Draft Submittal Log 565-21-101 Halls and Walls.pdf

PDF 744 KB Posted

Attached to
Z1DA--Renovate Halls and Walls Basement and First Floor
Solicitation number
36C24623B0041
Issued by

About this file

This document contains a submittal log for a renovation project at a Veteran Affairs medical center. It lists over 100 submittal items required from the contractor, including plans, schedules, shop drawings, samples, manuals, and certifications. Submittals cover general requirements, safety, carpentry, firestopping, sealants, glazing, flooring, ceilings, wall protection, plumbing, HVAC, electrical, communications, fire alarm and detection systems. Due dates range from 10 days after bid acceptance to 15 days after project completion. The related federal contract opportunity is to renovate halls and walls on the basement and first floors of the Fayetteville VA Medical Center in North Carolina.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PHASING SCHEDULE

Halls and Walls 1 st Floor Building 1

Fayetteville NC

Bid Documents Submission

July 14, 2022

Client Project No. 565-21-101

Guidon Project No. 21.9001 lsplichal Text Box Submittal Log

NUMBER Name REFERENCE Description WHEN

01 00 00 GENERAL REQUIREMENTS-

Construction Security

Requirements

1.5.A General Contractor shall submit a security plan that defines both physical and administrative procedures that will remain effective for the entire duration of the project.

01 00 00 GENERAL REQUIREMENTS-

Document Control

1.5.E General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”

01 00 00 GENERAL REQUIREMENTS-

Phasing

1.5.I Contractor shall furnish the COR with a schedule of approximate phasing dates on which the

Contractor intends to accomplish work in each specific area of site, building or portion thereof

01 00 00 GENERAL REQUIREMENTS-

Utilities Services

1.5.N.2 Contractor shall submit a request to interrupt any such services 7 days in advance of proposed interruption

01 00 00 GENERAL REQUIREMENTS-

Survey

1.7.A Contractor shall make a thorough survey with the COR and a representative of VA Supply

Service of buildings, areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report

01 00 00 GENERAL REQUIREMENTS-

As-Built Drawings

1.14.C Contractor shall deliver two approved completed sets of as-built drawings in the electronic version

15 days after each completed phase

01 32 16.15 PROJECT SCHEDULES-

Contractor's Consultant

1.3.A Contractor shall submit a qualification proposal to the COR, within 10 days of bid acceptance.

10 days within bid acceptance.

01 32 16.15 PROJECT SCHEDULES- The

Complete Project Schedule

Submittal

1.5.A Contractor shall submit for the COR review; three blue line copies of the interim schedle on

30x42 inch and an electronic file.

Within 45 calendar days after receipt of NTP.

01 32 16.15 PROJECT SCHEDULES- The

Complete Project Schedule

Submittal

1.5.D Contractor shall submit to the COR; the final project schedule. Within 30 calendar days after receipt of the complete project interim schedule.

01 33 23 SHOP DRAWINGS, PRODUCT

DATA, AND SAMPLES- Submittal

Register

1.3 Submit samples required by Section 09 06 00, SCHEDULE FOR FINISHES, in quadruplicate.

Submit other samples in single units unless otherwise specified. Submittals will receive consideration only when covered by a transmittal letter signed by Contractor. Submittal drawings (shop, erection or setting drawings) and schedules, required for work of various trades, shall be checked before submission by technically qualified employees of Contractor for accuracy, completeness and compliance with contract requirements. For each drawing required, submit one legible photographic paper or vellum reproducible. Reproducible shall be full size and each drawing shall have marked thereon, proper descriptive title.

Reproducible shall be full size. Samples, shop drawings, test reports, certificates and manufacturers' literature and data, shall be submitted.

01 35 26 SAFETY REQUIREMENTS-

Submittals

1.4.C Submit the APP for review for compliance with contract requirements in accordance with

Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES

01 35 26 SAFETY REQUIREMENTS-

AHA

1.5.C.3 Submit AHA for review for compliance with contract requirements in accordance with

Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES for review

01 35 26 SAFETY REQUIREMENTS-

Infection Control

1.12.F Prepare a plan detailing project-specific dust protection measures with associated product data, including periodic status reports

01 35 26 SAFETY REQUIREMENTS-

Fire Safety

1.14.A Prior to start of work, prepare a plan detailing project-specific fire safety measures, including periodic status reports

06 10 00 ROUGH CARPENTRY-

Manufacturer’s Literature and

Data

1.3.D Submit data for lumber, panels, hardware and adhesives

06 10 00 ROUGH CARPENTRY-

Certificates

1.3.E Manufacturer’s certificate for unmarked lumber

07 84 00 FIRESTOPPING-

Qualifications

1.3.C Installer qualifications

07 84 00 FIRESTOPPING-

Qualifications

1.3.D Inspector qualifications

07 84 00 FIRESTOPPING-

Certified laboratory test reports

1.3.E ASTM E814 tests for systems not listed by FM, UL, or WH proposed for use

07 84 00 FIRESTOPPING-

Certificates

1.3.F from manufacturer attesting that firestopping materials comply with the specified requirements

07 84 00 FIRESTOPPING-

Inspections and Acceptance of

Work

3.5 Submit written reports indicating locations of and types of penetrations and type of firestopping used at each location; type is to be recorded by UL listed printed numbers

07 92 00 JOINT SEALANTS-

Qualifications

1.5.C Installer qualifications

07 92 00 JOINT SEALANTS-

Qualifications

1.5.D Contractor certification

07 92 00 JOINT SEALANTS-

Product Data

1.5.E Manufacturer's installation instructions for each product used

07 92 00 JOINT SEALANTS-

Samples

1.5.F Cured samples of exposed sealants for each color

07 92 00 JOINT SEALANTS-

Warranty

1.5.G Manufacturer warranty

08 41 13 ALUMINUM-FRAMED

ENTRANCES AND STOREFRONTS-

1.5.B Shop drawings showing size, configuration, fabrication, and installation details

08 41 13 ALUMINUM-FRAMED

ENTRANCES AND STOREFRONTS-

1.5.C Manufacturer's Literature and Data

08 80 00 GLAZING- Submittals 1.5.A Manufacturer's Certificates

08 80 00 GLAZING- Submittals 1.5.B Manufacturer's Warranty

08 80 00 GLAZING- Submittals 1.5.C Manufacturer's Literature and Data

08 80 00 GLAZING- Submittals 1.5.D Samples

09 05 16 SUBSURFACE PREPARATION

FOR FLOOR FINISHES-

Submittals

1.3.C Product Data

09 22 16 NON-STRUCTURAL METAL

FRAMING-

Manufacturer's Literature and

Data

1.4.B Studs, runners and accessories

09 22 16 NON-STRUCTURAL METAL

FRAMING-

Manufacturer's Literature and

Data

1.4.B Hanger inserts

09 22 16 NON-STRUCTURAL METAL

FRAMING-

Manufacturer's Literature and

Data

1.4.B Channels (Rolled steel)

09 22 16 NON-STRUCTURAL METAL

FRAMING-

Manufacturer's Literature and

Data

1.4.B Furring channels

09 22 16 NON-STRUCTURAL METAL

FRAMING-

Manufacturer's Literature and

Data

1.4.B Screws, clips and other fasteners

09 29 00 GYPSUM BOARD- Submittals 1.4.B Manufacturer's Literature and Data

09 30 13 CERAMIC/PORCELAIN TILING-

Submittals

1.3.B Samples

09 30 13 CERAMIC/PORCELAIN TILING-

Submittals

1.3.C Procduct data

09 51 00 ACOUSTICAL CEILINGS-

Submittals

1.5.B.1 Show size, configuration, fabrication, and installation details

09 51 00 ACOUSTICAL CEILINGS-

1.5.C Manufacturer's Literature and Data

09 65 13 RESILIENT BASE AND

ACCESSORIES- Submittals

1.5.B Manufacturer's Literature and Data

09 65 13 RESILIENT BASE AND

ACCESSORIES- Submittals

1.5.C Samples

09 65 16 RESILIENT SHEET FLOORING-

Submittals

1.4.B Manufacturer's Literature and Data

09 65 16 RESILIENT SHEET FLOORING-

Submittals

1.4.C Samples

09 65 19 RESILIENT TILE FLOORING-

Submittals

1.3.B Manufacturer's Literature and Data

09 65 19 RESILIENT TILE FLOORING-

Submittals

1.3.C Samples of each type, color, thickness, and finish.

09 65 19 RESILIENT TILE FLOORING-

Submittals

1.3.D Shop drawings indicating layout of patterns as shown on construction documents.

09 68 00 CARPETING- Submittals 1.4.B Product data

09 68 00 CARPETING- Submittals 1.4.C Samples

09 91 00 PAINTING-

Painter qualifications

1.3.B Painter Qualifications.

09 91 00 PAINTING-

Manufacturer's Literature and

Technical Data

1.3.C Manufacturer's Literature and Data

09 91 00 PAINTING-

Sample Panels

1.3.D After painters' materials have been approved and before work is started submit sample panels showing each type of finish and color specified

09 91 00 PAINTING-

Sample Panels

1.3.D Panels to Show Color: Composition board, 100 x 250 mm (4 x 10 inch)

09 91 00 PAINTING-

Sample Panels

1.3.D Panel to Show Transparent Finishes: Wood of same species and grain pattern as wood approved for use, 100 x 250 mm (4 x 10 inch face) minimum, and where both flat and edge grain will be exposed, 250 mm (10 inches) long by sufficient size, 50 x 50 mm (2 x 2 inch) minimum or actual wood member to show complete finish

09 91 00 PAINTING-

Sample Panels

1.3.D Attach labels to panel stating the following

09 91 00 PAINTING-

Sample Panels

1.3.D Federal Specification Number or manufacturers name and product number of paints used

09 91 00 PAINTING-

Sample Panels

1.3.D Specification code number specified in Section 09 06 00, SCHEDULE FOR FINISHES

09 91 00 PAINTING-

Sample Panels

1.3.D Product type and color

09 91 00 PAINTING-

Sample Panels

1.3.D Name of project

09 91 00 PAINTING-

Samples

1.3.D Sample of identity markers if used

10 26 00 WALL AND DOOR PROTECTION-

Submittals

1.4.C Shop drawings indicating design and installation details

10 21 23 WALL AND DOOR PROTECTION-

Submittals

1.3.D Manufacturer's Literature and Data

12 36 00 COUNTERTOPS- Submittals 1.3.B Shop drawings showing dimensions of section and methiod of assembly

12 36 00 COUNTERTOPS- Submittals 1.3.C Samples

21 13 13 WET-PIPE SPRINKLER SYSTEMS-

Qualifications

1.4.A.1 Provide a copy of the installing contractors fire sprinkler and state contractor's license.

21 13 13 WET-PIPE SPRINKLER SYSTEMS-

Drawings

1.4.A.2 Submit detailed 1:100 (1/8 inch) scale (minimum) working drawings, include graphical scales that allow the user to determine lengths when the drawings are reduced in size, plan showing the piping to the water supply test location

21 13 13 WET-PIPE SPRINKLER SYSTEMS-

Manufacturer’s Data Sheets

1.4.A.3 data sheets for all materials and equipment proposed for use on the system, include listing information and installation instructions in data sheets

21 13 13 WET-PIPE SPRINKLER SYSTEMS-

Final Document Submittals

1.4.A.4 Provide as-built drawings, testing and maintenance instructions, complete set of as-built drawings showing the installed system with specific interconnections, one full size (or size as directed by the COR) printed copy, one complete set in electronic pdf format, one complete set in AutoCAD format or a format as directed by the COR

21 13 13 WET-PIPE SPRINKLER SYSTEMS-

Material and Testing Certificate

1.4.A.4.a Provide a copy of a completed Material and Testing Certificate as indicated in NFPA 13, certificates shall be provided to document all parts of the installation

Upon completion of the sprinkler system installation

21 13 13 WET-PIPE SPRINKLER SYSTEMS-

Material and Testing Certificate

1.4.A.6.a One paper copy in a binder provided in pdf format on a compact disc or as directed by the

COR

21 13 13 WET-PIPE SPRINKLER SYSTEMS-

Operations and Maintenance

Manual

1.4.A.6.c One additional copy of the O&M Manual covering the system in a flexible protective cover

22 40 00 PLUMBING FIXTURES-

Submittals

1.4.C Manufacturer's Literature and Data

23 05 11 GENERAL WORK RESULTS FOR

HVAC-

Documentation

1.4.E If equipment is submitted which differs in arrangement from that shown, provide documentation proving equivalent performance, design standards and drawings that show the rearrangement of all associated systems. Additionally, any impacts on ancillary equipment or services such as foundations, piping, and electrical shall be the Contractor’s responsibility to design, supply, and install at no additional cost or time to the Government.

23 05 11 GENERAL WORK RESULTS FOR

HVAC-

Certification

1.4.F certify in writing that manufacturers of all major items of equipment have each reviewed contract documents, and have jointly coordinated and properly integrated their equipment and controls to provide a complete and efficient installation

Prior to submitting shop drawings

23 05 11 GENERAL WORK RESULTS FOR

HVAC-

Shop Drawings

1.4.G for interdependent items, containing applicable descriptive information, shall be furnished together. Coordinate and properly integrate materials and equipment to provide a completely compatible and efficient installation

23 05 11 GENERAL WORK RESULTS FOR

HVAC-

O&M Manuals

1.4.I Complete operating and maintenance manuals including wiring diagrams, technical data sheets, information for ordering replacement parts, and troubleshooting guide. Provide a listing of recommended replacement parts for keeping in stock supply, including sources of supply, for equipment. Include in the listing belts for equipment: Belt manufacturer, model number, size and style, and distinguished whether of multiple belt sets.

23 36 00 AIR TERMINAL UNITS-

Submittals

1.4.B Manufacturer's Literature and Data

23 36 00 AIR TERMINAL UNITS-

Submittals

1.4.C Certificates

23 36 00 AIR TERMINAL UNITS-

Submittals

1.4.D O&M manuals

23 37 00 AIR OUTLETS AND INLETS-

Submittals

1.4.B Manufacturer's Literature and Data

26 05 11 REQUIREMENTS FOR

ELECTRICAL INSTALLATIONS-

Shop Drawings

1.12.E.2 Elementary and interconnection wiring diagrams for communication and signal systems, control systems, and equipment assemblies

26 05 11 REQUIREMENTS FOR

ELECTRICAL INSTALLATIONS-

Product Data

1.12.E.3 Parts list which shall include information for replacement parts and ordering instructions 0

26 05 11 REQUIREMENTS FOR

ELECTRICAL INSTALLATIONS-

Maintenance and Operation

Manuals

1.12.F.1 Submit as required for systems and equipment specified in the technical sections 0

26 05 11 REQUIREMENTS FOR

ELECTRICAL INSTALLATIONS-

Sample

1.12.H.1 A minimum 300 mm (12 inches) length of each type and size of wire and cable along with the tag from the coils or reels from which the sample was taken

26 05 11 REQUIREMENTS FOR

ELECTRICAL INSTALLATIONS-

Sample

1.12.H.2 Each type of conduit coupling, bushing, and termination fitting 0

26 05 11 REQUIREMENTS FOR

ELECTRICAL INSTALLATIONS-

Sample

1.12.H.3 Conduit hangers, clamps, and supports 0

26 05 11 REQUIREMENTS FOR

ELECTRICAL INSTALLATIONS-

Sample

1.12.H.4 Duct sealing compound 0

26 05 11 REQUIREMENTS FOR

ELECTRICAL INSTALLATIONS-

Sample

1.12.H.5 Each type of receptacle, toggle switch, lighting control sensor, outlet box, manual motor starter, device wall plate, engraved nameplate, wire and cable splicing and terminating material, and branch circuit single pole molded case circuit breaker

26 05 19 LOW VOLTAGE ELECTRICAL

POWER CONDUCTORS AND

CABLING- Sumbittals

1.4.A.1 Submit shop drawings indicating electrical ratings and insulation type for each conductor and cable

26 05 19 LOW VOLTAGE ELECTRICAL

POWER CONDUCTORS AND

CABLING- Submittals

1.4.A.2 Certifications two weeks prior to final inspection

26 51 00 INTERIOR LIGHTING-

Shop Drawings

1.4.A.1 Submit the following information for each type of lighting fixture designated on the

LIGHTING FIXTURE SCHEDULE, arranged in order of lighting fixture designation: Material and construction details, include information on housing and optics system, physical dimensions and description, wiring schematic and connection diagram, installation details, energy efficiency data, photometric data based on laboratory tests complying with IES Lighting

Measurements testing and calculation guides, lamp data including lumen output (initial and mean), color rendition index (CRI), rated life (hours), and color temperature, ballast data including ballast type, starting method, ambient temperature, ballast factor, sound rating, system watts, and total harmonic distortion, for LED lighting fixtures submit US DOE LED

Lighting Facts label and IES L70 rated life

26 51 00 INTERIOR LIGHTING-

Manuals

1.4.A.2 Submit complete maintenance and operating manuals, including technical data sheets, wiring diagrams, and information for ordering replacement parts. If changes have been made to the maintenance and operating manuals originally submitted, submit updated maintenance and operating manuals

2 weeks prior to final inspection

26 51 00 INTERIOR LIGHTING-

Certifications

1.4.A.3 Certification by the Contractor that the interior lighting systems have been properly installed and tested

2 weeks prior to final inspection

27 05 11 REQUIREMENTS FOR

COMMUNICATIONS

INSTALLATIONS-

Parts list

1.7.B Provide parts list including quantity of spare parts

27 05 11 REQUIREMENTS FOR

COMMUNICATIONS

INSTALLATIONS-

Product information

1.7.C Provide manufacturer product information

27 05 11 REQUIREMENTS FOR

COMMUNICATIONS

INSTALLATIONS-

Provide Source Quality Control

Submittal

1.7.D Submit written certification from OEM indicating that proposed supervisor of installation and proposed provider of warranty maintenance are authorized representatives of OEM

27 05 11 REQUIREMENTS FOR

COMMUNICATIONS

INSTALLATIONS-

Provide Source Quality Control

Submittal

1.7.D Submit written certification from OEM that wiring and connection diagrams meet

Government Life Safety Guidelines

27 05 11 REQUIREMENTS FOR

COMMUNICATIONS

INSTALLATIONS-

Provide Source Quality Control

Submittal

1.7.D Pre-acceptance Certification

27 05 11 REQUIREMENTS FOR

COMMUNICATIONS

INSTALLATIONS-

Installer Qualifications

1.7.E Submit three installations of similar size and complexity furnished and installed by installer, installation location and name, owner’s name and contact information including address, telephone and email. Include date of project start and date of final acceptance, system project number, three paragraph description of each system related to this project. Provide delegated design submittals, required for all equipment anchors and supports.

27 05 11 REQUIREMENTS FOR

COMMUNICATIONS

INSTALLATIONS-

Test Equipment List

1.7.H Supply test equipment of accuracy better than parameters to be tested. Submit test equipment list. Supply only test equipment with a calibration tag from Government-accepted calibration service dated not more than 12 months prior to test. Provide sample test and evaluation reports

27 05 11 REQUIREMENTS FOR

COMMUNICATIONS

INSTALLATIONS-

Submittal Drawings

1.7.I Telecommunications Space Plans/Elevations and logical Drawings. Show access Panel

Schedule on Submittal Drawings and provide sustainable design submittals

27 05 11 REQUIREMENTS FOR

COMMUNICATIONS

INSTALLATIONS-

Test Reports

1.7.K Furnish electronic certified test reports to COR prior to final inspection and not more than

90 days after completion of tests

27 05 11 REQUIREMENTS FOR

COMMUNICATIONS

INSTALLATIONS-

CLOSEOUT SUBMITTALS

1.8.A Warranty certificate, evidence of compliance with requirements such as low voltage certificate of inspection, project record documents, instruction manuals and software that are a part of system

27 05 11 REQUIREMENTS FOR

COMMUNICATIONS

INSTALLATIONS-

Maintenance and Operation

Manuals

1.8.B Submit in accordance with Section 01 00 00, GENERAL REQUIREMENTS

27 05 11 REQUIREMENTS FOR

COMMUNICATIONS

INSTALLATIONS-

Record Wiring Diagrams

1.8.C Include Red Line Drawings, general drawing specifications, building composite floor plans.

Submit Record Wiring Diagrams within five business days after final cable testing, deliver record wiring diagrams as CAD files, and deliver four complete sets of electronic record wiring diagrams to COR on portable storage drive

27 05 11 REQUIREMENTS FOR

COMMUNICATIONS

INSTALLATIONS-

Maintenance Material

Submittals

1.9 After approval and prior to installation, furnish COR with the following

27 05 11 REQUIREMENTS FOR

COMMUNICATIONS

INSTALLATIONS-

Maintenance Material

Submittals

1.9.A A 300 mm (12 inch) length of each type and size of wire and cable along with tag from coils of reels from which samples were taken

27 05 11 REQUIREMENTS FOR

COMMUNICATIONS

INSTALLATIONS-

Maintenance Material

Submittals

1.9.A One coupling, bushing and termination fitting for each type of conduit

27 05 11 REQUIREMENTS FOR

COMMUNICATIONS

INSTALLATIONS-

Maintenance Material

1.9.A Samples of each hanger, clamp and supports for conduit and pathways

27 05 11 REQUIREMENTS FOR

COMMUNICATIONS

INSTALLATIONS-

Maintenance Material

Submittals

1.9.A Duct sealing compound

27 05 33 RACEWAYS AND BOXES FOR

COMMUNICATIONS SYSTEMS-

Submittals

1.3.A Size and location of cabinets, splice boxes and pull boxes

27 05 33 RACEWAYS AND BOXES FOR

COMMUNICATIONS SYSTEMS-

Submittals

1.3.A Layout of required conduit penetrations

27 05 33 RACEWAYS AND BOXES FOR

COMMUNICATIONS SYSTEMS-

Submittals

1.3.A Catalog cuts marked

27 05 33 RACEWAYS AND BOXES FOR

COMMUNICATIONS SYSTEMS-

Certification

1.3.B Provide letter prior to final inspection, certifying material

27 05 33 RACEWAYS AND BOXES FOR

COMMUNICATIONS SYSTEMS-

Penetrations

3.1.B Locate holes in advance of installation

27 05 33 RACEWAYS AND BOXES FOR

COMMUNICATIONS SYSTEMS-

Penetrations

3.1.B Pneumatic hammer, impact electric, hand or manual hammer type drills are not permitted;

COR may grant limited permission by request

27 05 33 RACEWAYS AND BOXES FOR

COMMUNICATIONS SYSTEMS-

Conduit Installation

3.1.C.22 Make only where necessary to avoid interferences and only after drawings showing proposed deviations have been submitted and approved

27 05 33 RACEWAYS AND BOXES FOR

COMMUNICATIONS SYSTEMS-

In Concrete Conduit

3.1.D.1.c Install conduit through concrete beams as accepted by COR prior to construction and after submittal of drawing

28 05 13 CONDUCTORS AND CABLES FOR

ELECTRONIC SAFETY AND

SECURITY-

Manufacturer's Literature and

Data

1.5.A.1 Showing each cable type and rating

28 05 13 CONDUCTORS AND CABLES FOR

ELECTRONIC SAFETY AND

SECURITY-

Certificates

1.5.A.2 Four copies of the certification that the material is in accordance with the drawings and specifications

2 weeks prior to final inspection

28 05 13 CONDUCTORS AND CABLES FOR

ELECTRONIC SAFETY AND

SECURITY-

Wiring Diagrams

1.5.A.3 Workstation outlets, jacks, and jack assemblies, patch cords, patch panels

28 05 13 CONDUCTORS AND CABLES FOR

ELECTRONIC SAFETY AND

SECURITY-

Drawings

1.4.A.4 Cable Administration Drawings

28 05 13 CONDUCTORS AND CABLES FOR

ELECTRONIC SAFETY AND

SECURITY-

Planning Documents

1.5.A.5 Project planning documents

28 05 13 CONDUCTORS AND CABLES FOR

ELECTRONIC SAFETY AND

SECURITY-

Maintenance Data

1.5.A.6 For wire and cable to include in maintenance manuals

28 05 26 GROUNDING AND BONDING

FOR ELECTRONIC SAFETY AND

SECURITY- Submittals

1.3.C Provide certified test reports of ground resistance

28 05 26 GROUNDING AND BONDING

FOR ELECTRONIC SAFETY AND

SECURITY- Submittals

1.3.D Certifications 2 Weeks prior to final inspection

28 31 00 FIRE DETECTION AND ALARM-

Drawings

1.4.B.1 Prepare drawings using AutoCAD. Include floor plans, riser diagrams, and detailed wiring diagrams. Contractor shall deliver to the COTR 3 sets of as-built drawings and one set of the as-built drawing computer files

2 weeks prior to final inspection

28 31 00 FIRE DETECTION AND ALARM-

Manuals

1.4.C.1 Submit simultaneously with the shop drawings, companion copies of complete maintenance and operating manuals including technical data sheets for all items used in the system, power requirements, device wiring diagrams, dimensions, and information for ordering replacement parts. Deliver 4 copies of the final updated maintenance and operating manual to the COTR

2 weeks prior to final inspection

28 31 00 FIRE DETECTION AND ALARM-

Certifications

1.4.D.1 Together with the shop drawing submittal, submit the technician's NICET level III fire alarm certification as well as certification from the control unit manufacturer that the proposed performer of contract maintenance is an authorized representative of the major equipment manufacturer

28 31 00 FIRE DETECTION AND ALARM-

Certifications

1.4.D.2 Submit a certification from either the control unit manufacturer or the manufacturer of each component that the components being furnished are compatible with the control unit

28 31 00 FIRE DETECTION AND ALARM-

Certifications

1.4.D.3 Submit a certification from the major equipment manufacturer that the wiring and connection diagrams meet this specification