This document is an Independent Cost Estimate (ICE) form prepared by Metro Transit for the 2025 Arterial BRT Plan Update Planning Support project. The estimate was prepared by Kyle Burrows and reviewed by Katie Roth on July 10, 2024. The project encompasses four primary task categories: Project Management and Administration, Technical Evaluation (including development of evaluation criteria, assessment of candidate corridors, ridership estimation, and documentation of results), Public Engagement (including development of public-facing materials, an interactive web map, and staff support for outreach activities), and associated professional services. The work is organized across four labor classifications—Principal/Project Manager, Senior Associate, Associate/Technician, and Administrative staff—with total direct labor hours estimated at 1,976 hours distributed across these classifications at varying hourly rates ranging from $30 to $80 per hour.

The total estimated direct labor cost is $130,840, with overhead calculated at 175 percent ($228,970) and profit at 10 percent ($35,981), resulting in a subtotal of $395,791. A 10 percent contingency of $39,579 is applied, bringing the total estimated contract amount to $435,370. No direct expenses are included in this estimate. The document indicates this is a consultant proposal for planning support related to the 2025 Arterial BRT Plan Update, with the cost estimate signed and finalized on July 10, 2024.

View the file

Other files

File Type Posted
Locally_Preferred_Alternative_(LPA).pdf PDF
METRO_RTA_LPA.xlsx XLSX spreadsheet
EX24059_Nelson_Nygaard_East_Colfax_final.doc.pdf PDF
Ice_form_-_LPA.pdf PDF
Davis-SL_Env_Des_Req_ICE_030123.pdf PDF
Ice_form.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Revised 10/31/2019 CONSULTANT PROPOSAL I.C.E.

Form G-06E

INDEPENDENT COST ESTIMATE

Overhead Rate** = 175.00% Profit*** = 10.00% ** Recommend using between 150.00% and 175.00%

Labor Classification

SERIES / TASK

Direct Labor Rate $80.00 $75.00 $65.00 $30.00

1.0: Project Management and Administration 54 162 162 54 432 $4,320 $12,150 $10,530 $1,620 28,620

2.1: Develop Technical Evaluation Critiera 24 48 160 4 236 $1,920 $3,600 $10,400 $120 16,040

2.2: Perform Technical Evaluation of Canidate Corridors 12 28 200 4 244 $960 $2,100 $13,000 $120 16,180

2.3: Ridership Estimation of Advanced Corridors 8 24 60 4 96 $640 $1,800 $3,900 $120 6,460

2.4: Document Technical Evalaution Results 12 36 340 4 392 $960 $2,700 $22,100 $120 25,880

3.1: Produce Public-facing Engagement Materials 20 36 200 4 260 $1,600 $2,700 $13,000 $120 17,420

3.2: Interactive Web Map 8 12 60 4 84 $640 $900 $3,900 $120 5,560

3.3: Staff Support of Outreach and Engagement Activities 0 16 200 16 232 Total Labor Hours/Labor Classification 138 362 1,382 94 1,976 Total Direct Labor $$/Labor Classif. $11,040 $27,150 $89,830 $2,820 $130,840 Total Overhead Cost $19,320 $47,513 $157,203 $4,935 $228,970 Profit $3,036 $7,466 $24,703 $776 $35,981 Expenses $0

TOTAL ESTIMATED COST $33,396 $82,129 $271,736 $8,531 $395,791

10% Contingency $39,579

TOTAL EST. CONTRACT AMOUNT $435,370

Date: Reviewed By:

signature required

Prepared By:

signature required

Admin

TOTAL

Principal/ Project Mgr

Senior Associate

Associate/ Technician

INDEPENDENT COST ESTIMATE

FOR CONSULTANT PROPOSAL

2025 Arterial BRT Plan Update Planning Support

*** Use 10.00%

7/10/2024 1 - Cost Estimate

7/10/24

ICE 2025 Arterial BRT Plan Update Planning Support Final Audit Report 2024-07-10

Created: 2024-07-10

By: Kyle Burrows (Kyle.Burrows@metrotransit.org)

Status: Signed

Transaction ID: CBJCHBCAABAADhbBLiqf3x31s-mSQ3DAIc-DMNEVTtUI

"ICE 2025 Arterial BRT Plan Update Planning Support" History Document created by Kyle Burrows (Kyle.Burrows@metrotransit.org)

2024-07-10 - 8:22:13 PM GMT

Document emailed to Katie Roth (katie.roth@metrotransit.org) for signature

2024-07-10 - 8:22:18 PM GMT

Email viewed by Katie Roth (katie.roth@metrotransit.org)

2024-07-10 - 8:50:14 PM GMT

Document e-signed by Katie Roth (katie.roth@metrotransit.org) Signature Date: 2024-07-10 - 8:50:32 PM GMT - Time Source: server

Agreement completed.

2024-07-10 - 8:50:32 PM GMT

Cost Estimate

2024-07-10T13:50:34-0700
Agreement certified by Adobe Acrobat Sign

File details come from the government source that posted it. Updated .