This document is a Data Item Description (DID) for an Acceptance Test Report (ATR) with the identifier DI-QCIC-81891, approved on January 18, 2013. The DID outlines the requirements for a contractor-generated report documenting qualification test results to demonstrate system conformance with performance specifications, work authorization documents, or contract requirements.
The document specifies seven key content requirements for the ATR, including: test article identification and description, test date and location, test operator details, comprehensive results analysis highlighting both satisfactory and unsatisfactory objectives, contractor conclusions and recommended corrective actions, full supporting analysis, and complete data sheets. The Office of Primary Responsibility is listed as AS/PMA251, and the contractor has flexibility in report format while being required to meet the specified content guidelines.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N0016726Q1024 CSS.pdf | ||
| Contract Data Requirements List CDRL A001 and A002.pdf | ||
| GFP Module Attachment.xlsx | XLSX spreadsheet | |
| DI-MGMT-80441D Government Property Inventory Report.pdf | ||
| Redacted_Sole Source Justification - Winch Repair.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DATA ITEM DESCRIPTION
Title: ACCEPTANCE TEST REPORT (ATR) Number: DI-QCIC-81891 Approval Date: 20130118 AMSC Number: N9313 Limitation: N/A DTIC Applicable: N/A GIDEP Applicable: N/A Office of Primary Responsibility: AS/PMA251 Applicable Forms: N/A
Use/relationship:
The ATR contains the results of the qualification tests performed by the contractor to demonstrate that the system conforms to the performance specifications, work authorization document, or contract requirements.
This Data Item Description (DID) contains format, content, and intended use information for the data product resulting from the work task described in the Statement of Work (SOW).
Requirements:
1. Format. Contractor’s format is acceptable.
2. Content. The ATR shall contain the following:
a. Test article identification and full description of test specimens utilized, including any deviations for the configuration specified in the applicable test plan.
b. Date and location of test or evaluation.
c. The operator who conducted the test.
d. Results obtained, including specific identification and discussion of objectives demonstrated satisfactorily and those not demonstrated satisfactorily.
e. Contractor’s conclusions, corrective action anticipated, recommendation to correct. deficiencies, and suggested improvements based on evaluation of the test.
f. All analysis and supporting data.
g. All data sheets.
3. End of DI-QCIC-81891.