Project Title: CONSTRUCTION OF A NEW DORMITORY AND WELCOME CENTER, AND THE DEMOLITION OF BUILDINGS 12, 14 AND 15 AT THE DETROIT JOB CORPS CENTER IN DETROIT, MI
A. The purpose of this amendment is to:
1. Provide a copy of the Attendance sheet from the Pre-Proposal/Bid Conference
2. Delete the last sentence of the second paragraph of Section M-1 which makes reference to Project Labor Agreement
3. Correct the spelling of the Facilities Manager’s last name From: Kahar To: Khari
4. Block # 13 Item D has been revised From: 180 Days To: 90 Days
5. Header in Section F has been revised to reflect “Section F Deliveries or Performance”
X
5. PROJECT NO.
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NO.
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NO. 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NO.
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended, X
(a) By completing Items 8 and 15, and returning ____1______ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR AC- KNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 10-83)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
BY September 12, 2012
Contractor X 1
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 NSN 7540-01-152-8070
PREVIOUS EDITION NOT USABLE Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(No., street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(If applicable)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
(X)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 2
0001 September 11, 2012 94-1291-2825 3169
ETA 1630
U.S. Department of Labor ETA/OCM SEE SECTION 6 Employment and Training Administration Office of Contracts Management 200 Constitution Ave. NW Room N-4643 Washington DC 20210
To all Offerors/Bidders DOL121RB20559
09-01-2012
DOL121RB20559-0001
Project Title: CONSTRUCTION OF A NEW DORMITORY AND WELCOME CENTER, AND THE DEMOLITION OF BUILDINGS 12, 14 AND 15 AT THE DETROIT JOB CORPS CENTER IN DETROIT, MI
6. Section G.5 “OPERATIONS, STORAGE AREAS AND SECURITY” paragraph No. 5 has been revised From: two weeks written notice To: five days written notice
7. Section G.9 “SCHEDULE OF PROGRESS” paragraph No. 2 has been revised From: three copies of an updated design/construction schedule To: five (5) copies of an updated design/construction schedule
8. Section G.12 “PAYMENTS TO CONTRACTOR” has been revised to reflect: Close-out documents specified in Section
G.22
9. Section G.20 “AS-BUILT RECORD OF MATERIALS AND INSTALLATION” has been revised From: Contractor shall provide an electronic (CAD discs) reproducible set of record drawings To: Contractor shall provide two (2) sets of marked up record prints
10. “As-built drawings in both red-lined print format and PDF on CD” and “Building System Commissioning results” has been added to Section G.21 “SUBSTANTIAL COMPLETION”
11. “Copies of all approved Shop Drawings, Operation and Maintenance manuals and Building System Commissioning manuals” in Section G.22 “CONTRACT CLOSEOUT” has been removed
12. FAR Clause 52.225-21 “Required Use of American Iron, Steel, and Manufactured Goods--Buy American Act-- Construction Materials” has been removed and replaced with FAR 52.225-11 “Buy American Act—Construction Materials under Trade Agreements” and 52.225-12 “Notice of Buy American Act Requirement—Construction Materials Under Trade Agreements”
13. Section L.9.1 has been revised From: “seven (5) workdays following the conference” To: “five (5) workdays following the conference”