DB ISID Sample Contract 2025 Tank and Soil Removal.pdf
PDF 1 MB Posted
- Attached to
- 2025 DB Tank & Soil ISID
- Solicitation number
- RFP-171-250000001560-3
- Issued by
- Michigan
About this file
This is a sample Design Build Indefinite-Scope, Indefinite-Delivery (ISID) Contract template from the State of Michigan Department of Technology, Management and Budget (DTMB) for 2025 Tank and Soil Removal services. The contract authorizes a Design Build Entity (DB Entity) to provide professional services for various State Departments and Facilities across multiple locations in Michigan. The contract will remain in effect for two years from the date of award but may be terminated by the State at any time. The DB Entity must provide design and construction services on an as-needed basis, with services including study, programming, schematic design, design development, construction documents, construction administration, and field services.
The contract does not guarantee any specific percentage or amount of work to the DB Entity. All work must be assigned and approved by the State through individual ISID projects before services can begin. The DB Entity's compensation is based on hourly billable rates for services rendered by personnel, plus authorized reimbursable expenses. Construction services are provided through either self-performed work (with prior approval) or subcontracted trades. The contract includes requirements for various types of insurance coverage, bonds, and compliance with prevailing wage rates. Special working conditions are detailed for different types of facilities including corrections, mental health, and other state properties.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
-1-
Design Build ISID
R 10/2024
STATE OF MICHIGAN
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
This contract authorizes the Design Build Entity to provide professional services. (Authority: 1984 PA 431)
CONTRACT FOR INDEFINITE-SCOPE, INDEFINITE-DELIVERY
FOR
2025 Tank and Soil Removal Design-Build Indefinite Scope Indefinite Delivery (ISID) SERVICES
THIS CONTRACT, authorized this DAY of MONTH in the year two-thousand and YEAR (2025x), by the State Administrative Board/Director, Department of Technology, Management and Budget, BETWEEN the STATE OF MICHIGAN acting through the STATE FACILITIES ADMINISTRATION, DESIGN AND CONSTRUCTION DIVISION of the DEPARTMENT OF
TECHNOLOGY, MANAGEMENT AND BUDGET, 3111
West Joseph Street, Lansing, Michigan, hereinafter called the State, and
DB ENTITY NAME
DB ENTITY ADDRESS Line 1
CITY, MI ZIP
hereinafter called the Design Build Entity (DB Entity), WHEREAS, the Department of Technology, Management and Budget State Facilities Administration (SFA), Design and Construction Division (DCD) [The Department] proposes securing Design Build Services for the following project:
Indefinite-Scope, Indefinite Delivery Contract No. 00XXX Department of Technology, Management and Budget State Facilities Administration, Design and Construction Division Design Build Indefinite-Scope, Indefinite-Delivery (ISID) Contract for Tank and Soil Removal Various State Departments and Facilities Various Site Locations, Michigan
NOW THEREFORE, the State of Michigan and the DB ENTITY in consideration of the covenants of this Contract agree as follows:
The State of Michigan has accepted the DB Entity’s offer to provide the goods or services in accordance with the Design Build Contract’s terms and specifications. The DB Entity agrees to supply the goods or services at the price and on this contract’s terms and conditions, and to assume and perform all the covenants and conditions required of the Contractor. The State of Michigan agrees to pay the DB Entity the Contract Price for the supply of the goods or services and the performance of the DB Entity’s covenants.
SAMPLE
rayyans Highlight
-2-
The DB Entity shall provide the design and construction services on an as-needed basis at Various State/Client Agencies within the various locations as defined by the State of Michigan, in strict accordance with the contract and subsequent ISID assignments.
The State of Michigan shall compensate the DB ENTITY for providing services as outlined in the terms and conditions of this Contract and any subsequent ISID assignment.
This ISID contract will remain in effect for two (2) years from the date of this contract award but may be unilaterally terminated by the State of Michigan, at any time, for cause or its convenience, by written notification of the State of Michigan, to the DB Entity.
This contract does not warrant or imply to the DB Entity entitlement to perform any specific percentage (%) amount of compensation, work or projects during the life of this contract.
The DB Entity is not to provide any design or construction services or incur any expenses until individual ISID projects are assigned to this contract and approved by the State of Michigan.
PLEASE NOTE: For this Design Build ISID contract, your permanent assigned ISID Contract Number, as noted above, must be provided on all correspondence and documents.
The DB ENTITY shall provide the professional services for the Project in the sequence outlined in this Contract in accordance with the Department’s approved and attached Appendix - Project/Program Statement and the attached Appendix - Department’s “Design and Construction Consultant Services Utilization Manual” and be solely responsible for such services. The DB ENTITY services shall be performed in strict accordance with this Contract.
SAMPLE
-3-
IN WITNESS, WHEREOF, each of the parties has caused this Design Build ISID Contract for Minor Projects to be executed by its duly authorized representatives on the dates shown beside their respective signatures, with the Contract to be effective upon the date on which the DB ENTITY received a copy executed by the authorized State of Michigan representative(s) by regular, registered, or certified mail or by delivery in person.
FOFOR THE DESIGN BUILD
ENENTITY:
Firm Name SIGMA Vendor Number
Signature
FOR THE STATE OF
MICHIGAN:
Date Title
Director Date
Department of Technology, Management and Budget
SAMPLE
-4-
NOW THEREFORE, the Department and the DB ENTITY, in consideration of the covenants of this Contract, agree as follows:
WHEREAS this Contract constitutes the entire agreement between the parties, any Contract Modification of this Contract and the Department’s approved and attached Project/Program Statement must be in writing, signed by duly authorized representatives of the parties, and shall be in such format and detail as the State may require. No Contract Modification may be entered into to compensate the DB ENTITY for correcting, or for responding to claims or litigation for, the DB ENTITY’s Contract Documents, design errors, omissions, or neglect on the part of the DB
ENTITY.
The definition of terms and conditions of this Contract are described and outlined in the following Articles and attached appendices.
This Contract provides two (2) distinct types of DB ENTITY services. These professional services may be coordinated and combined, or used singularly, depending upon the flexibility required by the Project.
The two (2) distinct types of DB ENTITY services for this Contract are defined as follows:
I. DESIGN SERVICES: Provide complete architectural and engineering design/build, specialized study services, or other professional services. The design work activities will be performed either by the DB ENTITY or through their Consultant(s).
The DB ENTITY’s design work may be provided by either the DB ENTITY’s office staff, or a third-party consultant procured by either the State of Michigan or the DB ENTITY. The Department may also elect to use a design/build approach combining the design and construction orders to provide an integrated, expedient, delivery approach.
Design and Construction Consultant (DB ENTITY) Services: The following Phase description(s) outline the DB ENTITY design services that may be necessary, but may not be limited to, accomplishing the scope of work.
Phase 100 - Study Provide complete and comprehensive Study Deliverables to meet the requirements of the Project.
Upon completion of all field investigation or research, prepare a complete Study Report with an executive summary, and in such detail, as the Project Director may prescribe.
Phase 200 - Programming Research the physical, functional, and programmatic relationships required by the State/Client Agency.
-5-
Prepare a Program Statement with a complete building or facility program, listing all spaces organized by department and staff classification, adjacencies, uses, and other needs. Include information on required environmental conditions, building systems, equipment, adjacencies, security, and special conditions needs for each space.
Acceptance and approval of the Program Statement by the Department does not limit subsequent inclusion of minor, but essential, programmatic or design details whose necessity and arrangement may best become apparent during subsequent Phases of the Project design.
Phase 300 - Schematic Design Upon written authorization from the Project Director, prepare Schematic Design Deliverables consistent with the Project requirements and the approved Program Statement. Schematic Design Deliverables shall consist of drawings, outline specifications, a Schematic Construction Cost Estimate, other related documentation, and shall diagrammatically depict the areas, scales, and relationships of the functions, as described in the approved Program Statement.
Acceptance of the Schematic Design by the Department does not limit subsequent inclusion of minor, but essential, schematic or design details whose necessity and arrangement may best become apparent during subsequent Phases of the Project design.
Phase 400 - Design Development Upon written authorization from the Project Director, prepare Design Development Deliverables based on the Owner-accepted Schematic Design.
Design Development Deliverables shall consist of drawings, specifications, Construction Cost Estimates, other related documentation, and shall further define the Project by fixing and describing the Project size, character, site relationships, and other appropriate elements including the civil, structural, architectural, mechanical, electrical, and fire suppression systems.
Phase 500 - Construction Documents and Bidding Documents Upon written authorization from the Project Director, and based on the Owner-approved Design Development, prepare Construction Documents that revise, refine, amplify, and depict, in detail, the Project. Construction Documents shall set forth, in detail, quality levels of and requirements for the construction, and shall consist of drawings and specifications that comply with applicable regulatory and construction code requirements, enacted at the time of completion of the one hundred percent (100%) Construction Documents. The Construction Documents shall contain all information necessary to bid and construct the
Prepare Bidding Documents in Phases/Bid packages appropriate to the Project requirements and funding.
-6-
Phase 600 - Construction Administration, Office Services Upon written authorization from the Project Director, provide all required construction administration and timely professional and administrative services, as the circumstances of the Construction may require, to allow the successful implementation of the Construction Documents into a completed Project, ready for occupancy, and/or for the use intended by the Owner.
Phase 700 - Construction, Field Services Upon written authorization from the Project Director, provide all required Construction Field Services, including timely inspection and professional services, as the circumstances of the Construction may require, to allow the successful implementation of the Construction Documents into a completed Project, ready for occupancy, and/or for the use intended by the Owner
II. CONSTRUCTION SERVICES: Provide complete construction labor, equipment, materials, and all appropriate construction services such as supervision, scheduling, estimating, etc., to construct the Project.
This Contract will provide all construction trades work. The DB ENTITY’s construction labor force may be used for select self-performed trades and general conditions work. Any self-performed trades and general conditions work must be justified and preapproved by the Director- FA. The DB ENTITY may also obtain construction trades subcontracts.
ARTICLE 1
PROFESSIONAL SERVICES
The DB ENTITY, their sub-contractors, and their consultants shall provide all professional and construction services, technical staff, and support personnel necessary to achieve the Project, in the best interest of the State, and be within the DB ENTITY’s not-to-exceed fee(s) authorized by the State. The Department shall provide Project objectives of scope, program, schedule, constraints, criteria, funding, and budget as promptly as practicable.
Project services shall comprise, without exception, every professional design/build construction discipline and expertise necessary to meet all the requirements of the Department’s approved and attached Appendix - Project/Program Statement and the Department’s, “Design and Construction Consultant Services Utilization Manual, Sample Department Design/Build Forms and Work Flow Procedures Chart”, be within the amount authorized by the State, and be in accordance with the industry-accepted standards for professional design/build construction practice and services. DB ENTITY services shall be provided in accordance with this Contract and their DB ENTITY’s Project Hourly Billing Rate Compensation.
Information: The Department will make available information known to the Department which may be needed to fulfill the professional responsibility of the DB ENTITY. This information may include but is not limited to prints of existing construction or record drawings and Department or Client Agency standards, regulations, schedules, and guides. Such documents shall be the most recent and accurate available. The use of any such data by the DB ENTITY shall be without contractual or legal significance, unless otherwise established elsewhere in this Contract.
However, the Department’s provision of information shall not relieve the DB ENTITY from the responsibility of conducting a field survey to verify existing conditions.
Principal-In-Charge: The DB ENTITY shall designate a principal-in-charge for this Project, to
-7-whom the Department will address questions and concerns regarding this Contract and the DB ENTITY’s performance.
Substitution: No substitution of any “Key Principal Personnel/Employee” identified in the DB ENTITY attached Proposal or of any of the DB ENTITY’s contractors or consultants will be allowed without written consent from the Project Director and a completed and approved Professional Services Contract Modification form (DTMB-0410).
Project Director: The Department will designate an individual to serve as the Project Director who shall be the State of Michigan’s primary representative in the Project Team and have the authority and responsibility to render Project decisions and furnish information. The DB ENTITY is responsible solely to the Project Director for the adequacy and timeliness of their services.
If the Department or Client Agency observes or otherwise becomes aware of any Defective Work or other fault or defect in the Project, the Department will provide prompt notice thereof to the
DB ENTITY.
The Project Director, or the Owner’s Field Representative, has the authority to require the DB ENTITY to respond to and resolve design related problems, construction field problems, and to attend Project related meetings. Unless delegated by specific written notice from the Department, the Owner’s Field Representative does not have any authority to order any changes in the scope of work or authorize any adjustments in Contract price or Contract time.
The Project Director has that sole authority.
Department’s Field Representative: The Department will designate an individual or individuals to serve as the Owner’s Field Representative (OFR) under the direction of the Project Director.
The OFR’s primary duty is to monitor the coordination and progress of the DB ENTITY’s services and the Construction Contractor(s)’ work. The OFR also acts as the liaison between, the DB ENTITY, the Client Agency, any of the Department’s consultants or contractors, and the Project Director. The OFR may be full or part-time, at the Department’s discretion.
First Interpreter: The DB ENTITY acknowledges the Project Director is the first interpreter of the DB ENTITY’s performance under this Contract.
Standard of Reasonable Care, Legal Responsibility: The DB ENTITY shall perform all its services in conformity with the standards of reasonable care and skill of the profession, notwithstanding any other provision herein. The DB ENTITY shall be responsible for the performance of persons retained by them and states that its employees, agents, officers, consultants, and subcontractors possess the experience, knowledge, licensure, and character to properly perform their duties.
Professional Qualifications: Professional services shall be performed by members of the profession involved, who practice under the authority of and who are governed by the license(s) issued under PA 299 of 1980 (Michigan Occupational Code).
-8-
Understanding of Project Scope: The DB ENTITY acknowledges having a clear understanding of the requested Project scope of work and the professional architectural and/or engineering study, design, construction, and construction administration services required to provide them.
Completeness: The DB ENTITY shall provide all services, technical staff, and support personnel necessary to achieve the Project, in accordance with the Appendices to this Contract, any applicable sections of the Michigan Compiled Laws, any applicable state rules and regulations, any applicable federal and local statutes, ordinances, rules, and regulations, and in accordance with the DB ENTITY’s attached Project Study, Design and Proposed Construction Schedule.
Sufficiency: The DB ENTITY agrees the terms and conditions of this Contract provide adequate compensation to provide the requested services; furthermore, any modification to the terms and conditions of this Contract will be requested in writing.
Subcontracts and Consultants: The DB ENTITY may use Subcontractors and Consultants upon written approval by the Department or by their inclusion in the Proposal. Consultants or Contractors to the DB ENTITY shall not be construed to have a contractual relationship between the Department and said consultant/subcontractor. The DB ENTITY holds the professional and contractual responsibility for any work performed or delivered under this Contract, regardless of whether the DB ENTITY or a consultant provided the work. Subcontracts for services under this Contract shall provide that work performed under such Subcontract shall be subject to provisions of this Contract and shall also provide that any duty or responsibility pertaining thereto, shall be accomplished to the benefit of the Department. Upon request, an electronic copy of each such Subcontract shall be furnished to the Department.
Understanding of Construction General Conditions: The DB ENTITY shall review and become familiar with the current MICHSpec and DCSpec General Conditions of the Contract for Construction and shall provide services and work consistent with these General Conditions. It is preferred that the DB ENTITY uses these General Conditions for its subcontracts for construction. The DB ENTITY may submit an alternate form of General Conditions for review by the Department. If approved, the DB ENTITY may use that alternate form of General Conditions.
Consultant: The DB ENTITY shall not employ nor consult with any firm(s) in completing its obligations who it anticipates will be a construction Bidder for the Project or any part thereof, unless specifically authorized, in writing, by the Department.
Cooperation with Department’s Consultants: The DB ENTITY agrees to cooperate with any Consultant retained by the Department.
Cooperation and Coordination with State Employees: The Project Director, the OFR, or other State employee(s) may perform duties or activities analogous or parallel to the DB ENTITY’s services outlined under this Contract. Notwithstanding these activities, the DB ENTITY shall provide all the services required under this Contract.
-9-
Construction Means and Methods: The DB ENTITY, through its subcontracts or by self-performing construction activities, shall be responsible for construction means, methods, techniques, sequences, procedure, and supervision or for safety precautions and programs in conjunction with the Project. The DB ENTITY is responsible for its internal safety policies, procedures, equipment, and precautions.
Increased Compensation for Additional Project Scope: The DB ENTITY shall immediately inform the Department whenever it believes the scope of services included in this Contract would be exceeded. The DB ENTITY’s base services fee may be increased only upon an accepted and approved Contract Modification (DTMB-0410)
Increased Compensation for Bulletins and Change Orders: The DB ENTITY’s base services fee will be increased for the preparation of Bulletins and Contract Change Orders resulting from increases in the scope of work or previously unknown field conditions, as approved by the Project Director, on an hourly billing rate basis. This compensation shall not exceed seven and half percent (7.5%) of the Construction Contractor’s quotation for the Bulletin or Contract Change Order, or an amount mutually agreed upon by the DB ENTITY and the Project Director.
Addenda and Bulletins: Upon notice or discovery, and as directed by the Project Director through issue of a Bulletin Authorization, the DB ENTITY shall perform the required services to issue Addenda to the Bidding Documents, or Bulletins to the Contract Documents, to correct or clarify errors, omissions, or ambiguities, without additional compensation.
Coordination and Communication: Coordinate the DB ENTITY’s staff, Consultants, and all other Project related resources. Preside at all Project related construction meetings. Prepare and distribute copies of minutes of all meetings, correspondence, memoranda, records of telephone or other conversations and communications, and reports of all on-site visitations.
Where essential or significant information is established or evaluated, where critical problems are identified, and/or where critical decisions are made outside meetings, incorporate a record of such into the next meeting record or provide and distribute written record to the Department and participants within two (2) business days following the date of occurrence. Otherwise meeting minutes shall be distributed within five (5) business days, as the Department may direct.
The DB ENTITY’s study and design/build construction schedule shall be detailed, dated, and time sequence related for all services appropriate for the scope of work.
The DB ENTITY shall field check and verify the accuracy of all drawings, and any data furnished by the Department, the State/Client Agency, or any other Project related source.
Professional Services and Instruments of Service Review: The Department shall review and accept or reject the DB ENTITY’s submittal of the respective phases of study or design services, Instruments of Service, and/or construction services, for conformance with the provisions of this agreement. The Department may require a written response to all questions and concerns raised regarding such services. The Department’s review and any acceptance of the DB ENTITY’s submittals does not relieve the DB ENTITY of its responsibilities. The Department will perform reviews and respond with comments, direction, or decisions promptly. The Department will coordinate Client Agency and Department staff comments prior to issuance.
Construction Inspection and Construction Administration: Where the DB ENTITY’s Contract includes provision and administration of construction contracts, the DB ENTITY shall use the Department’s “DTMB-0460 Project Procedures” package of forms and documents as
-10-included in the attached appendices.
Final Design/Build Bidding Documents and Review: The DB ENTITY shall provide their Bidding Documents for review to the Project Team at 50 and 90 percent (%) completion and incorporate all required modifications and comments. If the final design appears to exceed the Project Budget, review with the Department cost reduction options and incorporate them with the Department’s concurrence. Determine and confirm, in writing, the final design/build can be achieved within the Project Budget. Obtain written approval of the final Bidding Documents from the Department.
Code Compliance: The DB ENTITY’s Contract Documents shall comply with the State of Michigan Construction Code, 1972 PA 230, as amended, the State of Michigan Energy Code, the Americans With Disabilities Act (ADA) Accessibility Guide requirements, the State of Michigan Barrier-Free Access Code requirements, and all Project related construction code requirements, in effect at the time of award of this Contract. The DB ENTITY shall advise and assist the Department with decisions on the Americans with Disabilities Act accessibility compliance. Assist the Department in obtaining approval of the Project and its design by appropriate governmental regulating and/or code enforcement authorities. Soil Erosion and Sedimentation Control plans/drawings will be submitted to the Department, no later than at the final design, 90 percent completion submittal stage. Submit documents to the Department of Labor and Regulatory Affairs (LARA) for review in a timely manner allowing appropriate time for review/permitting processes by respective authorities, such that the Project schedule is not unnecessarily delayed. Assist the State/Client Agency to secure any appropriate construction code waivers. Incorporate all required modifications into the Contract Bidding Documents.
Follow through to ensure issuance of the construction codes and permits approvals. Secure all required design approvals before proceeding to construction. Any approval secured does not relieve the DB ENTITY from complying with the construction field Inspections review/enforcement requirements. Design code compliance and plan review approval fees shall be paid by the DB ENTITY and will be compensated by the Department to the DB ENTITY as an authorized Contract reimbursable expense.
Hazardous Materials: Where the Project involves work in an existing building and/or utility system, assist the Department to determine the scope of potential hazardous materials contamination that may require testing, abatement, and/or removal, prior to the renovation and/or during the new construction work of the Project. Hazardous materials testing and removal will be performed by the Department, with other Professionals, by separate Contract, who are licensed and insured to perform this service. Coordinate the services of this Contract with any hazardous material removal services required to implement this Project.
Sustainable Design and Construction: Sustainable Design and Construction practices shall be used wherever possible by the DB ENTITY.
-11-
Specifications: Performance specifications shall be used when feasible. If performance specifications are not feasible, the DB ENTITY shall name at least three (3) acceptable materials, products, or systems; and the specifications shall contain an "or equal" clause. Whenever possible, recycled materials and/or products produced in the State of Michigan, shall be named and given first preference. Proprietary specifications or allowances may be permitted, with the Department's acceptance and written approval, but only for special, unavoidable conditions.
Provide specifications, when requested by the Department, for purchasing or construction bidding items necessary to be pre-purchased through existing State Contracts, direct Bid materials, or equipment. Copies of the latest “State of Michigan Building Products List” may be obtained through the “Contract Connect” internet web site at http://www.michigan.gov/buymichiganfirst/0,1607,7-225-48676-209976--,00.html.
Checking Contract Documents: Check and coordinate all Contract Documents for completeness and accuracy. Cross-check and coordinate the requirements of all Contract Documents, including specifications, between the design disciplines for completeness, accuracy, and consistency.
Construction Bidding and Contracting Procedures: The DB ENTITY shall prepare and distribute Bidding Documents and instructions as required to accommodate predetermined construction Bid packages and/or Phases, conduct pre-bid meetings, and issue complete preconstruction Addenda to all qualified construction Bidders as required. Exert every practical means to obtain several, qualified, construction Bidders for every Construction Contract. The Department will make its online bidding advertisement system available. The DB ENTITY will be compensated by the Department with a Contract Change Order for providing the services necessary to rebid the Project for reason of defaulted or disqualified construction Bidder(s) or unacceptable price range as required by the Budget. The DB ENTITY’s construction bidding and contracting services are not complete until: (1) The lowest responsive, responsible, qualified construction Bidder’s Bid has been selected and accepted by the Department; and (2) The lowest responsive, responsible, qualified construction Bidder's Construction Contract has been fully executed by the construction Bidder and the DB ENTITY.
Construction Bid Evaluation and Recommendation of Construction Contract Awards:
Monitor, review, evaluate, and provide the Department with written recommendations for the apparent lowest responsive, responsible, qualified, construction Bidder within five (5) business days of the date of the Department’s construction Bid opening. Exempt from recommendation any firm that the DB ENTITY has business association with this Project, and any firm(s) having any Consultant the DB ENTITY has used in preparing the final Contract Documents or for any estimating work related to the Project. The DB ENTITY shall conduct pre-contract meetings with responsive, responsible, qualified, construction Bidder(s) to review, at minimum, the following items: (1) The design intent of the DB ENTITY’s final Contract Documents; and (2) To advise and assist the Construction Contractor(s) in understanding the requirements of the General Conditions, scope of work, and its Construction Contract award procedures. If applicable, the DB ENTITY firm shall use the MICHSPEC (Long Form) during the Project Construction Bidding and the Construction Contract Award.
http://www.michigan.gov/buymichiganfirst/0%2C1607%2C7-225-48676-209976--%2C00.html
-12-
Safety: In observed cases, which may involve danger to human life, immediate safety hazards to personnel, existing or impending damage to the Project, to State/Client Agency property, or to other property; as may be impacted by the Project, the DB ENTITY shall inform the Construction Contractor(s) of the situation and their observations. The DB ENTITY shall immediately record and report such situations to the Department and certify any accrued Project costs in writing.
The DB ENTITY shall have access to the Construction Contractor(s) work at all times.
Establish and maintain effective construction Phase administration, office procedures, systems, and records to progressively, and exclusively, manage and control the DB ENTITY’s obligations, commitments, achievements, and expenditures under this construction Phase administration.
Monitor the quality and progress of the Project construction Phase work. Maintain all necessary Project records, provide on-site visitation reports, and provide all administrative office action as may be necessary to inform the Construction Contractor(s), in writing, with respect to their compliance with the design intent of the DB ENTITY’s Phase 500 - Final Design Contract Documents/architectural and engineering drawings and specifications requirements.
Final Design/Build Correction Procedures: Correct, at no additional cost to the Department, any final design/build errors or omissions and/or other Project related deficiencies identified during the Construction Phase. All reproduction costs for design interpretation clarifications and Bulletins related to the DB ENTITY’s final design/build errors or omissions and similar, or avoidable costs shall be accounted as part of the DB ENTITY firm’s calculated mark-up. Provide design clarifications and interpretations of the Contract Documents requirements necessary to:
(1) Adequately describe the Project work; (2) Adapt final design/build documents to accommodate on-site field conditions identified during construction; (3) Refine design details that are not feasible and identified during construction; and (4) Comply with current construction/building codes, and all other Project related design and construction matters, as may be necessary to produce a complete Project.
Design Interpretations and Clarifications: For elements of construction having no respective change in cost to the State, the DB ENTITY will provide instructions, and/or design interpretations and clarifications for design details within five (5) business days of the Construction Contractor's request, record same, in writing; and revise the DB ENTITY firm’s original final design/build drawings and specifications as appropriate to the Project scope.
Marking and initialing of drawings is not an acceptable form of written instruction.
Shop Drawings/Submittals/Approvals: Monitor, evaluate, and provide administrative action, as necessary, to achieve timely processing of shop drawings and such other submittals and approvals that are the responsibility of the DB ENTITY. Maintain a record of all required, received, rejected, and approved submittals of shop drawings, color/material samples, finishes, and other items requiring the DB ENTITY’s approval. Notify the Construction Contractor(s), in writing, (copy to the Department) of delinquent submittals, the consequences of such delays, and prescribe a time schedule for their submittal/resubmittal which will not jeopardize the Project completion date.
-13-
No design revisions will be made as part of the DB ENTITY’s review and approval of shop drawings, or other submittals. In addition to all other functions, the DB ENTITY’s approval of shop drawings shall verify the submittals furnished conforms to the design intent of the Contract Documents. Provide written approval or rejection of shop drawings within ten (10) business days of receipt. Provide and distribute approved submittals as directed by the Department.
Construction Schedule Progress: Monitor, evaluate, and provide timely action, as necessary, to achieve the Project on time and on schedule. Advise and assist the Department in taking all practical steps necessary to address and complete the Project in the event of performance delays or defaults by the Construction Contractor(s). Evaluate any documentable impact on the Project construction schedule claimed by the Construction Contractor(s) arising from Bulletin work. Provide appropriate and timely action, under terms allowable under the Construction Contract, to implement any Bulletin work which the DB ENTITY and the Department consider critical to the Project construction schedule, but whose cost is disputed.
Within ten (10) business days of its receipt, evaluate and provide the Department with appropriate written recommendations, along with an analysis of any request by the Construction Contractor(s) for a time extension of their Construction Contract completion date.
No recommendation for a Construction Contract time extension may be submitted to the Department which is not substantiated by the DB ENTITY’s technical review and evaluation showing critical path work, noncritical path work, and float time for the complete Project and any work at issue and having such detail as to clearly document the Construction Contractor's claim.
Any recommendation for a time extension of the Construction Contractor’s Contract completion date must include a complete analysis of all direct and indirect costs of the Construction Contractor, the DB ENTITY, and the Department regarding the time extension.
Where the Project is not substantially complete on the Construction Contract completion date, the DB ENTITY may be liable for withholding of liquidated damages.
Construction Testing Program: Monitor, evaluate, and provide timely action in response to the results of the construction quality control and material testing program. In circumstances where the testing is not provided by the Department, evaluate and approve/disapprove the Construction Contractor(s) work plan for providing all construction test reports. Provide the Construction Contractor(s) and the Department with written evaluation of all construction test reports, copies of construction test reports, marked with the DB ENTITY’s approval or disapproval within five (5) business days of receipt of the report. Direct the Construction Contractor(s), in writing, to take appropriate, corrective, or replacement measures within a prescribed time period for any construction test reports not meeting the Construction Contract requirements. Follow up, as appropriate, to require the Construction Contractor(s) to achieve the design intent of the DB ENTITY’s final design Contract Documents, drawings, and specifications and avoid delays to any element of work which may, in the DB ENTITY’s opinion, result in a delay in the Construction Contract completion date. Notify the Construction Contractor, in writing, of any delinquent corrections/replacement and take administrative action in accordance with the Construction DB Entity performance text.
-14-
Construction Management and Inspection: The DB ENTITY shall provide and record sufficient field Inspections of the Project to administer the Project, as directly related to the degree of Project complexity and scope of work, up to and including full-time field Inspections.
The construction field Inspections shall occur as the construction on-site field conditions and the Project may require and during the regularly scheduled progress and payment meetings.
The DB ENTITY shall use only personnel having such professional expertise, experience, authority, and compatibility with departmental procedures as the Department may approve. The DB ENTITY agrees that such characteristics are essential for the successful completion of the Project. Such individuals shall be replaced for cause where the Department determines and notifies the DB ENTITY, in writing, of their unacceptable performance.
All construction progress Inspections shall be recorded in the form of a written report to the Department and the Construction DB Entity within five (5) business days of the Project construction progress Inspection. The purpose of such Inspection/visitations includes, but is not limited to: (1) Achieve and maintain a working familiarity with the status, quantity, and quality of the Project construction work in place; (2) Determine if the actual Project construction schedule progress is in accordance with the approved schedule; (3) Review the installation and determine the acceptability of preparations for, and installation of, pending critical components and activities; and (4) The Inspection of Project construction work completed or in progress by the DB Entity to determine and verify, in writing, to the Project Director and Owner’s Field Representative that the quantity and quality of all Project construction work is in accordance with the Contract Documents.
The DB ENTITY shall review the Project construction work in place and that which is sequentially planned. The DB ENTITY shall determine whether the actual Project construction schedule progress appears to be in accordance with the approved construction schedule and whether the quality of the work appears to be in accordance with the design intent of the Contract Documents and is without apparent defects or deficiencies. No on-site advertising by, or of, the DB ENTITY or Project signs other than those appropriate to locate an approved field office will be permitted.
Problem Solving Meetings: Conduct and record problem solving meetings between the DB ENTITY and its Consultants, the Construction Contractor(s), their subcontractors, the Department, Project Director, and their Owner’s Field Representative, and any construction managers and other affected parties, on-site or elsewhere to assess the construction work progress. Provide design interpretation decisions to resolve problems affecting the construction work. These problem-solving meetings shall be scheduled as the construction field conditions and the Project requirements may require, and/or shall be at such time as the Construction Contractor(s), the DB ENTITY, the Department, Project Director, Owner’s Field Representative, and any construction manager agree is appropriate to the Project work progress. Non-scheduled or emergency meetings shall be held at such time as necessary to maintain the schedule of various work items and to avoid delays in the Contract completion date. SAMPLE
-15-
Progress Meetings: Conduct and record monthly scheduled Project construction progress meetings with the Department, Project Director, Field Representative, the State/Client Agency, the Construction Contractor(s), and any construction manager. Assess work progress and provide timely action as necessary to maintain the work schedule and respond to and resolve all design related and construction items affecting the Project cost and be in compliance with the Contract Documents.
Final Project Inspection: Conduct final construction field Inspections of the Project, in concert with the Construction Contractor(s), the Department, Project Director, Field Representative, the State/Client Agency, and any construction manager. Final Project field Inspections shall be conducted to witness and record equipment start-up and all testing, verify, in writing, each Construction DB Entity has achieved Substantial Completion, prepared Punch List(s) items, and determine the status of any part of the Project work where the Department intends to take beneficial use or occupancy. Verify to the Project Director and OFR, in writing, the completeness and accuracy of the Construction Contractor’s as-built drawings and identify any corrections required.
Construction DB Entity Performance: Monitor and evaluate the Construction Contractor(s) performance and provide timely action to cause the Construction Contractor(s) to correct their construction deficiencies. With the Department's concurrence, the DB ENTITY may direct, in writing, the exposure and testing of any Project construction work, already in place or covered, which the DB ENTITY, and/or the Department, believes may not meet the design intent of the DB ENTITY’s final design requirements.
Notify the Construction Contractor, and the Department, in writing, within five (5) business days its identification of any aspect of the Construction Contractor's performance which is inconsistent with the Contract Documents requirements or which, in the DB ENTITY’s opinion, is inconsistent with the design intent of the Contract Documents. Prescribe a reasonable time for correction which will not jeopardize the Project construction schedule completion date. Exert all practical means necessary to require the Construction DB Entity to perform, as required by their Construction Contract, the design intent of the Contract Documents.
Deficient Performance: Upon identification of deficient performance, where the Construction DB Entity fails to provide timely or acceptable performance, the DB ENTITY shall proceed as follows: (1) Notify within three (3) business days the Department, the Construction Contractor, and any affected surety, in writing and by registered mail delivery, of the potential for the Construction Contractor’s default action and the DB ENTITY’s recommendation; (2) Identify applicable Construction Contract references, with design interpretation of such references, and clearly explain where the Construction Contractor's performance fails to meet the design intent of the DB ENTITY’s final design drawings and specifications requirements; and (3) Specify a time and date for the Construction DB Entity to begin active and continuous work towards Contract compliance with a specific time and date for completion.
-16-
Bulletin Authorization: Request authorization to issue each individual Bulletin. The DB ENTITY 's Bulletin Authorization request will: (1) Identify the problem requiring the change; (2) Describe clearly if such problem arises from the final design/build errors or omissions; (3) Identify the anticipated design cost and the estimated construction cost to implement the change(s); and (4) Describe clearly in the DB ENTITY’s opinion which part, if any, of the design and/or construction costs are the obligation of the State, the DB ENTITY or the Construction Contractor. Include a Contract Modification request for any work outside the scope of work. Identify any anticipated schedule implications.
Bulletins: All reproduction costs for design interpretations and clarifications and Bulletins related to the DB ENTITY’s final design/build errors or omissions and similar, or avoidable costs shall be accounted as part of the DB ENTITY’s calculated mark-up. Describe, by Bulletin, design revisions necessary to correct the final design/build errors or omissions, to address previously unidentified on-site field design conditions, to reduce costs, and for all other matters approved by the Department involving costs or credit to the State. Postponement of action on items in order to accumulate multi-item Bulletins is not permitted.
Prepare and issue Bulletins within ten (10) business days of receipt of the Department's authorization. Bulletins shall be in such form and detail as the Department may prescribe. All Bulletin revisions shall be incorporated, by the DB ENTITY, into the appropriate originals of all applicable Contract Documents. Revised drawings and specifications shall be issued as part of any Bulletin. Each Bulletin shall prescribe a schedule for the Construction Contractor's response.
Provide copies of each Bulletin to the Department and distribute as the Department may direct.
Evaluate the Construction Contractor's price quotation(s). Review and attempt to negotiate with the Construction DB Entity to provide the Department with costs that are consistent with the value of the Project Bulletin(s). Recommend appropriate action to the Department regarding the Construction Contractor's quotations within five (5) business days of receipt thereof.
Payment Procedures: Monitor, evaluate, and provide timely administrative action, as necessary, to certify or reject, as appropriate, and process the DB ENTITY’s subcontractors and consultants schedule of costs and monthly submitted payment requests.
The DB ENTITY will certify or reject all submitted payment requests from its subcontractors and consultants, in writing, within ten (10) business days of receipt in the DB ENTITY’s office. The DB ENTITY shall determine and certify to the Department, in writing, the dollar amount to be due in the subcontractor/consultant’s monthly payment request. or the DB ENTITY shall return the payment request, with explanation, rejecting the payment request certification. If a payment request is rejected, the request shall be returned to the submitting party accompanied by a written explanation, and a copy shall be given to the Department’s Project Director. If a payment request is returned to the DB Entity or subconsultant, that entity shall make the necessary corrections and resubmit that payment request to the DB ENTITY. SAMPLE
-17-
The DB ENTITY will issue a payment certification only pursuant to a correctly prepared and accurate payment request and only for acceptable work. Payment certification shall constitute a written representation by the DB ENTITY, that based on their on-site field Inspections, evaluations of field reports, test results, and other appropriate and available factors, the quantity and quality of work for which the payment request is certified has been accomplished in accordance with the Contract and if applicable, materials are properly stored on or off-site.
No payment certificate shall be submitted that requests payment for disputed Project work or any Project work showing deficient test results. No payment request certificate may be submitted after the Contract completion date which does not provide for withholding of assessable and/or projected liquidated damages. Pursuant to the Department's notification, the DB ENTITY’s certification shall reduce from the amount earned, two (2) times the amount of any current prevailing wage rate payment deficiency, as certified by the Department of Licensing and Regulatory Affairs, Wage and Hour Division against the Construction DB Entity or any DB Entity or sub supplier thereof (See attached Appendix – Project Prevailing Wage Trade Labor Rates).
Punch List: Prepare and distribute, as required, Punch Lists for each Construction Contract.
Prescribe a reasonable time schedule for completion of all items and identify an amount to be withheld from payment consisting of a minimum of two (2) times the estimated value of the unacceptable construction work plus an amount sufficient to assure available funds to cover all costs, as may become necessary to complete the remaining delinquent work. Distribute Punch Lists within five (5) business days of the final Inspection. Notify the Construction DB Entity of any delinquent Punch List construction corrections and take appropriate action.
Close-Out Procedures: Within thirty (30) calendar days after Substantial Completion of the Project, provide to the Project Director: (1) All Project code compliance approvals; (2) Final Inspections; (3) Final occupancy permits; (4) As-built drawings; (5) Copies of “Operation and Maintenance Manuals” of the Project systems; and (6) Equipment warranties and guarantees.
Operation and Maintenance Manuals: Provide three (3) hard copies and two (2) electronic copies of "Operation and Maintenance Manuals" of the Project systems and equipment. These manuals shall include copies of reduced size, as-built drawings, specifications, and all instructions published or furnished by respective manufacturers, construction code compliance certificates, and guarantees. The manuals shall also include a complete description of the DB ENTITY firm’s final design/build intent concepts, operation, and required maintenance of each system. Participate in the Construction Contractor's start-up and training instruction of the State/Client Agency personnel in the operation and use of the Project systems.
As-Built Documents: Provide as-built drawings incorporating and depicting all construction modifications, additions, and deletions made either by Addendum, Bulletin, supplemental written instructions, and the written notations into the Contract Documents within thirty (30) calendar days after Substantial Completion of each Project.