Davis-SL_Env_Des_Req_ICE_030123.pdf

PDF 133 KB Posted

Attached to
Locally Preferred Alternative (LPA)
Solicitation number
2026-05
Issued by
Summit County, Akron City, Ohio

About this file

This is an Independent Cost Estimate (ICE) prepared by HNTB Corporation for the Davis-Salt Lake Community Connector Environmental and Preliminary Engineering (PE) Design Phase, a project involving the Utah Transit Authority (UTA) Public-Private Mobility Solutions Consortium (PMSC). The estimate details labor, travel, and other direct costs for environmental assessment and design services across a 12-month project timeline. The scope encompasses environmental management and NEPA document preparation, community engagement activities, preliminary engineering for 40 sites, design coordination, cost estimating, right-of-way (ROW) plan development for 40 locations, and constructability review, requiring specialized personnel across 20 labor categories.

The total estimated cost is $1,096,956, comprised of $1,045,968 in labor charges across 6,098 hours and $50,988 in other direct costs (ODCs). Labor rates range from $140 per hour for various technical positions to $280 per hour for survey crews, with the Project Manager allocated 566 hours at $238 per hour and Environmental Manager allocated 564 hours at $196 per hour. Other direct costs include $6,105 in travel and living expenses (mileage, meals, per diem, temporary housing, and plane tickets), $375 in communications and shipping (postage, express mail, and plotting submissions), and $1,000 in reproduction costs for drawing sets and document copies. The estimate is based on the Request for Qualifications (RFQu) draft dated January 23, 2023, with the estimate prepared by Greg Thorpe on January 25, 2023.

View the file

Other files

File Type Posted
Locally_Preferred_Alternative_(LPA).pdf PDF
METRO_RTA_LPA.xlsx XLSX spreadsheet
EX24059_Nelson_Nygaard_East_Colfax_final.doc.pdf PDF
Ice_form_-_LPA.pdf PDF
ICE_2025_Arterial_BRT_Plan_Update_Planning_Support_-_signed.pdf PDF
Davis-SL_Env_Des_Req_ICE_030123.pdf PDF
Ice_form.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UTA PMSC HNTB Task Estimate

Date Rev Sht of

1/25/2023 0 1 5

Item Initials Contract Rate Hours

1 PM $238.00 566

2 EnvM $196.00 564

3 ES $168.00 408

4 GIS $140.00 304

5 LP $168.00 336

6 CEM $154.00 204

7 CIP $140.00 128

8 EngM $224.00 484

9 DEIII $182.00 440

10 DEII $154.00 296

11 CAD $140.00 712

12 SurM $182.00 164

13 SurC $280.00 320

14 RM $182.00 260

15 RT $140.00 200

16 CR $210.00 64

17 QC $168.00 48

18 AA $140.00 544

19 SS $154.00 56

Subtotals 6,098

See RFQu for Details of Tasks. Based upon current RRQu draft dated 1//23/23.

Comments

$13,440

$99,680

$29,848

$89,600

$47,320

$28,000

$1,104,436

$0subtotal (Vendor Cost)

TOTAL COST

$1,000

$7,480

Communications and Shipping $0

$375Reproduction

Other ( see Form C ) subtotal (ODC Cost)

$1,096,956

$6,105Travel and Living

$108,416

$80,080

$8,064

$76,160

$8,624

Other Direct Cost (ODC)

$45,584

Discipline

Environmental and DesignDavis-Salt Lake Community Connector- Environmental and PE Design Phase

Task Description

$42,560

$110,544

Hours and Labor Charges

Engineering Estimate Summary Form

HNTB Corporation

Company

Greg Thorpe

Estimated By

$17,920

$56,448

Name (Last, First)

$31,416

$68,544

$134,708

Salary LaborCategory

Project Manager

Environmental Manager

Environmental Scientist- 106, 4(f), 6(f)

GIS Technician

Land Use Planner

Community Engagement Manager

Community Involvement Planner

Engineering Manager

Design Engineer III

Design Engineer II

CAD Technician

Surveying Manager

Survey Crew

ROW Manager

ROW Technician

Constructability Reviewer

Quality Control Manager

Administrative Assistant

Safety Specialist

File: Davis-SL Env Des Req ICE 030123 ...Form A-Hrs & Labor Charges

UTA PMSC HNTB Task Estimate

Rev Date

0 1/25/2023

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 U=Sum(A:T)

Row

WBS

Number Subtask Description P M

E n v M

E S

G

IS

L P

C E

M

C

IP

E n g M

D E

II

I

D E

II

C A

D

S u rM

S u rC

R M

R T

C R

Q C

A A

S S

0 Unit Total

1 Project Management- assume 12 months 192 8 200

2 Administrative Coordination, Invoicing, status reports, etc. 96 288 384

3 Bi-Monthly meetings 72 96 168

4 Quality Management Plans 8 4 4 4 4 24 48

5 Environmental Management, assume 8 months 256 256

6 Environmental Scientist, data collection, traffic info and plans, etc. 192 192

7 GIS support, data development 256 256 40 24 24 40 640

8 Community Engagement Management 128 128 256

9 Meetings with Stakeholders and Public meetings- aqssume 16 total 64 64 64 64 64 320

10 FTA-Compliant NEPA Document preparation 24 80 120 40 40 304

11 Agency Coordination and Technical Analyses- assume 8 meetings 24 64 64 64 40 256

12 Comment period Assistance 8 16 32 8 16 12 16 108

13 Mitigation measures development 8 16 24 24 16 16 104

14 Final Document preparation 8 24 40 24 24 120

15 Preliminary Engineering (30%)- 40 sites 8 64 128 256 512 160 320 1,448

16 Design coordination meetings- monthly 12 24 24 24 24 108

17 Cost Estimating 16 80 160 80 80 24 440

18 Develop Basis of Design Report 8 40 40 40 40 16 184

19 Develop ROW Plans- assumes 40 locations 4 16 24 160 24 80 308

20 Determine permitting requirements 8 16 16 16 56

21 Constructability Review- assumes 2 meetings 4 16 24 40 40 24 148

22 Safety and Security Analysis memo 2 8 40 50

23 0

24 0

25 0

26 0

27 0

28 0

29 0

30 0

Total Hours 566 564 408 304 336 204 128 484 440 296 712 164 320 260 200 64 48 544 56 0 6,098

Estimate Detail Sheet Estimated By

Greg ThorpeHNTB Corporation

Task Description

Davis-Salt Lake Community Connector- Environmental and PE Design Phase

Company Discipline

Environmental and Design

File: Davis-SL Env Des Req ICE 030123...Form B- Task Desctriptions

UTA PMSC HNTB Task Estimate Printed:

1/25/2023 0 3 5

Subtotals

$0.65 per mile 2500 miles 1,625

$600.00 per trip 4 trips 2,400

$150.00 per night 8 nights 1,200

$40.00 per day 12 days 480 per day days 0

$1,400.00 Per Week Weeks 0

Per Month Months 0

Each 0

$50.00 Per Day 8 Days 400

6,105

Per Month Months 0

Per Month Months 0 per foot plots 0

$0.15 per copy 1000 copies 150

$0.25 per copy 500 copies 125

$0.25 per copy 400 copies 100

$1,000.00 1,000

Each 0

1,000

Amount

Total for Vendors

GSA Mileage Rate for 2023 @

Task Description

Lump Sum

Discipline

Environmental and Design

For All Subtasks

Meals

Tolls and Parking

Per Diem

Temp Housing

Plane tickets @

Hotel @

3/1/2023 15:18

Description Unit cost Quantity

Other Direct Expenses

Additional Lump Sum Cost

Davis-Salt Lake Community Connector- Environmental and PE Design Phase

Estimate ODC/Vendor Detail Sheet

HNTB Corporation

Company

Greg Thorpe

Estimated By

Rental Car

Express mail

Relocation

Other

Subtotal Travel

Other

Subtotal Communications/Shipping

Postage/Freight

$0

Plotting submissions

Reproductions, 8 1/2x11 @ sets

Reproductions, 11x17 @

Reproductions, Drawings @

Vendors / Professional Services

Subtotal Reproduction

Name Description of work

Sub Total Direct Expenses

Miscellaneous Expenses

Reference manuals

Other

Sub Total Other

$7,480

File: Davis-SL Env Des Req ICE 030123 ...Form C- ODCs

1/25/2023 0 4 5

Assumptions:

3/1/2023 15:18

Basis of Estimate / Exclusions

Basis of Estimate / Exclusions

Davis-Salt Lake Community Connector- Environmental and PE Design Phase

Company

Greg Thorpe

Estimated By

HNTB Corporation

Task Description

Exclusions:

Discipline

Environmental and Design

See RFQu for Details of Tasks. Based upon current RRQu draft dated 1//23/23.

File: Davis-SL Env Des Req ICE 030123 ...Form D- Basis of Estimate

1/25/2023 0 5 5

3/1/2023 15:18

Basis of Estimate / Potential Risk

Company Estimated By

HNTB Corporation Greg Thorpe

Task Description Discipline

Davis-Salt Lake Community Connector- Environmental and PE Design Phase Environmental and Design

Basis of Estimate / Potential Risk

File: Davis-SL Env Des Req ICE 030123 ...Form E- Potential Risks

File details come from the government source that posted it. Updated .