This document is a Project Manual for the Career Connect Campus - Technology Bid Package, a project of the Kalamazoo Regional Educational Service Agency (KRESA) located in Kalamazoo, Michigan. The project includes all low voltage systems such as audio/video, cabling, clocks, electronic access control, electronic surveillance, infrastructure equipment, and paging for the new Career and Technical Education Center project. Bids are due on December 19, 2023 at 4:00 PM EST to the KRESA building. A pre-bid meeting will be held virtually on December 5, 2023 at 3:30 PM EST. The contract will be awarded to the responsive, responsible bidder and the contract form will be AIA Document A101. The contract includes a performance bond and payment bond, each at 100% of the contract sum.
The project has a fixed budget, and the owner is tax-exempt. Payments will be made monthly based on progress, with 10% retainage withheld until final completion. The project must be completed within the contract time, with liquidated damages applicable for late completion. The contract includes provisions for dispute resolution, termination, and suspension.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT DOCUMENTS
AND
SPECIFICATIONS
FOR THE
KALAMAZOO REGIONAL
EDUCATIONAL SERVICE
AGENCY
Career Connect Campus Technology Bid Package
November 29, 2023
Kalamazoo Regional Educational Service Agency Wightman
Career Connect Campus - Technology Bid Package 11/29/2023
Project No. 214175
TABLE OF CONTENTS 00 00 01 - 1
00 00 00 PROCUREMENT AND CONTRACT REQUIREMENTS
00 01 01 PROJECT TITLE PAGE
00 11 13 ADVERTISEMENT FOR BIDS
00 21 13 INSTRUCTIONS TO BIDDERS
00 22 13 SUPPLEMENTARY INSTRUCTIONS TO BIDDERS
00 25 13 PRE-BID MEETINGS
00 31 13 PRELIMINARY SCHEDULES
00 41 13 BID FORM - STIPULATED SUM (SINGLE-PRIME CONTRACT)
00 43 13 BID SECURITY FORMS
00 43 23 ALTERNATES FORM
00 43 24 FAMILIAL DISCLOSURE STATEMENT
00 43 25 IRAN AFFIDAVIT OF COMPLIANCE
00 43 93 BID SUBMITTAL CHECKLIST
00 51 00 NOTICE OF AWARD
00 60 00 PROJECT FORMS
A101-2017 OWNER/ CONTRACTOR AGREEMENT
A101-2017 EXHIBIT A
A201-2017 GENERAL CONDITIONS
A701-1997 INSTRUCTIONS TO BIDDERS
27 00 00 COMMUNICATIONS
27 05 00 BASIC COMMUNICATIONS SYSTEMS REQUIREMENTS
27 05 03 THROUGH PENETRATION FIRE STOPPING
27 05 26 COMMUNICATIONS BONDING
27 05 28 INTERIOR COMMUNICATION PATHWAYS
27 05 43 EXTERIOR COMMUNICATION PATHWAYS
27 05 53 IDENTIFICATION AND ADMINISTRATION
27 11 00 COMMUNICATION EQUIMENT ROOMS (CER)
27 13 00 BACKBONE CABLING REQUIREMENTS
27 15 00 HORIZONTAL CABLING REQUIREMENTS
27 17 10 TESTING
27 17 20 STRUCTURED CABLING SYSTEM WARRANTY
27 41 00 PROFESSIONAL AUDIO_VIDEO SYSTEM
27 51 13 PAGING SYSTEMS
28 00 00 ELECTRONIC SAFETY AND SECURITY
28 05 00 BASIC ELECTRONIC SAFETY AND SECURITY SYSTEM REQUIREMENTS
28 05 03 THROUGH PENETRATION FIRE STOPPING
28 13 00 ELECTRONIC ACCESS CONTROLS
28 23 00 VIDEO SURVEILLANCE
28 26 05 RESCUE ASSISTANCE COMMUNICATION
END OF TABLE OF CONTENTS
Project No. 214175
PROJECT TITLE PAGE 00 01 01 - 1
DOCUMENT 00 01 01 - PROJECT TITLE PAGE
1.1 PROJECT MANUAL
A. Career & Technical Education Center � Technology Bid Package. (Project No. 214175)
Career Connect Campus 3500 Vanrick Drive Kalamazoo, MI 49001
B. Owner:
Kalamazoo RESA 1819 East Milham Road Portage, MI 49002
C. Architect:
Wightman & Associates 433 East Ransom Street Kalamazoo, MI 49007 Tel: 269-927-0100 Fax: 269-927-1300 www.gowightman.com
D. Issued: November 29, 2023
E. Copyright (2023, Wightman & Associates). All rights reserved.
END OF DOCUMENT 00 01 01
Project No. 214175
ADVERTISEMENT FOR BIDS 00 11 13 - 1
DOCUMENT 00 11 13 - ADVERTISEMENT FOR BIDS
1.1 PROJECT INFORMATION
A. Notice to Bidders: Qualified bidders may submit bids for the project as described in this Document. Submit bids according to the Instructions to Bidders.
B. Project Identification: Career Connect Campus � Technology Bid Package
Project Location: Career Connect Campus 3500 Vanrick Drive Kalamazoo, Michigan 49001
C. Owner: Kalamazoo Regional Educational Service Agency 1819 East Milham Road Portage, Michigan 49002
D. Architect: Wightman & Associates 433 East Ransom Street Kalamazoo, Michigan 49007 Web Site: www.gowightman.com
E. Project Description: All low voltage systems shown in the project documents including audio/video, cabling, clocks, electronic access control, electronic surveillance, infrastructure equipment, and paging. for the entire building of the new Career and Technical Education Center Project. Note: Fire alarms, wireless access points, switches, and patch cables are by others and not included in this bid package.
F. Construction Contract: Bids will be received for the following Work:
1. General Contract Bids shall be received from one prime contractor for all work as outlined in the Specifications and Construction Drawings.
2. All applicable laws, ordinances, and the rules and regulations of all authorities having jurisdiction over the construction of the project shall apply to the project throughout.
3. Contractors shall note that the project is subject to the Common Construction Wage Act (effective July 1, 2015) for record-keeping, and all terms of this Act shall be followed in their entirety.
4. The contract form for the project will be AIA Document A101.
5. Contract will be made to the responsive, responsible bidder awarded by the
Owner.
6. Kalamazoo Regional Educational Service Agency is tax-exempt. Contractors are responsible for appropriate sales/use tax in accordance with the State of Michigan Department of Treasury.
Project No. 214175
ADVERTISEMENT FOR BIDS 00 11 13 - 2
1.2 BID SUBMITTAL AND OPENING
The Owner will receive sealed lump sum bids until the bid time and date at the location given below. Owner will consider bids prepared in compliance with the Instructions to Bidders issued by Owner, and delivered as follows:
1. Bid Date: December 19, 2023.
2. Bid Time: 4:00 p.m. Eastern Standard Time.
3. Location: Kalamazoo RESA
1819 East Milham Road Portage, MI 49001
B. Bids will thereafter be publicly opened and read aloud.
C. Bids shall be submitted on the forms provided with all blanks populated. Bid form and other documents required to be submitted with the bid shall be enclosed in a sealed envelope with the Bidder�s name, addressed to:
Kalamazoo Regional Educational Service Agency, Attention: Career Connect Center - Technology Bid Package.
1.3 BID SECURITY
A. Each bid must be accompanied by a Familial Disclosure and Iran Sanctions Act Compliance forms completed as provided by law.
B. Bid security shall be submitted with each bid in the amount of five (5) percent of the bid amount.
C. Bids received after the designated time for closing will be returned unopened.
D. No bids may be withdrawn for a period of 60 days after the opening of bids. The owner reserves the right to reject any and all bids and to waive informalities and irregularities.
1.4 PRE-BID MEETING
A. Pre-bid Meeting: See Document 002513 "Pre-bid Meetings."
B. Pre-bid Meeting: A pre-bid meeting for all bidders will be held virtually on Tuesday, December 5, 2023, at 3:30 p.m. Eastern Standard Time. Prospective prime bidders are requested to attend.
1. Bidders' Questions: The architect will provide responses at the Pre-bid Meeting to bidders' questions received up to two (2) business days prior to the meeting.
Project No. 214175
ADVERTISEMENT FOR BIDS 00 11 13 - 3
1.5 DOCUMENTS
A. Online Procurement and Contracting Documents: Obtain access after November 29, 2023, at 3:00 p.m. by contacting the following:
1. Dodge Lead Center: www.dodgeprojects.construction.com
2. Wightman Bidding Website: https://bids.gowightman.com/
B. Viewing Procurement and Contracting Documents: Examine after November 21, 2023, at the locations below:
1. Wightman & Associates, Inc., 433 East Ransom Street, Kalamazoo, MI 49007
1.6 TIME OF COMPLETION
A. Successful bidder shall begin the Work on receipt of the Notice to Proceed and shall complete the Work within the Contract Time.
1.7 BIDDER'S QUALIFICATIONS
A. Bidders must be properly licensed under the laws governing their respective trades and be able to obtain insurance and bonds required for the Work.
B. A 100% Performance Bond, and a separate Labor and Material Payment Bond, and Insurance in a form acceptable to the Owner will be required as part of each Bid.
C. Each bid proposal shall include all labor, material, and services necessary to complete the project in strict accordance with the contract documents as prepared and on file in the office of Wightman & Associates, Inc. The Owner reserves the right to reject any or all bids.
D. Each bidder is responsible for inspecting the project site and for reading and being thoroughly familiar with the Contract Documents and Specifications. Failure of omission of any Bidder to do any of the foregoing shall not relieve the Bidder from any obligation with respect to their bid.
1.8 NOTIFICATION
A. This Advertisement for Bids document is issued by order of the Kalamazoo Regional Educational Service Agency.
END OF DOCUMENT 00 11 13
Project No. 214175
INSTRUCTIONS TO BIDDERS 00 21 13 - 1
DOCUMENT 00 21 13 - INSTRUCTIONS TO BIDDERS
1.1 INSTRUCTIONS TO BIDDERS
A. AIA Document A701, "Instructions to Bidders," is hereby incorporated into the Procurement and Contracting Requirements by reference.
1. A copy of AIA Document A701, "Instructions to Bidders," is bound in this Project Manual.
END OF DOCUMENT 00 21 13
Project No. 214175
SUPPLEMENTARY INSTRUCTIONS TO BIDDERS 00 22 13 - 1
DOCUMENT 00 22 13 - SUPPLEMENTARY INSTRUCTIONS TO BIDDERS
1.1 INSTRUCTIONS TO BIDDERS
A. Instructions to Bidders for Project consist of the following:
1. AIA Document A701, "Instructions to Bidders," a copy of which is bound in this Project Manual.
2. The following Supplementary Instructions to Bidders that modify and add to the requirements of the Instructions to Bidders.
1.2 SUPPLEMENTARY INSTRUCTIONS TO BIDDERS, GENERAL
A. The following supplements modify AIA Document A701, "Instructions to Bidders."
Where a portion of the Instructions to Bidders is modified or deleted by these Supplementary Instructions to Bidders, unaltered portions of the Instructions to Bidders shall remain in effect.
B. REPRESENTATIONS
C. Revise Section 2.1.3 to strike, �The Bidder has visited the site, become familiar . . .�
D. Add Section 2.1.3.1:
1. 2.1.3.1 - The Bidder has investigated all required fees, permits, and regulatory requirements of authorities having jurisdiction and has properly included in the submitted bid the cost of such fees, permits, and requirements not otherwise indicated as provided by Owner.
2. State of Michigan.
E. Add Section 2.1.5:
1. 2.1.6 - The Bidder has incorporated into the Bid adequate sums for work performed by subcontractors whose qualifications meet those indicated in the Procurement and Contracting Documents.
1.3 ARTICLE 3 - BIDDING DOCUMENTS
A. Revise Section 3.1 Copies to strike, �. . .in the number and for the deposit sum, if any, stated therein. The deposit will be refunded to Bidders who submit a bona fide Bid and return the Bidding Documents in good condition within ten days after receipt of Bids.
The cost of replacement of missing or damaged documents will be deducted from the deposit. A Bidder receiving a Contract award may retain the Bidding Documents and the Bidder�s deposit will be refunded.
B. 3.2 - Interpretation or Correction of Procurement and Contracting Documents:
Project No. 214175
SUPPLEMENTARY INSTRUCTIONS TO BIDDERS 00 22 13 - 2
1. Revise Section 3.2.2 to read �. . .shall reach the Architect at least four business days prior to the date for receipt of Bids.�
2. Revise Section 3.3.2 to read �. . .has been received by the Architect at least five business days prior to the receipt of Bids.�
3. Revise Section 3.4.3 �will be issued no later than four calendar days prior to the date for receipt of Bids. . . �
1.4 ARTICLE 4 - BIDDING PROCEDURES
A. 4.1 - Preparation of Bids:
1. Add Section 4.1.1.1:
2. Add Section 4.1.8:
a. 4.1.8 - Bids shall include applicable sales and use taxes.
b.
1.5 ARTICLE 7 - PERFORMANCE BOND AND PAYMENT BOND
A. 7.1 - Bond Requirements:
1. Revise Section 7.1.1 to strike, �If stipulated in the Bidding Documents, the . . .� �
1.6 ARTICLE 9 - EXECUTION OF THE CONTRACT
A. Add Article 9:
1. 9.1.1 - Subsequent to the Notice of Intent to Award, and within 10 days after the prescribed Form of Agreement is presented to the Awardee for signature, the Awardee shall execute and deliver the Agreement to Owner through Architect, in such number of counterparts as Owner may require.
2. 9.1.2 - Owner may deem as a default the failure of the Awardee to execute the Contract and to supply the required bonds when the Agreement is presented for signature within the 15 days.
3. 9.1.4 - In the event of a default, Owner may declare the amount of the Bid security forfeited and elect to either award the Contract to the next responsible bidder or re-advertise for bids.
END OF DOCUMENT 00 22 13
Project No. 214175
PREBID MEETINGS 00 25 13 - 1
DOCUMENT 00 25 13 � PRE-BID MEETINGS
1.1 PRE-BID MEETING
A. Owner and Architect will conduct a Pre-bid meeting as indicated below:
1. Meeting Date: December 5, 2023
2. Meeting Time: 3:30 p.m. EST.
3. Location: Virtually via Microsoft Teams at https://teams.microsoft.com/l/meetup-join/19%3ameeting_OWRjZjhjYzMtMzc3MC00YWJjLTlmMGUtY2I1NzFlNWY4Zj A0%40thread.v2/0?context=%7b%22Tid%22%3a%22ef1960ce-394f-420e-92c0- 55d423f8150a%22%2c%22Oid%22%3a%223633bfd4-f501-4a3c-bc5f-dbbb661f17fb%22%7d
a. Meeting ID: 288 874 677 399
b. Passcode: u5Pfy9
B. Attendance:
1. Prime Bidders: Attendance at Pre-Bid meeting is recommended.
C. Bidder Questions:
1. Submit written questions to be addressed at the Pre-Bid meeting a minimum of two business days prior to the meeting. Send to Stefany Holland at sholland@gowightman.com
2. Questions following the meeting shall be submitted to Stefany Holland at sholland@gowightman.com
D. Agenda: Pre-Bid meeting agenda will include a review of topics that may affect the proper preparation and submittal of bids, including the following:
1. Procurement and Contracting Requirements:
a. Advertisement for Bids.
b. Instructions to Bidders.
c. Bidder Qualifications.
d. Bonding.
e. Insurance.
f. Bid Security.
g. Bid Form and Attachments.
h. Bid Submittal Requirements.
i. Bid Submittal Checklist.
j. Notice of Award.
2. Communication during Bidding Period:
a. Obtaining documents.
b. Access to Project Web site.
c. Bidder's Requests for Information.
Project No. 214175
PREBID MEETINGS 00 25 13 - 2
d. Bidder's Substitution Request/Prior Approval Request.
e. Addenda.
3. Contracting Requirements:
a. Agreement.
b. The General Conditions.
c. The Supplementary Conditions.
d. Other Owner requirements.
4. Construction Documents:
a. Scopes of Work.
b. Temporary Facilities.
c. Use of Site.
d. Work Restrictions.
e. Alternates, Allowances, and Unit Prices.
f. Substitutions following award.
5. Separate Contracts:
a. Work by Owner.
b. Work of Other Contracts.
6. Schedule:
a. Project Schedule.
b. Contract Time.
c. Bidder Questions.
7. Post-Meeting Addendum.
E. Minutes: Entity responsible for conducting meeting will record and distribute meeting minutes to attendees. Minutes of meeting are issued as Available Information and do not constitute a modification to the Procurement and Contracting Documents.
Modifications to the Procurement and Contracting Documents are issued by written Addendum only.
END OF DOCUMENT 00 25 13
Project No. 214175
PRELIMINARY SCHEDULES 00 31 13 - 1
DOCUMENT 00 31 13 - PRELIMINARY SCHEDULES
1.1 PROJECT SCHEDULE
A. This Document, with its referenced attachments, is part of the Procurement and Contracting Requirements for the Project. They provide the Owner's information for the Bidders' convenience and are intended to supplement rather than serve in lieu of the Bidders' investigations. They are available for Bidders' convenience and information but do not affect Contract Time requirements. This Document and its attachments are not part of the Contract Documents.
B. Available Project information includes the following:
1. Bid Schedule
a. 12/05/2023 � Pre-Bid Meeting @ 3:30 PM, Virtual
b. 12/19/2023 � Bids due @ 4:00 PM, KRESA Building
c. 12/21/2023 � Post-Bid Interviews, KRESA Building
d. 12/22/2023 � Bid Recommendation to Owner
e. 01/2024 � Contract Award
C. The project schedule, including design and construction milestones, is available for viewing following this Section. CSM Group�s schedule is provided for reference.
1. Technology contractor key dates are:
a. 03/2024 � Access Control Pre-Installation Meeting
b. 06/2024 � Network Operational
c. 09/2024 through 01/2025 � Equipment Installation
d. 10/2024 � Site Surveillance Camera Installation
e. 01/2025 � Flat Panel Installation
f. 02/2025 through 03/2025 � Owner Training
g. 02/18/2025 - Substantial Completion
h. 03/2025 � Warranty Commencement
D. Related Requirements:
1. Document 00 41 13 "Bid Form - Stipulated Sum (Single-Prime Contract)" for Contract Time.
END OF DOCUMENT 00 31 13
ID %
Complete
Task Name Duration Start Finish
0 39% KRESA 840 days Mon 1/3/22 Tue 4/8/25 25 96% Bid Phase 449 days Mon 1/3/22 Tue 9/26/23 81 70% Submittals & Procurement 471 days Fri 9/16/22 Wed 7/17/24 87 60% Mass Timber / CLT Deck 120 days Thu 1/5/23 Thu 6/22/23 88 85% Insulated Metal Panels 150 days Mon 3/20/23 Wed 10/18/23 90 80% Roofing Insulation 180 days Fri 12/2/22 Mon 8/14/23 91 60% Architectural/Structural Materials (Doors, Hardware, Millwork) 90 days Mon 3/20/23 Tue 7/25/23 92 75% Elevators 180 days Mon 3/20/23 Thu 11/30/23 94 50% Electrical Primary Switch Gear, Transformers, & Panels 381 days Fri 1/20/23 Wed 7/17/24 95 70% HVAC Equipment (RTU's) 200 days Thu 6/1/23 Wed 3/13/24 96 70% Mechanical/Piping 90 days Mon 3/20/23 Tue 7/25/23 97 0% Fire Protection 60 days Mon 3/20/23 Mon 6/12/23 98 50% Generator 265 days Mon 3/20/23 Mon 4/1/24 99 50% Curtainwall 180 days Mon 3/20/23 Thu 11/30/23
100 50% Food Service Equipment 120 days Mon 3/20/23 Wed 9/6/23 128 19% Construction Phase 820 days Mon 1/3/22 Tue 3/11/25 129 71% Sitework 541 days Thu 9/1/22 Wed 10/9/24
141 80% Rough Grading 300 days Wed 3/1/23 Wed 5/1/24 142 0% Electrical Utility Connection to Building 5 days Mon 6/3/24 Fri 6/7/24
143 0% Plumbing Utility Connection to Building 5 days Mon 6/3/24 Fri 6/7/24
144 0% F/R/P Generator Pad 5 days Tue 3/26/24 Mon 4/1/24
145 0% Install Generator 30 days Tue 4/2/24 Mon 5/13/24 146 0% Exterior Entrance Bridge 30 days Thu 5/2/24 Thu 6/13/24
147 0% Storm Sewer Lift Station 5 days Mon 5/6/24 Fri 5/10/24 148 0% Site Concrete, Curb, Sidewalk 30 days Mon 6/24/24 Mon 8/5/24
149 0% Fencing/Gates 20 days Mon 6/24/24 Mon 7/22/24
150 0% Monument Sign/Signage 10 days Mon 6/24/24 Mon 7/8/24
151 0% Monument Sign/Signage 10 days Mon 6/24/24 Mon 7/8/24
152 0% Irrigation 15 days Tue 7/30/24 Mon 8/19/24
153 0% Delineator & Topsoil Cap 10 days Tue 8/6/24 Mon 8/19/24
154 0% Final Grade 20 days Tue 8/13/24 Tue 9/10/24
155 0% Landscaping 20 days Tue 8/13/24 Tue 9/10/24
156 0% Parking Lot Base 5 days Tue 8/20/24 Mon 8/26/24
157 0% Parking Lot - Top Course 5 days Wed 10/2/24 Tue 10/8/24
158 0% Striping 1 day Wed 10/9/24 Wed 10/9/24
159 9% Building Construction 815 days Mon 1/3/22 Tue 3/4/25
161 0% DELAY ACTIVITES (weather, material, resources) 1 day Mon 1/3/22 Mon 1/3/22
162 0% List delay here 1 day Mon 1/3/22 Mon 1/3/22 163 52% Excavation & Structural 597 days Mon 1/3/22 Wed 4/24/24
164 79% Excavation & Structural - Area B 250 days Mon 3/27/23 Mon 3/18/24
171 50% Backfill 6 days Fri 5/5/23 Mon 10/23/23 178 0% Final Grade/Install stone 3 days Mon 10/16/23 Wed 10/18/23 182 0% Seal concrete 1 day Mon 10/23/23 Mon 10/23/23
Hoffman Bros
Buist
RW LaPine
Cannon Concrete
Buist
Hoffman Bros
Cannon Concrete
Cannon Concrete
Clark
DJ Landscaping
Hoffman Bros
Hoffman Bros
DJ Landscaping
Hoffman Bros
Michigan Paving
Michigan Paving
Hoffman Bros
Hoffman Bros
Applied Flooring
9/17 11/5 12/24 2/11 3/31 5/19 7/7 8/25 10/13 12/1 1/19 3/9 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter
KRESA CTE Center Mon 11/27/23
Task Name Duration Start Finish
183 0% Area B - Pour 1st Floor (includes 7 day cure time)
7 days Tue 2/13/24 Wed 2/21/24
184 0% Install Interior Thicken Slab Mason Walls 8 days Wed 2/21/24 Fri 3/1/24 185 0% Install Metal Pan Stairs & Landings 10 days Thu 2/22/24 Wed 3/6/24 186 0% Pour Locker Bases 1 day Mon 3/4/24 Mon 3/4/24 187 0% Pour stairs & landing 3 days Thu 3/7/24 Mon 3/11/24 188 0% Install Railing - Stair & Landing 5 days Tue 3/12/24 Mon 3/18/24 189 55% Excavation & Structural - Area D 595 days Mon 1/3/22 Mon 4/22/24
197 25% Exterior Non-load Bearing Masonry Walls 5 days Tue 10/17/23 Mon 10/23/23 198 75% Remaining Waterproofing/Insulation 1 day Tue 10/24/23 Tue 10/24/23 199 25% Remaining Backfill 1 day Wed 10/25/23 Wed 10/25/23 200 75% Underground Utilities - Plumbing 15 days Tue 10/17/23 Mon 11/6/23 201 75% Underground Utilities - Electrical 15 days Tue 10/17/23 Mon 11/6/23 202 0% Area D - 2nd Floors Pour Prep Time 3 days Mon 11/6/23 Wed 11/8/23 203 0% Area D - 2nd Floors Pour 4 days Thu 11/9/23 Tue 11/14/23 204 0% Area D - 2nd Floors Pour (cure time) 7 days Wed 11/15/23 Fri 11/24/23 205 0% Seal concrete 4 days Mon 11/27/23 Thu 11/30/23 206 0% Install Metal Pan Stairs & Landings 10 days Mon 1/3/22 Fri 1/14/22 207 0% Final Grade/Install stone 2 days Thu 2/1/24 Fri 2/2/24 208 0% Pour stairs & landing 3 days Tue 3/12/24 Thu 3/14/24 209 0% Area D - 1st Floors Pour (includes 7 day cure time) 10 days Mon 3/18/24 Fri 3/29/24
210 0% Interior Masonry Walls 15 days Mon 4/1/24 Fri 4/19/24 211 0% Pour Locker Bases 1 day Mon 4/22/24 Mon 4/22/24 212 42% Excavation & Structural - Area C 203 days Fri 4/14/23 Wed 1/31/24
218 70% Area C - Structural Steel & Level 2 Decking Installation
20 days Tue 10/17/23 Mon 11/13/23
219 50% Remaining Backfill 5 days Tue 11/14/23 Mon 11/20/23 220 50% Underground Utilities - Electrical 10 days Tue 11/21/23 Tue 12/5/23 221 50% Underground Utilities - Plumbing 10 days Tue 11/21/23 Tue 12/5/23 222 0% Final Grade/Install stone 3 days Wed 12/6/23 Fri 12/8/23 223 0% Area C - Pour 2nd Floor Slab 10 days Mon 12/11/23 Fri 12/22/23 224 0% Area C - Pour 1st Floor Slab 10 days Tue 12/26/23 Tue 1/9/24 225 0% Seal concrete 4 days Wed 1/10/24 Mon 1/15/24 226 0% Install Metal Pan Stairs & Landing 10 days Wed 1/10/24 Tue 1/23/24 227 0% Interior Masonry Walls 15 days Wed 1/10/24 Tue 1/30/24 228 0% Pour stairs & landing 3 days Wed 1/24/24 Fri 1/26/24 229 0% Pour Locker Bases 1 day Wed 1/31/24 Wed 1/31/24 230 36% Excavation & Structural - Area A/E/F 246 days Tue 5/9/23 Wed 4/24/24
236 50% Exterior/Interior Load Bearing Masonry Walls 30 days Mon 9/18/23 Fri 10/27/23 238 50% Waterproofing/Insulation 1 day Mon 10/16/23 Mon 10/16/23 239 0% Remaining Backfill 1 day Tue 10/17/23 Tue 10/17/23 240 0% Area A/E/F - Structural Steel & Level 2 Decking
Installation 30 days Tue 11/14/23 Wed 12/27/23
241 15% Underground Utilities - Electrical 6 wks Thu 12/28/23 Thu 2/8/24 242 15% Underground Utilities - Plumbing 6 wks Thu 12/28/23 Thu 2/8/24 243 0% Final Grade/Install stone 5 days Mon 2/5/24 Fri 2/9/24 244 0% Area A/E/F - Pour 2nd Floor 20 days Mon 2/12/24 Fri 3/8/24 245 0% Seal concrete 4 days Tue 2/13/24 Fri 2/16/24 246 0% Area A/E/F - Pour 1st Floor 20 days Mon 3/11/24 Fri 4/5/24 247 0% Install Metal Pan Stairs & Landing 10 days Mon 4/8/24 Fri 4/19/24 248 0% Pour stairs & landing 3 days Mon 4/22/24 Wed 4/24/24 249 0% Pour Locker Bases 2 days Mon 4/8/24 Tue 4/9/24
Cannon Concrete
Leidal & Hart
OIK
Cannon Concrete
OIK
OIK
Leidal & Hart
CJs Coating
Hoffman Bros
RW LaPine
Buist
Cannon Concrete
Cannon Concrete
Applied Flooring
Hoffman Bros
OIK
Cannon Concrete
Leidal & Hart
Cannon Concrete
Area C - Structural Steel & Level 2 Decking Installation
Hoffman Bros
Buist
RW LaPine
Hoffman Bros
Cannon Concrete
Cannon Concrete
Applied Flooring
OIK
Leidal & Hart
OIK
Cannon Concrete
Leidal & Hart
CJs Coating
Hoffman Bros
Area A/E/F - Structural Steel & Level 2 Decking Installation
Underground Utilities - Electrical
Underground Utilities - Plumbing
Final Grade/Install stone
Area A/E/F - Pour 2nd Floor
Applied Flooring
Area A/E/F - Pour 1st Floor
OIK
OIK
Cannon Concrete
9/17 11/5 12/24 2/11 3/31 5/19 7/7 8/25 10/13 12/1 1/19 3/9
Task Name Duration Start Finish
250 8% Core & Shell 317 days Thu 6/8/23 Wed 9/4/24
251 66% Structural Steel/Fire Proofing 202 days Thu 6/8/23 Fri 3/22/24
254 0% Area B - Fireproofing 8 days Tue 10/17/23 Thu 10/26/23 255 0% Area D - Fireproofing 8 days Mon 11/27/23 Wed 12/6/23 256 0% Area C/A/E/F - Fireproofing 10 days Mon 3/11/24 Fri 3/22/24 257 0% Mass Timber and CLT Deck 157 days Mon 10/30/23 Mon 6/10/24
258 0% Area B - CLT Deck 8 days Mon 10/30/23 Wed 11/8/23 259 0% Area D - CLT Deck 8 days Mon 12/4/23 Wed 12/13/23 260 0% Area C - Glulam Beams 15 days Wed 1/10/24 Tue 1/30/24 261 0% Area C - CLT Deck 5 days Wed 1/31/24 Tue 2/6/24 262 0% Area A/E/F - Glulam Beams 15 days Mon 4/8/24 Fri 4/26/24 263 0% Area A/E/F - CLT Deck 15 days Mon 4/29/24 Fri 5/17/24 264 0% Area C/A/E/F - Nano Panel 15 days Mon 5/20/24 Mon 6/10/24 265 0% Façade & Windows 209 days Thu 11/9/23 Wed 9/4/24
266 0% Exterior - Area B 65 days Thu 11/9/23 Mon 2/12/24 267 0% Exterior Façade (CFMF) 25 days Thu 11/9/23 Thu 12/14/23 268 0% Exterior Façade (IMP) 20 days Fri 12/15/23 Mon 1/15/24 269 0% Curtain Wall/Glazing 35 days Fri 12/22/23 Mon 2/12/24 270 0% Exterior - Area D 65 days Thu 12/14/23 Fri 3/15/24 271 0% Exterior Façade (CFMF) 25 days Thu 12/14/23 Fri 1/19/24 272 0% Exterior Façade (IMP) 20 days Mon 1/22/24 Fri 2/16/24 273 0% Curtain Wall/Glazing 35 days Mon 1/29/24 Fri 3/15/24 274 0% Exterior - Area C 70 days Wed 2/7/24 Tue 5/14/24 275 0% Exterior Façade (CFMF) 25 days Wed 2/7/24 Tue 3/12/24 276 0% Exterior Façade (IMP) 20 days Wed 3/13/24 Tue 4/9/24 277 0% Curtain Wall/Glazing 35 days Wed 3/27/24 Tue 5/14/24 278 0% Exterior - Area A/E/F 75 days Mon 5/20/24 Wed 9/4/24 279 0% Exterior Façade (CFMF) 30 days Mon 5/20/24 Mon 7/1/24 280 0% Exterior Façade (IMP) 20 days Tue 7/2/24 Tue 7/30/24 281 0% Curtain Wall/Glazing 35 days Wed 7/17/24 Wed 9/4/24 282 0% Exterior Façade (ACM) - All Areas 20 days Wed 7/31/24 Tue 8/27/24 283 0% Exterior Façade (Screen Wall) - A, E, F 20 days Wed 7/10/24 Tue 8/6/24 284 0% Roofing 169 days Thu 11/9/23 Tue 7/9/24
285 0% Area B - Roof Membrane Installation 3 days Thu 11/9/23 Mon 11/13/23 286 0% Area B - Roofing Installation 15 days Fri 12/1/23 Thu 12/21/23 287 0% Area D - Roof Membrane Installation 3 days Thu 12/14/23 Mon 12/18/23 288 0% Area D - Roof Installation 15 days Mon 1/8/24 Fri 1/26/24 289 0% Area C - Skylight Framing 3 days Fri 2/2/24 Tue 2/6/24 290 0% Area C - Roof Installation 15 days Wed 2/7/24 Tue 2/27/24 291 0% Area C - Skylight Installation 3 days Fri 2/23/24 Tue 2/27/24 292 0% Area A/E/F - Roof Installation 35 days Mon 5/20/24 Tue 7/9/24 293 0% Building Shell Complete - Area B 0 days Mon 2/12/24 Mon 2/12/24
294 0% Building Shell Complete - Area D 0 days Fri 3/15/24 Fri 3/15/24
295 0% Building Shell Complete - Area C 0 days Tue 5/14/24 Tue 5/14/24
296 0% Building Shell Complete - Area A/E/F 0 days Wed 9/4/24 Wed 9/4/24
297 0% Interior Build Out 320 days Fri 12/1/23 Tue 3/4/25
298 0% Primary Switch Gear & Panels 35 days Thu 7/18/24 Thu 9/5/24
299 0% Area B 219 days Fri 12/1/23 Wed 10/9/24
300 0% Area B - Level 2 185 days Fri 12/1/23 Wed 8/21/24
H & H Painting
H & H Painting
H & H Painting
Christman
Christman
Christman
Christman
Area A/E/F - Glulam Beams
Area A/E/F - CLT Deck
Christman
Bouma Corp
Universal Wall
Forman Glass
Bouma Corp
Universal Wall
Forman Glass
Bouma Corp
Universal Wall
Forman Glass
Bouma Corp
Universal Wall
Forman Glass
Universal Wall
Universal Wall
McDonald Roofing
McDonald Roofing
McDonald Roofing
McDonald Roofing
Forman Glass
McDonald Roofing
Forman Glass
Area A/E/F - Roof Installation
Building Shell Complete - Area B
Building Shell Complete - Area D
Building Shell Complete - Area C
Building Shell Complete - Area A/E/F
Buist
9/17 11/5 12/24 2/11 3/31 5/19 7/7 8/25 10/13 12/1 1/19 3/9
Task Name Duration Start Finish
301 0% Mechanical Mains 25 days Fri 12/1/23 Mon 1/8/24 302 0% Electrical Mains 25 days Fri 12/1/23 Mon 1/8/24 303 0% Piping/Plumbing Mains 25 days Fri 12/1/23 Mon 1/8/24 304 0% Fire Protection Mains 25 days Fri 12/1/23 Mon 1/8/24 305 0% Wall Framing 27 days Fri 12/22/23 Wed 1/31/24 306 0% MEP In Wall Installation 30 days Tue 1/9/24 Mon 2/19/24 307 0% Ceiling Framing 15 days Thu 1/25/24 Wed 2/14/24 308 0% Hang Drywall 15 days Tue 2/20/24 Mon 3/11/24 309 0% Finish Drywall 10 days Tue 3/12/24 Mon 3/25/24 310 0% Interior Glass & Glazing 10 days Tue 3/26/24 Mon 4/8/24 311 0% Millwork 5 days Tue 3/26/24 Mon 4/1/24 312 0% Painting/Tile/Wall Coverings 30 days Tue 3/26/24 Mon 5/6/24 313 0% Ceilings 22 days Tue 4/23/24 Wed 5/22/24 314 0% Flooring 25 days Tue 5/7/24 Tue 6/11/24 315 0% Lighting/Electronics 17 days Wed 5/29/24 Thu 6/20/24 316 0% HVAC/Plumbing Trim Out 17 days Wed 5/29/24 Thu 6/20/24 317 0% FP Trim Out 12 days Mon 6/3/24 Tue 6/18/24 318 0% Install Lockers 2 days Thu 5/23/24 Fri 5/24/24 319 0% Connect/Install Owner Equipment 35 days Mon 6/3/24 Mon 7/22/24 320 0% Install Doors & Hardware 15 days Wed 6/5/24 Tue 6/25/24 321 0% Install Overhead/Coiling Doors/Fire Curtains 10 days Thu 8/8/24 Wed 8/21/24 322 0% Final Cleaning 10 days Tue 7/23/24 Mon 8/5/24 323 0% T&B 5 days Tue 8/6/24 Mon 8/12/24 324 0% Area B - Level 1 199 days Tue 1/2/24 Wed 10/9/24
325 0% Mechanical Mains 25 days Tue 1/2/24 Mon 2/5/24 326 0% Electrical Mains 25 days Tue 1/2/24 Mon 2/5/24 327 0% Piping/Plumbing Mains 25 days Tue 1/2/24 Mon 2/5/24 328 0% Fire Protection Mains 25 days Tue 1/2/24 Mon 2/5/24 329 0% Wall Framing 28 days Mon 3/4/24 Wed 4/10/24 330 0% MEP In Wall Installation 30 days Mon 3/18/24 Fri 4/26/24 331 0% Ceiling Framing 15 days Thu 4/4/24 Wed 4/24/24 332 0% Hang Drywall 15 days Mon 4/29/24 Fri 5/17/24 333 0% Finish Drywall 10 days Mon 5/20/24 Mon 6/3/24 334 0% Interior Glass & Glazing 10 days Tue 6/4/24 Mon 6/17/24 335 0% Millwork 5 days Tue 6/4/24 Mon 6/10/24 336 0% Painting/Tile/Wall Coverings 30 days Tue 6/4/24 Tue 7/16/24 337 0% Flooring 25 days Tue 7/2/24 Tue 8/6/24 338 0% Ceilings 23 days Mon 7/15/24 Wed 8/14/24 339 0% Lighting/Electronics 18 days Mon 7/15/24 Wed 8/7/24 340 0% HVAC/Plumbing Trim Out 18 days Mon 7/15/24 Wed 8/7/24 341 0% FP Trim Out 13 days Fri 7/19/24 Tue 8/6/24 342 0% Install Doors & Hardware 15 days Wed 7/31/24 Tue 8/20/24 343 0% Connect/Install Owner Equipment 35 days Wed 8/7/24 Wed 9/25/24 344 0% Final Cleaning 10 days Thu 9/26/24 Wed 10/9/24 345 0% Area D 242 days Mon 1/8/24 Mon 12/16/24
346 0% Area D - Level 2 180 days Mon 1/8/24 Wed 9/18/24
347 0% Mechanical Mains 25 days Mon 1/8/24 Fri 2/9/24 348 0% Electrical Mains 25 days Mon 1/8/24 Fri 2/9/24 349 0% Piping/Plumbing Mains 25 days Mon 1/8/24 Fri 2/9/24 350 0% Fire Protection Mains 25 days Mon 1/8/24 Fri 2/9/24 351 0% Wall Framing 27 days Mon 1/29/24 Tue 3/5/24 352 0% MEP In Wall Installation 30 days Mon 2/12/24 Fri 3/22/24 353 0% Ceiling Framing 15 days Wed 2/28/24 Tue 3/19/24
RW LaPine
Buist
RW LaPine
Blaze FP
Bouma Corp
Bouma Corp,RW LaPine
Bouma Corp
Bouma Corp
Bouma Corp
Forman Glass
Hazelhoff
H & H Painting
Bouma Corp
Yoxheimer Tile
Buist
RW LaPine
Blaze FP
Rayhaven
Clark
Overhead Doors BC
RW LaPine
RW LaPine
Buist
RW LaPine
Blaze FP
Bouma Corp
Buist,RW LaPine
Bouma Corp
Bouma Corp
Bouma Corp
Forman Glass
Hazelhoff
H & H Painting
Yoxheimer Tile
Bouma Corp
Buist
RW LaPine
Blaze FP
Clark
RW LaPine
Buist
RW LaPine
Blaze FP
Bouma Corp
Buist,RW LaPine
Bouma Corp
9/17 11/5 12/24 2/11 3/31 5/19 7/7 8/25 10/13 12/1 1/19 3/9
Task Name Duration Start Finish
354 0% Hang Drywall 15 days Mon 3/25/24 Fri 4/12/24 355 0% Finish Drywall 15 days Mon 4/15/24 Fri 5/3/24 356 0% Interior Glass & Glazing 10 days Mon 5/6/24 Fri 5/17/24 357 0% Millwork 25 days Mon 5/6/24 Mon 6/10/24 358 0% Painting/Wall Covering 30 days Tue 5/28/24 Tue 7/9/24 359 0% Ceilings 23 days Fri 6/7/24 Wed 7/10/24 360 0% Flooring 25 days Tue 6/25/24 Tue 7/30/24 361 0% Lighting/Electronics 18 days Wed 7/17/24 Fri 8/9/24 362 0% HVAC/Plumbing Trim Out 18 days Wed 7/17/24 Fri 8/9/24 363 0% Kitchen Equipment Installation 18 days Wed 7/17/24 Fri 8/9/24 364 0% Connect/Install Owner Equipment 35 days Wed 7/17/24 Wed 9/4/24 365 0% Install Lockers 2 days Thu 7/18/24 Fri 7/19/24 366 0% FP Trim Out 13 days Fri 7/19/24 Tue 8/6/24 367 0% Install Doors & Hardware 15 days Wed 7/24/24 Tue 8/13/24 368 0% Install Coiling Doors/Fire Curtains 10 days Mon 8/12/24 Fri 8/23/24 369 0% Final Cleaning 10 days Thu 9/5/24 Wed 9/18/24 370 0% T&B 5 days Thu 9/12/24 Wed 9/18/24 371 0% Area D - Level 1 222 days Mon 2/5/24 Mon 12/16/24
372 0% Mechanical Mains 25 days Mon 2/5/24 Fri 3/8/24 373 0% Electrical Mains 25 days Mon 2/5/24 Fri 3/8/24 374 0% Piping/Plumbing Mains 25 days Mon 2/5/24 Fri 3/8/24 375 0% Fire Protection Mains 25 days Mon 2/5/24 Fri 3/8/24 376 0% Wall Framing 28 days Mon 4/22/24 Thu 5/30/24 377 0% MEP In Wall Installation 30 days Mon 5/6/24 Mon 6/17/24 378 0% Ceiling Framing 15 days Thu 5/23/24 Thu 6/13/24 379 0% Hang Drywall 15 days Tue 6/18/24 Tue 7/9/24 380 0% Finish Drywall 15 days Wed 7/10/24 Tue 7/30/24 381 0% Interior Glass & Glazing 10 days Wed 7/31/24 Tue 8/13/24 382 0% Millwork 25 days Wed 7/31/24 Wed 9/4/24 383 0% Painting/Wall Covering 30 days Wed 8/21/24 Wed 10/2/24 384 0% Ceilings 23 days Tue 9/3/24 Thu 10/3/24 385 0% Flooring 25 days Thu 9/19/24 Wed 10/23/24 386 0% Lighting/Electronics 18 days Thu 10/10/24 Mon 11/4/24 387 0% HVAC/Plumbing Trim Out 18 days Thu 10/10/24 Mon 11/4/24 388 0% FP Trim Out 13 days Mon 10/14/24 Wed 10/30/24 389 0% Connect/Install Owner Equipment 35 days Mon 10/14/24 Mon 12/2/24 390 0% Install Doors & Hardware 15 days Thu 10/17/24 Wed 11/6/24 391 0% Final Cleaning 10 days Tue 12/3/24 Mon 12/16/24 392 0% Area C 207 days Wed 2/7/24 Tue 11/26/24 393 0% Area C - Level 1 207 days Wed 2/7/24 Tue 11/26/24
394 0% Mechanical Mains 25 days Wed 2/7/24 Tue 3/12/24 395 0% Electrical Mains 25 days Wed 2/7/24 Tue 3/12/24 396 0% Piping/Plumbing Mains 25 days Wed 2/7/24 Tue 3/12/24 397 0% Fire Protection Mains 25 days Wed 2/7/24 Tue 3/12/24 398 0% Wall Framing 28 days Wed 2/28/24 Fri 4/5/24 399 0% Ceiling Framing 15 days Mon 4/1/24 Fri 4/19/24 400 0% MEP In Wall Installation 30 days Wed 3/13/24 Tue 4/23/24 401 0% Hang Drywall 30 days Wed 5/15/24 Wed 6/26/24 402 0% Finish Drywall 30 days Thu 6/13/24 Thu 7/25/24 403 0% Interior Glass & Glazing 10 days Fri 7/26/24 Thu 8/8/24 404 0% Ceilings 23 days Fri 7/26/24 Tue 8/27/24 405 0% Millwork 25 days Fri 7/26/24 Thu 8/29/24 406 0% Painting/Wall Covering 30 days Fri 7/26/24 Fri 9/6/24
Bouma Corp
Bouma Corp
Forman Glass
Hazelhoff
H & H Painting
Bouma Corp
Yoxheimer Tile
Buist
RW LaPine
Stafford Smith
Rayhaven
Clark
Overhead Doors BC
RW LaPine
RW LaPine
Buist
RW LaPine
Blaze FP
Bouma Corp
Buist,RW LaPine
Bouma Corp
Bouma Corp
Bouma Corp
Forman Glass
Hazelhoff
H & H Painting
Bouma Corp
Yoxheimer Tile
Buist
RW LaPine
Blaze FP
Clark
RW LaPine
Buist
RW LaPine
Blaze FP
Bouma Corp
Bouma Corp
Buist,RW LaPine
Bouma Corp
Bouma Corp
Forman Glass
Bouma Corp
Hazelhoff
H & H Painting
9/17 11/5 12/24 2/11 3/31 5/19 7/7 8/25 10/13 12/1 1/19 3/9
Task Name Duration Start Finish
407 0% Flooring 25 days Fri 8/23/24 Fri 9/27/24 408 0% Lighting/Electronics 18 days Fri 8/30/24 Wed 9/25/24 409 0% HVAC/Plumbing Trim Out 18 days Fri 8/30/24 Wed 9/25/24 410 0% Install Lockers 2 days Mon 9/9/24 Tue 9/10/24 411 0% FP Trim Out 13 days Wed 9/18/24 Fri 10/4/24 412 0% Connect/Install Owner Equipment 35 days Wed 9/18/24 Tue 11/5/24 413 0% Install Doors & Hardware 15 days Mon 9/23/24 Fri 10/11/24 414 0% Install Coiling Doors/Fire Curtains 10 days Thu 9/26/24 Wed 10/9/24 415 0% Final Cleaning 10 days Wed 11/6/24 Tue 11/19/24 416 0% T&B 5 days Wed 11/20/24 Tue 11/26/24 417 0% Area C - Level 2 187 days Wed 2/28/24 Tue 11/19/24
418 0% Mechanical Mains 25 days Wed 2/28/24 Tue 4/2/24 419 0% Electrical Mains 25 days Wed 2/28/24 Tue 4/2/24 420 0% Piping/Plumbing Mains 25 days Wed 2/28/24 Tue 4/2/24 421 0% Fire Protection Mains 25 days Wed 2/28/24 Tue 4/2/24 422 0% Wall Framing 28 days Wed 3/20/24 Fri 4/26/24 423 0% Ceiling Framing 15 days Mon 4/22/24 Fri 5/10/24 424 0% MEP In Wall Installation 30 days Wed 4/3/24 Tue 5/14/24 425 0% Hang Drywall 30 days Wed 5/15/24 Wed 6/26/24 426 0% Finish Drywall 30 days Thu 6/13/24 Thu 7/25/24 427 0% Interior Glass & Glazing 10 days Fri 7/26/24 Thu 8/8/24 428 0% Ceilings 23 days Fri 7/26/24 Tue 8/27/24 429 0% Millwork 25 days Fri 7/26/24 Thu 8/29/24 430 0% Painting/Wall Covering 30 days Fri 7/26/24 Fri 9/6/24 431 0% Flooring 25 days Fri 8/23/24 Fri 9/27/24 432 0% Lighting/Electronics 18 days Fri 8/30/24 Wed 9/25/24 433 0% HVAC/Plumbing Trim Out 18 days Fri 8/30/24 Wed 9/25/24 434 0% FP Trim Out 13 days Wed 9/18/24 Fri 10/4/24 435 0% Connect/Install Owner Equipment 35 days Wed 9/18/24 Tue 11/5/24 436 0% Install Doors & Hardware 15 days Mon 9/23/24 Fri 10/11/24 437 0% Final Cleaning 10 days Wed 11/6/24 Tue 11/19/24 438 0% Area A/E/F 201 days Mon 5/20/24 Tue 3/4/25
439 0% Area A/E/F - Level 1 197 days Mon 5/20/24 Wed 2/26/25
440 0% Mechanical Mains 25 days Mon 5/20/24 Mon 6/24/24 441 0% Electrical Mains 25 days Mon 5/20/24 Mon 6/24/24 442 0% Piping/Plumbing Mains 25 days Mon 5/20/24 Mon 6/24/24 443 0% Fire Protection Mains 25 days Mon 5/20/24 Mon 6/24/24 444 0% Wall Framing 26 days Fri 5/31/24 Mon 7/8/24 445 0% Ceiling Framing 15 days Mon 6/24/24 Mon 7/15/24 446 0% MEP In Wall Installation 30 days Fri 6/21/24 Fri 8/2/24 447 0% Hang Drywall 25 days Thu 9/5/24 Wed 10/9/24 448 0% Finish Drywall 25 days Thu 10/10/24 Wed 11/13/24 449 0% Millwork 25 days Thu 10/31/24 Thu 12/5/24 450 0% Painting 30 days Thu 10/31/24 Thu 12/12/24 451 0% Interior Glass & Glazing 10 days Thu 11/7/24 Wed 11/20/24 452 0% Ceilings 22 days Thu 11/14/24 Mon 12/16/24 453 0% Flooring 25 days Thu 11/21/24 Fri 12/27/24 454 0% Install Lockers 2 days Fri 12/13/24 Mon 12/16/24 455 0% Lighting/Electronics 18 days Fri 12/13/24 Thu 1/9/25 456 0% HVAC/Plumbing Trim Out 18 days Fri 12/13/24 Thu 1/9/25 457 0% FP Trim Out 13 days Tue 12/17/24 Mon 1/6/25 458 0% Connect/Install Owner Equipment 30 days Tue 12/17/24 Wed 1/29/25 459 0% Install Doors & Hardware 15 days Fri 12/20/24 Mon 1/13/25
Yoxheimer Tile
Buist
RW LaPine
Rayhaven
Blaze FP
Clark
Overhead Doors BC
RW LaPine
RW LaPine
Buist
RW LaPine
Blaze FP
Bouma Corp
Bouma Corp
Buist,RW LaPine
Bouma Corp
Bouma Corp
Forman Glass
Clark
Hazelhoff
H & H Painting
Yoxheimer Tile
Buist
RW LaPine
Blaze FP
Clark
RW LaPine
Buist
RW LaPine
Blaze FP
Bouma Corp
Bouma Corp
Buist,RW LaPine
Bouma Corp
Bouma Corp
Hazelhoff
H & H Painting
Forman Glass
Bouma Corp
Yoxheimer Tile
Rayhaven
Buist
RW LaPine
Blaze FP
Clark
9/17 11/5 12/24 2/11 3/31 5/19 7/7 8/25 10/13 12/1 1/19 3/9
Task Name Duration Start Finish
460 0% Install Coiling Doors/Fire Curtains 10 days Fri 1/10/25 Thu 1/23/25 461 0% Final Cleaning 15 days Thu 1/30/25 Wed 2/19/25 462 0% T&B 5 days Thu 2/20/25 Wed 2/26/25 463 0% Area A/E/F - Level 2 176 days Tue 6/25/24 Tue 3/4/25
464 0% Mechanical Mains 25 days Tue 6/25/24 Tue 7/30/24 465 0% Electrical Mains 25 days Tue 6/25/24 Tue 7/30/24 466 0% Piping/Plumbing Mains 25 days Tue 6/25/24 Tue 7/30/24 467 0% Fire Protection Mains 25 days Tue 6/25/24 Tue 7/30/24 468 0% Wall Framing 26 days Wed 7/10/24 Wed 8/14/24 469 0% Ceiling Framing 15 days Thu 8/1/24 Wed 8/21/24 470 0% MEP In Wall Installation 30 days Wed 7/31/24 Wed 9/11/24 471 0% Hang Drywall 25 days Thu 9/12/24 Wed 10/16/24 472 0% Finish Drywall 25 days Thu 10/17/24 Wed 11/20/24 473 0% Millwork 25 days Thu 11/7/24 Thu 12/12/24 474 0% Painting 30 days Thu 11/7/24 Thu 12/19/24 475 0% Interior Glass & Glazing 10 days Thu 11/14/24 Wed 11/27/24 476 0% Ceilings 22 days Thu 11/21/24 Mon 12/23/24 477 0% Flooring 25 days Fri 11/29/24 Mon 1/6/25 478 0% HVAC/Plumbing Trim Out 18 days Fri 12/6/24 Thu 1/2/25 479 0% Lighting/Electronics 18 days Fri 12/20/24 Thu 1/16/25 480 0% Install Lockers 2 days Fri 12/20/24 Mon 12/23/24 481 0% FP Trim Out 13 days Tue 12/24/24 Mon 1/13/25 482 0% Install Doors & Hardware 15 days Mon 12/30/24 Mon 1/20/25 483 0% Connect/Install Owner Equipment 30 days Tue 12/31/24 Tue 2/11/25 484 0% Final Cleaning 15 days Wed 2/12/25 Tue 3/4/25 485 0% T&B 5 days Tue 1/21/25 Mon 1/27/25 486 0% Elevators 79 days Wed 7/17/24 Tue 11/5/24 487 0% Elevator (Area A) 15 days Wed 7/17/24 Tue 8/6/24 488 0% Elevator (Area F) 15 days Wed 8/7/24 Tue 8/27/24 489 0% Elevator Interior Finishes 4 days Thu 10/31/24 Tue 11/5/24 490 0% Project Acceptance 136 days Wed 8/28/24 Tue 3/11/25
491 0% MEP Rough-in Inspection - Mains 5 days Wed 8/28/24 Wed 9/4/24 492 0% MEP In Wall Inspection 5 days Thu 9/5/24 Wed 9/11/24 493 0% CSM Final QC Inspection Walkthrough 5 days Fri 1/10/25 Thu 1/16/25 494 0% Agency Final Inspections 3 days Fri 1/17/25 Tue 1/21/25 495 0% Punch list Walkthrough w/ Owner & A/E 5 days Wed 2/12/25 Tue 2/18/25 496 0% Punchlist Completion 15 days Wed 2/19/25 Tue 3/11/25 497 0% Attic Stock Turn-Over to Owner 2 days Wed 1/22/25 Thu 1/23/25
498 0% Owner Training 5 days Wed 1/22/25 Tue 1/28/25
499 0% Project Turnover To KRESA 0 days Tue 3/11/25 Tue 3/11/25
500 0% Project Closeout 19 days Wed 3/12/25 Tue 4/8/25
501 0% Warranty Period (24 month) Begins 0 days Wed 3/12/25 Wed 3/12/25 502 0% Provide Project Closeout Documentation 0 days Tue 4/8/25 Tue 4/8/25
Overhead Doors BC
RW LaPine
Mechanical Mains
Electrical Mains
Piping/Plumbing Mains
Fire Protection Mains
Wall Framing
Bouma Corp
MEP In Wall Installation
Hang Drywall
Finish Drywall
Hazelhoff
Painting
Forman Glass
Bouma Corp
Flooring
RW LaPine
Buist
Rayhaven
FP Trim Out
Clark
Connect/Install Owner Equipment
Final Cleaning
RW LaPine
Punch list Walkthrough w/ Owner & A/E
Punchlist Completion
Project Turnover To KRESA
Warranty Period (24 month) Begins
Provide Project Closeout Documentation
9/17 11/5 12/24 2/11 3/31 5/19 7/7 8/25 10/13 12/1 1/19 3/9
Kalamazoo Regional Educational Service AgencyWightman Career Connect Campus - Technology Bid Package11/29/2023 Project No. 214175
BID FORM - STIPULATED SUM (SINGLE-PRIME CONTRACT) 00 41 13 - 1
DOCUMENT 00 41 13 - BID FORM - STIPULATED SUM (SINGLE-PRIME CONTRACT)
1.1 BID INFORMATION
A. Bidder: ___________________________________________________________.
B. Project Name: Career Connect Campus � Technology Bid Package
C. Project Location: 3500 Vanrick Drive, Kalamazoo, MI 49001
D. Owner: Kalamazoo Regional Educational Service Agency
E. Architect: Wightman & Associates, Inc.
F. Architect Project Number: 214175
1.2 CERTIFICATIONS AND BASE BID
A. Base Bid, Single-Prime (All Trades) Contract: The undersigned Bidder, having carefully examined the Procurement and Contracting Requirements, Conditions of the Contract, Drawings, Specifications, and all subsequent Addenda, as prepared by Wightman and Associates and Architect's consultants, and being familiar with all conditions and requirements of the Work, hereby agrees to furnish all material, labor, equipment and services, including all scheduled allowances, necessary to complete the construction of the above-named project, according to the requirements of the Procurement and Contracting Documents, for the stipulated sum of:
1. ________________________________________________ Dollars ($______________).
2. The above amount may be modified by amounts indicated by the Bidder on the attached Document 00 43 23 "Alternates Form."
1.3 BID GUARANTEE
A. The undersigned Bidder agrees to execute a contract for this Work in the above amount and to furnish surety as specified within 10 days after a written Notice of Award, if offered within 60 days after receipt of bids, and on failure to do so agrees to forfeit to Owner the attached cash, cashier's check, certified check, U.S. money order, or bid bond, as liquidated damages for such failure, in the following amount constituting five percent (5%) of the Base Bid amount above:
1. ________________________________________________ Dollars ($______________).
Project No. 214175
BID FORM - STIPULATED SUM (SINGLE-PRIME CONTRACT) 00 41 13 - 2
B. In the event Owner does not offer Notice of Award within the time limits stated above, Owner will return to the undersigned the cash, cashier's check, certified check, U.S. money order, or bid bond.
1.4 SUBCONTRACTORS AND SUPPLIERS
A. Attach a list of all subcontractors to be used and the expected work performed. Also, areas of work that will be self-performed.
1.5 TIME OF COMPLETION
A. The undersigned Bidder proposes and agrees hereby to commence the Work of the Contract Documents on a date specified in a written Notice to Proceed to be issued by Architect and shall fully complete the Work within that Contract Time.
1.6 ACKNOWLEDGMENT OF ADDENDA
A. The undersigned Bidder acknowledges receipt of and use of the following Addenda in the preparation of this Bid:
1. Addendum No. 1, dated ____________________.
2. Addendum No. 2, dated ____________________.
3. Addendum No. 3, dated ____________________.
4. Addendum No. 4, dated ____________________.
1.7 BID SUPPLEMENTS
A. The following supplements are a part of this Bid Form and are attached hereto.
1. Section 00 43 13 - Alternates.
2. Section 00 43 23 Familial Disclosure Statement.
3. Section 00 43 25 Iran Affidavit of Compliance.
1.8 SUBMISSION OF BID
A. Respectfully submitted this ____ day of ____________, 2023.
B. Submitted By:________________________________________________ (Name of bidding firm or corporation).
C. Authorized Signature:__________________________________________ (Handwritten signature)
D. Signed By:___________________________________________________
Project No. 214175
BID FORM - STIPULATED SUM (SINGLE-PRIME CONTRACT) 00 41 13 - 3
(Type or print name)
E. Title:________________________________________________________ (Owner/Partner/President/Vice President)
F. Witnessed By:________________________________________________ (Handwritten signature)
G. Attest:______________________________________________________ (Handwritten signature)
H. By:_________________________________________________________ (Type or print name)
I. Title:________________________________________________________
J. Street Address:________________________________________________
K. City,State,Zip:_________________________________________________
L. Phone:______________________________________________________
END OF DOCUMENT 00 41 13
Project No. 214175
BID SECURITY FORMS 00 43 13 - 1
DOCUMENT 00 43 13 - BID SECURITY FORMS
1.1 BID FORM SUPPLEMENT
A. A completed bid bond form is required to be attached to the Bid Form.
1.2 BID BOND FORM
A. AIA Document A312-2010 "Bid Bond" is the recommended form for a bid bond. A bid bond acceptable to Owner, or other bid security as described in the Instructions to Bidders, is required to be attached to the Bid Form as a supplement.
B. Copies of AIA standard forms may be obtained from The American Institute of Architects; https://www.aiacontracts.org/; email: docspurchases@aia.org; (800) 942- 7732.
END OF DOCUMENT 00 43 13
Project No. 214175
ALTERNATES FORM 00 43 23 - 1
DOCUMENT 00 43 23 - ALTERNATES FORM
1.1 BID INFORMATION
A. Bidder: ___________________________________________________________.
B. Project Name: Career Connect Campus � Technology Bid Package
C. Project Location: 3500 Vanrick Drive, Kalamazoo, MI 49001
D. Owner: Kalamazoo Regional Educational Service Agency
E. Architect: Wightman & Associates, Inc.
F. Architect Project Number: 214175
1.2 BID FORM SUPPLEMENT
A. This form is required to be attached to the Bid Form.
1.3 DESCRIPTION
A. The undersigned Bidder proposes the amount below be added to or deducted from the Base Bid if particular alternates are accepted by Owner. Amounts listed for each alternate include costs of related coordination, modification, or adjustment.
B. If the alternate does not affect the Contract Sum, the Bidder shall indicate "NO
CHANGE."
C. If the alternate does not affect the Work of this Contract, the Bidder shall indicate "NOT
APPLICABLE."
D. The Bidder shall be responsible for determining from the Contract Documents the affects of each alternate on the Contract Time and the Contract Sum.
E. Owner reserves the right to accept or reject any alternate, in any order, and to award or amend the Contract accordingly within [60] days of the Notice of Award unless otherwise indicated in the Contract Documents.
F. Acceptance or non-acceptance of any alternates by the Owner shall have no affect on the Contract Time unless the "Schedule of Alternates" Article below provides a formatted space for the adjustment of the Contract Time.
Project No. 214175
ALTERNATES FORM 00 43 23 - 2
1.4 SCHEDULE OF ALTERNATES
A. Alternate No. 1: Provide an alternate cost to replace the 110� monitor (AV-FDD-11) to a 98� (AV-FPD-98) where shown in the large Conference Room F210, and medium Conference Room F110.
1. ADD____ DEDUCT____ NO CHANGE____ NOT APPLICABLE____.
2. ________________________________________________Dollars
B. Alternate No. 2: Provide an alternate cost to replace the DirectView LED in the Commons CR110 to a video wall using a monitor array equal to diagonal size of 217�.
1. ADD____ DEDUCT____ NO CHANGE____ NOT APPLICABLE____.
2. ________________________________________________Dollars
1.5 SUBMISSION OF BID SUPPLEMENT
A. Respectfully submitted this ____ day of ____________, 2023.
B. Submitted By:________________________________________________ (Name of bidding firm or corporation)
C. Authorized Signature:__________________________________________ (Handwritten signature)
D. Signed By:__________________________________________________ (Type or print name)
E. Title:_______________________________________________________ (Owner/Partner/President/Vice President)
END OF DOCUMENT 00 43 23
Project No. 214175
FAMILIAL DISCLOSURE STATEMENT 00 43 24 - 1
FAMILIAL DISCLOSURE STATEMENT
AFFIDAVIT OF ______________________________
(insert name of affiant)
STATE OF MICHIGAN )
) ss
COUNTY OF __________________ )
_______________________________________ makes this Affidavit under oath and (insert name of affiant) states as follows:
1. I am a/the:
G President G Vice-President G Chief Executive Officer G Member G Partner G Owner G Other (please specify) ________________________ of [insert name of contractor], a bidder for construction services for Kalamazoo Regional
Educational Service Agency.
2. I have personal knowledge and/or I have personally verified that the following are all of the familial relationships existing between the owner(s) and the employee(s) of the aforementioned contractor and the school district�s superintendent and/or board members:
Project No. 214175
FAMILIAL DISCLOSURE STATEMENT 00 43 24 - 2
3. I have authority to bind the aforementioned contractor with the representations contained herein, and I am fully aware that the school district will rely on my representations in evaluating bids for construction services.
4. I declare the above information to be true to the best of my knowledge, information, and belief. I could completely and accurately testify regarding the information contained in this affidavit if requested to do so.
(signature of affiant)
Dated: ________________
Subscribed and sworn before me in ________________ County, Michigan, on the _____ day of ___________________, 20____.
__________________________________________ (signature)
____________________________________________ (printed)
Notary public, State of Michigan, County of ________________
My Commission expires on _____________________________
Acting in the County of ________________________________
(This form is required to be attached to the bid form.)
Project No. 214175
IRAN ECONOMIC SANCTIONS ACT CERTIFICATION
I am the _________ ___ (title) of ______________________________ (bidder), or I am bidding in my individual capacity (�Bidder�), with authority to submit a binding bid for the provision of construction services to…