Division 01 Specs.pdf
PDF 479 KB Posted
- Attached to
- General Facility Repairs-Patch Barracks Federal contract opportunity
- Solicitation number
- W912DY21R0037
About this file
This Request for Proposal (RFP) solicits a firm fixed price design-build contract for general facility repairs to an existing barracks building at Patch Barracks in Stuttgart, Germany. The work includes repairs and renovations to correct deficiencies and improve the condition of the building. The RFP was issued by the Department of the Army Corps of Engineers Engineering Support Center Huntsville as a full and open competition under NAICS code 236220 for commercial and institutional building construction. Responses are due by the date specified in the RFP. The selected contractor will be responsible for both design and construction services to complete the required repairs to the barracks facility.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFP Amendment 0002.pdf | ||
| RFP Amendment P00001.pdf | ||
| SOW APPENDIX 13 - Bldg 2324 Drawings.pdf | ||
| SOW APPENDIX 7 - Bldg 2324 Photos.pdf | ||
| SOW APPENDIX 9 - Bldg 2324 Floor Plan and New Offices.pdf | ||
| SOW APPENDIX 11 - Construction Security Plan_Bldg 2324.pdf | ||
| SOW APPENDIX 8 - Bldg 2324 New Offices Concept.pdf | ||
| SOW APPENDIX 10 - FFE Design Submittal Requirements Matrix.pdf | ||
| SOW APPENDIX 12 - Bldg 2324 HVAC Survey Report.pdf | ||
| RFP W912DY21R0037.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Facility Repair and Renewal FRR
SECTION 01 11 00
SUMMARY OF WORK
08/11
PART 1 GENERAL
1.1 REFERENCES
The Contractor is responsible for obtaining and updating all publications referenced in contract documents. LEED and Energy Conservation requirements for work done under the individual task orders are required to coordinate and incorporate all Army ECBs published with an issued date on or before the time of award of the task order. The dates of the publications provided in contract documents are those in effect at the time of award of this contract. Work done under the individual task orders shall utilize the latest issue of the publications dated at the time of award of the task order. When a required publication is not referenced, the Contractor shall utilize a commercial standard that has national applications.
U.S. DEPARTMENT OF DEFENSE (DOD)
Army ECBs Army Engineering Construction Bulletins
Army Standards Approved Army Standards
EISA 2007 Energy Independence and Security Act of
EPACT 2005 Energy Policy Act of 2005
UFC 1-200-01 (2010; Change 2) General Building Requirements
UFC 3-410-02 (2012) Lonworks (R) Direct Digital Control for HVAC and Other Local Building Systems
UFC 3-470-01 (2012) Lonworks (R) Utility Monitoring and Control System (UMCS)
UFC 4-010-01 (2012) DoD Minimum Antiterrorism Standards for Buildings
U.S. ARMY INFORMATION SYSTEMS ENGINEERING COMMAND (USAISEC)
I3A (2010) Technical Guide for Installation Information Infrastructure Architecture
INTERNATIONAL CODE COUNCIL (ICC)
ICC IPC (2009) International Plumbing Code
U.S. GREEN BUILDING COUNCIL (USGBC)
LEED Leadership in Energy and Environmental Design(tm) Green Building Rating System for New Construction and Major Renovation
SECTION 01 11 00 Page 1
(LEED-NC)
LEED GBDC LEED Reference Guide for Green Building Design and Construction
AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING
ENGINEERS (ASHRAE)
ASHRAE 90.1 (2007) Energy Standard for Buildings Except Low-Rise Residential Buildings
ASHRAE 189.1 (2009) Standard for the Design of High-Performance Green Buildings Except Low-Rise Residential Buildings
1.2 SUBMITTALS
SD-01 Preconstruction Submittals
Site Investigation Report; G Disruption Plan
1.3 WORK COVERED BY CONTRACT DOCUMENTS
The Contractor shall complete all work and services under this contract in accordance with schedules that are established in each task order. Work will vary from site to site and will require extensive knowledge of facilities repair and renewal (FRR) projects. Submittal dates will be included in the individual task orders. These dates identify when information is due in the issuing Government office and other addresses identified in the individual task orders. The types and numbers of submittals and dates and places for review meetings shall be established by each task order under this contract.
1.3.1 Project Description
This contract is intended to provide quick response for facility repair, renovation, conversion, alteration, additions, construction, equipment procurement / installation, and maintenance services on installed equipment/systems at Government installations and facilities. The contractor may be required to survey the problem areas, evaluate and recommend solutions, develop and implement work plans in a timely manner within negotiated costs. Typical projects may include, but are not limited to, the following:
1.3.1.1 Architectural Work
Enclosures, shelters, building systems, mobile buildings, chimneys, grout, mortar, concrete, brick, concrete masonry units (CMUs), waterproofing, insulation, caulking and sealants, roofing, gutters, drains, metal decking, joists, siding and exterior surfacing, levellers, docks, ramps, stairs, shelving, windows, doors, painting, finishes, louvers, awnings, shutters, panels, grills, ceilings, acoustical areas, walls, paneling, flooring (conductive and nonconductive), carpeting, tiles, builder's hardware, signage, metals, woods and plastics, millwork, thermal and moisture protection, lead based paint abatement, fireproofing, equipment systemization layouts, building fixtures, and handicap systemization.
SECTION 01 11 00 Page 2
1.3.1.2 Civil Work
Topographic surveying, grading and earthwork, surface and subsurface storm drainage and drainage control structures, storm water management, erosion and sediment control, clearing and grubbing, paving and surfacing for roads, parking areas, and sidewalks, parking layout, pavement markings, traffic control and signage, gates and fencing, curbs and gutters, railroads, dewatering, landscaping, seeding and sodding, riprap, geotechnical investigations, slope stabilization, foundations, borings, trenching, piles and caissons, spill containment, berms, demolition, and wetlands delineation.
1.3.1.3 Cost Engineering Work
Life cycle costing, benefit-cost analyses, economic analysis, and cost estimating services.
1.3.1.4 Electrical Work
Electrical distribution and network balancing (aerial and underground), transmission lines, poles (telephone and power), towers, ducts, raceways, conduits, tubing, connectors, wires, cable, cable trays, outlet boxes, cabinets and enclosures, supports, fiber optics cable and equipment, manholes, concrete pads, insulators, lighting arrestors, transformers, capacitors, switches, relays, fuses, grounding, lightning protection, cathodic protection, service entrances, panelboards, circuit breakers, motor control centers, special equipment/systems, targeting systems, resistance heating, starters, uninterrupted power supplies (UPS), beacons, batteries, generators, solar systems, receptacles, lighting fixtures, lamps, ballasts, equipment connections, special outlets, disconnect switches, splices, terminations, control systems, minor revisions to electronic security systems, utilities monitoring and control systems (UMCS), and similar micro processor environmental control systems, audio and visual communication systems, telephone systems, instrumentation systems, and fire detection and alarm systems.
1.3.1.5 Environmental Work
Industrial and sanitary sewers, waste treatment facilities, septic tanks with drains, portable toilets, wells, water treatment facilities, water distribution systems, potable and fire water supplies including wells, piping, pumps, valves, sprinklers, water use analyses, leakage analyses, and hazardous waste analyses, and disposal of waste products.
1.3.1.6 Mechanical Work
Heating, ventilation, and air-conditioning (HVAC) systems and components, central plant and utility distribution studies, high temperature water systems, chillers, refrigerants, cooling towers, air handling equipment, energy conservation, heat transfer surfaces, furnaces, air distribution, valves, pumps and associated piping and ducts; conveying systems, elevators, dumbwaiters, moving walks, box conveyors, hoists and cranes, lifts, escalators, boilers, material handling systems, dryers, steam lines, transient tubes, shredders, plumbing fixtures, special equipment/systems, sterilization systems, fuel distribution (i.e., propane, natural gas, and slurries), petroleum oil lubricants (POL), storage tanks for fuel, gas, water and sewage; piping systems, fire suppression (water, chemical, and gas), fuel use and leak analyses, sterilizers, compressed air production and distribution systems, industrial gas distribution systems, exhaust
SECTION 01 11 00 Page 3 systems, steam systems, pipe insulation, and plumbing systems involving water, solids, and hazardous waste.
1.3.1.7 Safety Improvements
Life safety, fire protection systems, industrial safety and hygiene, inflammatory gases, asbestos and/or lead based paint evaluation and removal/encapsulation, light fixtures containing PCB's evaluation/removal, blast distances, and Failure Mode and Effective Analyses (FMEA), Occupational Safety and Hazards Act (OSHA) and American Disability Act (ADA) evaluations.
1.3.1.8 Antiterrorism and Force Protection
Unless otherwise specified in project task orders projection measures specified in UFC 4-010-01 are required. The element of those standards that has the most significant impact on projects is providing protection against explosives effects. That protection can either be achieved using conventional construction (including specific window requirements) in conjunction with establishing relatively large standoff distances to parking, roadways, and installation perimeters or through building hardening, which will allow lesser standoff distances. The facility requirements listed in these specifications assume that the minimum standoff distances can be met, permitting conventional construction.
Lesser standoff distances (with specific minimums) are not desired;
however, they can be provided, but will require structural hardening of the building. The following list highlights the major points:
Standoff distance from roads, parking and installation perimeter;
and/or structural blast mitigation
Blast resistant windows, frames, anchors, supports
Progressive collapse resistance for all facilities three stories or higher
Mass notification system
Mailrooms have separate HVAC systems and are sealed from the rest of the building
1.3.1.9 Structural Work
Structural design and analysis of building systems and ancillary structures (concrete, masonry, steel, etc.), foundations, underwater structures, reinforced concrete, equipment mounting, shock isolation, reinforced masonry, wood, joists, decks, structural framed systems, seismic evaluations of existing structures, connections, non-building structures, welding procedures, detailing of structural components and hardened (protective) structures, earthquake consideration of utility systems;
non-building structures such as elevated tanks, vertical tanks on ground, horizontal tanks, retaining walls and buried structures; anchorage and support of mechanical and electrical equipment; and applications of industry building codes and standards.
1.3.1.10 Systems Work
Human factors engineering; upgrade assessments, equipment inventories and O&M documentation to obtain support; and energy system surveys.
SECTION 01 11 00 Page 4
System/equipment and life safety repair and maintenance efforts for existing systems/equipment may be required. Logistical support shall be provided where required. Accreditation surveys to determine if FRR efforts will be conducted.
1.3.1.11 Microprocessor Control Systems
Building Automation Systems (BAS), Energy Monitoring Control Systems (EMCS), Utility Monitoring and Control Systems (UMCS) and similar microprocessor control systems.
1.3.2 Location
This contract may apply to various Department of Defense (DOD) installations and facilities (CONUS), the National Guard, and, pursuant to applicable authorities for interagency and intergovernmental support, to federal agencies, state and local governments on a case specific basis.
Task orders may be awarded for work to be performed through-out the United States, including Alaska, Hawaii, and all US territories, for the following Government agencies: Department of Defense, Department of Homeland Security, Veteran's Administration, State Department, Department of Interior, Department of Energy, Department of Transportation, and state and local governments.
1.4 TECHNICAL CRITERIA
Some applicable federal, state/commonwealth and industry standards are referenced below. The publications listed below form the basis of the work required in individual task orders under this contract. Additional publications may be identified as required in the task orders. The Contractor is responsible for obtaining and updating all publications listed below as well as any others it may use in response to the requirements of task orders. Work performed under individual task orders must adhere with the current version at the time of task order award of applicable Unified Facility Criteria (UFC) documents, DOD Army Engineering and Construction Bulletins (ECB), and Army Standards for specific Facility Types. When a required publication is not referenced in this list, or in the task order, the Contractor shall utilize one that has national applications or provide one from the cited website below. Where conflict arises between publications, the most stringent shall apply. The UFCs and ECBs are available from the Whole Building Design Guide (WBDG) at http://www.wbdg.org/references/pa_dod.php. Army ECBs provide design directives and guidance that revises and/or augments applicable UFCs.
Approved Army Standards for specific Facility Types are available from http://mrsi.usace.army.mil/fdt/Army%20Standards/Forms/AllItems.aspx. In addition, the Contractor must adhere with the current version at the time of task order award of applicable Unified Facility Criteria (UFC) documents. Please note UFC 1-200-01 references applicable UFCs and the current version of those UFCs are required.
Army ECBs* Army Standards
EISA 2007
EPACT 2005
ASHRAE 90.1-2007*
ASHRAE 189.1-2009*
I3A
ICC IPC
LEED*
SECTION 01 11 00 Page 5
LEED GBDC*
UFC 1-200-01
UFC 3-410-02**
UFC 3-470-01**
Memorandum, Office of the Assistant Chief of Staff for Installation Management, Sustainable Management of Waste in Military Construction, Renovation, and Demolition Activities, 6 February 2006 (Specifications must contain UFGS-01 57 20.00 10 ENVIRONMENTAL PROTECTION, UFGS-01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT, and UFGS-02 41 00 DEMOLITION AND DECONSTRUCTION. The submittals required by these specifications should be identified on the project submittal register.)
*LEED and Energy Conservation requirements for work done under the individual task orders are required to coordinate and incorporate all Army ECBs published with an issued date on or before the time of award of the task order.
**These UFCs are applicable but are not currently included in UFC 1-200-01.
1.5 CERTIFICATION OF TASK ORDERS
Unless otherwise indicated in the project task order, active registered professional engineers, architects, and industrial hygienists shall certify work plan/design documentation with their signature and stamp all task order efforts, ensuring proper usage of codes and standards. Each drawing sheet shall be certified. The cover sheet of the specification sheet shall be certified. Design documentation shall be certified by the appropriate design discipline. The contractor shall provide certification in accordance with the state and local requirements when required i.e.; New York requires certified New York professionals.
The contractor shall use only personnel who possess current EPA, state and local (as necessary), accredited and licensed as Asbestos Inspectors, Asbestos Management Planners and Asbestos Project Designers, as appropriate, for the asbestos work defined in this Contract. The contractor shall employ only Accredited Lead Risk Assessor(s) (inspectors) to perform the LBP work defined in this Contract. These accredited asbestos personnel shall be accredited in the state that the work is being conducted (as applicable).
1.6 DEFINITIONS
1.6.1 Site Investigation
The site investigation is an inspection of an installation or facility to evaluate areas and to obtain specific information pertaining to a proposed FRR action.
Validation of the task order scope of work (SOW) shall also be accomplished during the initial site meeting. This requires customer, contractor, and Huntsville contract management participation. During the process of verification of the SOW each item shall be reviewed by the attendees and agreed to as evidenced by date and signature by the appropriate parties at the meeting (typically the customer and contractor leads) on each item in the SOW.
SECTION 01 11 00 Page 6
1.6.2 Work Plan
The work plan is minimal design documentation required for Huntsville Center (HNC) to monitor the Contractor's efforts with regard to scope, schedules, costs, codes, and standards in order to perform a FRR action to construct and/or correct a facilities repair and/or renewal situation. The level of detail in the work plan is contingent upon the effort delineated in the task order scope of work, scope of work validation and information gathered during the site visit by the contractor. The detail can vary from a major project which may include detailed drawings, engineering calculations, criteria, manufacturers' data, comprehensive schedules, cost estimates, etc. to a minor project which may only require sketches, simple schedules, catalog cuts, etc.
1.6.3 Facilities Repair and Renewal (FRR) Project
The FRR project is a project undertaken to construct or correct a facilities repair and/or renewal situation identified by the facility with details taken from a site survey, site visit, feasibility study, or related sources. These projects may involve operation, facilities repair and renewal, as stated in the task order, to remedy the situation. They are activated by a task order based on the facility requirements.
1.6.4 Facilities Repair and Renewal (FRR) Action
The FRR action is the action taken to construct or correct a facilities repair and/or renewal situation. It results from the implementation of a work plan or other documents as provided.
1.6.5 Task Order
A task order is a directive issued to the Contractor by the Contracting Officer, which states the requirements for the FRR actions to be performed under this contract. Tasks are defined as individual efforts to be performed by a Contractor, which are contained in a task order.
1.6.6 Task Element
Each task order may consist of up to three phases of work known as a task element. These elements are 1) Site Investigation, 2) Work Plan and 3) FRR Action. Note that the contractor shall not proceed to the next task element until directed to do so by the Contracting Officer.
1.7 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
SECTION 01 11 00 Page 7
1.8 LOCATION OF UNDERGROUND FACILITIES
Obtain digging permits prior to start of excavation. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.8.1 Notification Prior to Excavation
Notify the Contracting Officer at least 7 days prior to starting excavation work.
1.9 SECURITY REQUIREMENTS
Contract Clause FAR 52.204-2 Alt II, Security Requirements applies.
Provide site security (fencing, lighting, or guard service) as required by each task order. However, at a minimum, the Contractor shall maintain the site and all other contractor-controlled areas in such a manner as to minimize the risk of theft, vandalism, injury, or accident. The Contractor shall comply with site security regulations.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
3.1 ACTIVITIES UNDER FACILITY REPAIR AND RENEWAL (FRR) PROJECTS
The activities to be performed by the Contractor under this contract and subsequent task orders are described in general terms below (this list is not all-inclusive). The specific tasks and task elements to be performed will be identified in each task order. Generally, costs associated with each task element will be negotiated and agreed upon prior to start of effort on the task order; however, upon direction of the Contracting Officer by issuance of a time-and-materials (T&M) order, the Contractor shall immediately start the first task element and usually the order will be negotiated to a firm-fixed price as soon as possible. The Contracting Officer reserves the right to modify duties and time periods in the tasks.
At the completion of each approved task order, the results, documented and conceptual, become the property of the Government.
3.1.1 Element 1 Site Investigation
Upon direction of the Contracting Officer, a site investigation shall be initiated. Prior to any site investigation, a site survey/visit proposal and an abbreviated accident prevention plan (AAPP) shall be submitted, within five working days after the acceptance of the site survey proposal by the Contracting Officer or receipt of a unilateral T&M task order, the Contractor shall start a site survey. Within five working days after the conclusion of the site survey, unless otherwise identified in the individual task order or directed by the Contracting Officer, the Contractor shall prepare and submit to the Contracting Officer, a site survey report. The site survey report shall identify any needed project related information/data that was not available.
3.1.1.1 Site Survey
Visit the site, building, or area as directed or indicated in the task order. Provide visual digital media documenting the proposed facility, SECTION 01 11 00 Page 8 repair, and rehabilitation (FRR) action project with emphasis on the particular items to be removed/recovered. Unless stated otherwise in a task order, the site investigation shall involve the following as a minimum:
a. Investigate each of the problem areas stated in the task order.
Investigate and analyze any obvious code or accreditation violations.
b. Review existing as-built drawings, maintenance records, and other pertinent documentation as required to fulfill the requirements of the task order.
c. Interview on-site maintenance personnel and staff as required to fulfill the requirements of the task order.
d. Gather data required to prepare a site description, a hazard and risk analysis, a site control document, and a site disruption plan, which itemizes actual, probable and potential interruptions to installation operations along with recommendations to reduce the effects of unavoidable interruptions.
e. Develop a basis during the visit to prepare budget cost proposals for the FRR action elements listed in the task order.
f. Operate existing systems/equipment, as applicable, under the direction of installation personnel in order to isolate and evaluate problem areas.
g. Investigate and document the presence or absence of asbestos/lead-based paint in the proposed work areas and surrounding areas with the goal of preparing an abatement plan.
To accomplish this the Contractor shall interview facility personnel and review existing documentation as required. At the completion of the documentation review, the Contractor shall conduct an on-site investigation of the proposed work area in conjunction with facility personnel to visually locate and identify asbestos/lead-based paint insulation or surface coverings, which cannot be proven to be non-asbestos, shall be considered to be asbestos and treated accordingly. If no asbestos/lead-based paint is encountered or presumed present, the Contractor shall so certify in writing.
3.1.1.2 Site Investigation Report
Prepare and submit a Site Investigation Report documenting the site investigation. Include meeting minutes; site conditions, all data gathered, customer requirements and Scope clarifications. Include a synopsis which defines all design alternatives evaluated as well as the results. Present the Report in a three ring binder(s) and submit as a stand alone document, or as a part of the work plan as required by the task order. The Site Investigation Report shall include (as a minimum, or as defined in the Task Order) individual sections for each of the topics defined below.
a. Site Description. Provide a brief description of the site under investigation, including a complete summary of safety and health hazards anticipated on site.
b. Site Information. Provide a list of people contacted during the visit, as well as any relevant information obtained.
SECTION 01 11 00 Page 9
c. Hazard Assessment and Risk Analysis. Provide a complete description of the work to be performed with a complete summary of hazards anticipated. Identify the safety and health hazards that may be encountered for each task or site operation to be performed. Each task/operation is to be discussed separately.
Material Safety Data Sheets (MSDS) for each hazardous substance discovered or brought on site shall be documented.
d. Problem Areas. Include a narrative description of each problem area (related to FRR action) that was investigated during the visit. Also include a list of any code or accreditation violations in these areas. Indicate areas investigated which warrant further study and those, which do not warrant further efforts.
e. Disruption Plan. Develop and submit a site disruption plan, signed off by installation personnel, which identifies actual, probable, and potential interruptions to installation operation with corrective actions.
f. Asbestos and/or Lead-Based Paint Abatement (Removal/Encapsulation) Plan. The report shall contain an abatement plan and schedule for the abatement of any asbestos and/or lead-based paint in the work and surrounding area, both identified by type, percent and location. This plan shall contain recommendations for in-place or removal abatement procedures. The plan shall be monitored throughout the FRR action effort.
Abatement shall be carried out in a manner, which minimizes the cost and impact on the FRR action; i.e., encapsulating lead-based paint and/or asbestos containing equipment and areas where possible instead of removing the materials. If the abatement will be handled by others, then a conclusive statement shall be included specifically stating the responsible party who will be performing the abatement. If there is no lead based paint and/or asbestos, then include a statement such as, "No lead based paint or asbestos is involved." No FRR action effort shall begin until the work area is abated of hazardous material, or is certified asbestos/lead-based paint free.
g. Preliminary Studies. Include any preliminary studies, feasibility studies, life cycle cost analysis, or any other reports, documentation, or general information used in decision making, preliminary design, or design alternates. Life cycle cost studies shall be performed in accordance with National Institute of Technology and Standards Handbook 135 utilizing Department of Energy Escalation Rates and other applicable data as specified in the task order or directed by the Contracting Officer.
h. Proposed Work Plan. Clearly define the scope of work to be included in the work plan. Define the recommendations for resolving each problem area that was investigated. Include any drawings/sketches/schedules, which may be applicable to the proposed FRR action. Describe any equipment/system to be supplied as part of the FRR action.
i. Cost Proposals. The Site Investigation Report shall include a final cost proposal for the preparation of the work plan and a budget cost proposals for the performance of the FRR Action.
SECTION 01 11 00 Page 10
3.1.2 Element 2 Work Plan (Design)
The work plan (design) shall be developed by the Contractor in accordance with the level of effort specified by the task order. The complexity of the work plan for an FRR action on a major project such as replacement of major equipment, rehabilitation or renewal of large or complex facilities, etc. may consist of detailed drawings, specifications, schedules, etc.
while a work plan for an FRR action on a minor project such as a motor or pump replacement may consist of simple sketches, catalog cuts, a simple schedule, etc. Regardless of the size of the FRR action project the work plan shall provide adequate detail to effectively carry out the FRR action process. Submit as specified in Section 01 33 10.05 20 DESIGN SUBMITTAL
PROCEDURES.
3.1.3 Element 3 FRR Action
Begin work on the FRR action of the facility or installation in accordance with the approved work plan or as otherwise directed by the Contracting Officer following the approved work schedule.
3.2 LEVEL OF EFFORT
The type and magnitude of task order projects will vary greatly; the contractor is expected to prepare the level of design and documentation appropriate to the size and complexity of the project.
-- End of Section --
SECTION 01 11 00 Page 11
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
11/11
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. The following shall be submitted in accordance with Section 01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES and Section 01 33 10.05 20
DESIGN SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Progress and completion pictures; G
SD-04 Samples
Color boards; G
SD-07 Certificates
Telephone Conversation/Correspondence Record
Certification of Computer Media
Monthly Progress Report
1.2 COLOR BOARDS FOR AIR FORCE PROJECTS
Submit five sets of color boards within 90 calendar days after Contract Award. Each set of boards shall include samples of colors and finishes of interior surfaces, such as walls, floors, and ceilings. The samples shall be presented on 8 by 10-1/2 inches boards (modules) with a maximum spread of 24 by 31-1/2 inches for foldouts. Modules shall be designed to fit in a standard loose-leaf, three-ring binder. Where special finishes such as architectural concrete, carpet, or prefinished textured metal panels are required, samples not less than 12 inches square shall be submitted with the board. If more space is needed, more than one board per set may be submitted. The Contractor shall certify that he has reviewed the color samples in detail and that the color samples are in strict accordance with contract drawings and specifications, except as may be otherwise explicitly stated. Submittal of color samples shall not relieve the Contractor of the responsibility to submit samples required elsewhere herein.
1.3 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten views from points located by the Contracting Officer. Submit a view location sketch indicating points of view. Submit with the monthly invoice two sets of digital photographs each set on a separate CD-R, cumulative of
SECTION 01 30 00 Page 1 all photos to date. Indicate photographs demonstrating environmental procedures. Photographs for each month shall be in a separate monthly directory and each file shall be named to indicate its location on the view location sketch. The view location sketch shall also be provided on the CD as digital file. All file names shall include a date designator. Cross reference submittals in the appropriate daily report. Photographs shall be provided for unrestricted use by the Government.
1.4 TASK ORDER DOCUMENTATION
1.4.1 Telephone Conversation/Correspondence Record
Maintain a record of each substantive phone conversation and written correspondence related to the performance of this contract. Sort the record by task order. Submit a summary of the phone conversations and written correspondence to the Contracting Officer, or authorized representative, monthly and is due not later than the 10th of the following month. For this contract, "substantive" is defined as:
a. all calls to or from Army personnel that require action by either the Army or the Contractor.
b. all calls to or from Army personnel that directly or indirectly affect contract terms and conditions.
c. all calls to or from federal, state, or local regulatory agency personnel.
d. all calls to Contractor personnel that require calling party to be referred to the Public Affairs Office.
1.4.2 Certification of Computer Media
Certify all delivery media (floppy disks, CD roms, thumb drive, etc.) for computer data to be compatible with installation computer equipment and to be free of known computer viruses. Furnish a compatibility certification and the name(s) and release date(s) of the virus scanning software used to analyze the delivery media to the Government at the time of delivery. The release or revision date of the virus scanning software shall be the current version, which has detected the latest known viruses at the time of delivery of the media. If analysis of the delivery media by the Government finds evidence of incompatibility or virus infection, the media will be returned to the Contractor. The Contractor shall resubmit the media at no cost to the Government.
1.4.3 MONTHLY PROGRESS REPORT
Submit a narrative report in tabular form, which details each activity shown on the schedule for the reporting period. This report shall be coordinated with the Design and Construction Schedule. Specific contents are:
a. Summarize progress by estimated percent of completion for each FRR project.
b. Remarks section shall be provided for the Contractor to describe any problems in detail which caused lag in schedule as well as plans to get back on schedule.
SECTION 01 30 00 Page 2
c. A summary monthly progress report addressing each active task order covering all quality control measures, along with related QC reports for that month
1.5 MINIMUM INSURANCE REQUIREMENTS
Procure and maintain during the entire period of performance under this contract the following minimum insurance coverage:
a. Comprehensive general liability: $500,000 per occurrence
b. Automobile liability: $200,000 per person, $500,000 per occurrence for bodily injury, $20,000 per occurrence for property damage
c. Workmen's compensation as required by Federal and State workers' compensation and occupational disease laws.
d. Employer's liability coverage of $100,000, except in States where workers compensation may not be written by private carriers.
e. Others as required by State.
1.6 CONTRACTOR SPECIAL REQUIREMENTS
1.6.1 Asbestos Containing Material
All contract requirements of "Engineering Control of Asbestos Containing Materials" assigned to the Private Qualified Person (PQP) shall be accomplished directly by a first tier subcontractor.
1.7 SUPERVISION
Have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours. In addition, if a Quality Control (QC) representative is required on the contract, then that individual shall also have fluent English communication skills.
1.8 PARTNERING
To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, the Contractor and their Subcontractors. Key personnel from the Supported Command, the End User (who will occupy the facility), Contractor and Subcontractors, and the Designer of Record will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project that is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule.
The Contracting Officer will provide Information on the Partnering Process and a list of key and optional personnel who should attend the Partnering meeting.
1.8.1 Formal Partnering
Provide and host the Partnering sessions with key personnel of the Project Team, including Contractor personnel and Government personnel. Pay all
SECTION 01 30 00 Page 3 costs associated with the Partnering effort including the Facilitator, the meeting room, and other incidental items. In exception, participants shall bear their own costs for meals, lodging, and transportation associated with the Partnering sessions.
Before a Partnering session, coordinate with the Facilitator all requirements for incidental items (such as audio-visual equipment, easels, flipchart paper, colored markers, note paper, pens/pencils, colored flash cards, etc.), and have these items available at the Partnering session.
Provide copies of documents for distribution to all attendees.
The Facilitator shall be experienced in conducting Partnering Workshops, and shall be acceptable to both the Government and the Contractor. The Facilitator is responsible for leading the team in a timely manner and making sure that issues are identified and resolved. A list of Partnering Facilitators is available from the Contracting Officer.
a. The Initial Partnering Session shall be a duration of one day minimum. It shall be located at a place off the construction site, as agreed to by the Contracting Officer and the Contractor.
It may take place concurrently with the Pre-Construction Meeting.
b. The Follow-on Partnering Session(s) generally last a half day or less. Schedule them at 3 to six month intervals, or when needed.
Participants are encouraged to utilize electronic means to expedite meetings. Meetings may be held at a location off-Base, at the project site, or in a Government Facility on Base.
Follow-on meetings may be held concurrently with other scheduled meetings. Attendees need only be those required to resolve current issues. Recommend using the same Facilitator from the Initial Partnering session to achieve best results and for continuity.
1.9 PRE-FACILITY REPAIR AND RENEWAL (FRR) CONFERENCE
This conference will be held at the location specified by the Contracting Officer, or authorized representative. The purpose of this pre-FRR action conference is to enable the Contracting Officer, or authorized representative, to outline the procedures that will be followed by the Government in its administration of the contract and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government's supervision and inspection of contract work, security requirements, regulations, etc. The Contracting Officer, or authorized representative, may invite installation, using service, engineering, and/or security personnel as well as other involved Government personnel to attend this conference.
1.9.1 Discussion Items
The following is a list of items for discussion during this conference.
This is not considered to be a complete listing.
a. Authority of the Contracting Officer, or authorized representative, and procedures for administering the contract.
b. Contractor labor standards provisions.
c. Contract modification and administration procedures.
SECTION 01 30 00 Page 4
d. Payment estimate data and procedures.
e. Contractor insurance requirements.
f. Contractor performance evaluation.
1.9.2 Installation Rules and Regulations
Regardless of whether site of the work is on a military reservation or on a civilian installation associated with the military, all rules and regulations issued by the Commanding Officer/Director covering general safety, security, sanitary requirements, pollution control, work hours, storage areas, utility availability and use, utility interruptions, site conditions, environmental compliance, clean up, conduct and dress, work in areas with others, excavation permits, access to work areas, traffic regulations, as well as any other pertinent information requested by the Contractor or provided by the authorized installation technical representative shall be observed by the Contractor. Information regarding these requirements may be obtained by contacting the authorized installation technical representative, who will provide such information or assist in obtaining same from appropriate authorities.
1.9.3 Work Hours and Government Holidays
Specific work hours will be set for each task order. Standard work hours should be set at preliminary teleconference or by Contracting Officer. If not set prior, standard work hours should be between 0800-1700 unless otherwise set by Contracting Officer. Note that government employees may not be accessible during the following government holidays: New Years Day, Martin Luther King Birthday, President's Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veteran's Day, Thanksgiving Day, and Christmas Day.
1.10 AVAILABILITY OF CADD DRAWING FILES
After award and upon request, the electronic "Computer-Aided Drafting and Design (CADD)" drawing files will only be made available to the Contractor for use in preparation of construction drawings and data related to the referenced contract subject to the following terms and conditions.
Data contained on these electronic files shall not be used for any purpose other than as a convenience in the preparation of construction drawings and data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor shall make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor shall, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
These electronic CADD drawing files are not construction documents.
Differences may exist between the CADD files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic CADD files, nor does it make representation to the compatibility of these files with the Contractors
SECTION 01 30 00 Page 5 hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished CADD files, the signed and sealed construction documents shall govern. The Contractor is responsible for determining if any conflict exists. Use of these CADD files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project.
If the Contractor uses, duplicates and/or modifies these electronic CADD files for use in producing construction drawings and data related to this contract, all previous indicia of ownership (seals, logos, signatures, initials and dates) shall be removed.
1.11 ELECTRONIC MAIL (E-MAIL) ADDRESS
The Contractor shall establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments in Microsoft, Adobe Acrobat, and other similar formats. Within 10 days after contract award, the Contractor shall provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes, terrorist threats, etc. Multiple email address will not allowed.
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). The Contractor shall promptly notify the Contracting Officer, in writing, of any changes to this email address.
1.12 COST PROPOSALS
Prior to performing any task as defined by a task order, the Contractor shall submit cost proposals. The Contractor shall not initiate any work on a project until the Contracting Officer approves or waives the associated cost proposal for each task. Submit cost proposals with detailed backup for each task. Format each cost proposal as prescribed by the Contracting Officer. The cost for preparing all cost proposals is an overhead expense and will not be separately reimbursed.
1.13 PUBLIC AFFAIRS
The Contractor shall not publicly disclose any data generated or reviewed in accordance with DFARS clause 252.204-7000, Disclosure of Information.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 30 00 Page 6
SECTION 01 32 01.00 10
PROJECT SCHEDULE
08/08
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
ECB 2005-10 (2005) Scheduling Requirements for Testing of Mechanical Systems in Construction Contracts
ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Schedule; G
1.3 QUALITY ASSURANCE
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating (activity status) and preparation of reports. The authorized representative shall be experienced in scheduling and have previously developed, created, and maintained at least 2 electronic schedules for projects similar in nature and complexity to this project and shall be experienced in the use of the scheduling software that meets the requirements of this specification.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to the Contract Clause, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the sequence in which the Contractor proposes to perform the work
SECTION 01 32 01.00 10 Page 1
Facility Repair and Renewal RFR and dates on which the Contractor contemplates starting and completing all schedule activities. The scheduling of the entire project, including the design and construction sequences, is required. The scheduling of design and construction is the responsibility of the Contractor. Contractor management personnel shall actively participate in its development.
Designers, Subcontractors and suppliers working on the project shall also contribute in developing and maintaining an accurate Project Schedule.
Provide a schedule that is a forward planning as well as a project monitoring tool.
3.1.1 Approved Project Schedule
Use the approved Project Schedule to measure the progress of the work and to aid in evaluating time extensions. Make the schedule cost loaded and activity coded. The schedule will provide the basis for all progress payments. If the Contractor fails to submit any schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.
3.1.2 Schedule Status Reports
Provide a Schedule Status Report on at least a monthly basis. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, take steps necessary to improve its progress including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.
3.1.3 Default Terms
Failure of the Contractor to comply with the requirements of the Contracting Officer shall be grounds for a determination, by the Contracting Officer, that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of the contract.
3.2 BASIS FOR PAYMENT AND COST LOADING
Use the schedule as the basis for determining contract earnings during each update period and therefore the amount of each progress payment. Lack of an approved schedule update, or qualified scheduling personnel, will result in the inability of the Contracting Officer to evaluate contract earned value for the purposes of payment. Failure of the Contractor to provide all required information will result in the disapproval of the preliminary, initial and subsequent schedule updates. In the event schedule revisions are directed by the Contracting Officer and those revisions have not been included in subsequent revisions or updates, the Contracting Officer may hold retainage up to the maximum allowed by contract, each payment period, until such revisions to the Project Schedule have been made. Activity cost loading shall be reasonable, as determined by the Contracting Officer. The aggregate value of all activities coded to a contract CLIN shall equal the value of the CLIN on the Schedule.
SECTION 01 32 01.00 10 Page 2
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
The computer software system utilized to produce and update the Project Schedule shall be capable of meeting all requirements of this specification. Failure of the Contractor to meet the requirements of this specification will result in the disapproval of the schedule.
3.3.1 Critical Path Method
Use the Critical Path Method (CPM) of network calculation to generate the Project Schedule. Prepare the Project Schedule using the Precedence Diagram Method (PDM).
3.3.2 Level of Detail Required
Develop the Project Schedule to an appropriate level of detail. Failure to develop the Project Schedule to an appropriate level of detail, as determined by the Contracting Officer, will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2.1 Activity Durations
Reasona…