DEC 2025 Equipment Only Consolidation Schedule

This document is a consolidation schedule outlining the timeline for a December 2025 equipment procurement process managed by the NAC (National Acquisition Center). The schedule establishes key milestones for all equipment modalities across the entire acquisition lifecycle, beginning with requirements submission and concluding with delivery order awards.

The procurement process follows a structured timeline with the following critical dates: requirements must be submitted to NAC by December 31, 2025; a Pre-Solicitation Notice will be published on January 28, 2026; the Request for Offers (RFO) and requirements will be posted on February 4, 2026; vendors have until February 18, 2026 to submit equipment questions; NAC will publish responses to vendor questions by March 11, 2026; vendors must submit offers by April 8, 2026; customers will receive vendor offers on April 15, 2026; customers must submit technical evaluations and best value selections by May 6, 2026; NAC will assign Contracting Officer (CO) workload on May 13, 2026; and the goal for awarding delivery orders is August 11, 2026, which represents approximately 90 days from CO workload assignment. All dates are identified as estimates and subject to change.

View the file

Other files

File Type Posted
DEC 2025 EQ Consolidation - RFO Updated.docx DOCX document
36A79726Q0004 0003.docx DOCX document
Continuation page..docx DOCX document
36A79726Q0004 0002.docx DOCX document
Copy of DEC 2025 EQ Consolidation - Schedule of Line Items W QA HD.xlsx XLSX spreadsheet
Updated Zipped Files.zip ZIP file
36A79726Q0004 0001.docx DOCX document
Vendor Folders.zip ZIP file
Copy of DEC 2025 EQ Consolidation - Schedule of Line Items-NAC-HTM.xlsx XLSX spreadsheet
DEC 2025 EQ Consolidation - RFO.docx DOCX document
VA Directive 6550 - New Appendix A - published Jun. 2023 02.pdf PDF
506B60008 - 558B69002.zip ZIP file
36A79726Q0004_1.docx DOCX document
Vendor Workup Spreadsheet - 36A79726Q0004.xlsx XLSX spreadsheet
VA Directive 6550 - New Appendix A - published Jun. 2023.pdf PDF
Memorandum for Training.pdf PDF
558B69003 - 674B60111.zip ZIP file
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEC 2025 Equipment Only Consolidation Schedule

Dates* Milestone – All Modalities

12/31/2025 Requirements due to the NAC in FORCE

1/28/2026 Publish Pre-Solicitation Notice

2/4/2026 Post Requirements and Request for Offers (RFO)

2/18/2026 Vendors to submit Equipment Questions to NAC

3/11/2026 NAC Published Responses to Vendor Questions via Amendment

4/8/2026 Vendors to Submit Offers to NAC

4/15/2026 Customers Receive Vendor Offers via the Shared Drive

5/6/2026 Customers Submit Technical Evaluations (Best Value Selections)

5/13/2026 NAC Assigns CO Workload

8/11/2026 Goal to Award Delivery Orders (90 Days from Assignment)

*Dates are estimates and are subject to change