THE CONTRACTOR SHALL BE REQUIRED TO HAVE AN OVERALL FIRE SAFETY PROGRAM THAT SHALL
INCLUDE:
B. GOOD HOUSEKEEPING
C. FIRE PROTECTION SERVICES AS FOLLOWS:
a. DURING DEMOLITION OF EXISTING SCOPE OF WORK AREA OF EXISTING SYSTEMS DURING
DEMOLITION SHALL BE KEPT FULLY OPERATIONAL AS LONG AS FEASIBLY POSSIBLE AND KEEP
DISRUPTIONS TO FIRE ALARM AND FIRE SPRINKLER SYSTEM SHALL BE KEPT TO A MINIMUM.
• COORDINATE REQUIREMENTS AND RESPONSIBILITIES WITH VA FIRE SAFETY REPRESENTATIVE ON RESPONSIBILITIES OF FIRE FIGHTING OR CONTACTING OF LOCAL FIRE…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .