This document is the Hospital Physical Environment Document List & Review Tool, a compliance evaluation checklist used by Joint Commission surveyors during hospital accreditation surveys, effective April 20, 2024.
The tool systematically documents hospital compliance with Physical Environment (PE) standards across multiple categories. Key documentation requirements include: current building drawings with fire safety features, fire control plans with staff training records, and written evidence of regular fire inspections by state or local agencies. Fire protection and suppression systems require extensive testing and inspection at prescribed frequencies—quarterly testing of pressure supervisory devices, semiannual testing of valve supervisory switches and water flow devices, monthly testing of electric motor-driven fire pumps, and weekly testing of diesel-engine-driven fire pumps. Emergency power systems must be tested monthly for functional operation of lighting and exit signs, with 12-month battery-powered light tests and monthly Level 1 SEPSS functional tests. Medical gas and vacuum systems require documented testing and maintenance of critical components per hospital policy, with at least quarterly inspections recommended if less frequent than annual. Fire drills must occur once per shift per quarter in health care occupancies with all drills unannounced and conducted at varying times. Additional requirements address utility system management, medical equipment inspection and maintenance (with 100% completion rates for high-risk equipment), water management programs, hazardous materials inventory and procedures, and security incident procedures. The tool includes compliance status indicators (Compliant, Not Compliant, Not Applicable, Awaiting Documentation) and spaces for documenting testing dates and comments throughout the review process.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26326Q1029 A0003_1.docx | DOCX document | |
| D.5 Price Schedule Template.xlsx | XLSX spreadsheet | |
| 36C26326Q1029 A0003.pdf | ||
| 36C26326Q1029 A0002.pdf | ||
| 36C26326Q1029 A0001.pdf | ||
| 36C26326Q1029 A0001_1.docx | DOCX document | |
| 36C26326Q1029_1.docx | DOCX document | |
| 36C26326Q1029.pdf | ||
| D.4 VHA-Joint Commission Clarification Document effective 1-October-2023.pdf | ||
| D.2 QASP-Fire Alarm Inspection Services.pdf | ||
| D.1 DOL WD 2015-5369.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Copyright: 2026 Joint Commission Hospital Survey Process Guide - Compliance Evaluation Tools Page 522 of 709
Hospital Physical Environment Document List & Review Tool Revised - Effective: 4/20/2024
The following pages present documentation required by the Hospital Accreditation program Physical Environment (PE) standards. The Life Safety surveyor will begin review of these documents soon after arrival for the on-site survey. Surveyors may request other documents, as needed, throughout the survey. This list also includes some elements of performance that do not require documentation but appear as reminders to both organizations and surveyors of these expectations.
Please conduct during Facility Orientation.
Legend: C=Compliant; NC=Not compliant; NA=Not applicable; IOU=Surveyor awaiting documentation
STANDARD -
EPs
See Legend Document / Requirement Yes No C NC NA IOU PE.03.01.01 Buildings serving patients comply w/ NFPA 101 (2012)
EP 1
Current and accurate drawings w/ fire safety features & related square footage
a. Areas of building fully sprinklered (if building only partially sprinklered)
b. Locations of all hazardous storage areas
c. Locations of all fire-rated barriers
d. Locations of all smoke-rated barriers
e. Sleeping and non-sleeping suite boundaries, including size of identified suites
f. Locations of designated smoke compartments
g. Locations of chutes and shafts
h. Any approved equivalencies or waivers
EP 5
The hospital maintains written evidence of regular inspection and approval by state or local fire control agencies.
EP 2 The hospital maintains current Basic Building Information (BBI) within the Statement of Conditions (SOC).
COMMENTS:
Copyright: 2026 Joint Commission Hospital Accreditation Survey Process Guide Page 523 of 709
STANDARD -
EPs See Legend Document / Requirement Yes No
C NC NA IOU
PE.03.01.0
1 Hospital Manages Fire Risk – Fire Response Plan
EP 4
The hospital has written fire control plans that include provisions for prompt reporting of fires; extinguishing fires; protection of patients, staff, and guests; evacuation; and cooperation with firefighting authorities.
Staff periodically instructed on/kept informed of duties under plan
Copy of plan readily available with telephone operator or security
NFPA 101-2012: 18/19.7.1; 7.2
Please conduct after Facility Orientation, during Document Review activity.
STANDARD -
EPs
See Legend Document / Requirement Frequency Q1 Semi
Q2 Q3 Semi
Q4 AnnualC NC NA IOU
PE.04.01.01 Fire Protection and Suppression Testing and Inspection
EP 2
(Specific content addressed on K-tag
Tool)
Testing for pressure supervisory indicating devices (including both high- and low-air pressure switches), water level supervisory indicating devices, water temperature supervisory indicating devices, room temperature supervisory indicating devices, and other suppression system supervisory initiating devices NFPA 72-2010: Table 14.4.5
Quarterly
Testing for valve supervisory switches NFPA 72-2010: Table 14.4.5 Semiannual
Testing for other supervisory initiating devices NFPA 72-2010: Table 14.4.5
Annually
Water flow devices Semiannual
Copyright: 2026 Joint Commission Hospital Accreditation Survey Process Guide Page 524 of 709
STANDARD -
EPs
See Legend Document / Requirement Frequency Q1 Semi
Q2 Q3 Semi
Q4 AnnualC NC NA IOU
PE.04.01.01 Fire Protection and Suppression Testing and Inspection
EP 2 NFPA 72-2010: Table 14.4.5 NFPA 25-2011: Table 5.1.1.2 Tamper switches NFPA 72-2010: Table 14.4.5 Semiannual
EP 2
Duct, heat, smoke detectors, and manual fire alarm boxes NFPA 72-2010: Table 14.4.5; 17.14
Annually
EP 2
Notification devices (audible & visual), and door-releasing devices NFPA 72-2010: Table 14.4.5
Annually
EP 2
Emergency services notification transmission equipment NFPA 72-2010: Table 14.4.5
Annually
EP 2
Electric motor-driven fire pumps tested under no-flow conditions
NFPA 25-2011: 8.3.1; 8.3.2
Monthly
Diesel-engine-driven fire pumps tested under no-flow conditions
NFPA 25-2011: 8.3.1; 8.3.2
Weekly
EP 2
Sprinkler systems main drain tests on all risers NFPA 25-2011: 13.2.5; 13.3.3.4; Table 13.1.1.2; Table 13.8.1
Annually
EP 2
Fire department connections inspected (Fire hose connections N/A) NFPA 25-2011: 13.7; Table 13.1.1.2
Quarterly
EP 2
Fire pump(s) tested – under flow Fire pump supervisory signals for pump running and pump power loss tested
NFPA 25-2011: 8.3.3; 8.3.3.4
EP 2 Standpipe flow test every 5 years 5 years
Copyright: 2026 Joint Commission Hospital Accreditation Survey Process Guide Page 525 of 709
STANDARD -
EPs
See Legend Document / Requirement Frequency Q1 Semi
Q2 Q3 Semi
Q4 AnnualC NC NA IOU
PE.04.01.01 Fire Protection and Suppression Testing and Inspection
NFPA 25-2011: 6.3.1; 6.3.2; Table 6.1.1.2
EP 2
Kitchen suppression semi-annual testing NFPA 96-2011: 11.2 Semiannual
EP 2
Carbon dioxide systems tested NFPA 12-2011:4.8.3.2 Annually
Halon systems NFPA 12A-2009: 6.1 Semiannual
Other special systems per National Fire Protection Association standards and manufacturers’ recommendations
NFPA 11-2010; NFPA 16-2011; NFPA 17-
2009; NFPA 17A-2009
EP 2
Portable fire extinguishers inspected monthly
NFPA 10-2010: 7.2.2; 7.2.4
Monthly
EP 2
Portable fire extinguishers maintained annually
NFPA 10-2010: 7.1.2; 7.2.2; 7.2.4; 7.3.1
Annually
EP 2
Fire hoses hydro tested 5 years after install; every 3 years thereafter NFPA 1962-2008: Chapter 7 and NFPA 25-2011: Chapter 6
5 years / 3 years
EP 2
Smoke and fire dampers tested to verify full closure
NFPA 90A-2012: 5.4.8; NFPA 80-2010:
19.4; NFPA 105-2010: 6.5
1 year after install
At least every 6 years thereafter
EP 2
Smoke detection shutdown devices for HVAC tested
NFPA 90A-2012: 6.4.1
Annually
EP 2
All horizontal and vertical roller and slider doors tested Annually
Copyright: 2026 Joint Commission Hospital Accreditation Survey Process Guide Page 526 of 709
STANDARD -
EPs
See Legend Document / Requirement Frequency Q1 Semi
Q2 Q3 Semi
Q4 AnnualC NC NA IOU
PE.04.01.01 Fire Protection and Suppression Testing and Inspection
NFPA 80-2010: 5.2.14.3; NFPA 105-
2010: 5.2.1; 5.2.2
EP 2 (or
PE.03.01.01,
EP 3)
Inspection and testing of door assemblies by qualified person. Does not include nonrated doors, including corridor doors to patient care rooms and smoke barrier doors.
NFPA101-2012: 7.2.1.5.10.1; 7.2.1.5.11;
7.2.1.15; NFPA 80-2010: 4.8.4; 5.2.1;
5.2.3; 5.2.4; 5.2.6; 5.2.7; 6.3.1.7; NFPA
105-2010: 5.2.1
Annually
EP 2 (or
PE.03.01.01,
EP 3)
Elevators with firefighters’ emergency operations
NFPA 101-2012: 9.4.3; 9.4.6
Monthly
EP 1
Documentation of maintenance testing and inspection activities for EPs 1-3 includes: activity name; date; inventory of devices, equipment or other items;
frequency; contact info for person performing activity; NFPA standard; activity results
NFPA 25-2011: 4.3; 4.4; NFPA 72-2010:
14.2.1; 14.2.2; 14.2.3; 14.2.4
COMMENTS:
STANDARD -
EPs See Legend Document / Requirement Frequency Yes No / Missing Date
C NC NA IOU
PE.03.01.01
EP 3 and
PE.04.01.01
EP 1
Emergency Power Systems are Maintained and Tested
EP 3 or EP1 At least monthly performs functional test of emergency lighting systems and exit signs Monthly
Copyright: 2026 Joint Commission Hospital Accreditation Survey Process Guide Page 527 of 709
STANDARD -
EPs See Legend Document / Requirement Frequency Yes No / Missing Date
C NC NA IOU
PE.03.01.01
EP 3 and
PE.04.01.01
EP 1
Emergency Power Systems are Maintained and Tested required for egress and task lighting for a minimum duration of 30 seconds, along with a visual inspection of other exit signs
NFPA 101-2012: 7.9.3; 7.10.9; NFPA 99-
2012: 6.3.2.2.11.5
EP 3 or EP1
Every 12 months performs functional test of battery powered lights on the inventory required for egress and exit signs for a duration of 1 ½ hours
For new construction, renovation, or modernization battery-powered lighting in locations where deep sedation and general anesthesia are administered is tested annually for 30 minutes with test results and completion dates documented
NFPA 101-2012: 7.9.3; 7.10.9; NFPA 99-
2012: 6.3.2.2.11.5
Annually
EP 3 or EP1
Functional test of Level 1 SEPSS, monthly;
Level 2 SEPSS, quarterly, for 5 minutes or as specified for its class Annual test at full load for 60% of full duration of its class
NFPA 111-2010: 8.4
Monthly Quarterly Annually
Note 1: Non-SEPSS tested per manufacturer’s specifications Per Mfr.
Note 2: Level 1 SEPSS defined for critical areas and equipment Note 3: Class defines minimum time which SEPSS is designed to operate at rated load without recharging
EP 3 or EP1
Emergency power supply system (EPSS) inspected weekly, including all associated components and batteries
NFPA 110-2010: 8.3.1; 8.3.3; 8.3.4; 8.4.1
Weekly
Copyright: 2026 Joint Commission Hospital Accreditation Survey Process Guide Page 528 of 709
STANDARD -
EPs See Legend Document / Requirement Frequency Yes No / Missing Date
C NC NA IOU
PE.03.01.01
EP 3 and
PE.04.01.01
EP 1
Emergency Power Systems are Maintained and Tested
EP 3 or EP1
Emergency generators tested monthly for 30 continuous minutes under load (plus cool-down)
NFPA 99-2012: 6.4.4.1
Monthly
EP 3 or EP1
Monthly load test for diesel-powered emergency generators conducted with dynamic load at least 30% of nameplate rating or meets mfr. recommended prime movers’ exhaust gas temperature; OR
Monthly
Emergency generators tested once every 12 months using supplemental loads of 50% of nameplate rating for 30 minutes, followed by 75% of nameplate rating for 60 minutes for total of 1 ½ continuous hours
NFPA 99-2012: 6.4.4.1
Annually
EP 3 or EP1
All automatic and manual transfer switches monthly/12 times per year with results and completion dates documented
NFPA 99-2012: 6.4.4.1
Monthly
EP 3 or EP1 Fuel quality test to ASTM standards NFPA 110-2010: 8.3.8 Annually
EP 3 or EP1 Generator load test once every 36 months for 4 hours NFPA 110-2010, Chapter 8
36 Months
EP 3 or EP1 Generator 4-hour test performed at, at least 30% nameplate NFPA 110-2010, Chapter 8
36 Months
Copyright: 2026 Joint Commission Hospital Accreditation Survey Process Guide Page 529 of 709
STANDARD -
EPs
See Legend Document / Requirement
THIS MAY BE SCORED AS
CONDITIONAL OR
STANDARD
Testing Dates
C NC NA IOU Yes No
PE.04.01.0
Medical Gas and Vacuum Systems are
Inspected and Tested
EP 3
Test, inspect and maintain critical components of piped medical gas and vacuum systems, waste anesthetic gas disposal (WAGD), and support gas systems on the inventory.
Inventory of critical components includes at least all source subsystems, control valves, alarms, manufactured assemblies containing patient gases, and inlets and outlets with activities, dates and results documented
No prescribed frequency; recommend risk assessment if < annual
NFPA 99-2012: 5.1.14.2; 5.1.15; 5.2.14;
5.3.13
Per policy
EPs 1, 3 Location of and signage for bulk oxygen systems
NFPA 99-2012: 5.1.3.5.12
On Bldg. Tour
EPs 1, 3 Emergency oxygen supply connection NFPA 99-2012: 5.1.3.5.13 On Bldg. Tour
EPs 1, 3
Review medical gas installation/modification/breech certification results for cross connection, purity, correct gas, and pressure
NFPA 99-2012: 5.1.2; 5.1.4; 5.1.14.4.1;
5.1.14.4.6; 5.2.13
As applicable
EP 1
Medical gas supply and zone valves are accessible and clearly labeled NFPA 99-2012: Table 5.1.11
NFPA 99-2012: 5.1.4; 5.1.11.1; 5.1.11.2;
5.1.14.3; 5.2.11; 5.3.13.3; 5.3.11
On Bldg. Tour
EP 1
Handling, transfer, storage, labeling, transfilling of cylinders
NFPA 99-2012: 11.5.3.1; 11.6.1; 11.6.2;
11.6.5; 11.7.3
Per policy
Copyright: 2026 Joint Commission Hospital Accreditation Survey Process Guide Page 530 of 709
STANDARD -
EPs
See Legend Document / Requirement
THIS MAY BE SCORED AS
CONDITIONAL OR
STANDARD
Testing Dates
C NC NA IOU Yes No
PE.04.01.0
Medical Gas and Vacuum Systems are
Inspected and Tested
COMMENTS:
STANDARD -
EPs
See Legend Document / Requirement Frequency Q1 Q2 Q3 Q4
AnnualC NC NA IOU
PE.03.01.0
1 Fire Drills
EP 3
Fire drills once per shift per quarter in health care occupancies; Quarterly in each building defined as ambulatory health care occupancy (If available, please provide five quarters of fire drill data)
NFPA 101-2012: 18/19: 7.1.7
Quarterly
EP 3 Fire drills every 12 months from date of last drill: Business Occupancies Annually
EP 3
When quarterly fire drills are required, ALL are unannounced
• Drills held at unexpected times and under varying conditions – at least one hour apart for each shift from quarter to quarter through four consecutive quarters
• Drills include transmission of fire alarm signal and simulation of emergency fire conditions
NFPA 101-2012: 18/19: 7.1.7; 7.1;
7.2; 7.3
Quarterly (See fire drill matrix)
PE.04.01.0
1 EP 1
Fire exit drills for operating rooms/surgical suites.
NFPA 99-2012: 15.13.3.10.3
Copyright: 2026 Joint Commission Hospital Accreditation Survey Process Guide Page 531 of 709
STANDARD -
EPs
See Legend Document / Requirement Frequency Q1 Q2 Q3 Q4
AnnualC NC NA IOU
PE.03.01.0
1 Fire Drills
PE.04.01.0
1 EP 1
Annual emergency procedures and fire training drills for hyperbaric facilities that include recording of time to evacuate all persons from area, involves applicable staff, and focuses on prevention and simulated extinguishment and evacuation.
NFPA 99-2012: 14.2.4.5.4;
14.3.1.4.5 NFPA 99-2012: B.14.2 and B.14.3
Annually
COMMENTS:
STANDARD -
EPs
See Legend Document / Requirement Frequency Yes No / Missing Date C NC NA IOU Manages risks associated with utility systems
PE.03.01.0
1 EP 3 or
PE.04.01.0
1 EP 1
In critical care areas designed to control airborne contaminants (such as biological agents, gases, fumes, dust), the ventilation system provides appropriate pressure relationships, air-exchange rates, filtration efficiencies, temperature and humidity.
(form of and frequency of assessment per hospital policy)
Note: For more information about areas designed for control of airborne contaminants, the basis for design compliance is the Guidelines for Design and Construction of Health Care Facilities, based on the edition used at the time of design (if available).
Copyright: 2026 Joint Commission Hospital Accreditation Survey Process Guide Page 532 of 709
STANDARD -
EPs
See Legend Document / Requirement Yes No C NC NA IOU
PE.04.01.0
Manages risks associated with utility systems
– Water Management Program
EP 1 Verify individual or team responsible for oversight and implementation of the water management program
EP 2
Review water management program to verify the following components are included:
• Diagram of water supply sources, treatment systems, processing steps, control measures, and end-use points
• Water risk management plan identifies areas where potentially hazardous conditions may occur o Note: Refer to the Centers for Disease Control and
Prevention’s “Water Infection Control Risk Assessment (WICRA) for Healthcare Settings” tool as an example for conducting a water-related risk assessment.
• Plan for addressing the use of water in areas of buildings where water may have been stagnant for a period of time
• Evaluation of immunocompromised patients
• Monitoring protocols and acceptable ranges for control measures
EP 3
Verify that the water management program includes documentation of the following:
• Results of all monitoring activities
• Corrective actions and procedures to follow if test results are outside of acceptable limits
• Corrective actions taken when control limits are not maintained
EP 4
Verify water management program reviewed annually and when changes have been made to the water system that add risk, new equipment or at-risk systems have been added that could generate aerosols or be source for Legionella
COMMENTS:
STANDARD -
EPs
See Legend Document / Requirement Yes No C NC NA IOU
PE.04.01.0
1 Management of Medical Equipment Risks
EP 2 Non-deemed status requirement: Maintains either a written inventory of all medical equipment or a written inventory of selected equipment categorized
Copyright: 2026 Joint Commission Hospital Accreditation Survey Process Guide Page 533 of 709
STANDARD -
EPs
See Legend Document / Requirement Yes No C NC NA IOU
PE.04.01.0
1 Management of Medical Equipment Risks by physical risk associated with use (including all life-support equipment) and equipment incident history.
Evaluates new types of equipment before initial use to determine whether they should be included in the inventory.
OR
Deemed status requirement: Maintains a written inventory of all medical equipment.
EP 2 High-risk medical equipment identified on the inventory
EP 2
Inventory includes activities and associated frequencies for maintaining, inspecting, and testing all medical equipment on the inventory.
COMMENTS:
STANDARD -
EPs
See Legend Document / Requirement Frequency Yes No / Missing Date C NC NA IOU
PE.04.01.0
1 Medical equipment inspection, testing and maintenance
EP 2
All high-risk equipment.
Note 1: High-risk equipment includes medical equipment for which there is a risk of serious injury or even death to a patient or staff member should it fail, which includes life-support equipment.
Note 2: Required activities and associated frequencies for maintaining, inspecting, and testing of medical equipment must have a 100% completion rate.
EP 2
Non-high-risk equipment identified on the medical equipment inventory
EP 2
Conducts performance testing of and maintains all sterilizers
Copyright: 2026 Joint Commission Hospital Accreditation Survey Process Guide Page 534 of 709
STANDARD -
EPs
See Legend Document / Requirement Frequency Yes No / Missing Date C NC NA IOU
PE.04.01.0
1 Medical equipment inspection, testing and maintenance
EP 1, 2
All occupancies containing hyperbaric facilities comply with construction, equipment, administration, and maintenance requirements of NFPA 99- 2012: Chapter 14.
COMMENTS:
STANDARD -
EPs
See Legend Document / Requirement Frequency Yes No / Missing Date C NC NA IOU
PE.04.01.0
1 Utility system Inspection, testing and maintenance
EP 2
High-risk utility system components on the inventory with completion date and results of activities documented
Note 1: A high-risk utility system includes components for which there is a risk of serious injury or even death to a patient or staff member should it fail, which includes life-support equipment.
Note 2: Required activities and associated frequencies for maintaining, inspecting, and testing of utility systems components must have a 100% completion rate.
EP 2
Infection control utility system components on the inventory with completion date and results of activities documented
Note 1: Required activities and associated frequencies for maintaining, inspecting, and testing of utility systems components must have a 100% completion rate.
EP2
Non-high-risk utility system components on the inventory with completion date and results of activities documented
EP 2
Line isolation monitors (LIM), if installed, are tested at least monthly by actuating the LIM test switch. For LIM circuits with automated self-testing, a manual test is performance at least annually.
Copyright: 2026 Joint Commission Hospital Accreditation Survey Process Guide Page 535 of 709
STANDARD -
EPs
See Legend Document / Requirement Frequency Yes No / Missing Date C NC NA IOU
PE.04.01.0
1 Utility system Inspection, testing and maintenance
NFPA 99-2012: 6.3.2; 6.3.3; 6.3.3.3.2; 6.3.4
COMMENTS:
STANDARD -
EPs
See Legend Document / Requirement Frequency Yes No / Missing Date C NC NA IOU
NPG.11.01.0
NPG.02.04.0
The hospital manages security risks.
EP 2 The hospital has written procedures to follow in the event of a security incident, including an infant or pediatric abduction.
EP 3
The hospital conducts an annual worksite analysis related to its workplace violence prevention program. The hospital takes actions to mitigate or resolve the workplace violence safety and security risks based upon findings from the analysis.
Note: A worksite analysis includes a proactive analysis of the worksite, an investigation of the hospital’s workplace violence incidents, and an analysis of how the program’s policies and procedures, training, education, and environmental design reflect best practices and conform to applicable laws and regulations.
Copyright: 2026 Joint Commission Hospital Accreditation Survey Process Guide Page 536 of 709
STANDARD -
EPs
See Legend Document / Requirement Frequency Yes No / Missing Date C NC NA IOU
NPG.11.01.
01 The hospital collects information to monitor conditions in the environment.
EP 3
EP 1 The hospital develops and implements processes for monitoring, internally reporting, and investigating the following:
- Injuries to patients or others within the hospital’s facilities
- Occupational illnesses and staff injuries
- Incidents of damage to its property or the property of others
- Safety and security incidents involving patients, staff, or others within its facilities, including those related to workplace violence
- Hazardous materials and waste spills and exposures
- Fire safety management problems, deficiencies, and failures
- Medical or laboratory equipment management problems, failures, and use errors
- Utility systems management problems, failures, or use errors
STANDARD -
EPs
See Legend Document / Requirement Addressed in policy? Implemented as required?
C NC NA IOU Yes No Yes No
PE.03.02.0
1 Interim Life Safety Measures (ILSM)
EP 1 ILSM policy identifying when and to what extent ILSM implemented
PE.03.01.0
1 EP 8 and
PE.03.02.0
1EP 2
Alarms out of service 4 or more hours in 24 hours or sprinklers out of service more than 10 hours in 24 hours in an occupied building - Fire watch / Fire Dept. notification
NFPA 101-2012: 9.6.1.6; 9.7.6; NFPA 25-
2011: 15.5.2
EP 3 Signs for alternate exits posted
EP 4 Daily inspection of routes of egress (See also
19.7.9.2 RE: daily inspections)
EP 5 Temporary but equivalent systems while system is impaired
EP 6 Additional firefighting equipment provided
EP 7 Smoke tight non-combustible temporary barriers
EP 8 Increased surveillance implemented
EP 9 Storage and debris removal
Copyright: 2026 Joint Commission Hospital Accreditation Survey Process Guide Page 537 of 709
STANDARD -
EPs
See Legend Document / Requirement Addressed in policy? Implemented as required?
C NC NA IOU Yes No Yes No
PE.03.02.0
1 Interim Life Safety Measures (ILSM)
EP 10 Additional training on firefighting equipment
EP 11 Additional fire drill per shift per quarter
EP 12 Temporary systems tested and inspected monthly
EP 13 Additional training on building deficiencies, construction hazards, temp measures
EP 14 Training for impaired structural or impaired compartment fire safety features
EP 15 Other ILSM's
COMMENTS:
NOTE: Please complete the following during building tour
STANDARD -
EPs
See Legend Document / Requirement Frequency Yes No / Missing Date C NC NA IOU
PE.02.01.0
1 The hospital manages risks related to hazardous materials and waste.
EP 1
The hospital maintains a written, current inventory of hazardous materials and waste that it uses, stores, or generates. The only materials that need to be included on the inventory are those whose handling, use, and storage are addressed by law and regulation. (See also IC.02.01.01, EP 6;
MM.01.01.03, EPs 1 and 2)
EP 4
The hospital has written procedures, including the use of precautions and personal protective equipment, to follow in response to hazardous material and waste spills or exposures.
EP 2
For managing hazardous materials and waste, the hospital has the permits, licenses, manifests, and safety data sheets required by law and regulation.